Quick-mounting dam panel ladder

By designing a quick-installation dam panel ladder, using steel grating treads and triangular supports for connection, the problems of inconvenient transportation and unstable operation during dam panel construction were solved, achieving a stable, safe, and efficient construction environment.

CN225015032UActive Publication Date: 2026-11-24SINOHYDRO BUREAU 12 CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202521911745.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-09-05
Publication Date
2026-11-24
Estimated Expiration
2035-09-05

AI Technical Summary

Technical Problem

In existing construction methods, large climbing ladders are inconvenient to transport and construction workers are unstable when working on the dam panel, posing safety hazards. Traditional rope ladders are lightweight but unstable, increasing the labor intensity of workers.

Method used

A quick-installation dam panel ladder was designed, which uses steel grating plates and triangular brackets for connection. It is positioned by steel wire rope clamps and traction steel wire ropes. The support rods can be folded to reduce the volume, making it easy to transport and install.

Benefits of technology

It provides a stable and safe construction environment, reduces shaking, lowers the labor intensity of workers, improves construction efficiency, and reduces manufacturing and transportation costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225015032U_ABST
    Figure CN225015032U_ABST
Patent Text Reader

Abstract

This utility model discloses a quick-assembly ladder for dam panels, comprising two traction steel wire ropes and multiple step units sequentially connected between the two traction steel wire ropes. Each step unit includes a footboard and a triangular bracket located at the front bottom of the footboard. The triangular bracket includes two support rods symmetrically connected to the inner walls of both sides of the footboard frame. Diagonal braces connect the outer sides of each support rod to the corresponding outer walls of the footboard frame. The support rods, diagonal braces, and footboard frame together form a right-angled triangular support structure. A connecting plate is also provided between the bottoms of the two support rods. This application features a simple structure, light weight, low cost, and easy portability, making it particularly suitable for rapid assembly and use on dam panels.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of dam panel ladder technology, specifically to a quick-installation dam panel ladder. Background Technology

[0002] In the construction of water conservancy and hydropower projects, the construction of concrete face panels is a crucial step in ensuring the safe operation of dams. Dam face panels are typically massive, steep slope structures, covering an area of ​​tens of thousands of square meters. Their smooth surfaces lack effective footholds, making the construction environment quite harsh.

[0003] Currently, due to the large area of ​​the dam, using large ladders for construction would be a huge undertaking, as the ladders themselves are large and heavy, and transporting them to the dam would be an enormous project, making it unsuitable for dam construction.

[0004] Therefore, existing construction methods typically involve workers standing directly on slopes or using rope ladders, but both methods are highly unstable. First, when workers stand on the dam panel, their bodies must maintain a twisted, suspended, or semi-suspended posture for extended periods, making them highly susceptible to instability and falls. Even with safety harnesses, the protective effect is very limited. Second, traditional rope ladders are often made by connecting multiple wooden strips with hemp rope. To reduce overall weight, the wooden strips are usually small, only about one-third the size of a worker's foot. This makes working on the wooden strips very strenuous and inconvenient, increasing the worker's workload. Furthermore, the hemp rope is prone to wear and tear, posing a potential safety hazard. Utility Model Content

[0005] To solve the above-mentioned technical problems, this utility model provides a quick-installation dam panel ladder.

[0006] A quick-installation dam panel ladder includes two traction steel wire ropes and multiple step units connected sequentially between the two traction steel wire ropes. Each step unit includes a step and a triangular bracket located at the front bottom of the step. The triangular bracket includes two support rods, which are symmetrically connected to the inner walls of both sides of the step frame. An inclined brace is connected between the outer side of each support rod and the outer wall of the corresponding step frame. The support rods, the inclined brace, and the step frame together form a right-angled triangular support structure. A connecting plate is also provided between the bottoms of the two support rods.

[0007] A further technical solution is: the bottom surface of the connecting plate is flush with the bottom surface of the support rod, and the bottom surface of the support rod is provided with an inclined support surface that is consistent with the inclination angle of the dam.

[0008] A further technical solution is as follows: the support rod is fixedly connected to the pedal frame by bolts, the diagonal brace includes a first link and a second link, the first link and the second link are connected by bolts, the other end of the first link is fixedly connected to the outer wall of the pedal frame by bolts, and the other end of the second link is fixedly connected to the outer side of the support rod by bolts.

[0009] A further technical solution is: the support rod is rotatably connected to the pedal frame; an alignment protrusion is provided on the outer side of the support rod; one end of the diagonal brace is rotatably connected to the outer wall of the pedal frame; the other end of the diagonal brace is provided with an alignment groove that matches the alignment protrusion; and a storage groove that matches the alignment protrusion is also provided on the outer wall of the pedal frame.

