Combined anti-seismic support and hanger with multiple reinforcement structures
By employing a dual locking mechanism of positioning bolts and limit screws, along with an equidistant positioning hole design, the problem of traditional supports and hangers being prone to failure under vibration conditions is solved, achieving stability and flexibility of the load-bearing point and improving installation efficiency and adaptability.
Patent Information
- Application Number
- CN202522599485.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-08
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-08
AI Technical Summary
Traditional supports and hangers rely on the locking force of a single bolt or clamp, which is prone to failure under vibration or earthquake, leading to displacement or detachment of the load-bearing point. Furthermore, the adjustment of the load-bearing point position is inflexible, making it difficult to meet the precise installation requirements of complex pipeline layouts.
It adopts a dual locking mechanism of vertical positioning with positioning bolts and horizontal clamping with limiting screws, combined with equidistant positioning holes and slider groove design, to provide multiple reinforcement structures, ensuring the stability and flexible adjustment of the load-bearing point under vibration environment.
It improves the seismic performance and installation efficiency of supports and hangers, prevents the load-bearing points from falling off, enables rapid positioning and flexible adjustment of the load-bearing points, eliminates the need for secondary drilling on site, and adapts to complex pipeline layouts.
Smart Images

Figure CN225015941U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of support and hanger technology, specifically relating to a combined seismic support and hanger with multiple reinforcement structures. Background Technology
[0002] In building electromechanical engineering, support and hanger systems are used to suspend and fix equipment such as pipes, air ducts, and cable trays, and are a key guarantee for their safe and stable operation. Especially in earthquake-prone areas, the seismic performance of supports and hangers is of paramount importance.
[0003] Existing traditional supports or some simple combined supports typically use channel steel as the main load-bearing beam, and fix the load-bearing points to the channel steel by clamps or bolts;
[0004] Traditional fixing methods often rely on the locking force of a single bolt or clamp. Under long-term vibration or sudden earthquakes, a single locking point is prone to failure due to fatigue or excessive impact force, leading to relative displacement or even separation between the load-bearing point and the main beam. This can cause pipeline equipment to fall, resulting in serious safety accidents. Furthermore, the position adjustment of the load-bearing point is not flexible enough, usually requiring precise measurement and drilling, which is a cumbersome process. The hole positions are fixed and cannot be fine-tuned, making it difficult to meet the precise installation requirements of complex pipeline layouts. Therefore, we propose a combined seismic bracing system with multiple reinforcement structures. Utility Model Content
[0005] To address the issues raised in the background section regarding traditional fixing methods that often rely on the locking force of a single bolt or clamp, which can easily fail under long-term vibration or sudden earthquakes due to fatigue or excessive impact, leading to relative displacement or even detachment between the load-bearing point and the main beam, potentially causing pipeline equipment to fall and resulting in serious safety accidents, this invention provides a combined seismic bracing system with multiple reinforcement structures.
[0006] To achieve the above objectives, this utility model provides the following technical solution: a combined seismic bracing system with multiple reinforcement structures, including a hanging plate, wherein multiple positioning holes are equidistantly opened on the upper surface of the hanging plate along the length direction, a lifting block is sleeved on the outside of the hanging plate through a slot, the lifting block is connected to the corresponding positioning hole on the hanging plate through positioning bolts, and an installation block is detachably installed below the lifting block;
[0007] Both ends of the lifting plate are provided with reserved grooves, and a slider is movably installed in the reserved groove. One end of the slider is provided with a threaded hole, and a limit screw is screwed into the threaded hole. The slider can slide to a position adjacent to the side of the lifting block, and the end of the slider is pressed against the side of the lifting block by tightening the limit screw.
[0008] As a preferred embodiment of the combined seismic bracing system with multiple reinforcement structures of this utility model, both ends of the hanging plate are equipped with mounting blocks. One of the mounting blocks is pre-welded to the hanging plate, and the other mounting block is detachably fixed to the hanging plate by a threaded pin.
[0009] As a preferred embodiment of the combined seismic bracing system with multiple reinforcement structures of this utility model, each of the mounting blocks is fixed with a shock-absorbing block above it, and a positioning block is horizontally fixed on the shock-absorbing block. The positioning block is provided with mounting holes for connection with the building structure.
