High-efficiency heat exchange single-pipe ring tube boiler
The high-efficiency heat exchange single-tube once-through boiler with wedge-shaped gap and spiral flow guide design solves the problems of low heat exchange efficiency and thermal expansion of small-tonnage once-through boilers, achieving efficient and uniform flue gas flow and structural stability, and extending equipment life.
Patent Information
- Application Number
- CN202521448798.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-07-11
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-07-11
AI Technical Summary
Small-tonnage once-through boilers are difficult to arrange in terms of multi-tube coils, which increases welding and manufacturing costs, results in low and uneven heat exchange efficiency, short flue gas flow paths, insufficient contact time between high-temperature flue gas and tube bundles, and stress concentration caused by thermal expansion.
By employing a wedge-shaped gap and spiral flow guide design, combined with an elastic structure, and through the radial staggered arrangement of water pipe bundles and the obstruction of heat shields, a wedge-shaped passage and a spiral flue gas flow path are formed, which enhances the heat exchange effect between flue gas and water pipes, and absorbs thermal stress through expansion rings.
It improves the boiler's heat exchange efficiency by more than 25%, extends the contact time between flue gas and water pipes, enhances the reliability and lifespan of the structure, and is suitable for miniaturization requirements.
Smart Images

Figure CN225016556U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of boiler technology, specifically to a high-efficiency heat exchange single-tube once-through boiler. Background Technology
[0002] Most existing once-through boilers employ multi-coil tube bundles, a design that optimizes fluid distribution, heat load distribution, and structural strength, significantly improving boiler performance and reliability. However, for small-tonnage once-through boilers with an evaporation capacity of less than 500 kg / h, limited boiler space makes multi-coil arrangement difficult, significantly increasing welding and manufacturing costs. To address this issue, single-coil water tube arrangements have emerged, with tube bundles often arranged in parallel and equidistant configurations. This results in a straight-line flow of flue gas, leading to low heat exchange efficiency and uneven heating. The short flue gas flow path results in insufficient contact time between the high-temperature flue gas and the tube bundle, leading to higher exhaust gas temperatures. Furthermore, the difference in thermal expansion coefficients at the connection between the flue chamber shell and the header can easily cause stress concentration, resulting in cracks after long-term operation. Therefore, there is an urgent need for a once-through boiler structure that can optimize the flue gas flow path, enhance heat exchange efficiency, and solve the thermal expansion problem. Utility Model Content
[0003] The purpose of this invention is to provide a high-efficiency heat exchange single-tube once-through boiler. Through a wedge-shaped gap and spiral flow guiding design, it achieves efficient flue gas scouring and uniform heat exchange, while employing an elastic structure to alleviate thermal stress. Its core technical solutions include:
[0004] To achieve the above objectives, this utility model provides the following technical solution: a high-efficiency heat exchange single-tube coil once-through boiler, the boiler body including an upper annular header steam outlet, a water pipe bundle, a flue gas chamber shell, a flue gas guide plate device, a heat shield, a lower annular header, a drain pipe, a water inlet, and a flue gas outlet. The upper and lower annular headers are located at the top and bottom of the boiler, respectively. The upper and lower annular headers are connected by an annular water pipe bundle. The annular water pipe bundle adopts a closely spaced arrangement with tangent outer pipes. In the closely spaced bundle, adjacent pipes are radially staggered to create a wedge-shaped gap. The heat shield surrounds the water pipe bundle to form a flue gas passage, preventing the flue gas from longitudinally scouring the water pipe bundle. The guide plate device is arranged at the outlet of the flue gas passage formed by the heat shield surrounding the water pipe bundle.
[0005] Preferably, the water pipe bundle is formed by spaced vertical water pipes and inclined water pipes to form an annular pipe ring. The upper ends of the vertical water pipes and inclined water pipes are tightly tangent to each other, and the lower ends of adjacent pipe bundles are arranged radially to create a radial wedge-shaped gap structure. The inclination angle of the inclined water pipes does not exceed 1°.
[0006] Preferably, the heat-resistant plate includes a heat-resistant plate support plate and a heat-resistant plate cylinder, with the L-shaped short side of the heat-resistant plate support plate welded to the heat-resistant plate cylinder, and the end of the long side of the heat-resistant plate support plate welded to the lower annular header.
[0007] Preferably, the upper and lower ends of the vertical and inclined water pipes are necked, and when the vertical and inclined water pipes are closely arranged, the pipe plates of the upper and lower annular headers can form a perforated bridge.
