A natural gas boiler water preheating device
By using a stirring heating device and an auxiliary conveying device, the problems of inconsistent water temperature and insufficient preheating in the boiler were solved, thereby improving temperature uniformity and working efficiency.
Patent Information
- Application Number
- CN202522541374.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-29
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-11-29
AI Technical Summary
Existing water preheating devices for natural gas boilers cannot ensure that the water temperature is uniform throughout the boiler body, and cannot perform secondary heating when preheating is insufficient, which reduces the device's working capacity and practicality.
A stirring and heating device is used to agitate the water with a motor and stirring blades to ensure a uniform temperature. If the preheating is insufficient, secondary heating is carried out through a heat-conducting copper shell and an electric heating rod. An auxiliary conveying device delivers water to the water tower assembly through a pump body and a water delivery hose.
This improved the working capacity and practicality of the boiler water preheating device, ensured consistent water temperature throughout, and reduced the difficulty and workload of the work.
Smart Images

Figure CN225016491U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of boiler preheating technology, specifically relating to a water preheating device for a natural gas boiler. Background Technology
[0002] A boiler is an energy conversion device. The energy input to a boiler includes the chemical energy of fuel and electrical energy. The boiler outputs steam, high-temperature water, or organic heat carriers with a certain amount of thermal energy. The original meaning of "boiler" refers to a water-filled container heated over a fire, while "furnace" refers to the place where fuel is burned. A boiler consists of two main parts: the boiler and the furnace. The hot water or steam produced in a boiler can directly provide the heat energy needed for industrial production and daily life, or it can be converted into mechanical energy through a steam power unit, or further converted into electrical energy through a generator.
[0003] Existing natural gas boiler water preheating devices cannot make the water temperature in all parts of the boiler body more uniform, and cannot reheat the water inside the boiler body when preheating is insufficient, thus reducing the working capacity of the device; and it is inconvenient to send the water that needs to be preheated to the water tower, thus reducing the practicality of the device. Utility Model Content
[0004] To address the problems mentioned in the background section, this invention provides a natural gas boiler water preheating device, characterized by high operating capacity and strong practicality.
[0005] To achieve the above objectives, the present invention provides the following technical solution: a natural gas boiler water preheating device, comprising a boiler body, a water tower assembly fixedly installed on one side of the boiler body, a solar water heater assembly fixedly installed on one side of the boiler body and above the water tower assembly, a condensing assembly fixedly installed on the side of the boiler body away from the water tower assembly and the solar water heater assembly, a stirring and heating device installed near the center of the boiler body, and an auxiliary conveying device provided on the outside of the water tower assembly. The stirring and heating device includes a support frame. The support frame is fixedly installed below the boiler body. A motor is fixedly installed on the inner side of the support frame. Multiple stirring blades are fixedly installed on the outer side of the motor output end and on the inner side of the boiler body. A heating component is fixedly installed on the upper part of the support frame.
[0006] Preferably, two anti-slip rubber layers are fixedly installed on the lower part of the support frame.
[0007] Preferably, the heating assembly includes a heat-conducting copper shell, and multiple heat-conducting copper shells are fixedly installed above the support frame and outside the multiple stirring blades, and multiple heating rods are fixedly installed inside the heat-conducting copper shells.
[0008] Preferably, an electronic thermometer is fixedly installed on the top of the support frame and on one side of the plurality of thermally conductive copper shells.
[0009] Preferably, the auxiliary conveying device includes a pump body, the pump body is fixedly installed on the side of the water tower assembly away from the boiler body, an inlet hose is fixedly installed below the liquid inlet end of the pump body, and a delivery hose is fixedly installed above the liquid outlet end of the pump body.
[0010] Preferably, a threaded sleeve is fixedly installed on the top of the water delivery hose near the side of the water tower assembly.
[0011] Preferably, a filter screen is fixedly installed on the bottom side of the water delivery hose away from the support frame.