[0010] As a preferred embodiment of the combined seismic bracing system with multiple reinforcement structures of this utility model, the lifting block is provided with a slot that matches the cross-sectional shape of the hanging plate, and the lifting block is sleeved on the hanging plate through the slot.
[0011] As a preferred embodiment of the combined seismic bracing system with multiple reinforcement structures of this utility model, positioning plates are fixed on both sides of the mounting block, and the positioning plates are detachably connected to the upper mounting block by bolts passing through the positioning plates.
[0012] As a preferred embodiment of the combined seismic bracing system with multiple reinforcement structures of this utility model, the slider forms a sliding engagement connection with the groove on the reserved groove wall.
[0013] As a preferred embodiment of the combined seismic bracing system with multiple reinforcement structures of this utility model, there are multiple lifting blocks and sliders, and each lifting block can be clamped and limited on both sides by two sliders through limiting screws.
[0014] Compared with the prior art, the beneficial effects of this utility model are as follows: This application effectively solves the problem of easy failure of single-point fixing of traditional supports and hangers by combining the vertical positioning of the positioning bolts and the horizontal clamping of the limiting screws. Even if the vertical positioning bolts loosen under strong vibration, the horizontal limiting screws can still firmly hold the lifting block to prevent its displacement and fall off, with high safety redundancy. The combination of the pre-set equidistant positioning holes on the hanging plate and the standardized lifting block allows the bearing point to be quickly positioned, combined and adjusted at any pre-set hole position on the hanging plate according to actual needs, without the need for secondary drilling on site, which greatly improves the installation efficiency and flexibility. The sliding engagement design of the slider and the groove in the reserved slot ensures that the reinforcing component itself will not fall off the main structure. After installation, the slider slides to both sides of the lifting block and locks, forming a clamping constraint on the lifting block, providing active anti-fall-off protection, and preventing the problems of insufficient seismic reliability and poor positioning flexibility and low accuracy of traditional fixing methods. Attached Figure Description
[0015] The accompanying drawings are provided to further illustrate the present invention and form part of the specification. They are used together with the embodiments of the present invention to explain the present invention, but do not constitute a limitation thereof. In the drawings:
[0016] Figure 1 This is a schematic diagram of the overall structure of this utility model;
[0017] Figure 2 This is a schematic diagram of the connection structure between the lifting plate and the lifting block of this utility model;
[0018] Figure 3 This is a schematic diagram of the lifting block of this utility model;
[0019] Figure 4 This is a schematic diagram of the front and back structures of the hanging plate of this utility model.
[0020] In the diagram: 1. Hanging plate; 2. Set block; 3. Shock-absorbing block; 4. Positioning block; 5. Lifting block; 6. Mounting block; 7. Positioning plate; 8. Positioning hole; 9. Positioning bolt; 10. Reserved groove; 11. Sliding block; 12. Threaded hole; 13. Limiting screw; 14. Slot. Detailed Implementation
[0021] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.
[0022] Example 1
[0023] like Figures 1-4 As shown;
[0024] A combined seismic bracing system with multiple reinforcement structures includes a hanging plate 1. Multiple positioning holes 8 are equidistantly spaced along the length of the upper surface of the hanging plate 1. A lifting block 5 is fitted onto the outside of the hanging plate 1 via a slot 14. The lifting block 5 is connected to the corresponding positioning holes 8 on the hanging plate 1 via positioning bolts 9. An installation block 6 is detachably installed below the lifting block 5. Both ends of the hanging plate 1 have reserved grooves 10. A slider 11 is movably installed within the reserved grooves 10. One end of the slider 11 has a threaded hole 12, within which a limiting screw 13 is screwed. The slider 11 can slide to a position adjacent to the side of the lifting block 5, and its end is pressed against the side of the lifting block 5 by tightening the limiting screw 13.
[0025] In this implementation plan, the dual locking mechanism, combining vertical positioning of the positioning bolt 9 with horizontal clamping of the limiting screw 13, effectively solves the problem of easy failure of single-point fixing of traditional supports and hangers. Even if the vertical positioning bolt 9 loosens under strong vibration, the horizontal limiting screw 13 can still firmly hold the lifting block 5, preventing its displacement and fall off, thus providing high safety redundancy. The pre-set equidistant positioning holes 8 on the hanging plate 1, combined with the standardized lifting block 5, allow the load-bearing point to be quickly positioned, combined, and adjusted at any pre-set hole position on the hanging plate 1 according to actual needs, without the need for secondary drilling on site, greatly improving installation efficiency and flexibility. The sliding engagement design of the slider 11 and the groove in the reserved slot 10 ensures that the reinforcing component itself will not fall off the main structure. After installation, the slider 11 slides to both sides of the lifting block 5 and locks, forming a clamping constraint on the lifting block 5, providing active anti-fall-off protection.