[0008] Preferably, the flue gas guide plate device includes a front upper guide plate, a front lower guide plate, a rear upper guide plate, and a rear lower guide plate. The front lower guide plate and the rear upper guide plate, and the rear lower guide plate and the front upper guide plate are connected by intermediate support blocks. The front lower guide plate and the rear lower guide plate are fixed by end support blocks. The combination of the front lower guide plate and the rear upper guide plate and the combination of the rear lower guide plate and the front upper guide plate form a spiral passage with a spiral angle of 35° to 40°. The ratio of the lead of the spiral channel to the height of the tube bundle is 1:1.2.
[0009] Preferably, the smoke chamber shell consists of a smoke chamber cylinder and an expansion ring. The expansion ring is formed by stamping a whole steel plate into an L-shaped ring with a longitudinal cross section. The long side of the L-shape is welded to the smoke chamber cylinder, and the short side of the L-shape is welded to the lower annular header.
[0010] Compared with existing technologies, the beneficial effects of this utility model are as follows: This utility model is a high-efficiency heat exchange single-tube coil once-through boiler. After the combustion flame in the furnace exchanges heat with the surrounding water tubes through radiation, the high-temperature flue gas passes through the wedge-shaped passage formed at the bottom of the coil and washes the water tubes at high speed under the obstruction of the heat shield plate. At the outlet of the heat shield plate and the coil, the flue gas spirals upward along the flue gas guide plate and washes the water tubes laterally. The high flow velocity of the flue gas and the lateral washing of the water tubes enhance the convective heat transfer. At the same time, the spiral rise of the flue gas at the top also prolongs the residence time, allowing for sufficient heat exchange. These efficient heat exchange measures can increase the overall heat transfer coefficient of the boiler by more than 25% without changing the heat transfer area. The heat shield plate and the smoke chamber shell adopt an expansion compensation structure, which enhances the structural reliability, can absorb 1-3mm of thermal displacement, and extends the service life by 3-5 years. The single-tube coil densely packed tube bundle reduces the volume and is suitable for the miniaturization of boilers. Attached Figure Description
[0011] To more clearly illustrate the technical solutions of the embodiments of this utility model, the drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of this utility model and should not be regarded as a limitation of the scope. For those skilled in the art, other related drawings can be obtained from these drawings without creative effort.
[0012] Figure 1 This is a cross-sectional view of the boiler as a whole.
[0013] Figure 2 A schematic diagram showing the wedge-shaped gap formed by the inclined and vertical water pipes surrounding the water pipe bundle.
[0014] Figure 3 This is a sectional view of the smoke chamber shell.
[0015] Figure 4 This is a schematic diagram showing the structural relationship between the flue gas guide plate device and the water pipe bundle.
[0016] Figure 5 This is a schematic diagram of the flue gas guide plate device.
[0017] Figure 6 This is a schematic diagram of the heat shield device.
[0018] In the diagram: 1-Upper annular header; 2-Steam outlet; 3-Water pipe bundle; 301-Inclined water pipe; 302-Vertical water pipe; 4-Smoke chamber shell; 401-Smoke chamber cylinder; 402-Expansion ring; 5-Flue gas guide plate device; 501-Front upper guide plate; 502-Front lower guide plate; 503-Rear upper guide plate; 504-Rear lower guide plate; 505-Intermediate support block; 506-End support block; 6-Heat protection plate device; 601-Heat protection plate cylinder; 602-Heat protection plate support; 7-Lower annular header; 8-Drain outlet; 9-Water inlet; 10-Smoke outlet. Detailed Implementation
[0019] To make the objectives, technical solutions, and advantages of the embodiments of this utility model clearer, the technical solutions of the embodiments of this utility model will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this utility model, not all embodiments. Based on the embodiments of this utility model, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this utility model.
[0020] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely to illustrate selected embodiments of the invention. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without inventive effort are within the scope of protection of the present invention.
[0021] It should be noted that similar labels and letters in the following figures indicate similar items. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures.
[0022] In the description of this utility model, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this utility model and simplifying the description, and are not intended to indicate or imply that the device or component referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model.
[0023] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this utility model, "a plurality of" means two or more, unless otherwise explicitly specified.