[0010] A further technical solution is: when the support rod of each step unit is perpendicular to the tread frame, the connecting plate of the previous step unit is in close contact with the outer wall of the tread frame of the next step unit, so that each step unit is arranged in a continuous step shape.

[0011] A further technical solution is: the pedal includes a support frame and horizontal and vertical bars arranged intersectingly within the support frame.

[0012] A further technical solution is as follows: the pedal is made of steel grating with a length of 800-900mm and a width of 300-320mm, and the support rod is made of 25mm×3mm flat steel or 25mm×25mm×3mm angle steel with a height of 200-220mm.

[0013] A further technical solution is: steel wire rope clamps are provided at the rear end of the outer wall on both sides of the pedal frame, and the steel wire rope clamps of each step unit are sequentially clamped and connected to the traction steel wire rope.

[0014] A further technical solution is: the traction wire rope is composed of multiple sections of galvanized pressed wire rope connected in series, with each section of wire rope having its ends pressed into rope loops by steel sleeves, and the rope loops of adjacent sections of wire rope are connected by shackles.

[0015] A further technical solution is to connect the upper and lower ends of the traction wire rope to anchor points set at the top and bottom of the dam, respectively.

[0016] The beneficial effects of this utility model are: This application discloses a quick-assembly dam panel ladder, which uses steel grating treads and triangular supports to form step units. The triangular supports are erected on the dam slope, providing stable support for the treads, resulting in more even stress distribution and reduced swaying during operation. Steel wire rope clamps connect the step units to traction steel wire ropes, which position, fix, and pull each step unit, ensuring the overall stability of the ladder. Furthermore, the support rods of the step units can be folded and stored at the bottom of the treads, reducing the overall volume and making handling and transportation more convenient and space-saving.

[0017] The ladder of this application provides workers with a safer and more stable working surface, making it easier and less strenuous for workers to walk and move. In addition, the ladder of this application has a simple structure, is lightweight, has low manufacturing cost, and is easy to carry. It is particularly suitable for rapid assembly and use on dam panels, ensuring the safety of workers while improving construction efficiency. Attached Figure Description

[0018] Figure 1 This is a structural schematic diagram of the ladder of this utility model; Figure 2 This is a structural diagram of a stepped unit; Figure 3 This is a schematic diagram of a structure in one implementation where the diagonal brace is open; Figure 4 yes Figure 3 A schematic diagram of the retracted diagonal brace; Figure 5 This is a schematic diagram of the ladder of this utility model on the dam body.

[0019] In the diagram: 1. Stepped unit, 2. Traction wire rope, 3. Step, 4. Bearing frame, 5. Horizontal bar, 6. Vertical bar, 7. Triangular bracket, 8. Wire rope clamp, 9. Support rod, 10. Diagonal brace, 11. Connecting plate, 12. Inclined support surface, 13. Dam panel, 14. First connecting rod, 15. Second connecting rod, 16. Alignment groove, 17. Alignment protrusion, 18. Storage groove. Detailed Implementation

[0020] The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, illustrating only the basic structure of the present invention, and therefore only show the components relevant to the present invention.

[0021] In the description of this utility model, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation on the utility model.

[0022] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.

[0023] A type of quick-installation dam panel ladder, such as Figure 1-5 As shown, the structure includes two traction steel wire ropes 2 and multiple stepped units 1 connected sequentially between the two traction steel wire ropes 2. Each stepped unit 1 includes a step 3 and a triangular bracket 7 located at the bottom front of the step 3. The triangular bracket 7 includes two support rods 9, the tops of which are symmetrically connected to the inner walls on both sides of the edge of the step 3. A diagonal brace 10 connects the outer wall of each support rod 9 to the outer wall of the corresponding edge of the step 3. The support rods 9, the diagonal brace 10, and the corresponding edge of the step 3 together form a right-angled triangular support structure. A connecting plate 11 is also provided between the bottoms of the two support rods 9. The triangular bracket 7 is erected on the dam slope to provide support for the step 3, ensuring the stable arrangement of each stepped unit 1.

[0024] The bottom surface of the connecting plate 11 is flush with the bottom surface of the support rod 9. The bottom surface of the support rod 9 is provided with an inclined support surface 12 that is consistent with the inclination angle of the dam. By setting the inclined support surface 12, the triangular bracket 7 is stably placed on the dam slope, the stress distribution is more uniform, and the shaking during operation is reduced.