[0026] In an optional embodiment, mounting blocks 2 are installed at both ends of the hanging plate 1. One mounting block 2 is pre-welded to the hanging plate 1, while the other mounting block 2 is detachably fixed to the hanging plate 1 by means of a threaded pin.
[0027] In this implementation plan: pre-welding ensures the permanent stability and structural strength of the connection at one end of the main frame of the support and hanger, providing a solid foundation for the whole. The detachable design at the other end gives the support and hanger excellent installation flexibility. In narrow or complex spaces, one end of the hanging plate 1 can be fixed first, and then the other end can be connected by fitting the mounting block 2, which greatly facilitates on-site construction and solves the problem of inconvenient installation of the overall welded structure.
[0028] In an optional embodiment, a shock-absorbing block 3 is fixed above each of the mounting blocks 2, and a positioning block 4 is horizontally fixed on the shock-absorbing block 3. The positioning block 4 has mounting holes for connection with the building structure.
[0029] In this implementation plan, the shock absorber 3 can effectively absorb and buffer the vibration energy from the building structure, preventing this energy from being directly transmitted to the hanging plate 1 and the pipeline equipment it carries, thus playing a positive role in seismic protection.
[0030] In an optional embodiment, the lifting block 5 is provided with a slot 14 that matches the cross-sectional shape of the lifting plate 1, and the lifting block 5 is fitted onto the lifting plate 1 through the slot 14.
[0031] In this implementation plan, the "clamp-type" connection enables stepless adjustment and rapid positioning of the lifting block 5 along the length of the hanging plate 1. During installation, workers can easily slide the lifting block 5 to any desired position and then tighten it, solving the problems of traditional supports and hangers requiring pre-drilling and inflexible positioning, greatly improving installation efficiency and adaptability to complex pipeline layouts.
[0032] In an optional embodiment, positioning plates 7 are fixed on both sides of the mounting block 6, and the positioning plates 7 are detachably connected to the lifting block 5 above by bolts passing through the positioning plates 7.
[0033] In this implementation plan, the mounting block 6 and the lifting block 5 are detachably connected by the positioning plate 7 and bolts, making the load-bearing mounting block 6 an independent modular unit that can be replaced according to the specifications of the pipes or equipment it supports. This achieves functional diversification and facilitates later maintenance and adjustment. If the mounting block 6 needs to be replaced or repaired, only the bolts need to be loosened, without disassembling the entire lifting block 5, which greatly reduces maintenance costs and time.
[0034] In an optional embodiment, the slider 11 forms a sliding engagement connection with the groove on the wall of the reserved groove 10.
[0035] In this implementation scheme: the sliding engagement connection provides a stable movement trajectory for the slider 11, so that it is subjected to uniform force when tightening the lifting block 5, and will not deflect or twist, thereby ensuring the effectiveness and reliability of the horizontal limiting reinforcement.
[0036] In an optional embodiment, there are multiple lifting blocks 5 and sliders 11, and each lifting block 5 can be clamped and limited on both sides by two sliders 11 through limiting screws 13.
[0037] In this implementation plan, the support and hanger system is highly configurable. Multiple independent bearing points can be flexibly installed on the hanging plate 1 according to the actual number and distribution of pipelines. Each bearing point can obtain the same and independent double reinforcement effect through the sliders 11 on both sides.
[0038] Working principle:
[0039] First, one end of the hanging plate 1 is connected to a pre-welded mounting block 2. According to the layout requirements of the equipment to be suspended, such as pipes and cables, the position of the lifting block 5 in the length direction of the hanging plate 1 is determined. The lifting block 5 is provided with a slot 14 that matches the cross-sectional shape of the hanging plate 1, so that it can be directly clipped onto the hanging plate 1 from the side. Multiple positioning holes 8 are equidistantly arranged along the upper surface of the hanging plate 1 to provide discrete positioning points for the lifting block 5. After the lifting block 5 is slid to the predetermined position, the positioning bolt 9 is passed through the screw hole of the lifting block 5 and screwed into the corresponding positioning hole 8 to achieve the initial position fixation of the lifting block 5 on the hanging plate 1.