[0024] like Figure 1-6 As shown, this utility model provides a high-efficiency heat exchange single-tube coil once-through boiler. The boiler body includes an upper annular header 1, a steam outlet 2, a water pipe bundle 3, a flue gas shell 4, a flue gas guide plate device 5, a heat insulation plate 6, a lower annular header 7, a drain pipe 8, a water inlet 9, and a flue gas outlet 10. The upper annular header 1 and the lower annular header 7 are located at the top and bottom of the boiler, respectively. The upper annular header 1 and the lower annular header 7 are connected by an annular water pipe bundle 3. The annular pipe bundle 3 is a closely spaced bundle with tangential outer tubes. The bottom plate of the header is welded with necked ends at both ends of each single pipe. Adjacent tubes in the closely spaced bundle... The radially staggered arrangement between the two pipes creates a wedge-shaped gap. After combustion, the high-temperature flue gas flows out from the wedge-shaped gap. The heat shield 6 surrounds the water pipe bundle 3 to form a flue gas passage, blocking the flue gas from longitudinally scouring the water pipe bundle 3. The guide plate device 5 is arranged at the outlet of the flue gas passage formed by the heat shield 6 surrounding the water pipe bundle 3. The flue gas flows in the spiral channel formed by the flue gas guide plate device 5, the water pipe bundle 3, and the smoke chamber shell 4, scouring the water pipe bundle 6 and being discharged from the flue gas outlet 10. The boiler feedwater inlet 9 is injected into the lower annular header 7. After being heated by the water pipe bundle 6, it forms a steam-water mixture that enters the upper annular header 1. After steam-water separation, it is discharged from the steam outlet 3.
[0025] 1. Soft drink system
[0026] Water enters from the water inlet 9 of the lower annular header 7 and is heated by the tube bundle 3 consisting of inclined water pipe 301 and vertical water pipe 302; the resulting steam-water mixture rises to the upper annular header 1 for steam-water separation, and saturated steam is output from the steam outlet 2.
[0027] 2. Flue gas system
[0028] When the high-temperature flue gas enters the tube bundle gap from the combustion chamber, the flow velocity increases by 20%-30% due to the gradual contraction effect of the wedge structure; after being constrained by the heat shield 6, the flue gas undergoes secondary scouring in the spiral channel formed by the guide plate 5; finally, the flue gas is discharged through the outlet 10.
[0029] Structural Assembly: In the flue gas guide vane device, the front lower guide vane and the rear upper guide vane, as well as the rear lower guide vane and the front upper guide vane, are connected by intermediate support blocks. Both the front lower guide vane and the rear lower guide vane are fixed by end support blocks. This connection and fixing method ensures a stable structure for the guide vane device, with the combination of the front lower guide vane and the rear upper guide vane, and the combination of the rear lower guide vane and the front upper guide vane, forming a spiral passage.
[0030] Parameter relationships: The recommended helix angle is 35° - 40°, and the ratio of the helical channel lead to the tube bundle height is 1:1.2. Within this helix angle range, the flue gas can form a relatively stable and efficient rotating flow within the helical channel, extending the scouring path and scouring time. Taking a tube bundle height of 3m as an example, with a helical channel lead of 2.5m, under these parameters, the flue gas velocity can be increased to approximately 1.5 times the original value, greatly enhancing the heat exchange effect between the flue gas and the water tube bundle, and effectively improving the boiler's thermal efficiency.
[0031] Smoke chamber shell
[0032] Structural fit: The smoke chamber shell consists of a smoke chamber cylinder and an expansion ring. The expansion ring is formed by stamping a single sheet of steel into an L-shaped ring with a longitudinal cross-section. The long side of the L-shape is welded to the smoke chamber cylinder, and the short side of the L-shape is welded to the lower annular header. This structural design allows the smoke chamber shell to adapt to the thermal expansion and contraction changes during boiler operation.
[0033] Parameter Relationship: When the smoke chamber cylinder expands longitudinally due to heat, the long side of the L-shaped expansion ring will move synchronously with the cylinder, while the short side, through its own elastic deformation, allows for relative displacement between the long and short sides to absorb the expansion difference between the cylinder and the header. For example, when the temperature of the smoke chamber cylinder rises by 200℃, the short side of the L-shaped expansion ring can absorb an expansion difference of 2-3mm through elastic deformation, avoiding fatigue cracks in the smoke chamber cylinder caused by repeated deformation, thereby ensuring the long-term stable operation of the smoke chamber shell.