[0012] Compared with the prior art, the beneficial effects of this utility model are: 1. This utility model, by setting up a stirring and heating device, can stir the water inside the boiler body through the cooperation of a motor and stirring blades, thereby making the water temperature in all parts of the boiler body more uniform. Furthermore, it can use the cooperation of electric heating rods and other structures to reheat the water inside the boiler body when preheating is insufficient, thus improving the working capacity of the device.
[0013] 2. By setting up an auxiliary conveying device, this utility model can deliver water that needs to be preheated into the water tower assembly through the cooperation of the pump body and water delivery hose, thereby reducing the difficulty of the work, alleviating the labor burden of the staff, and improving the practicality of the device. Attached Figure Description
[0014] Figure 1 This is a perspective view of the present utility model; Figure 2 This is a three-dimensional sectional view of the present invention; Figure 3 This is a three-dimensional sectional view of the stirring and heating device of this utility model; Figure 4 This is a perspective view of the auxiliary conveying device of this utility model.
[0015] In the diagram: 1. Boiler body; 2. Condensing assembly; 3. Stirring and heating device; 31. Support frame; 32. Anti-slip rubber layer; 33. Heating assembly; 331. Electronic thermometer; 332. Thermally conductive copper shell; 333. Heating rod; 34. Motor; 35. Stirring blade; 4. Auxiliary conveying device; 41. Pump body; 42. Water supply hose; 43. Threaded sleeve; 44. Inlet hose; 45. Filter screen; 5. Water tower assembly; 6. Solar water heater assembly. Detailed Implementation
[0016] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model. Example
[0017] Please see Figure 1-4 The present invention provides the following technical solution: a natural gas boiler water preheating device, including a boiler body 1, a water tower assembly 5 fixedly installed on one side of the boiler body 1, a solar water heater assembly 6 fixedly installed on one side of the boiler body 1 and above the water tower assembly 5, a condensing assembly 2 fixedly installed on the side of the boiler body 1 away from the water tower assembly 5 and the solar water heater assembly 6, a stirring heating device 3 installed near the center of the boiler body 1, and an auxiliary conveying device 4 provided on the outside of the water tower assembly 5. The stirring and heating device 3 includes a support frame 31. The support frame 31 is fixedly installed below the boiler body 1. A motor 34 is fixedly installed on the inner side of the support frame 31. Multiple stirring blades 35 are fixedly installed on the outer side of the output end of the motor 34 and on the inner side of the boiler body 1. A heating component 33 is fixedly installed on the upper part of the support frame 31.
[0018] Specifically, two anti-slip rubber layers 32 are fixedly installed on the bottom of the support frame 31. By adopting the above technical solution, the friction between the device and the ground can be increased by the two anti-slip rubber layers 32, preventing accidental slippage.
[0019] Specifically, the heating assembly 33 includes a heat-conducting copper shell 332. Multiple heat-conducting copper shells 332 are fixedly installed above the support frame 31 and on the outside of multiple stirring blades 35. Multiple electric heating rods 333 are fixedly installed on the inside of the heat-conducting copper shells 332. By adopting the above technical solution, the water inside the boiler body 1 can be reheated when the preheating is insufficient through the cooperation of the electric heating rods 333 and other structures.
[0020] Specifically, an electronic thermometer 331 is fixedly installed on the top of the support frame 31 and on one side of multiple heat-conducting copper shells 332. By adopting the above technical solution, the staff can use the electronic thermometer 331 to determine whether the temperature of the water in the boiler body 1 is sufficient when needed, thus better meeting the needs of the work.
[0021] In this embodiment, when it is necessary to preheat the water in the natural gas boiler, the operator heats the water in the water tower component 5 through the solar water heater component 6. Then the hot water enters the boiler body 1. The operator starts the motor 34 in the support frame 31 of the stirring heating device 3 to drive each stirring blade 35 to stir the water, so that the temperature of the water in each place tends to be uniform. The condensing component 2 condenses the evaporated water back into water and sends it back into the boiler body 1.
