Underground rock cavern energy storage sealing structure with monitoring function

By employing a multi-layered composite sealing structure and a systematic monitoring scheme, the problems of unstable sealing performance and lack of overall monitoring system in underground rock cave energy storage projects have been solved, enabling safe storage of high-pressure gas and real-time safety assessment, thereby improving the safety and reliability of energy storage facilities.

CN225015091UActive Publication Date: 2026-11-24CHINA RAILWAY SIYUAN SURVEY & DESIGN GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522822182.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-31
Publication Date
2026-11-24
Estimated Expiration
2035-12-31

AI Technical Summary

Technical Problem

In existing underground rock cave energy storage projects, the sealing performance is unstable and the monitoring system lacks integrity, which increases the risk of gas leakage and makes it difficult to detect safety hazards in a timely manner.

Method used

It adopts a multi-layer composite sealing structure design, including a sealing steel lining, an asphalt slip layer, a concrete lining, and artificial surrounding rock, and is equipped with a systematic monitoring scheme, which uses sensors to monitor the stress and strain state of each layer and the working parameters inside the chamber in real time.

Benefits of technology

It improves the reliability and stability of the sealing structure, enables real-time monitoring and safety assessment of energy storage facilities, reduces the risk of gas leakage, and enhances safety and reliability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225015091U_ABST
    Figure CN225015091U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of underground energy storage engineering technology, specifically a sealed structure for underground rock cave energy storage with monitoring function. It includes an underground cavern with a regular cross-section, and from the inside out, the following components are arranged sequentially: a sealing steel lining, formed by segmented welding to create a sealed structure, with strain gauges and a temperature sensor 1 mounted on the sealing steel lining; an asphalt slip layer, disposed outside the sealing steel lining; a concrete lining, disposed outside the asphalt slip layer, with a deformation monitoring device mounted on the concrete lining; and artificial surrounding rock, disposed outside the concrete lining. A second temperature sensor and a pressure sensor are located within the cavern. This utility model employs a multi-layered composite sealing structure design and a systematic monitoring scheme to solve the technical problems of unstable sealing performance and lack of overall monitoring system integration in existing technologies, thereby improving the safety and reliability of underground rock cave energy storage facilities.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of underground energy storage engineering technology, and in particular to an underground rock cave energy storage sealing structure with monitoring function. Background Technology

[0002] With the global energy structure transformation and the rapid development of renewable energy, large-scale energy storage technology has become crucial for ensuring the stable operation of the power grid. Deep underground space rock tunnel energy storage technologies, especially compressed air storage, hydrogen storage, and natural gas storage, have attracted widespread attention due to their advantages such as large storage capacity, high safety, and minimal environmental impact. The core of these energy storage technologies lies in how to safely and efficiently store high-pressure gases in complex underground environments, which places extremely high demands on the sealing structure design and long-term stability monitoring of underground tunnels.

[0003] Existing underground rock cavern energy storage projects mainly rely on natural rock caves or artificially excavated chambers, achieving safe gas storage through the installation of support structures and sealing layers. Regarding sealing, current technologies often employ single materials, such as high-performance polymer materials or steel linings. While these provide a degree of airtightness, their sealing performance easily deteriorates under high pressure and frequent inflation / deflation conditions, increasing the risk of gas leakage. In terms of structural stability, traditional support structures such as shotcrete and anchor bolts, although offering some stability, are prone to fatigue failure and crack propagation under the cyclic loading of high-pressure gas, affecting the long-term safety of the structure.

[0004] In terms of monitoring, existing monitoring systems mainly focus on monitoring the gas pressure and temperature inside the chamber, lacking real-time monitoring of key indicators such as deformation of the sealing structure, interlayer stress state, and crack development. In addition, existing monitoring equipment mostly operates independently, lacking system integration, resulting in scattered monitoring data that is difficult to comprehensively analyze and provide early warnings. This affects the assessment of the overall operational status of energy storage facilities and hinders the timely detection and handling of potential safety hazards. Utility Model Content

[0005] In view of the shortcomings of the existing technology, the purpose of this utility model is to propose an underground rock cave energy storage sealing structure with monitoring function. It adopts a multi-layer composite sealing structure design and a systematic monitoring scheme to solve the technical problems of unstable sealing performance and lack of integrity of the monitoring system in the existing technology, thereby improving the safety and reliability of underground rock cave energy storage facilities.