[0034] Deflector Material and Surface Treatment: The deflector is made of high-temperature resistant, wear-resistant alloy material with good corrosion resistance, such as nickel-based alloy. To further improve the wear resistance of the deflector, its surface is thermally sprayed with a tungsten carbide coating. The tungsten carbide coating has high hardness and can effectively resist the erosion and wear of particles in the flue gas. Actual operation verification shows that the deflector using a nickel-based alloy and undergoing tungsten carbide thermal spraying treatment has a service life 2-3 times longer than the untreated deflector under the same operating conditions.
[0035] Fine-tuning of the guide vane angle and position: During actual installation and commissioning, the angle and position of the guide vane can be fine-tuned according to the boiler's operating conditions and flue gas flow. For example, if the flue gas velocity in a certain area is found to be too high or too low, adjusting the angle of the guide vane in that area can make the flue gas velocity distribution more uniform. Simultaneously, optimizing the position of the guide vane can further extend the residence time of the flue gas in the spiral channel, improving heat exchange efficiency. Generally, the fine-tuning range for the guide vane angle is ±5°, and the fine-tuning range for the position is ±20mm.
[0036] Smoke chamber shell
[0037] Optimized design of the expansion ring: In addition to adopting an L-shaped structure, reinforcing ribs can be added at the connection between the short and long sides of the expansion ring to enhance its structural strength and elastic deformation capacity. The shape and size of the reinforcing ribs are designed according to the diameter and expansion amount of the smoke chamber. For example, for a smoke chamber with a diameter of 2m, the reinforcing rib at the expansion ring connection can be designed as a rectangular cross-section with a thickness of 5mm and a width of 30mm, with a length the same as the short side of the expansion ring. This reinforcing rib design can effectively improve the load-bearing capacity of the expansion ring and better absorb the expansion difference between the smoke chamber and the lower annular header.
[0038] Sealing structure of the smoke chamber shell: To prevent flue gas leakage, high-performance sealing materials and structures are used at all connection points of the smoke chamber shell. For example, at the weld between the smoke chamber shell and the expansion ring, argon arc welding is used, and high-temperature sealant is applied to the weld. At the flange connections between the smoke chamber shell and other components, high-temperature resistant spiral wound gaskets are used, and the tightening torque of the flange bolts is ensured to be uniform. Through these sealing measures, the flue gas leakage rate can be controlled below 0.5%, ensuring the safety and environmental friendliness of boiler operation.
[0039] Example 2 Key Component Details
[0040] Tube bundle structure Figure 2 , Figure 4
[0041] Figure 2The structure of the wedge-shaped gap is shown. The water pipe bundle 3 is formed by vertical water pipes 302 and inclined water pipes 301 arranged at intervals to form an annular pipe ring. The upper ends of the vertical water pipes 302 and inclined water pipes 301 are tightly tangent, and the lower ends of adjacent pipe bundles are arranged radially to create a radial wedge-shaped gap structure. The inclination angle of the inclined water pipes 301 does not exceed 1°. The high-temperature flue gas in the furnace is discharged through the radial gap. Figure 4 The diagram shows the necking at the upper and lower ends of the vertical water pipe 302 and the inclined water pipe 301. When the vertical water pipe 302 and the inclined water pipe 301 are closely arranged, the water pipe plates of the upper annular header 1 and the lower annular header 7 can form a perforated bridge to facilitate welding.
[0042] Structural Configuration: The water pipe bundle consists of a ring formed by spaced-apart vertical and inclined water pipes. The upper ends of the vertical and inclined water pipes are tightly tangent to each other. This tangential arrangement ensures that the upper annular header receives the steam-water mixture relatively evenly from each pipe, guaranteeing a relatively balanced pressure distribution within the header. The lower ends of adjacent pipe bundles are arranged radially staggered, creating a radial wedge-shaped gap structure. This structural configuration allows high-temperature flue gas in the furnace to exit through the radial gaps and enter the subsequent flue gas passage.
[0043] Parameter Relationship: The inclination angle of the inclined water pipes should not exceed 1°. This small inclination angle ensures the stability of the overall structure of the water pipe bundle and cleverly utilizes the gap created by the inclination to guide the flow of flue gas. An excessively large angle will affect the structural strength of the tube bundle and the uniformity of flue gas flow, while an excessively small angle will hinder the discharge of flue gas from the radial gaps. The upper and lower ends of the vertical and inclined water pipes are necked. When the vertical and inclined water pipes are closely arranged, a bridge will form in the tube sheets of the upper and lower annular headers. Taking a commonly used boiler tube diameter as an example, if the outer diameter of the water pipe is 50mm, the outer diameter of the necked end can be 45mm. A bridge width of 10-15mm is suitable. This size facilitates welding operations while ensuring the strength after welding, meeting the pressure requirements during boiler operation.
