A formwork system for a shaft heading machine launch structure

By designing a template system suitable for shaft tunneling machines, the problem of unstable installation of the V-shaped cutterhead of the shaft tunneling machine was solved, and the stability and accuracy were improved, ensuring the construction safety and installation accuracy of the shaft tunneling machine.

CN225015077UActive Publication Date: 2026-11-24浙江中水数建科技有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202620015103.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2026-01-07
Publication Date
2026-11-24
Estimated Expiration
2036-01-07

AI Technical Summary

Technical Problem

Existing horizontal tunnel launching technology cannot be applied to the V-shaped cutterhead of vertical shaft tunneling machines, resulting in unstable cutterhead installation and difficulty in achieving self-stabilization. Furthermore, the template system has insufficient rigidity or inaccurate positioning, failing to provide a precise installation base.

Method used

Design a template system for the starting structure of a vertical shaft tunneling machine, including a base template, template support components and tie rods. The base template is matched with the V-shaped cutterhead of the vertical shaft tunneling machine and fixed by the template support components and tie rods to ensure the stability and accuracy of the template system. Fiberglass tie rods are used to anchor to the shaft wall to distribute the lateral pressure of the concrete and prevent deformation.

Benefits of technology

It achieved stable installation of the cutterhead of the shaft tunneling machine, ensuring installation accuracy and construction safety, solving the problem of limited installation space during shaft tunneling machine construction, and improving the lateral pressure resistance and deformation resistance of the formwork system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225015077U_ABST
    Figure CN225015077U_ABST
Patent Text Reader

Abstract

This utility model discloses a template system for the launching structure of a vertical shaft tunneling machine, including a base template, a template support assembly, and tie rods. The base template is set on the excavation face of the vertical shaft, and the bottom end of the template extends into the guide shaft. The base template has a profile that matches the V-shaped cutterhead of the vertical shaft tunneling machine. The template support assembly is set on the outside of the base template to support it. Multiple tie rods are set on the inside of the base template between it and the shaft wall to fix the base template. The template system of this application is easy to install, fast, highly accurate, and stable, and is particularly suitable for fabricating the launching structure of the V-shaped cutterhead in the vertical shaft tunneling machine excavation process based on the guide shaft.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of shaft tunneling machine technology, specifically to a shaft tunneling machine excavation starting structure based on a guide shaft. Background Technology

[0002] Currently, the main method of tunnel boring machine (TBM) excavation in China involves horizontal tunneling. In this process, the TBM installation and launch are both carried out on the ground, and the cutterhead is planar. The requirements for the TBM launch structure are simply to complete the blasting excavation of a certain length of tunnel, ensuring that the TBM's support shoes can effectively support the tunnel wall to provide propulsion reaction force. Because the cutterhead in horizontal tunneling is planar and stable, there are no special structural requirements for the excavation face, making the construction relatively simple.

[0003] However, when using tunnel boring machines (TBMs) for vertical shaft excavation, the existing horizontal tunnel launching technology cannot be directly applied due to the change in working conditions. To facilitate TBM construction, a central pilot shaft is used for muck removal during the excavation process, and the TBM cutterhead is designed with a "V" shape. Due to the limitations of the V-shaped structure, if the cutterhead is directly installed on the horizontal working face formed by blasting excavation, the contact between the cutterhead and the working face is unstable, making it prone to swaying or tilting and difficult to achieve self-stabilization. Therefore, a launching structure specifically designed for the characteristics of a V-shaped cutterhead is needed.

[0004] The formwork design of the launching structure directly determines the forming quality of the launching structure. If the formwork system is not rigid enough or the positioning is inaccurate, the poured concrete launching structure will not be able to provide a precise installation base for the V-shaped cutterhead, and the stability of the cutterhead installation cannot be guaranteed, resulting in initial deviations after the cutterhead is installed.

[0005] Therefore, there is an urgent need for a template system for the launching structure that adapts to the characteristics of the V-shaped cutterhead of a shaft tunneling machine. Utility Model Content

[0006] To solve the above-mentioned technical problems, this utility model provides a template system for the starting structure of a vertical shaft tunneling machine.

[0007] A template system for the starting structure of a shaft tunneling machine includes a base template, a template support assembly, and tie rods. The base template is set on the shaft excavation face, and the bottom end of the template extends into the guide shaft. The base template has a profile that matches the V-shaped cutterhead of the shaft tunneling machine. The template support assembly is set on the outside of the base template to support it. Multiple tie rods are set on the inside of the base template between it and the shaft wall to fix the base template.