[0025] In one implementation, such as Figure 2 As shown, the support rod 9 is fixedly connected to the edge of the pedal 3 by bolts. The diagonal brace 10 includes a first connecting rod 14 and a second connecting rod 15, which are connected by bolts. The other end of the first connecting rod 14 is fixedly connected to the outer side of the edge of the pedal 3 by bolts, and the other end of the second connecting rod 15 is fixedly connected to the outer side of the support rod 9 by bolts. In this embodiment, the connection of the triangular bracket 7 is more stable, simple to manufacture, and lower in cost.

[0026] In another preferred embodiment, such as Figure 3 and Figure 4As shown, the top of the support rod 9 is rotatably connected to the inner wall of the pedal 3 frame via rivets. An alignment protrusion 17 is provided on the outer side of the support rod 9. One end of the diagonal brace 10 is rotatably connected to the outer side of the pedal 3 frame, and the other end of the diagonal brace 10 is provided with an alignment groove 16 that matches the alignment protrusion 17. The alignment groove 16 is used to lock the alignment protrusion 17, so that the diagonal brace 10 is securely connected between the support rod 9 and the pedal 3. A storage groove 18 that matches the alignment protrusion 17 is provided on the outer wall of the pedal 3 frame. When the diagonal brace 10 is disengaged, the storage groove 18 accommodates the alignment protrusion 17 on the support rod 9, allowing the support rod 9 to fold to the bottom of the pedal 3. In this embodiment, installation and disassembly are convenient and quick, improving construction efficiency; and the overall volume of the ladder is reduced during transport, facilitating transportation.

[0027] When transporting the ladder, the step unit 1 can be folded, with the support rod 9 folded at the bottom of the step 3. The alignment protrusion 17 on the support rod 9 is accommodated in the storage groove 18 on the outer wall of the step 3 frame, which greatly reduces the volume of the step 3 unit and facilitates movement. When installation and use are required, the support rod 9 is rotated outside the step 3 so that the two are perpendicular to each other. Then, the diagonal brace 10 is rotated so that the alignment groove 16 engages with the alignment protrusion 17 on the support rod 9, locking the diagonal brace 10 between the step 3 and the support rod 9, achieving a stable connection between the step 3 and the support rod 9. When disassembling the ladder, the diagonal brace 10 is rotated in the opposite direction to fold up, facilitating storage, handling, and transportation of the support rod 9.

[0028] When the support rod 9 of each step unit 1 of the ladder is perpendicular to the edge of the tread 3, that is, when each step unit 1 is in the unfolded state, the connecting plate 11 of the upper step unit is in close contact with the outer wall of the edge of the tread 3 of the lower step unit, so that each step unit is arranged in a continuous step shape to facilitate workers to walk on the ladder.

[0029] The step 3 includes a rectangular support frame 4 and horizontal bars 5 and vertical bars 6 arranged intersecting within the support frame. Specifically, the step 3 can be made of steel grating with a length of 800-900mm and a width of 300-320mm. The steel grating is made of 303 flat steel and 6mm twisted square steel. The step 3 can accommodate 1-2 people standing and working. The support rod 9 is made of 25mm×3mm flat steel or 25mm×25mm×3mm angle steel, and the height of the support rod 9 is 200-220mm to facilitate workers climbing up and down the ladder.

[0030] Steel wire rope clamps 8 are provided at the rear ends of the outer walls on both sides of the footplate 3 frame. The steel wire rope clamps 8 of each step unit are sequentially clamped and connected to the traction steel wire ropes 2. Specifically, the steel wire rope clamps 8 can be U-bolts. After the two ends of the U-bolts pass through the footplate 3 frame, they are locked and fixed by two nuts, thereby clamping the steel wire ropes that have passed through. By connecting the steel wire rope clamps 8 on both sides of the footplate 3 to the traction steel wire ropes 2 on both sides respectively, the step unit 1 is fixed between the two traction steel wire ropes 2.

[0031] The traction wire rope 2 is composed of multiple sections of galvanized pressed wire rope connected in series. Each section has its ends pressed into loops by steel sleeves, and the loops of adjacent sections are connected by shackles. Specifically, each section of wire rope has a diameter of 12mm and a length of 10m.

[0032] The upper and lower ends of the traction steel wire rope 2 are connected to anchor points set at the top and bottom of the dam, respectively. Specifically, the anchor points at the top or bottom of the dam can be one of the following: counterweight blocks, concrete block anchors, or winches, to ensure the overall stability of the climbing ladder.