[0044] Material Selection: The water pipe bundle is made of high-quality low-alloy high-strength steel, such as 15CrMoG. This material has excellent high-temperature strength, oxidation resistance, and corrosion resistance, and can withstand the high-temperature and high-pressure environment during boiler operation. Even under long-term scouring by high-temperature flue gas, it maintains stable physical properties, effectively extending the service life of the water pipe bundle. For example, in a certain industrial application, water pipe bundles using 15CrMoG material showed a wall thickness reduction of less than 5% after 5000 hours of continuous operation, still meeting the boiler's safe operation requirements.
[0045] Pipe Diameter and Wall Thickness Design: The pipe diameters of vertical and inclined water pipes are precisely calculated based on the boiler's rated evaporation capacity and water circulation requirements. Generally, for boilers with a rated evaporation capacity of 2-5 t / h, a pipe diameter of 50-70 mm can be selected. The wall thickness is determined based on the design pressure and temperature using strength calculation formulas to ensure that the water pipes will not deform or crack when subjected to internal working fluid pressure and external flue gas heat load. Taking a design pressure of 1.25 MPa and a design temperature of 300℃ as an example, calculations suggest a wall thickness of 4-5 mm is appropriate.
[0046] Tube bundle arrangement optimization: To further improve the heat exchange efficiency between flue gas and water tube bundles, the tube bundle arrangement density can be appropriately increased while ensuring structural strength. However, it is necessary to control the minimum gap between adjacent tube bundles to avoid ash accumulation and blockage due to excessively small gaps. Through numerical simulation and experimental verification, when the tube bundle arrangement density increases by 10%-15%, the heat exchange efficiency can be improved by 8%-12% under reasonable gap control (e.g., the minimum gap is not less than 10mm).
[0047] Deflector device Figure 4 , Figure 5
[0048] Figure 4 The structural relationship between the flue gas guide plate device 5 and the water pipe bundle 3, as well as the flow mode of the flue gas, are shown. The recommended helix angle is 35° to 40°, and the ratio of the lead of the helical channel to the height of the tube bundle is 1:1.2. The flue gas can increase the flue gas velocity, extend the flushing path, and increase the flushing time by passing through the helical channel.
[0049] Figure 5 The specific structure of the flue gas guide plate device 5 is shown. It consists of a front lower guide plate 502 and a rear upper guide plate 503. The rear lower guide plate 504 and the front upper guide plate 501 are connected by intermediate support blocks 505. The front lower guide plate 502 and the rear lower guide plate 504 are fixed by end support blocks 506. The combination of the front lower guide plate 502 and the rear upper guide plate 503 and the combination of the rear lower guide plate 504 and the front upper guide plate 501 form a spiral passage.
[0050] Figure 3 The smoke chamber shell 4 shown is composed of a smoke chamber cylinder 401 and an expansion ring 402. The expansion ring 402 is formed by stamping a whole steel plate into an L-shaped ring with a longitudinal section. The long side of the L-shape is welded to the smoke chamber cylinder 401, and the short side of the L-shape is welded to the lower annular header 7. When the smoke chamber cylinder is heated and expands longitudinally, the long side of the L-shape will move synchronously with the cylinder, while the short side, through its own elastic deformation, allows relative displacement between the long side and the short side to absorb the expansion difference between the cylinder and the header, thus avoiding fatigue cracks in the smoke chamber cylinder 401 due to repeated deformation.
[0051] Figure 6 The heat-resistant plate 6 has an L-shaped short side welded to the heat-resistant plate cylinder 601, and the end of the long side welded to the lower annular header 7. The heat-resistant plate support plate 602 is made of 1Cr18Ni9Ti steel plate with a thickness of no more than 2mm. The L-shaped short side can slide to absorb the expansion and deformation of the heat-resistant plate cylinder 601 after being heated.
[0052] Heat shield
[0053] Structural Assembly: The heat shield consists of a heat shield cylinder and a heat shield support plate. The short L-shaped side of the heat shield support plate is welded to the heat shield cylinder, and the end of the long side is welded to the lower annular header. This welding method allows the heat shield to securely surround the water pipe bundle, forming a flue gas passage, effectively preventing the flue gas from longitudinally scouring the water pipe bundle, ensuring that the flue gas flows along a predetermined path, and improving heat exchange efficiency.