[0006] To achieve the above objectives, this utility model provides the following technical solution: An underground rock cavern energy storage sealing structure with monitoring function includes an underground cavern with a regular cross-section, and arranged sequentially from the inside to the outside: A sealed steel liner is formed by segmented welding to create a closed structure. The sealed steel liner is equipped with strain gauges and a temperature sensor. An asphalt slip layer is disposed on the outside of the sealing steel liner; A concrete lining is provided on the outside of the asphalt slip layer, and a deformation monitoring device is provided on the concrete lining. Artificial surrounding rock is provided on the outside of the concrete lining; The chamber is equipped with a temperature sensor and a pressure sensor; The monitoring system is electrically connected to the second temperature sensor, the pressure sensor, the strain gauge, the first temperature sensor, and the deformation monitoring device.

[0007] Preferably, the deformation monitoring device includes a joint gauge disposed on the outer surface of the concrete lining, an optical fiber sensor disposed inside the concrete lining, and a stress sensor.

[0008] Preferably, the artificial surrounding rock is formed by shotcrete and anchor bolts.

[0009] Preferably, the sealing steel liner has end caps at both ends, which are welded and fixed to the sealing steel liner, and the end caps have an air inlet and an air outlet.

[0010] Preferably, the thickness of the asphalt slip layer is 5-20 mm.

[0011] Preferably, the sealing steel liner is made of stainless steel or carbon steel.

[0012] Preferably, the cross-section of the chamber is circular, elliptical, or horseshoe-shaped.

[0013] Preferably, the artificial surrounding rock is further provided with a stress sensor two and a temperature sensor three.

[0014] Compared with the prior art, the present invention has the following beneficial effects: (1) This utility model improves the sealing reliability by setting up a multi-layer composite sealing structure consisting of a sealing steel lining, an asphalt slip layer, a concrete lining, and artificial surrounding rock. The setting of the asphalt slip layer allows relative displacement between the layers under high-pressure gas cyclic load, reducing stress concentration caused by interlayer stress transmission and extending the service life of the sealing structure. The concrete lining provides structural support, and the artificial surrounding rock enhances the stability of the original rock. The multi-layer structure works together to ensure the long-term stable operation of the chamber under high-pressure conditions.

[0015] (2) The present invention sets up sensors in the sealed steel lining, concrete lining, artificial surrounding rock and chamber and connects them to the monitoring system, realizing synchronous monitoring of stress and strain state, deformation characteristics and working parameters of each layer of the sealed structure and chamber; real-time data of each part is obtained by multi-layered sensors, which facilitates the analysis of the response law of each layer of structure under different load conditions, and provides data support for the safety assessment and early warning of energy storage facilities. Attached Figure Description

[0016] Figure 1 This is a cross-sectional schematic diagram of an underground rock cave energy storage sealing structure with monitoring function according to this utility model.

[0017] In the diagram: 1. Tunnels; 2. Sealed steel lining; 3. Asphalt slip layer; 4. Concrete lining; 5. Artificial surrounding rock; 11. Temperature sensor; 12. Pressure sensor; 21. Strain gauge; 22. Temperature sensor one; 41. Crack gauge; 42. Fiber optic sensor; 43. Stress sensor one; 51. Stress sensor two; 52. Temperature sensor three. Detailed Implementation

[0018] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of the present utility model.