[0022] Then, the staff observes whether the temperature of the water in the boiler body 1 meets the preheating requirements through the electronic thermometer 331 in the heating component 33. If the temperature is too low due to insufficient sunlight or other reasons, the electric heating rods 333 in each heat-conducting copper shell 332 can be activated to preheat the water a second time. When the required temperature is reached, the preheating work is completed. The anti-slip rubber layer 32 plays a role in preventing the device from sliding accidentally. Example
[0023] The difference between this embodiment and embodiment 1 is that the auxiliary conveying device 4 includes a pump body 41. The pump body 41 is fixedly installed on the side of the water tower assembly 5 away from the boiler body 1. A water inlet hose 44 is fixedly installed below the liquid inlet end of the pump body 41, and a water delivery hose 42 is fixedly installed above the liquid outlet end of the pump body 41. By adopting the above technical solution, the water that needs to be preheated can be sent into the water tower assembly 5 through the cooperation of the pump body 41 and the water delivery hose 42, thereby reducing the difficulty of the work and alleviating the labor burden of the staff.
[0024] Specifically, a threaded sleeve 43 is fixedly installed on the top of the water supply hose 42 near the water tower assembly 5. By adopting the above technical solution, the staff can connect or disconnect the water supply hose 42 and the water tower assembly 5 through the threaded sleeve 43 when needed, thereby better meeting the needs of the work.
[0025] Specifically, a filter screen 45 is fixedly installed on the side of the bottom of the water supply hose 42 away from the support frame 31. By adopting the above technical solution, external impurities are prevented from entering the interior of the water supply hose 42 and other structures, reducing the possibility of adverse effects on operation.
[0026] In this embodiment, when water needs to be added to the water tower assembly 5, the operator can connect the water delivery hose 42 in the auxiliary conveying device 4 to the water tower assembly 5 via a thread, then connect the end of the inlet hose 44 to an external water source, start the pump body 41, and under the action of the pump body 41, the water filtered by the filter screen 45 enters the pump body 41, and then passes through the water delivery hose 42 and the threaded sleeve 43 into the water tower assembly 5, thereby adding water, reducing the difficulty of adding water and alleviating the workload of the operator.
[0027] The structure and principle of the boiler body 1, the condensing assembly 2 consisting of a condensing box, a drive motor, a rotating shaft, a suction impeller, a first gas pipe, a water receiving tank, a reflector plate, a condensing plate, a second gas pipe, a one-way valve, a serpentine pipe, a water pump, a third water pipe, and a fourth water pipe, the water tower assembly 5 consisting of a water tower, an inlet pipe, and a second water pipe, and the solar water heater assembly 6 consisting of a solar water heater and a first water pipe have been disclosed in a natural gas boiler water preheating device disclosed in announcement number CN212081208U. Its working principle is that before use, the device's sealing is checked. The solar water heater fully utilizes solar energy, saving resources, and heats the water inside the water tower until it is transported to the boiler body for rapid preheating. Since the top of the boiler body contains residual heat, it is further heated by the drive motor. The motor drives the shaft to rotate, which in turn drives the suction impeller to rotate, creating negative pressure inside the first gas pipe. This draws the waste heat from the top of the boiler body along with the gas into the condenser. Since the gas contains a large amount of moisture, the moisture is collected by the condenser plate and enters the water receiving tank by gravity. Through a one-way valve, the moisture-containing air is transported to the boiler body through the second gas pipe. The gas passes through a serpentine tube, contacting the collected moisture to increase the contact area and prevent heat loss. By turning on the water pump, the water receiving tank, which still contains heat, is transported to the boiler body through the fourth water pipe, thus recycling the water resources. The insulation cotton inside the second gas pipe ensures that heat is not lost during gas transport, resulting in better performance.
[0028] The electronic thermometer 331 in this utility model is a previously disclosed technology, and the selected model is DT1310+187. Its working principle is to use a K-type thermocouple as a temperature sensor, which consists of a closed circuit composed of two metal wires of different materials. When the measuring end (hot end) of the thermocouple is inserted into a high-temperature liquid, while the other end (cold end) is in a lower and more stable temperature environment, a thermoelectric potential is generated in the circuit due to the temperature difference between the two ends. The magnitude of the thermoelectric potential is proportional to the temperature difference between the two ends. By measuring the magnitude of the thermoelectric potential, the temperature of the liquid being measured can be indirectly determined.