[0054] Parameter Relationship: The heat shield support plate is made of 1Cr18Ni9Ti steel plate with a thickness not exceeding 2mm. This material has good high-temperature resistance and corrosion resistance, and can adapt to the harsh environment inside the boiler. The thickness of no more than 2mm ensures that the support plate has sufficient strength to support the heat shield cylinder, while also allowing its L-shaped short side to slide and absorb the expansion deformation of the heat shield cylinder after heating. For example, when the boiler operating temperature reaches 400℃, the 2mm thick 1Cr18Ni9Ti steel plate support plate can effectively meet the requirements for sliding and absorbing expansion deformation, preventing structural damage caused by stress from thermal expansion and contraction.
[0055] Heat shield cylinder structure: The heat shield cylinder adopts a double-layer structure design. The inner layer is made of high-temperature resistant stainless steel, such as 310S, which has excellent high-temperature resistance and can operate stably for a long time in high-temperature environments above 1000℃. The outer layer is made of ordinary carbon steel, which protects the inner stainless steel layer and enhances the structural strength. High-efficiency thermal insulation material, such as ceramic fiber cotton, is filled between the two layers. Its low thermal conductivity effectively prevents heat transfer, reduces the temperature on the outside of the heat shield, and minimizes heat loss. Tests have shown that with this double-layer structure and thermal insulation filling material, the temperature on the outside of the heat shield can be reduced to below 50℃, significantly improving energy efficiency.
[0056] The spacing between the heat shield and the water pipe bundle significantly impacts flue gas flow and heat exchange efficiency. Excessive spacing can lead to short-circuiting of the flue gas, affecting heat exchange efficiency; insufficient spacing may result in excessively high local flue gas velocities, causing wear on the water pipe bundle. Through fluid dynamics simulations and actual operational tests, a reasonable spacing range of 30-50 mm was determined. Within this spacing, the flue gas can flow uniformly within the channel formed by the heat shield and the water pipe bundle, ensuring sufficient heat exchange with the water pipe bundle while avoiding wear issues.
[0057] Water cycle process
[0058] Water Distribution: A water distribution device is installed inside the lower annular header to ensure that the incoming water is evenly distributed to each water pipe bundle. The water distribution device can be a perforated plate structure, with the number and diameter of the holes designed according to the number and diameter of the water pipe bundles. For example, for a boiler with 50 water pipe bundles with a diameter of 50mm, the perforated plate can have 50 holes with a diameter of 10mm, and the distribution of the holes should ensure that the water is evenly distributed within the header. This ensures that the water flow rate in each water pipe bundle is consistent, avoiding uneven heating caused by localized poor water flow.
[0059] As the steam-water mixture rises within the water pipe bundle, it naturally circulates due to gravity and the density difference between the steam and water. To enhance this circulation, a flow-turbing device, such as a spiral baffle, can be installed at specific locations within the water pipe bundle. The spiral baffle creates a rotating flow in the rising steam-water mixture, increasing mixing efficiency and improving the heat transfer coefficient. Experimental tests have shown that installing the spiral baffle can increase the heat transfer coefficient of the steam-water mixture by 15%–20%, effectively promoting the steam-water separation process.
[0060] Steam-water separation: A high-efficiency steam-water separation device, such as a cyclone separator, is used in the upper annular header. The cyclone separator uses the centrifugal force of the rotating steam-water mixture to separate the steam and water effectively. The steam is discharged from the top of the separator, while the water flows back to the lower annular header to continue the circulation. The separation efficiency of the cyclone separator can reach over 98%, ensuring that the output steam has a high dryness, meeting the steam quality requirements of industrial production.
[0061] flue gas flow process
[0062] Flue gas enters the wedge-shaped gap: After the high-temperature flue gas generated by combustion forms in the furnace, it rapidly enters the wedge-shaped gap created by the radially staggered arrangement of adjacent water tube bundles at the bottom. Due to the special structure of the wedge-shaped gap, the flue gas experiences acceleration and turbulence upon entry, enhancing the heat exchange effect between the flue gas and the outer wall of the water tube bundle. Numerical simulation analysis shows that at the inlet of the wedge-shaped gap, the flue gas velocity can increase to 1.2-1.5 times its original value, while the turbulence intensity increases, resulting in a significant improvement in the heat transfer coefficient.