[0019] Example like Figure 1 An underground rock cavern energy storage sealing structure with monitoring function includes an underground cavern 1 with a regular cross-section, and arranged sequentially from the inside to the outside as follows: The sealing steel liner 2 is formed into a sealed structure by segmented welding. The sealing steel liner 2 is equipped with a strain gauge 21 and a temperature sensor 22. An asphalt slip layer 3 is disposed on the outside of the sealing steel liner 2; A concrete lining 4 is provided on the outside of the asphalt slip layer 3, and a deformation monitoring device is provided on the concrete lining 4; Artificial surrounding rock 5 is set on the outside of the concrete lining 4; The chamber 1 is equipped with a temperature sensor 11 and a pressure sensor 12; The monitoring system is electrically connected to the second temperature sensor 11, the pressure sensor 12, the strain gauge 21, the first temperature sensor 22, and the deformation monitoring device.

[0020] Chamber 1, as the core space of the energy storage system, is used to store high-pressure gases, including compressed air, hydrogen, and natural gas, providing the necessary volume for the energy storage facilities. Its cross-sectional shape and size are determined according to the gas storage requirements. Chamber 1 is arranged from the inside out with a sealed steel lining 2, an asphalt slip layer 3, a concrete lining 4, and artificial surrounding rock 5, forming a multi-layer composite sealed structure. Temperature sensor 11 and pressure sensor 12 are installed in chamber 1 to monitor the temperature and pressure of the gas inside chamber 1 and to monitor the operating parameters of the energy storage medium in real time.

[0021] The sealing steel liner 2, as the first sealing barrier, is formed into a sealed structure through segmented welding. It directly withstands the high-pressure gas inside the chamber 1, preventing gas leakage. The thickness of the sealing steel liner 2 is 10-50mm, preferably 20-30mm. Strain gauges 21 and temperature sensors 22 are installed on the sealing steel liner 2 to monitor the strain state and temperature change of the sealing steel liner 2 under the action of high-pressure gas. The strain gauges 21 are arranged on the outer surface of the sealing steel liner 2, evenly distributed along the circumference and longitudinal direction of the chamber 1, and can monitor the strain of the steel liner in real time. The temperature sensor 22 is fixed on the sealing steel liner 2 to monitor the temperature response of the steel liner during the inflation and deflation process.

[0022] The asphalt slip layer 3 is set between the sealing steel lining 2 and the concrete lining 4. The asphalt slip layer 3 plays a role in isolation and transition, protecting the sealing steel lining 2 from direct contact with the concrete, preventing unevenness or local protrusions on the concrete surface from damaging the sealing steel lining 2, and at the same time providing a certain degree of flexible transition to adapt to the deformation differences between the sealing steel lining 2 and the concrete lining 4.

[0023] The concrete lining 4 provides structural support, bears the pressure of the surrounding rock and the load transmitted by the steel lining, forms a support structure with high rigidity, protects the internal sealing system, and together with the artificial surrounding rock 5, ensures the overall stability of the chamber 1. A deformation monitoring device is installed on the concrete lining 4 to monitor the deformation and stress state of the concrete lining 4.

[0024] In this embodiment, the artificial surrounding rock 5 is formed by shotcrete and anchor bolts to reinforce and stabilize the original rock, improve the bearing capacity and integrity of the surrounding rock, reduce the deformation of the surrounding rock, and provide a stable support environment for the internal concrete lining 4.

[0025] The monitoring system is electrically connected to temperature sensor 11, pressure sensor 12, strain gauge 21, temperature sensor 22, and deformation monitoring device via cable or wireless means to realize real-time monitoring and data acquisition of internal working parameters and structural status of each layer of the chamber 1. The monitoring system is set up in the ground testing room and includes a data acquisition unit, a data processor, and a display and early warning device. It can process and analyze the collected data and issue an early warning signal when the monitored parameters exceed the preset threshold.

[0026] In this embodiment, the deformation monitoring device includes a joint gauge 41 disposed on the outer surface of the concrete lining 4, an optical fiber sensor 42 disposed inside the concrete lining 4, and a stress sensor 43.

