Tube bundle type container hydrogen supply pressure reducing device
By employing a redundant design of dual gas supply pipelines, a staged pressure reduction system, and a dual-branch layout for nitrogen purging, the continuity and safety issues of hydrogen supply in continuous production scenarios of existing hydrogen supply pressure reduction devices have been resolved, achieving a safe and stable hydrogen supply process.
Patent Information
- Application Number
- CN202522830315.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-31
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-31
AI Technical Summary
Existing hydrogen supply and pressure reduction devices have poor hydrogen supply continuity in continuous production scenarios, limited nitrogen purging coverage, and imprecise safety protection component layout, posing safety hazards.
It adopts a dual gas supply pipeline redundancy design, a staged pressure reducing valve in parallel, a nitrogen purging dual-branch layout, a precise arrangement of emergency shut-off valve, hydrogen filter and check valve, and configuration of total output pipeline and pressure detection components.
It has achieved safe, stable and continuous operation of the hydrogen supply process, and improved the safety protection capability of the device and the controllability of the hydrogen supply quality.
Smart Images

Figure CN225016259U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of hydrogen supply equipment technology, and in particular to a tubular container hydrogen supply depressurization device. Background Technology
[0002] As a clean secondary energy source, hydrogen energy's development and utilization have become an important direction for promoting energy structure transformation. In the storage and transportation of hydrogen, high-pressure tubular containers are currently one of the mainstream methods. The key to achieving end-use is to safely, stably, and continuously supply high-pressure hydrogen to hydrogen-using facilities under reduced pressure. This process relies on a dedicated hydrogen supply and pressure reduction device, which must perform multi-stage pressure reduction, pipeline purification, leak protection, and precise pressure control of high-pressure hydrogen under extremely high safety standards.
[0003] Currently, most common hydrogen supply pressure reducing devices employ a single-line gas supply combined with a series of pressure reducing valves, and integrate nitrogen purging functionality into the pipeline to replace air and prevent explosions. However, this existing technology still has significant shortcomings in practical applications: First, the single-line gas supply structure lacks redundancy; when a single pressure reducing valve fails or the pipeline requires maintenance, the entire system must be shut down, severely impacting the continuity of hydrogen supply and failing to meet the needs of continuous production scenarios. Second, nitrogen purging pipelines are typically simply designed with limited purging coverage, easily leaving hydrogen residues at complex pipeline nodes or within valve cavities, creating safety hazards. Third, the placement of safety protection components (such as emergency shut-off, filtration, and backflow prevention) often fails to precisely match the pipeline pressure levels and operating procedures, potentially leading to delayed or ineffective protection. Therefore, there is an urgent need for a bundled containerized hydrogen supply pressure reducing device with higher reliability, more thorough purging capabilities, and more refined safety protection. Utility Model Content
[0004] To address the shortcomings of existing technologies, the purpose of this invention is to provide a tubular container hydrogen supply and depressurization device that features continuous hydrogen supply, precise depressurization, safety protection, and efficient purging.
[0005] The above-mentioned utility model objective is achieved through the following technical solution:
[0006] A tubular container hydrogen supply pressure reducing device includes: a first gas supply line and a second gas supply line; the input ends of the first gas supply line and the second gas supply line are both used to connect to the tubular container, and the input ends are each equipped with a disconnect valve in series.
[0007] The first gas supply line and the second gas supply line are each equipped with a first-stage pressure reducing valve and a second-stage pressure reducing valve connected in series; the output ends of the two second-stage pressure reducing valves merge to form a merged line, and the merged line is equipped with two independent third-stage pressure reducing valves connected in parallel;
[0008] A nitrogen purging device, comprising a first nitrogen branch and a second nitrogen branch; the first nitrogen branch is connected to the first gas supply line and the second gas supply line respectively; the second nitrogen branch is connected to the confluence line.