[0008] A further technical solution is: the base template includes an upper template section and a lower template section welded together. Both the upper template section and the lower template section are in the shape of a frustum, which is larger at the top and smaller at the bottom, corresponding to the outline and size of the upper and lower halves of the V-shaped cutter head, respectively.

[0009] A further technical solution is: the template support assembly includes a first support member and a second support member. The first support member includes main ribs and secondary ribs arranged in a grid pattern around the base template on the outer wall of the base template. The second support member includes a multi-layer skeleton arranged along the axial direction. Each skeleton includes multiple skeleton rods distributed radially. One end of the skeleton rods converges at the center, and the other end is fixedly connected to the main rib.

[0010] A further technical solution is as follows: the main ribs are arranged along the generatrix direction of the base template, and multiple main ribs are arranged in a circumferential array on the outside of the base template; the secondary ribs are arranged circumferentially along the outer wall of the base template, and multiple secondary ribs are arranged in layers at intervals along the axial direction of the base template; the secondary ribs are fixed to the outer wall of the base template.

[0011] A further technical solution is: the multi-layer frame includes an upper frame, a middle frame and a lower frame correspondingly set at the top of the upper template segment, the connection between the upper template segment and the lower template segment and the bottom of the lower template segment, and a strut is vertically set between the central convergence points of two adjacent frames.

[0012] A further technical solution is to provide several diagonal bracing ribs between the first support member and the second support member.

[0013] A further technical solution is to use No. 10 I-beams for the main beams and frame members, and φ28 steel bars for the secondary beams.

[0014] A further technical solution is: multiple tie members are arranged in a circumferential array around the inner wall of the base template, with one end of the tie member fixedly connected to the base template and the other end inclined downward and anchored into the rock strata of the shaft wall.

[0015] A further technical solution is to use fiberglass tie bars for the tie components.

[0016] A further technical solution is: an operating pit template is set between the top of the inner side wall of the base template and the vertical shaft wall, and the operating pit template is constructed by building a rectangular trench structure using multiple steel plates.

[0017] The beneficial effects of this utility model are: By placing the base template of this application on the excavation face above the pilot shaft, and pouring concrete between the base template and the shaft wall, a concrete base is formed as the starting structure for the excavation of the shaft tunneling machine. The base template is compatible with the profile size of the cutterhead, so that the cutterhead can be stably placed in the concrete base during subsequent installation, which can stably support the cutterhead and ensure the installation accuracy of the cutterhead, thereby effectively ensuring the accurate starting position of the shaft tunneling machine.

[0018] The base formwork of this application adopts an internal tension and external support formwork fixing system. The tie members are glass fiber tie bars anchored to the well wall. By setting tie members, the base formwork is prevented from running or deforming during the pouring process, ensuring stability. The external support adopts a first support member and a second support member. The first support member is fixed to the outside of the formwork, and the second support member adopts a radially arranged skeleton and is connected to the first support member. The two work together to evenly distribute the lateral pressure of the concrete generated during the pouring process, preventing the formwork from deforming or becoming unstable in the vertical and lateral directions. This improves the lateral pressure resistance and deformation resistance of the formwork system, ensuring structural safety and dimensional accuracy during the concrete pouring process.

[0019] Furthermore, by arranging the operating pit formwork between the base formwork and the shaft, and reserving the pit space for workers to install and operate during concrete pouring, the problem of limited installation space and construction difficulties for the subsequent shaft tunneling machine is solved, and workers can conveniently carry out their work using this space.

[0020] The template system of this application is easy to install, fast, highly accurate, and stable. It is particularly suitable for making the starting structure of the V-shaped cutterhead under the tunneling machine excavation process based on the guide shaft in vertical shafts. Attached Figure Description

[0021] Figure 1 This is a longitudinal section view of the template system for the starting structure of a shaft tunneling machine. Figure 2 This is a diagram showing the layout of the starting structure for the shaft boring machine inside the shaft. Figure 3 This is a schematic diagram of the base template and template support components; Figure 4 yes Figure 3 Enlarged view of point A in the middle; Figure 5 This is a top view of the upper skeleton; Figure 6 This is the expanded diagram of the upper template segment; Figure 7 This is the expanded diagram of the template segment.