[0027] The joint gauge 41 is installed on the outer surface of the concrete lining 4 to monitor the contact state and joint changes between the concrete lining 4 and the artificial surrounding rock 5. The joint gauge 41 is evenly arranged along the circumference of the chamber 1, with a measuring point set at intervals of 3-5 meters. The joint gauge 41 is fixed to the outer surface of the concrete lining 4 by embedded parts, and its measuring end extends into the interior of the artificial surrounding rock 5. When relative displacement or joints occur between the concrete lining 4 and the artificial surrounding rock 5, the joint gauge 41 can capture the changes in displacement in a timely manner, providing data support for assessing the overall structural integrity.

[0028] The fiber optic sensor 42 is shallowly embedded inside the concrete lining 4, and uses distributed fiber optic sensing technology to continuously monitor the deformation of the concrete lining 4. The fiber optic sensor 42 is a fiber optic grating sensor, which is arranged in a grid pattern along the circumference and longitudinal direction of the chamber 1, and can acquire the strain distribution information of the concrete lining 4 along the entire length of the chamber 1. The fiber optic sensor 42 is fixed inside the concrete lining 4 by pre-embedding. When the concrete lining 4 deforms, the optical properties of the fiber change. The deformation location and deformation amount can be identified by demodulation equipment, so as to realize real-time monitoring of crack development and local deformation.

[0029] Stress sensor 43 is embedded inside the concrete lining 4 to monitor the stress state of the concrete under load. Stress sensor 43 is a vibrating wire stress gauge, arranged in layers along the circumference and radial direction of the chamber 1, and can monitor the stress distribution of the concrete lining 4 at different depths and in different directions. Stress sensor 43 is pre-embedded inside the concrete during the concrete pouring process, and its placement depth is determined according to the monitoring requirements. It is generally set at 1 / 3 and 2 / 3 of the thickness of the concrete lining 4. The data collected by stress sensor 43 can determine whether the concrete lining 4 is within the safe stress range, assess its bearing capacity and fatigue life, and provide a basis for structural safety assessment.

[0030] The joint gauge 41, fiber optic sensor 42, and stress sensor 43 together constitute the deformation monitoring device for the concrete lining 4, realizing comprehensive monitoring of the outer surface gaps, internal deformation, and internal stress of the concrete lining 4, and enabling timely detection of abnormal deformation or stress concentration phenomena of the concrete lining 4.

[0031] In this embodiment, the sealing steel liner 2 is provided with end caps at both ends, and the end caps are welded and fixed to the sealing steel liner 2. The end caps are provided with an air inlet and an air outlet.

[0032] The sealing steel liner 2 has end caps at both ends to seal the openings at both ends of the chamber 1, forming a complete sealed gas storage space. The end caps are elliptical or dished, and their material is the same as that of the sealing steel liner 2, made of Q345 steel plate or stainless steel plate. The end caps and the sealing steel liner 2 are fixedly connected by full penetration welding to ensure that the weld quality meets the high-pressure airtightness requirements. The end caps are provided with air inlets and outlets for connecting external energy storage equipment such as compressors. The pipe diameters of the air inlets and outlets are determined according to the flow requirements of the energy storage system and are not limited here.

[0033] The inner surface of the end cap is flush with the inner surface of the sealing steel lining 2, forming a smooth inner wall to avoid airflow disturbance and local stress concentration; the outer side of the end cap is also provided with an asphalt slip layer 3 and a concrete lining 4, which are consistent with the structural layers of the main body of the chamber 1, forming a complete multi-layer composite sealing structure.

[0034] In this embodiment, the thickness of the asphalt slip layer 3 is 5-20 mm.

[0035] In this embodiment, the material of the sealing steel liner 2 is stainless steel or carbon steel.

[0036] In this embodiment, the cross-section of the chamber 1 is circular, elliptical, or horseshoe-shaped.

[0037] Concrete lining 4 is constructed using cast-in-place concrete or shotcrete.

[0038] In this embodiment, the artificial surrounding rock 5 is also equipped with a stress sensor 2 51 and a temperature sensor 3 52.

