A settlement monitoring point fixing structure for construction of a railway culvert

By combining anchoring seats, bearing seats, and transmission rods, the problem of uneven settlement between culverts and railway subgrade and foundation soil was solved, enabling synchronous transmission and multi-dimensional monitoring of settlement data, and improving the accuracy and completeness of monitoring data.

CN225015916UActive Publication Date: 2026-11-24SINOHYRDO ENG BUREAU 3 CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202620028343.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2026-01-12
Publication Date
2026-11-24
Estimated Expiration
2036-01-12

AI Technical Summary

Technical Problem

The existing fixed structure of the monitoring point cannot synchronously transmit the coordinated deformation of the culvert, railway subgrade and foundation soil, resulting in delayed or distorted settlement data.

Method used

The system employs a combination structure of anchoring seat, bearing seat, and transmission rod. The anchoring seat penetrates deep into the foundation soil through barbs and anchoring wings. The bearing seat is integrated with the anchoring seat. The outer buffer layer of the transmission rod absorbs vibration energy, and the positioning cone scale reflects displacement changes.

Benefits of technology

It enables the synchronous transmission of settlement deformation of culverts and foundation, reduces vibration interference, improves the authenticity and completeness of monitoring data, and reduces monitoring errors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225015916U_ABST
    Figure CN225015916U_ABST
Patent Text Reader

Abstract

This utility model discloses a settlement monitoring point fixing structure for railway culvert construction, relating to the field of railway construction technology. It includes an anchoring seat, which is columnar with a slot fixed at its top and anchoring wings fixed on both sides, each wing having barbs fixed on its sides. The bearing seat provided by this utility model is tightly fitted to the inner wall of the anchoring seat through a reinforcing plate in the through-hole of the boss, forming an integrated connection between the anchoring seat and the bearing seat. This ensures that the settlement deformation of the culvert and its foundation can be synchronously transmitted to the bearing seat. The buffer layer on the outside of the transmission rod absorbs construction vibration energy, preventing gaps between the transmission rod and the through-hole caused by vibration. Furthermore, the graphite lubricating layer on the inside of the buffer layer reduces the frictional resistance of the transmission rod as it moves with the settlement, ensuring smooth transmission of deformation and effectively reducing vibration interference with settlement data transmission, thus improving the accuracy of monitoring data.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of railway construction technology, specifically to a settlement monitoring point fixing structure for construction of culverts crossing railways. Background Technology

[0002] During the construction of culverts crossing railways, the junction between the culvert and the railway subgrade, as well as the joints of culvert sections and the foundation soil, are prone to uneven settlement due to construction disturbances, directly affecting railway operational safety. Existing monitoring point fixing structures are mostly independently installed on the culvert surface or the top of the subgrade, forming a rigid detachment from the culvert and the foundation soil. This prevents the synchronous transmission of coordinated deformation among the three, and construction vibrations can easily cause gaps between the fixing structure and the monitored object, resulting in delayed or distorted settlement data. Utility Model Content

[0003] In view of the problems existing in the fixed structure of settlement monitoring points for construction of culverts crossing railways, this utility model is proposed.

[0004] Therefore, the purpose of this utility model is to provide a fixed structure for settlement monitoring points during the construction of culverts crossing railways, which solves the problem that the joint between the culvert and the railway subgrade, the joint of the culvert section, and the foundation soil are prone to uneven settlement due to construction disturbance.

[0005] To achieve the above objectives, this utility model provides the following technical solution: A settlement monitoring point fixing structure for construction of a railway culvert includes an anchor seat, which is columnar. A slot is fixedly opened on the top of the anchor seat, and anchor wings are fixedly provided on both sides of the anchor seat. Barbs are fixedly provided on both sides of the anchor wings. A bearing seat is provided on the inner side wall of the anchor seat. A boss is fixedly provided on one side and the top of the bearing seat. A through hole is fixedly provided on one side of the boss and the top of the bearing seat. A reinforcing plate is fixedly provided in one of the through holes. One side of the reinforcing plate is attached to the inner wall of the anchor seat. A transmission rod is provided in the other through hole. A buffer layer is fixedly provided on the outer side wall of the transmission rod.

[0006] Preferably, the outer wall of the anchor seat is fixedly provided with two fixing rings, and a positioning cone is slidably provided inside the two fixing rings.

[0007] Preferably, the outer wall of the positioning cone is fixedly provided with scale lines.

[0008] Preferably, reinforcing ribs are fixed on both sides of the anchoring wing.

[0009] Furthermore, the barbs and anchoring wings are arranged at obtuse angles.

[0010] Preferably, a graphite lubricating layer is fixedly provided on the inner wall of the buffer layer.