[0022] In the picture: 1. Base formwork; 2. First support component; 3. Second support component; 4. Tie component; 5. Upper formwork section; 6. Lower formwork section; 7. Main rib; 8. Secondary rib; 9. Concrete base; 10. Operating pit; 11. Shaft; 12. Excavation face; 13. Guide shaft; 14. Shaft boring machine; 15. Upper half of V-shaped cutterhead; 16. Lower half of V-shaped cutterhead; 17. Operating pit formwork; 18. Upper frame; 19. Middle frame; 20. Lower frame; 21. Support rod; 22. Frame members; 23. Diagonal bracing rib. Detailed Implementation

[0023] The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, illustrating only the basic structure of the present invention, and therefore only show the components relevant to the present invention.

[0024] In the description of this utility model, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation on the utility model.

[0025] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.

[0026] A template system for the launching structure of a shaft tunneling machine, such as Figures 1-7 As shown, the structure includes a base template 1, a template support assembly, and tie rods 4. The base template 1 is set on the excavation face 12 of the shaft 11, and the bottom end of the template extends into the guide shaft 13. The base template 1 has a profile and dimensions that match the V-shaped cutterhead of the shaft boring machine. The template support assembly is located on the outside of the base template 1 to support it. Multiple tie rods 4 are located on the inside of the base template 1 between it and the shaft wall of the shaft 11 to fix the base template 1. It should be noted that the inside of the base template refers to the side facing the concrete, and the outside of the base template refers to the side facing away from the concrete.

[0027] The base template 1 includes an upper template section 5 and a lower template section 6 welded together. Both the upper template section 5 and the lower template section 6 are frustum-shaped, wider at the top and narrower at the bottom, corresponding to the outline and dimensions of the upper half 15 and the lower half 16 of the V-shaped cutterhead, respectively. The bottom end of the lower template section 6 extends into the guide shaft 13. Specifically, both the upper template section 5 and the lower template section 6 are made of 3mm thick steel plate.

[0028] The template support assembly includes a first support member 2 and a second support member 3. The first support member 2 includes a main rib 7 and a secondary rib 8 arranged in a grid pattern around the base template 1 on the outer wall of the base template 1. The second support member 3 includes a multi-layer skeleton arranged along the axial direction. Each skeleton includes multiple skeleton rods 22 distributed radially. One end of the skeleton rods 22 converges at the center, and the other end is fixedly connected to the main rib.

[0029] The main ribs 7 are arranged along the generatrix direction of the base template 1, and multiple main ribs 7 are arranged in a circumferential array on the outside of the base template 1; the secondary ribs 8 are arranged circumferentially along the outer wall of the base template 1, and multiple secondary ribs 8 are arranged in layers at intervals along the axial direction of the base template 1; the secondary ribs 8 are fixed to the outer wall of the base template 1.

[0030] The multi-layer frame includes an upper frame 18, a middle frame 19, and a lower frame 20, which are respectively set at the top of the upper template segment 5, at the connection between the upper template segment 5 and the lower template segment 6, and at the bottom of the lower template segment 6. A strut 21 is vertically set between the central convergence points of two adjacent frames.

[0031] Specifically, the main joists 7 are made of No. 10 I-beams, with 15 to 25 joists; the secondary joists 8 are made of φ28 steel bars, spaced at 200 to 300 mm intervals. The frame members 22 are made of No. 10 I-beams, with 8 to 10 joists.

[0032] Preferably, a number of diagonal bracing ribs 23 are provided between the first support member 2 and the second support member 3 to enhance stability and assist in force bearing, increase the rigidity of the template support component, coordinate force bearing, and ensure accurate dimensions of the formed structure.

[0033] The operating pit template 17 is set between the top of the inner wall of the base template 1 and the wall of the shaft 11. It forms a recessed operating platform for personnel to work in after pouring. The operating pit template 17 is constructed from multiple steel plates to form a rectangular pit structure. Two to four operating pit templates 17 can be arranged according to the cutterhead structure and construction needs. By arranging the operating pit templates 17, an operating pit 10 is formed after concrete pouring, serving as the operating space for subsequent cutterhead installation and facilitating personnel access to the operating pit 10 for work. The operating pit template 17 is fixed by multiple fiberglass tie bars and a fixed truss to ensure its stability during the pouring process.