[0009] The above technical solution employs a redundant dual-supply pipeline design. The input-end disconnect valve can quickly cut off the gas supply and prevent leakage in the event of accidental pipeline pulling. The primary and secondary pressure reducing valves reduce pressure in stages, achieving stable control of hydrogen pressure. Two independent tertiary pressure reducing valves are connected in parallel in the merged pipeline, enabling "one for use and one for backup." In the event of a single failure, there is no need to shut down the unit for switching, improving the reliability of continuous operation. The nitrogen purging device has two branches connected to the dual-supply pipeline and the merged pipeline respectively, which can purge critical pipeline sections to prevent residual hydrogen from mixing with air to form an explosive mixture, ensuring the safety of unit start-up, shutdown, and maintenance.
[0010] As a further technical solution of this utility model: an emergency shut-off valve is connected in series on both the first gas supply pipeline and the second gas supply pipeline, and the emergency shut-off valve is located between the pull-off valve and the first-stage pressure reducing valve.
[0011] By adding an emergency shut-off valve between the breakaway valve and the first-stage pressure reducing valve through the above technical solution, the upstream gas source can be quickly cut off in case of sudden situations such as abnormal pipeline pressure or leakage, so as to avoid high-pressure hydrogen impacting the downstream pressure reducing components, improve the safety protection level of the device, and reduce the risk of accident expansion.
[0012] As a further technical solution of this utility model: a hydrogen filter is connected in series on both the first gas supply pipeline and the second gas supply pipeline, and the hydrogen filter is located between the emergency shut-off valve and the first-stage pressure reducing valve.
[0013] By using the above technical solution, a hydrogen filter is installed between the emergency shut-off valve and the first-stage pressure reducing valve. This filter can remove impurities such as solid particles from the hydrogen, preventing impurities from causing wear and jamming of the pressure reducing valve core, extending the service life of the pressure reducing valve, and ensuring stable pressure reduction accuracy while preventing pressure fluctuations caused by impurities clogging the valve.
[0014] As a further technical solution of this utility model: a check valve is connected in series on both the first gas supply pipeline and the second gas supply pipeline, and the check valve is located between the emergency shut-off valve and the hydrogen filter.
[0015] By placing the check valve between the emergency shut-off valve and the hydrogen filter using the above technical solution, it is possible to prevent downstream gas backflow from causing secondary pollution to the filter and pipeline; at the same time, it prevents external air backflow, ensures the purity of hydrogen in the pipeline, and avoids the safety hazards caused by hydrogen-air mixing.
[0016] As a further technical solution of this utility model: the output ends of the two three-stage pressure reducing valves are combined to form a total output pipeline, and the total output pipeline is provided with a nitrogen purging port for discharging the mixed gas after purging.
[0017] Through the above technical solution, the output ends of the two parallel three-stage pressure reducing valves are combined into a total output pipeline to ensure consistent hydrogen supply pressure. The total output pipeline is equipped with a nitrogen purging port, which can centrally discharge the hydrogen-nitrogen mixed gas, improve purging efficiency, simplify pipeline structure, and avoid the problems of pipeline complexity and incomplete purging caused by multiple purging ports.
[0018] As a further technical solution of this utility model, it also includes a pressure detection component, which is disposed on the main output pipeline.
[0019] By placing the pressure detection component on the main output pipeline, the final output pressure after three-stage pressure reduction can be accurately monitored, ensuring that the hydrogen supply pressure meets the standard. Relying on the structure of the main output pipeline, measurement errors caused by improper detection location are avoided, making it easier to detect and adjust pressure anomalies in a timely manner and improving the operational stability of the device.
[0020] In summary, this utility model has at least one of the following beneficial technical effects:
[0021] 1. This utility model discloses a tubular container hydrogen supply pressure reducing device, which achieves safe, stable and continuous operation of the hydrogen supply process through a redundant design of dual gas supply pipelines, staged pressure reduction and parallel setting of three-stage pressure reducing valves, and a nitrogen purging dual-branch layout.
[0022] 2. This utility model discloses a tubular container hydrogen supply pressure reducing device, which achieves rapid control of upstream gas source and ensures hydrogen cleanliness through the precise arrangement of emergency shut-off valve, hydrogen filter and check valve, thereby improving the device's safety protection capability.