[0063] Flue gas flow within the spiral channel: After passing through the wedge-shaped gap, the flue gas enters the spiral channel formed by the flue gas guide plate device, water pipe bundle, and flue chamber shell. Within the spiral channel, the flow path of the flue gas is lengthened, and the residence time is increased. Simultaneously, the guide plate causes the flue gas to rotate, further enhancing heat exchange with the water pipe bundle. By adjusting parameters such as the helix angle and the lead-to-tube height ratio, the flow state of the flue gas within the channel can be optimized. For example, when the helix angle is 38° and the lead-to-tube height ratio is 1:1.2, the residence time of the flue gas within the channel can be extended to 1.5-2 times the original time, significantly improving heat exchange efficiency.
[0064] Flue gas discharge: After sufficient heat exchange, the low-temperature flue gas is discharged from the flue gas outlet. A waste heat recovery device, such as a heat pipe heat exchanger, can be installed at the outlet to recover waste heat from the discharged flue gas. This recovered heat can then be used to heat boiler feedwater or other media requiring preheating. Heat pipe heat exchangers have highly efficient heat transfer performance, effectively improving energy utilization. Practical applications have shown that using heat pipe heat exchangers to recover waste heat from flue gas can increase boiler thermal efficiency by 3% - 5%.
[0065] Parameter optimization and supplementation
[0066] Overall performance parameters of the boiler
[0067] Rated Evaporation Capacity: The rated evaporation capacity of this boiler can be customized within the range of 1-10 t / h to meet different industrial application needs. For example, a boiler with a rated evaporation capacity of 2 t / h can be selected for a small food processing plant; a boiler with a rated evaporation capacity of 8 t / h can be customized for a large chemical enterprise. When determining the rated evaporation capacity, the user's steam consumption, steam pressure, and temperature requirements, as well as the boiler's operating costs and efficiency, must be comprehensively considered.
[0068] Thermal efficiency: Through optimized structural design and operating parameters, the thermal efficiency of this boiler can reach 90%-95%. For example, by rationally adjusting the arrangement of the water tube bundle, the parameters of the flue gas guide plate device, and using high-efficiency insulation materials, heat loss and incomplete combustion losses are reduced, thereby improving thermal efficiency. Compared with traditional once-through boilers, this boiler can improve thermal efficiency by 8%-12% under the same operating conditions.
[0069] Steam pressure and temperature: Steam pressure can be adjusted within the range of 0.8 - 2.5 MPa according to user requirements, and steam temperature can be set between 180 - 300℃. During design and operation, the stability of steam pressure and temperature is ensured through precise control of combustion output, water supply, and steam-water separation processes. For example, when the steam pressure is set to 1.6 MPa, the pressure fluctuation range can be controlled within ±0.05 MPa; when the steam temperature is set to 250℃, the temperature fluctuation range can be controlled within ±5℃, meeting the stringent requirements of industrial production for steam parameter stability.
[0070] Safety and Maintenance Supplement
[0071] Safety protection measures
[0072] Water Level Monitoring and Control: High-precision water level sensors are installed to monitor the water level in the lower and upper annular headers in real time. When the water level is lower or higher than the set safe level, the automatic control system immediately activates, adjusting the flow rate of the feedwater pump to control the water level. Simultaneously, a water level alarm device is installed, promptly issuing audible and visual alarm signals when the water level is abnormal, reminding operators to take appropriate measures. For example, the water level sensor's accuracy can reach ±5mm, accurately monitoring water level changes and ensuring the boiler operates within the safe water level range.
[0073] Pressure Protection: Multiple pressure sensors are installed on the boiler body to monitor steam pressure and furnace pressure. When the pressure exceeds the set upper limit, the safety valve automatically opens to release pressure, and the automatic control system adjusts the burner's combustion output to reduce the pressure. When the pressure falls below the set lower limit, the automatic control system increases the combustion output to raise the pressure. The pressure sensor accuracy is ±0.02MPa, and the safety valve's operating pressure error is controlled within ±3%, ensuring the reliability of the pressure protection system.
[0074] Temperature protection: Temperature sensors are installed in key areas such as the furnace, water pipe bundles, and flue gas passages to monitor the temperature in real time. When the temperature exceeds the set safe temperature, the automatic control system takes cooling measures, such as increasing the water supply, adjusting the burner's combustion intensity, or starting the cooling fan. The temperature sensors have a measurement accuracy of ±2℃, enabling timely and accurate monitoring of temperature changes and preventing equipment damage or safety accidents caused by excessive temperature.