[0034] Multiple tie members 4 are arranged in a circumferential array around the side wall of the base template 1. The tie members 4 are inclined, with one end extending into the base template 1 and fixedly connected to it, and the other end inclined downward and anchored into the rock strata of the shaft wall 11. The circumferentially arrayed tie members 4 support the base template 1, allowing it to be embedded in the poured concrete base 9, thus ensuring stability during template installation and concrete pouring.

[0035] Tie member 4 is made of fiberglass tie bars. Specifically, the anchorage length of the fiberglass tie bars into the rock strata of shaft 11 is 1.5m, and the circumferential spacing is 0.5m. After the concrete base 9 is poured, the base formwork 1 is removed, and the fiberglass tie bars remain in the concrete. After the cutterhead is installed, the base concrete needs to be removed with the cutterhead. If traditional steel reinforcement bars are used, it will be detrimental to the cutterhead excavation. However, this material has high tensile strength and low hardness, which can avoid damage to the cutterhead and cutting tools.

[0036] Based on the above-described preferred embodiments of this utility model, and through the foregoing description, those skilled in the art can make various changes and modifications without departing from the technical concept of this utility model. The technical scope of this utility model is not limited to the contents of the specification, but must be determined according to the scope of the claims.

Claims

1. A template system for the launching structure of a vertical shaft tunneling machine, characterized in that, The system includes a base template, a template support assembly, and tie rods. The base template is set on the face of the shaft excavation and the bottom end of the pit template extends into the guide shaft. The base template has a profile that matches the V-shaped cutterhead of the shaft tunneling machine. The template support assembly is set on the outside of the base template to support the base template. Multiple tie rods are set on the inside of the base template between the base template and the shaft wall to fix the base template.

2. The template system for the starting structure of a vertical shaft tunneling machine according to claim 1, characterized in that, The base template includes an upper template section and a lower template section welded together. Both the upper and lower template sections are truncated cones, which are larger at the top and smaller at the bottom, corresponding to the outline and dimensions of the upper and lower halves of the V-shaped cutter head, respectively.

3. The template system for the starting structure of a vertical shaft tunneling machine according to claim 1, characterized in that, The template support assembly includes a first support member and a second support member. The first support member includes main ribs and secondary ribs arranged in a grid pattern around the base template on the outer wall of the base template. The second support member includes a multi-layer skeleton arranged along the axial direction. Each skeleton includes multiple skeleton members distributed radially. One end of the skeleton members converges at the center, and the other end is fixedly connected to the main rib.

4. The template system for the starting structure of a vertical shaft tunneling machine according to claim 3, characterized in that, The main ribs are arranged along the generatrix of the base template, and multiple main ribs are arranged in a circumferential array on the outside of the base template; the secondary ribs are arranged circumferentially along the outer wall of the base template, and multiple secondary ribs are arranged in layers at intervals along the axial direction of the base template; the secondary ribs are fixed to the outer wall of the base template.

5. The template system for the starting structure of a vertical shaft tunneling machine according to claim 4, characterized in that, The multi-layered frame includes an upper frame, a middle frame, and a lower frame, which are respectively set at the top of the upper template section, at the connection between the upper template section and the lower template section, and at the bottom of the lower template section. A strut is vertically set between the central convergence points of two adjacent frames.

6. The template system for the starting structure of a vertical shaft tunneling machine according to claim 3, characterized in that, Several diagonal bracing ribs are provided between the first support member and the second support member.

7. The template system for the starting structure of a vertical shaft tunneling machine according to claim 3, characterized in that, The main beams and frame members are made of No. 10 I-beams, and the secondary beams are made of φ28 steel bars.

8. The template system for the starting structure of a vertical shaft tunneling machine according to claim 1, characterized in that, Multiple tie members are arranged in a circumferential array around the inner wall of the base template. One end of the tie member is fixedly connected to the base template, and the other end is inclined downward and anchored into the rock strata of the shaft wall.

9. A template system for the starting structure of a vertical shaft tunneling machine according to claim 8, characterized in that, The tie rods are made of glass fiber.

10. A template system for the starting structure of a vertical shaft tunneling machine according to claim 1, characterized in that, An operating pit template is set between the top of the inner side wall of the base template and the vertical shaft wall. The operating pit template is constructed by building a rectangular trench structure using multiple steel plates.