[0040] Below the initially fixed hoisting block 5, the mounting block 6 is detachably installed. The mounting block 6 directly supports equipment such as pipes and air ducts. Positioning plates 7 are fixed on both sides of the mounting block 6. The positioning plates 7 are fixed relative to the hoisting block 5 above by bolts, so as to stably transfer the mounting block 6 and the load it bears to the hoisting block 5 and the hoisting plate 1.
[0041] Pre-reserved slots 10 are provided on both ends of the hanging plate 1. Multiple sliders 11 are movably installed in each pre-reserved slot 10 and can slide along the length of the pre-reserved slot 10. After all the hanging blocks 5 are installed and initially fixed in place, the sliders 11 are slid from one end of the pre-reserved slot 10 to both sides of the hanging block 5 so that they are close to the hanging block 5. The limiting screws 13 are screwed into the threaded holes 12 until their ends press against the side of the hanging block 5. Through the combined action of the limiting screws 13 on both sides of the sliders 11, the hanging block 5 is clamped and limited in the horizontal direction. This dual positioning effectively prevents the hanging block 5 from loosening, slipping or even falling off in the vibration environment, and greatly improves the overall seismic performance of the support.
[0042] After installation, another mounting block 2 is inserted from the other end of the hanging plate 1 and fixed with threaded pins to form a stable installation base beam. A shock-absorbing block 3 is installed above each mounting block 2, and a positioning block 4 is horizontally fixed on the shock-absorbing block 3. By using bolts to pass through the holes on the positioning block 4, the entire support frame is firmly installed on the required position on the building structure, thus completing the suspension and fixing of the main body of the support.
[0043] Finally, it should be noted that the above description is merely a preferred embodiment of this utility model and is not intended to limit the utility model. Although the utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this utility model should be included within the protection scope of this utility model.
Claims
1. A combined seismic bracing system with multiple reinforcement structures, comprising a suspension plate (1), characterized in that: The upper end face of the hanging plate (1) is provided with a plurality of positioning holes (8) at equal intervals along the length direction. The hanging plate (1) is fitted with a lifting block (5) through a slot (14). The lifting block (5) is connected to the corresponding positioning hole (8) on the hanging plate (1) through a positioning bolt (9). An installation block (6) is detachably installed below the lifting block (5). Both ends of the lifting plate (1) are provided with reserved grooves (10). A slider (11) is movably arranged in the reserved groove (10). One end of the slider (11) is provided with a threaded hole (12). A limiting screw (13) is screwed into the threaded hole (12). The slider (11) can slide to a position adjacent to the side of the lifting block (5) and tighten the limiting screw (13) so that its end is pressed against the side of the lifting block (5).
2. The combined seismic bracing system with multiple reinforcement structures according to claim 1, characterized in that: Both ends of the hanging plate (1) are equipped with mounting blocks (2). One of the mounting blocks (2) is pre-welded to the hanging plate (1), while the other mounting block (2) is detachably fixed to the hanging plate (1) by means of a threaded pin.
3. The combined seismic bracing system with multiple reinforcement structures according to claim 2, characterized in that: Each of the assembly blocks (2) is fixed with a shock-absorbing block (3) on top, and a positioning block (4) is horizontally fixed on the shock-absorbing block (3). The positioning block (4) has an installation hole for connecting with the building structure.
4. The combined seismic bracing system with multiple reinforcement structures according to claim 1, characterized in that: The hoisting block (5) has a slot (14) that matches the cross-sectional shape of the hoisting plate (1), and the hoisting block (5) is fitted onto the hoisting plate (1) through the slot (14).
5. The combined seismic bracing system with multiple reinforcement structures according to claim 1, characterized in that: Positioning plates (7) are fixed on both sides of the mounting block (6). The positioning plates (7) are detachably connected to the lifting block (5) above by bolts passing through them.
6. The combined seismic bracing system with multiple reinforcement structures according to claim 1, characterized in that: The slider (11) and the groove on the wall of the reserved groove (10) form a sliding engagement connection.
7. The combined seismic bracing system with multiple reinforcement structures according to claim 1, characterized in that: There are multiple lifting blocks (5) and sliders (11). Each lifting block (5) can be clamped and limited on both sides by two sliders (11) through limiting screws (13).