[0023] 3. This utility model discloses a tubular container hydrogen supply pressure reduction device, which achieves unified output of hydrogen after pressure reduction and real-time pressure monitoring through the integration of the total output pipeline and the configuration of pressure detection components, ensuring stable and controllable hydrogen supply quality. Attached Figure Description
[0024] Figure 1 This is a connection diagram of a tubular container hydrogen supply and depressurization device according to the present invention.
[0025] Reference numerals in the attached diagram: 1. First gas supply line; 2. Second gas supply line; 3. Tube bundle container; 4. Breakaway valve; 5. Nitrogen purging device; 51. First nitrogen branch; 52. Second nitrogen branch; 6. Primary pressure reducing valve; 7. Secondary pressure reducing valve; 8. Tertiary pressure reducing valve; 9. Merging line; 10. Emergency shut-off valve; 11. Hydrogen filter; 12. Check valve; 13. Nitrogen purging port; 14. Pressure detection component. Detailed Implementation
[0026] The technical solutions in the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of this application without creative effort are within the scope of protection of this application.
[0027] In the description of this application, it should be noted that the terms "upper," "lower," "inner," "outer," "top / bottom," etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this application. Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance.
[0028] In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installed," "equipped with," "sleeved / connected," "connected," etc., should be interpreted broadly. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be a connection within two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.
[0029] Example 1:
[0030] Reference Figure 1 The present invention discloses a tubular container hydrogen supply pressure reducing device, which includes a first gas supply pipeline 1 and a second gas supply pipeline 2, which constitute two symmetrical and independent gas supply channels. The input ends of both pipelines are used to connect to the tubular container 3, and a breakaway valve 4 is connected in series at each input end. The breakaway valve 4 can automatically disconnect and seal when the pipeline is subjected to accidental mechanical pulling, forming the first physical anti-leakage barrier.
[0031] To ensure a smooth pressure transition and achieve redundant control, a primary pressure reducing valve 6 and a secondary pressure reducing valve 7 are connected in series on both the first gas supply line 1 and the second gas supply line 2. These two valves work together to perform initial graded pressure reduction. The outputs of the two secondary pressure reducing valves 7 converge into a manifold line 9, on which two independently operating tertiary pressure reducing valves 8 are connected in parallel. The inputs of both tertiary valves 8 are connected to the manifold line 9, and their outputs converge into the main output line. This allows for "one in use, one on standby" operation or parallel operation according to flow demand. Hydrogen supply does not need to be interrupted in the event of a single pressure reducing valve failure or maintenance, significantly improving gas supply continuity and system reliability.
[0032] To ensure operational safety during start-up, shutdown, maintenance, and leak handling, a nitrogen purging device 5 is also provided. This nitrogen purging device 5 includes a structurally independent first nitrogen branch 51 and a second nitrogen branch 52. The first nitrogen branch 51 is connected to both the first gas supply line 1 and the second gas supply line 2, enabling independent purging and replacement of each inlet branch. The second nitrogen branch 52 is connected to the merging line 9, purging the section of pipe from the merging point to the three-stage pressure reducing valve 8. This dual-branch, zoned purging design ensures thorough gas replacement of all critical pipes and cavities within the device, effectively preventing the formation of an explosive atmosphere by mixing hydrogen and air.
[0033] To further enhance safety and system cleanliness, an emergency shut-off valve 10 is connected in series between the break-off valve 4 and the primary pressure reducing valve 6 on the first gas supply line 1 and the second gas supply line 2. This emergency shut-off valve 10 can be quickly closed upon triggering by a control system command or an abnormal signal, providing a second, rapid, and active gas supply cut-off protection after the break-off valve 4 to prevent the accident from escalating.
[0034] Downstream of the emergency shut-off valve 10 and upstream of the primary pressure reducing valve 6, a hydrogen filter 11 (filtration accuracy 30μm) is also connected in series to filter out solid particles entrained in the hydrogen, protect the downstream precision pressure reducing valve assembly from wear and blockage, and ensure pressure reducing accuracy and valve life.