[0011] The technical effects and advantages provided by this utility model in the above technical solution are as follows: 1. In this utility model, the bearing seat is tightly fitted to the inner wall of the anchor seat through the reinforcing plate in the through hole of the boss, forming an integrated connection between the anchor seat and the bearing seat. This ensures that the settlement deformation of the culvert and the foundation can be transmitted to the bearing seat synchronously. The buffer layer on the outside of the transmission rod can absorb the construction vibration energy and avoid the vibration causing gaps between the transmission rod and the through hole. In addition, the graphite lubricating layer on the inside of the buffer layer can reduce the frictional resistance when the transmission rod moves with the settlement, ensuring that the transmission rod smoothly transmits deformation, effectively reducing the interference of vibration on the transmission of settlement data, and improving the authenticity of monitoring data.

[0012] 2. In this utility model, the anchoring seat adopts a columnar structure with barbed anchoring wings on both sides. The barbs and anchoring wings form an obtuse angle. The barbs can penetrate deep into the foundation soil to prevent the anchoring seat from loosening or shifting due to construction disturbance. At the same time, the reinforcing ribs on both sides of the anchoring wings can enhance the load-bearing and deformation resistance of the anchoring wings, avoid damage to the anchoring wings due to soil compression, and enable the anchoring seat to be stably buried in the foundation soil below the culvert. This provides a stable benchmark support for settlement monitoring and reduces monitoring errors caused by foundation instability of the monitoring point.

[0013] 3. In this utility model, the fixing ring on the outer wall of the anchoring seat plays a guiding and limiting role for the positioning cone, so that the positioning cone can be stably inserted into the surrounding soil. The scale line on the outer side of the positioning cone can intuitively reflect the displacement change of the positioning cone. Not only can the vertical settlement of the culvert and the foundation be monitored through the anchoring seat, bearing seat and transmission rod, but the scale of the positioning cone can also be used to help judge the lateral or vertical deformation of the surrounding soil. This makes up for the limitation of traditional monitoring that only focuses on a single part and improves the completeness and reference value of the monitoring data. Attached Figure Description

[0014] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in this utility model. For those skilled in the art, other drawings can be obtained based on these drawings.

[0015] Figure 1 This is a three-dimensional structural diagram of the present invention; Figure 2 For the present utility model Figure 1 Enlarged schematic diagram of part A; Figure 3 This is a schematic diagram of the internal structure of the transmission rod of this utility model.

[0016] Explanation of reference numerals in the attached figures: 1. Anchor seat; 2. Slot; 3. Anchor wing; 4. Barb; 5. Bearing seat; 6. Boss; 7. Through hole; 8. Reinforcing plate; 9. Conducting rod; 10. Buffer layer; 11. Fixing ring; 12. Positioning cone; 13. Scale line; 14. Reinforcing rib; 15. Graphite lubricating layer. Detailed Implementation

[0017] To enable those skilled in the art to better understand the technical solution of this utility model, the present utility model will be further described in detail below with reference to the accompanying drawings.

[0018] This utility model discloses a settlement monitoring point fixing structure for construction of culverts crossing railways.

