By using filling mold bags made of right-angled trapezoidal geotextiles, grouting is injected to form a grout-blocking isolation wall, which solves the leakage problem of steel structure isolation devices and improves the compactness of the filling body and the stability of the slope.
Patent Information
- Application Number
- CN202620020749.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2026-01-08
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2036-01-08
AI Technical Summary
Existing steel structure isolation devices are difficult to adapt to the cross-sectional shape of the mining area during backfilling mining, resulting in leakage of backfill paste, which affects slope stability and filling rate.
The filling mold bag is made of geotextile and has a right-angled trapezoidal structure with filling port, vent port, filling pipe and vent pipe. After grouting, it forms a grout blocking isolation wall to ensure the compactness and stability of the filling body.
It effectively seals cracks in the roof, floor, and coal face, increases the filling rate, and enhances slope stability and the support strength of the filling body.
Smart Images

Figure CN225015114U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to an isolation device, specifically a side-filled bag type isolation device. Background Technology
[0002] Backfilling mining is an important technological direction for green mining in coal mines. Its core objective is to liberate coal resources covered by the "three bottoms and above" (referring to the coal seam, coal mine, coal mine, and coal mine), effectively protect the ecological environment of the mining area, and extend the service life of the mine.
[0003] Against this backdrop, the side slope paste filling mining technology is specifically designed to address the challenge of safely and efficiently recovering coal trapped under overburden in open-pit mine slopes. This technology utilizes imported gangue, concrete, and other materials to prepare a paste, which is then used to effectively fill the goaf, thereby controlling the movement of overlying strata and ensuring the long-term stability of open-pit mine slopes. This method not only resolves the conflict between resource recovery and slope safety but also simultaneously achieves the resource utilization of mine solid waste.
[0004] To improve the filling rate of the goaf, isolation devices need to be installed at the goaf entrance to prevent the filling paste from flowing out of the goaf. Currently, the isolation devices are generally made of steel structures. However, steel structures are difficult to adapt to the shape of the mining section. Wide gaps are easily generated between the isolation device and the roof, floor and coal wall. During filling, the paste is prone to leakage, which leads to problems such as inconvenience in adjustment and loose roof connection, thus affecting slope stability. Summary of the Invention
[0005] To address the problems existing in the prior art, this utility model provides a side-wall filling bag-type isolation device that effectively seals cracks in the roof, floor, and coal wall, prevents paste leakage, and improves the filling rate.
[0006] To achieve the above objectives, the present invention provides the following technical solution: a side-filled bag type isolation device, including a filling mold bag, the upper part of the filling mold bag is provided with a filling port and a venting port, and the upper part of the filling mold bag is provided with a sampling filling pipe and a sampling filling venting pipe that penetrate the entire filling mold bag.
[0007] Furthermore, the longitudinal section of the filling mold bag is a right-angled trapezoid, and the filling port and the venting port of the filling bag are opened on the inclined surface of the filling mold bag. The mining filling pipe and the mining filling venting pipe both penetrate from the inclined surface of the filling mold bag to the straight surface of the filling mold bag.
[0008] Furthermore, the bottom of the inclined surface of the filling mold bag is provided with a filling bag fixing hole.
[0009] Furthermore, the filling pipe of the mining chamber is located on the centerline of the inclined plane.
[0010] Furthermore, there are two mining tunnel filling and exhaust pipes, symmetrically arranged on both sides of the mining tunnel filling pipe.
[0011] Furthermore, the filling bag is made of geotextile.
[0012] Compared with existing technologies, this utility model injects grout into the filling mold bag, allowing the grout to solidify and form a regular "grout-blocking isolation wall" within a preset shape and volume. As a sealed flexible container, the filling mold bag can effectively seal the cracks in the roof, floor, and coal wall, ensuring that the filling grout is completely retained within the target area. During the filling operation, the outer "skeleton" is formed first, and then the internal space is filled, ensuring the integrity and roof contact rate of the filling body, and significantly improving the support strength and stability of the filling body. Attached Figure Description
[0013] Figure 1 This is a schematic diagram of the structure of this utility model; Figure 2 This is a schematic diagram showing the arrangement and usage of this utility model; In the diagram: 1. Filling bag; 2. Filling bag vent; 3. Mining chamber filling vent pipe; 4. Mining chamber filling pipe; 5. Filling bag filling port; 6. Filling bag fixing hole; 7. Anchor bolt; 8. Mining chamber; 9. Roof; 10. Coal seam; 11. Floor. Detailed Implementation
[0014] The present invention will be further described below with reference to the accompanying drawings.
[0015] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.