[0035] In addition, a check valve 12 is connected in series on the pipe section between the emergency shut-off valve 10 and the hydrogen filter 11. The check valve 12 can strictly restrict the airflow direction, allowing hydrogen to flow only from the tube bundle container side to the output side, preventing downstream gas or air backflow, avoiding contamination of the hydrogen filter 11 and upstream pipeline, and eliminating safety hazards caused by gas backflow.
[0036] The outputs of the two parallel three-stage pressure reducing valves 8 converge again to form a final total output pipeline, on which a centralized nitrogen purging port 13 is provided. During system-wide purging before shutdown or maintenance, this nitrogen purging port 13 serves as a unified outlet for the purging mixture, making purging more concentrated and efficient, and avoiding the problems of pipeline complexity and increased potential leak points caused by multiple discharge ports.
[0037] Meanwhile, a pressure detection component 14 is also installed on the main output pipeline to monitor the final hydrogen supply pressure after three-stage pressure reduction in real time and accurately, providing operators with intuitive pressure data, ensuring that the output pressure meets the requirements of hydrogen-using equipment, and promptly detecting pressure abnormalities to ensure the stability of hydrogen supply quality.
[0038] The working process of this utility model is as follows: First, refer to the right-side vehicle connection and pipeline replacement steps to complete the connection of the first gas supply pipeline 1, the second gas supply pipeline 2, and the tubular container 3. After checking the integrity of the filling pipe filling joint and the closed status of the right-side pipeline discharge valve, open the corresponding valve of the nitrogen purging device 5. Introduce nitrogen into the dual gas supply pipeline and the merging pipeline 9 through the first nitrogen branch 51 and the second nitrogen branch 52 respectively. After filling, close the nitrogen inlet valve and open the pipeline discharge valve. When the pipeline is under positive pressure, close the discharge valve. Repeat the above purging and replacement operation 3 times to ensure that the air in the pipeline is completely discharged. Then, slowly open the cylinder valve and the main pipeline valve of the tubular container 3, opening and closing the pipeline discharge valve 3 times to check for leaks at the filling port joint. If a leak is found, close the main valve, open the discharge valve to depressurize, tighten the joint, and pressurize again to check for leaks until the leak test is qualified. Then open all the cylinder valves of the tubular container 3 and connect... Customer personnel at the site confirm the pressure gauge readings of the tube bundle; then, pressure is regulated by adjusting the first-stage pressure reducing valve 6 to 1.5 MPa, the second-stage pressure reducing valve 7 to 1.0 MPa, and the third-stage pressure reducing valve 8 to 0.09 MPa. Hydrogen gas passes through the first gas supply line 1 or the second gas supply line 2 in sequence, passing through the disconnect valve 4, the emergency shut-off valve 10, the check valve 12, the hydrogen filter 11, the first-stage pressure reducing valve 6, and the second-stage pressure reducing valve 7. After being depressurized by one of the third-stage pressure reducing valves 8 through the manifold line 9, it is then merged into the main output line to supply hydrogen externally. During operation, the pressure detection component 14 monitors the pressure of the main output line in real time. If any abnormal pressure or leakage occurs, the emergency shut-off valve 10 quickly cuts off the upstream gas source. During start-up, shutdown, or maintenance of the unit, purging is performed through the first nitrogen branch 51 and the second nitrogen branch 52 of the nitrogen purging device 5. The purged mixed gas is discharged from the nitrogen purging port 13 to ensure operational safety.