[0019] This utility model provides, for example Figure 1-3The settlement monitoring point fixing structure shown includes an anchor seat 1, which is columnar. A slot 2 is fixedly provided at the top of the anchor seat 1. Anchor wings 3 are fixedly provided on both sides of the anchor seat 1, and barbs 4 are fixedly provided on both sides of the anchor wings 3. A bearing seat 5 is provided on the inner wall of the anchor seat 1. A boss 6 is fixedly provided on one side and at the top of the bearing seat 5. A through hole 7 is fixedly provided on one side of the boss 6 and at the top of the bearing seat 5. A reinforcing plate 8 is fixedly provided in one of the through holes 7, with one side of the reinforcing plate 8 fitting against the inner wall of the anchor seat 1. A transmission rod 9 is provided in the other through hole 7, and a buffer layer 10 is fixedly provided on the outer wall of the transmission rod 9. First, the foundation fixing and benchmark establishment of the monitoring point are completed, and the columnar anchor seat 1 is... The anchoring wings 3 on both sides of the anchoring seat 1 are embedded in the soil beneath the culvert. The barbs 4 on both sides of the anchoring wings 3, set at an obtuse angle to the anchoring wings 3, penetrate deep into the soil to create a gripping effect, preventing the anchoring seat 1 from loosening or shifting due to construction disturbance or soil settlement. Simultaneously, the reinforcing ribs 14 on both sides of the anchoring wings 3 enhance their own deformation resistance, preventing breakage due to soil compression and ensuring the anchoring seat 1 remains stable, providing reliable benchmark support for subsequent settlement monitoring. Secondly, a settlement deformation transmission path is constructed. The bearing seat 5 on the inner wall of the anchoring seat 1 is tightly fitted to the inner wall of the anchoring seat 1 through a reinforcing plate 8 in the through hole 7 on one side of the boss 6. The reinforcing plate 8 provides fixation and support for the bearing seat 5. This design integrates the bearing seat 5 and the anchor seat 1 into a single structure. When the foundation soil settles, the settlement displacement of the anchor seat 1 can be directly transmitted to the bearing seat 5 through the reinforcing plate 8. When the culvert itself deforms due to construction disturbance or soil settlement, the contact surface between the inner wall of the culvert and the bearing seat 5 will also transmit the culvert deformation to the bearing seat 5. At this time, the transmission rod 9 inside the through hole 7 of the top boss 6 of the bearing seat 5 will undergo vertical displacement synchronously with the settlement of the bearing seat 5, realizing the direct transmission of the settlement deformation of the foundation and culvert to the transmission rod 9. The buffer layer 10 on the outside of the transmission rod 9 can absorb the vibration energy generated during construction, preventing the vibration from causing a gap between the transmission rod 9 and the through hole 7. The graphite lubrication layer 15 on the inside of the buffer layer 10 can reduce the impact between the transmission rod 9 and the buffer layer 15 when the transmission rod 9 moves with the settlement. The frictional resistance of the 10th layer ensures that the transmission rod 9 can smoothly and accurately reflect the settlement displacement. Finally, to expand the monitoring dimensions and assist in data reading, the two fixing rings 11 on the outer wall of the anchoring seat 1 guide and limit the positioning cone 12, so that the positioning cone 12 can be stably inserted into the surrounding soil of the culvert. When the surrounding soil settles or deforms laterally, the positioning cone 12 will slide along the fixing ring 11 with the soil displacement. The scale line 13 on the outer wall of the positioning cone 12 can intuitively display the displacement change of the positioning cone 12. The staff can read the data of the scale line 13 to help judge the deformation of the surrounding soil. Combined with the settlement data of the culvert and the foundation reflected by the transmission rod 9, a multi-dimensional settlement monitoring system is formed to fully grasp the settlement status of the construction area of ​​the railway culvert.

[0020] For easy location, such as Figure 1 As shown, two fixing rings 11 are fixedly provided on the outer wall of the anchor seat 1, and a positioning cone 12 is slidably provided inside the two fixing rings 11.

[0021] To make it easier to read the scale, such as Figure 1 As shown, the outer wall of the positioning cone 12 is fixed with a scale line 13.

[0022] And for easier support, such as Figure 1 As shown, reinforcing ribs 14 are fixed on both sides of the anchoring wing 3.

[0023] Finally, for easier use, such as Figure 1-3 As shown, the barbs 4 and the anchoring wing 3 are set at an obtuse angle, and the inner wall of the buffer layer 10 is fixed with a graphite lubricating layer 15.

[0024] The foregoing description only illustrates certain exemplary embodiments of the present invention. Undoubtedly, those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the above drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.

Claims

1. A settlement monitoring point fixing structure for construction of a railway culvert, comprising an anchoring seat (1), characterized in that, The anchoring seat (1) is columnar. A slot (2) is fixedly opened on the top of the anchoring seat (1). An anchoring wings (3) are fixedly provided on both sides of the anchoring seat (1). Barbs (4) are fixedly provided on both sides of the anchoring wings (3). A bearing seat (5) is provided on the inner wall of the anchoring seat (1). A boss (6) is fixedly provided on one side and the top of the bearing seat (5). A through hole (7) is fixedly provided on one side of the boss (6) and the top of the bearing seat (5). A reinforcing plate (8) is fixedly provided in one of the through holes (7). One side of the reinforcing plate (8) is attached to the inner wall of the anchoring seat (1). A transmission rod (9) is provided in the other through hole (7). A buffer layer (10) is fixedly provided on the outer wall of the transmission rod (9).

2. The settlement monitoring point fixing structure for construction of a railway culvert according to claim 1, wherein The anchor seat (1) has two fixing rings (11) fixed on its outer side wall, and a positioning cone (12) is slidably provided inside the two fixing rings (11).

3. The settlement monitoring point fixing structure for construction of a railway culvert according to claim 2, characterized in that, The outer wall of the positioning cone (12) is fixed with a scale line (13).

4. The settlement monitoring point fixing structure for construction of a railway culvert according to claim 1, characterized in that, The anchoring wing (3) is fixed with reinforcing ribs (14) on both sides.

5. The settlement monitoring point fixing structure for construction of a railway culvert according to claim 1, characterized in that, The barbs (4) and anchoring wings (3) are set at an obtuse angle.