[0016] like Figure 1 As shown, this utility model provides a side-filled bag type isolation device, including a filling mold bag 1 made of geotextile, snake skin bag or water-permeable but aggregate-impermeable membrane material. The upper part of the filling mold bag 1 is provided with a filling port 5 for injecting grout into the filling mold bag 1 and a filling bag exhaust port 2 for venting air when injecting grout into the filling mold bag 1. The upper part of the filling mold bag 1 is provided with a mining tunnel filling pipe 4 that runs through the entire filling mold bag 1 for injecting grout into the space inside the mining tunnel and a mining tunnel filling exhaust pipe 3 for venting air when injecting grout into the space inside the mining tunnel.
[0017] To improve the stability of the filling mold bag 1 during use, the longitudinal section of the filling mold bag 1 is a right trapezoid. The filling port 5 and the venting port 2 of the filling bag are opened on the inclined side of the filling mold bag 1. The mining chamber filling pipe 4 and the mining chamber filling venting pipe 3 both pass through the inclined side of the filling mold bag 1 to the straight side of the filling mold bag 1. During use, the inclined side faces outward from the mining chamber 8, and the straight side faces inward from the mining chamber 8.
[0018] In use, the filling mold bag 1 is first placed at the entrance of the mining tunnel. Then, grouting is performed on the filling mold bag 1. The filling port 5 and the vent port 2 of the filling bag are opened, while the filling pipe 4 and the vent pipe 3 of the mining tunnel are closed. Grouting is performed on the filling mold bag 1 through the filling port 5, and venting is performed through the vent port 2. When grout flows out of the vent port 2, it is confirmed that the filling mold bag 1 is full of grout. The filling mold bag 1 is a flexible device. After grouting, the upper end face of the filling mold bag 1 is tightly attached to the top plate 9, the lower end face is tightly attached to the bottom plate 11, and the two sides are tightly attached to the roadway wall. After the internal grout solidifies and hardens, it forms a grout-blocking isolation wall. To improve the stability of the filling mold bag 1, a filling bag fixing hole 6 is provided at the bottom of the inclined side of the filling mold bag 1. The filling mold bag 1 is fixed to the bottom plate 11 by anchor bolts 7.
[0019] After the filling mold bag 1 hardens to form a grout-blocking isolation wall, the filling and grouting equipment is connected to the filling pipe 4 of the mining chamber to perform secondary grouting on the closed area of the mining chamber 8. Whether the mining chamber 8 is full is determined by observing whether grout flows out of the filling vent pipe 3, ultimately achieving complete and dense filling of the entire roadway. To improve grouting efficiency, the filling pipe 4 is located on the centerline of the inclined plane. To accurately determine whether the grout in the mining chamber 8 is completely filled, i.e., whether the space between the filling mold bag 1 and the unmined coal seam 10 is completely filled, two filling vent pipes 3 are symmetrically arranged on both sides of the filling pipe 4. This utility model is of great significance for optimizing filling quality, reducing material loss, and promoting the standardization and intelligent development of sidewall filling technology. It also provides new technical support for the improvement of the green mining technology system in coal mines.
[0020] It will be apparent to those skilled in the art that this invention is not limited to the details of the exemplary embodiments described above, and that it can be implemented in other specific forms without departing from the spirit or essential characteristics of this invention. Therefore, the embodiments should be considered illustrative and non-limiting in all respects, and the scope of this invention is defined by the appended claims rather than the foregoing description. Thus, it is intended that all variations falling within the meaning and scope of equivalents of the claims be included within this invention. No reference numerals in the claims should be construed as limiting the scope of the claims.
[0021] The above description is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. Any minor modifications, equivalent substitutions and improvements made to the above embodiments based on the technical essence of the present utility model should be included within the protection scope of the technical solution of the present utility model.
Claims
1. A side-hill pack bag isolation device comprising a packer bag (1), characterized in that, The upper part of the filling mold bag (1) is provided with a filling bag filling port (5) and a filling bag venting port (2), and the upper part of the filling mold bag (1) is provided with a mining filling pipe (4) and a mining filling venting pipe (3) that penetrate the entire filling mold bag (1).
2. The side-filled bag-type isolation device according to claim 1, characterized in that, The longitudinal section of the filling mold bag (1) is a right trapezoid. The filling port (5) and the venting port (2) of the filling bag are opened on the inclined side of the filling mold bag (1). The mining filling pipe (4) and the mining filling venting pipe (3) both penetrate from the inclined side of the filling mold bag (1) to the straight side of the filling mold bag (1).
3. The side-filled bag-type isolation device according to claim 2, characterized in that, The bottom of the inclined side of the filling mold bag (1) is provided with a filling bag fixing hole (6).
4. The side-filled bag-type isolation device according to claim 2, characterized in that, The mining tunnel filling pipe (4) is located on the centerline of the inclined plane.
5. A side-filled bag-type isolation device according to claim 4, characterized in that, There are two mining tunnel filling and exhaust pipes (3), which are symmetrically arranged on both sides of the mining tunnel filling pipe (4).