[0033] To improve installation efficiency, the quick-installation dam panel ladder of this application can be installed in multiple sections. Each section uses two 10m long steel wire ropes for traction and positioning, and multiple step units are connected between the two steel wire ropes. When transporting the ladder from the factory to the top of the dam using transportation equipment, each step unit 1 is folded, and the support rod 9 of each step unit 1 is stored at the bottom of the footplate 3 to reduce the overall volume and facilitate transportation. Workers unfold and adjust each step unit 1 one by one at the top of the dam. After unfolding the support rod 9 of each step unit 1 so that it is perpendicular to the footplate at 90 degrees, the diagonal brace 10 is rotated so that the alignment groove 16 engages with the alignment protrusion 17 on the support rod 10, so that the footplate 3 frame, diagonal brace 10 and support rod 9 together form a right triangle to ensure the overall stability of the step unit. During installation, the first section of the ladder is lifted by hoisting equipment and transferred to the dam slope, and then the top of the traction steel wire rope is connected to the anchor point on the top of the dam. After initial installation, workers adjust the position of each step unit along the direction of the ladder to ensure that the inclined support surface 12 of the connecting plate 11 and the support rod 9 is tightly against the dam slope.

[0034] Install the next ladder segment as needed for construction. The upper end of the steel wire rope of the next ladder segment is connected to the lower end of the steel wire rope of the first ladder segment via a shackle. Continue installing the ladder segment by segment along the dam slope until all ladder segments are installed. The end of the traction steel wire rope 2 can be connected to the anchor point at the bottom of the dam. When construction is completed and the ladder needs to be dismantled, the alignment groove 17 and the alignment protrusion 16 can be separated by rotating the diagonal brace 10, and the support rod 10 can be folded at the bottom of the pedal 3 for easy quick deployment and transportation.

[0035] Based on the above-described preferred embodiments of this utility model, and through the foregoing description, those skilled in the art can make various changes and modifications without departing from the technical concept of this utility model. The technical scope of this utility model is not limited to the contents of the specification, but must be determined according to the scope of the claims.

Claims

1. A fast-assembly dam panel ladder characterized in that, It includes two traction steel wire ropes and multiple step units connected sequentially between the two traction steel wire ropes. Each step unit includes a step and a triangular bracket set at the front bottom of the step. The triangular bracket includes two support rods, which are symmetrically connected to the inner walls of both sides of the step frame. Each support rod is connected to the outer side of the corresponding step frame with a diagonal brace. The support rods, diagonal braces, and step frame together form a right-angled triangular support structure. A connecting plate is also provided between the bottoms of the two support rods.

2. A quick-fit dam panel ladder according to claim 1, characterized in that The bottom surface of the connecting plate is flush with the bottom surface of the support rod, and the bottom surface of the support rod is provided with an inclined support surface that matches the inclination angle of the dam.

3. A fast-fit dam panel ladder according to claim 1, characterised in that, The support rod is fixedly connected to the pedal frame by bolts. The diagonal brace includes a first link and a second link, which are connected by bolts. The other end of the first link is fixedly connected to the outer wall of the pedal frame by bolts, and the other end of the second link is fixedly connected to the outer side of the support rod by bolts.

4. A fast-fit dam panel ladder according to claim 1, characterised in that, The support rod is rotatably connected to the pedal frame; the support rod has an alignment protrusion on its outer side, one end of the diagonal brace is rotatably connected to the outer wall of the pedal frame, the other end of the diagonal brace has an alignment groove that matches the alignment protrusion, and the outer wall of the pedal frame also has a storage groove that matches the alignment protrusion.

5. A quick-fit dam panel ladder according to claim 3 or 4, characterised in that, When the support rod of each step unit is perpendicular to the tread edge, the connecting plate of the previous step unit is in close contact with the outer wall of the tread edge of the next step unit, so that each step unit is arranged in a continuous step shape.

6. A fast-pack dam panel ladder according to claim 1, wherein, The pedal includes a support frame and horizontal and vertical bars arranged intersectingly within the support frame.

7. A quick-fit dam panel ladder according to claim 6, characterized in that The pedals are made of steel grating with a length of 800-900mm and a width of 300-320mm. The support rods are made of 25mm×3mm flat steel or 25mm×25mm×3mm angle steel, and the support rod height is 200-220mm.

8. A fast-pack dam panel ladder according to claim 1, wherein, Steel wire rope clamps are provided at the rear end of the outer wall of the frame on both sides of the pedal. The steel wire rope clamps of each step unit are connected to the traction steel wire rope in sequence.

9. A fast-pack dam panel ladder according to claim 1, wherein, The traction wire rope is made up of multiple sections of galvanized pressed wire rope connected together. Each section of wire rope has its ends pressed into rope loops by steel sleeves. The rope loops of adjacent sections of wire rope are connected by shackles.

10. A fast-pack dam panel ladder according to claim 1, wherein, The upper and lower ends of the traction steel wire rope are connected to anchor points set at the top and bottom of the dam, respectively.