[0039] The implementation principle of this utility model is as follows: The dual-path layout of the first gas supply pipeline 1 and the second gas supply pipeline 2, along with two independent three-stage pressure reducing valves 8 connected in parallel on the merging pipeline 9, based on the principle of redundancy, solves the shutdown problem caused by a single gas supply pipeline or three-stage pressure reducing valve 8 failure through the layout of the dual gas supply pipelines and dual pressure reducing components as backups for each other, ensuring continuous hydrogen supply; the graded pressure reducing system composed of the first-stage pressure reducing valve 6, the second-stage pressure reducing valve 7, and the third-stage pressure reducing valve 8 follows the principle of gradual fluid pressure decay. Through the coordinated action of multiple pressure reducing components, the high-pressure hydrogen is reduced to the target pressure in stages, avoiding airflow turbulence caused by single-stage pressure reduction and achieving stable pressure control; the first nitrogen branch 51 and the second nitrogen branch 52 of the nitrogen purging device 5, relying on the inert properties of nitrogen, respectively perform gas replacement on the dual gas supply pipelines and the merging pipeline 9, eliminating the explosion risk of residual hydrogen mixed with air by utilizing the principle of inert gas to isolate oxygen; the nitrogen purging on the total output pipeline... Based on the principle of centralized emission, valve 13 improves the efficiency of hydrogen-nitrogen mixed gas discharge; emergency shut-off valve 10 is located between breakaway valve 4 and first-stage pressure reducing valve 6, following the "source blocking" safety principle, quickly cutting off the high-pressure gas source in case of emergencies, preventing downstream pressure reducing valves from being damaged by high-pressure impact; hydrogen filter 11 is based on the principle of physical interception, blocking solid particulate impurities in hydrogen through the filter medium, preventing impurities from wearing or jamming the valve cores of various pressure reducing components, ensuring pressure reducing accuracy and equipment life; check valve 12 utilizes the principle of unidirectional fluid dynamics, preventing downstream gas backflow from contaminating hydrogen filter 11 and pipeline through the unidirectional opening and closing structure of the valve core, while blocking external air backflow, maintaining hydrogen purity and cleanliness; pressure detection component 14 is located in the main output pipeline, based on the principle of direct end pressure monitoring, avoiding the interference of pressure loss in intermediate pipeline sections such as dual gas supply pipelines and merging pipeline 9 on the detection results, ensuring accurate hydrogen supply pressure data, and providing a reliable basis for pressure regulation.
[0040] The embodiments described herein are preferred embodiments of this utility model and are not intended to limit the scope of protection of this utility model. Therefore, all equivalent changes made to the structure, shape, and principle of this utility model should be included within the scope of protection of this utility model.
Claims
1. A tube bundle type container hydrogen supply pressure reducing device characterized by, include: First gas supply line (1) and second gas supply line (2); the input ends of the first gas supply line (1) and the second gas supply line (2) are both used to connect to the tubular container (3), and the input ends are all equipped with a breakaway valve (4) in series; The first gas supply line (1) and the second gas supply line (2) are each connected in series with a first-stage pressure reducing valve (6) and a second-stage pressure reducing valve (7); the output ends of the two second-stage pressure reducing valves (7) merge to form a merging line (9), and the merging line (9) is provided with two independent third-stage pressure reducing valves (8) in parallel; A nitrogen purging device (5) includes a first nitrogen branch (51) and a second nitrogen branch (52); the first nitrogen branch (51) is connected to the first gas supply line (1) and the second gas supply line (2) respectively; the second nitrogen branch (52) is connected to the confluence line (9).
2. The tubular containerized hydrogen supply depressurization device according to claim 1, characterized in that, An emergency shut-off valve (10) is connected in series on both the first gas supply line (1) and the second gas supply line (2). The emergency shut-off valve (10) is located between the pull-off valve (4) and the first-stage pressure reducing valve (6).
3. The tubular container hydrogen supply depressurization device according to claim 2, characterized in that, A hydrogen filter (11) is connected in series on both the first gas supply line (1) and the second gas supply line (2). The hydrogen filter (11) is located between the emergency shut-off valve (10) and the first-stage pressure reducing valve (6).
4. A tubular containerized hydrogen supply depressurization device according to claim 3, characterized in that, Check valves (12) are connected in series on both the first gas supply line (1) and the second gas supply line (2). The check valves (12) are located between the emergency shut-off valve (10) and the hydrogen filter (11).
5. A tubular containerized hydrogen supply depressurization device according to claim 1, characterized in that, The output ends of the two three-stage pressure reducing valves (8) merge to form a total output pipeline, which is provided with a nitrogen purging port (13) for discharging the mixed gas after purging.
6. A tubular containerized hydrogen supply depressurization device according to claim 5, characterized in that, It also includes a pressure detection component (14), which is disposed on the main output pipeline.