[0029] The working principle and usage process of this utility model are as follows: When it is necessary to preheat the water in the natural gas boiler, the staff heats the water in the water tower component 5 through the solar water heater component 6. Then the hot water enters the boiler body 1. The staff starts the motor 34 in the support frame 31 of the stirring heating device 3 to drive each stirring blade 35 to stir the water, so that the temperature of the water in each place tends to be uniform. The condensing component 2 condenses the evaporated water back into water and sends it back into the boiler body 1.
[0030] Then, the staff observes whether the temperature of the water in the boiler body 1 meets the preheating requirements through the electronic thermometer 331 in the heating component 33. If the temperature is too low due to insufficient sunlight or other reasons, the electric heating rods 333 in each heat-conducting copper shell 332 can be activated to preheat the water a second time. When the required temperature is reached, the preheating work is completed. The anti-slip rubber layer 32 plays a role in preventing the device from sliding accidentally.
[0031] When water needs to be added to the water tower assembly 5, the operator can connect the water delivery hose 42 in the auxiliary delivery device 4 to the water tower assembly 5 via a thread, then connect the end of the inlet hose 44 to an external water source, start the pump body 41, and under the action of the pump body 41, the water filtered by the filter screen 45 enters the pump body 41, and then passes through the water delivery hose 42 and the threaded sleeve 43 into the water tower assembly 5, thereby adding water, reducing the difficulty of adding water and alleviating the workload of the operator.
[0032] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A natural gas boiler water preheating device, comprising a boiler body (1), a water tower assembly (5) is fixedly installed on one side of the boiler body (1), a solar water heater assembly (6) is fixedly installed on one side of the boiler body (1) and above the water tower assembly (5), and a condensing assembly (2) is fixedly installed on one side of the boiler body (1) away from the water tower assembly (5) and the solar water heater assembly (6), characterized in that: A stirring and heating device (3) is installed in the center of the boiler body (1), and an auxiliary conveying device (4) is installed on the outside of the water tower assembly (5). The stirring and heating device (3) includes a support frame (31). The support frame (31) is fixedly installed below the boiler body (1). A motor (34) is fixedly installed on the inner side of the support frame (31). Multiple stirring blades (35) are fixedly installed on the outer side of the output end of the motor (34) and on the inner side of the boiler body (1). A heating component (33) is fixedly installed on the upper part of the support frame (31).
2. The natural gas boiler water preheating device according to claim 1, characterized in that: Two anti-slip rubber layers (32) are fixedly installed on the bottom of the support frame (31).
3. The natural gas boiler water preheating device according to claim 1, characterized in that: The heating assembly (33) includes a heat-conducting copper shell (332). Multiple heat-conducting copper shells (332) are fixedly installed above the support frame (31) and outside the multiple stirring blades (35). Multiple heating rods (333) are fixedly installed inside the heat-conducting copper shells (332).
4. A natural gas boiler water preheating device according to claim 3, characterized in that: An electronic thermometer (331) is fixedly installed on the top of the support frame (31) and on one side of a plurality of thermally conductive copper shells (332).
5. A natural gas boiler water preheating device according to claim 1, characterized in that: The auxiliary conveying device (4) includes a pump body (41). The pump body (41) is fixedly installed on the side of the water tower assembly (5) away from the boiler body (1). A water inlet hose (44) is fixedly installed below the liquid inlet end of the pump body (41), and a water delivery hose (42) is fixedly installed above the liquid outlet end of the pump body (41).
6. A natural gas boiler water preheating device according to claim 5, characterized in that: A threaded sleeve (43) is fixedly installed on the top of the water delivery hose (42) near the side of the water tower assembly (5).
7. A natural gas boiler water preheating device according to claim 5, characterized in that: A filter screen (45) is fixedly installed on the bottom side of the water delivery hose (42) away from the support frame (31).
Citation Information
Patent Citations
Natural gas boiler water preheating device
CN212081208U