[0039] Stress sensor 251 is a vibrating wire stress gauge, fixed in the artificial surrounding rock 5. The signal line is led out through a protective pipe and is used to monitor the stress change of the surrounding rock under high-pressure gas cyclic loading. Stress sensor 251 is evenly arranged along the circumference and longitudinal direction of the chamber 1, and monitoring sections are set at key parts such as the arch crown, arch waist and sidewalls, with a longitudinal spacing of 5-10 meters. Each monitoring section has 3-5 measuring points arranged radially.

[0040] Temperature sensor 352 is a thermocouple temperature sensor, which is buried in the artificial surrounding rock 5 to monitor the temperature distribution of the surrounding rock and evaluate the thermal stability of the surrounding rock. Temperature sensor 352 is arranged in layers along the radial direction of the chamber 1, with a longitudinal spacing of 10-20 meters. Temperature sensor 352 can monitor the temperature of the surrounding rock and evaluate the range of thermal influence of high temperature gas on the surrounding rock.

[0041] This invention utilizes a multi-layered composite sealing structure, combining a sealing steel lining 2, an asphalt slip layer 3, a concrete lining 4, and artificial surrounding rock 5 to form multiple protective barriers from the inside out, effectively improving the reliability of the sealing system. Simultaneously, by arranging different types of sensors on each layer, a comprehensive monitoring system is established, enabling real-time monitoring and safety assessment of the energy storage facility's operational status, providing technical assurance for the safe operation of deep underground rock-pit energy storage projects.

[0042] The above description is only a preferred embodiment of the present utility model, but the protection scope of the present utility model is not limited thereto. Any equivalent substitutions or changes made by those skilled in the art within the technical scope disclosed in the present utility model, based on the technical solution and the inventive concept of the present utility model, should be included within the protection scope of the present utility model.

Claims

1. A sealed energy storage structure for underground rock tunnels with monitoring function, characterized in that, The underground chamber (1) with a regular cross-section is arranged from the inside out as follows: The sealing steel liner (2) is formed into a closed structure by segmented welding. The sealing steel liner (2) is provided with strain gauges (21) and temperature sensor (22). An asphalt slip layer (3) is disposed on the outside of the sealing steel liner (2); A concrete lining (4) is provided on the outside of the asphalt slip layer (3), and a deformation monitoring device is provided on the concrete lining (4); Artificial surrounding rock (5) is set on the outside of the concrete lining (4); The chamber (1) is equipped with a temperature sensor (11) and a pressure sensor (12). The monitoring system is electrically connected to the second temperature sensor (11), the pressure sensor (12), the strain gauge (21), the first temperature sensor (22), and the deformation monitoring device.

2. The underground rock cavern energy storage sealing structure with monitoring function according to claim 1, characterized in that: The deformation monitoring device includes a joint gauge (41) installed on the outer surface of the concrete lining (4), an optical fiber sensor (42) installed inside the concrete lining (4), and a stress sensor (43).

3. The underground rock cavern energy storage sealing structure with monitoring function according to claim 1, characterized in that: The artificial surrounding rock (5) is formed by shotcrete and anchor bolts.

4. The underground rock cavern energy storage sealing structure with monitoring function according to claim 1, characterized in that: The sealing steel liner (2) has end caps at both ends, which are welded and fixed to the sealing steel liner (2). The end caps have an air inlet and an air outlet.

5. The underground rock cavern energy storage sealing structure with monitoring function according to claim 1, characterized in that: The thickness of the asphalt slip layer (3) is 5-20 mm.

6. The underground rock cavern energy storage sealing structure with monitoring function according to claim 1, characterized in that: The material of the sealing steel liner (2) is stainless steel or carbon steel.

7. The underground rock cavern energy storage sealing structure with monitoring function according to claim 1, characterized in that: The cross-section of the chamber (1) is circular, elliptical or horseshoe-shaped.

8. The underground rock cavern energy storage sealing structure with monitoring function according to claim 1, characterized in that: The artificial surrounding rock (5) is also equipped with stress sensor 2 (51) and temperature sensor 3 (52).