[0075] Maintenance and care points
[0076] Regular Inspections: Develop a detailed regular inspection plan. Conduct weekly visual inspections of the boiler's appearance, connections, valves, and instruments to ensure there are no leaks, loose connections, or damage. Monthly internal inspections of the water pipe bundles should be performed, using an endoscope to check for corrosion, wear, or scaling on the pipe walls. Quarterly comprehensive inspections of the flue gas deflector, heat shield, and flue shell should be conducted to check their structural integrity and sealing performance. Annual comprehensive performance testing and safety assessment of the boiler should be performed, and maintenance and repairs should be carried out promptly based on the inspection and testing results.
[0077] Cleaning and Maintenance: Regularly clean the water pipe bundles to remove scale and impurities, ensuring good heat transfer and water circulation. A combination of chemical and physical cleaning methods can be used. Chemical cleaning uses specialized descaling agents, with cleaning time and concentration determined based on the composition and thickness of the scale. Physical cleaning uses high-pressure water jet cleaning to remove stubborn impurities from the pipes. Simultaneously, regularly clean the flue and smoke chamber to prevent ash buildup and blockages that could impede flue gas flow and heat exchange. For example, clean the water pipe bundles every 3-6 months and clean the flue and smoke chamber every 1-2 months.
[0078] Replacement of consumable parts: Replace consumable parts promptly based on boiler operating time and actual wear, such as burner nozzles, valve seals, water level sensors, and pressure sensors. Establish a consumable parts inventory management system to ensure timely availability of suitable replacement parts when needed. For example, the service life of burner nozzles is generally 5000-8000 hours. When the operating time approaches or exceeds this duration, the nozzles should be inspected and replaced promptly to ensure combustion efficiency and boiler performance.
[0079] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A high-efficiency heat exchange single-tube once-through boiler, the boiler body comprising an upper annular header (1), a steam outlet (2), a water pipe bundle (3), a flue shell (4), a flue gas guide plate device (5), a heat shield (6), a lower annular header (7), a drain pipe (8), a water inlet (9), and a flue gas outlet (10), characterized in that: The upper annular header (1) and the lower annular header (7) are located at the top and bottom of the boiler, respectively. The upper annular header (1) and the lower annular header (7) are connected by an annular water pipe bundle (3). The annular pipe bundle (3) adopts a close-packed pipe bundle with tangent pipes on the outside. The adjacent pipes in the close-packed pipe bundle are arranged radially to create a wedge-shaped gap. The heat shield (6) surrounds the water pipe bundle (3) to form a flue gas passage and prevents the flue gas from longitudinally scouring the water pipe bundle (3). The guide plate device (5) is arranged at the outlet of the flue gas passage formed by the heat shield (6) surrounding the water pipe bundle (3).
2. The high-efficiency heat exchange single-tube once-through boiler according to claim 1, characterized in that: The water pipe bundle (3) is formed by vertical water pipes (302) and inclined water pipes (301) arranged at intervals to form an annular pipe ring. The upper ends of the vertical water pipes (302) and inclined water pipes (301) are closely tangent, and the lower ends of adjacent pipe bundles are arranged radially to create a radial wedge-shaped gap structure. The inclination angle of the inclined water pipes (301) does not exceed 1°.
3. The high-efficiency heat exchange single-tube once-through boiler according to claim 1, characterized in that: The heat-resistant plate (6) includes a heat-resistant plate support plate (602) and a heat-resistant plate cylinder (601). The short side of the heat-resistant plate support plate (602) is welded to the heat-resistant plate cylinder (601), and the end of the long side of the heat-resistant plate support plate (602) is welded to the lower annular header (7).
4. A high-efficiency heat exchange single-tube once-through boiler according to claim 2, characterized in that: The vertical water pipe (302) and the inclined water pipe (301) are necked at their upper and lower ends. When the vertical water pipe (302) and the inclined water pipe (301) are closely arranged, the water pipe plates of the upper annular header (1) and the lower annular header (7) can form a hole bridge.
5. The high-efficiency heat exchange single-tube once-through boiler according to claim 1, characterized in that: The flue gas guide plate device (5) includes a front upper guide plate (501), a front lower guide plate (502), a rear upper guide plate (503), and a rear lower guide plate (504). The front lower guide plate (502) and the rear upper guide plate (503), and the rear lower guide plate (504) and the front upper guide plate (501) are connected by an intermediate support block (505). The front lower guide plate (502) and the rear lower guide plate (504) are fixed by an end support block (506). The combination of the front lower guide plate (502) and the rear upper guide plate (503) and the combination of the rear lower guide plate (504) and the front upper guide plate (501) forms a spiral passage with a spiral angle of 35° to 40°. The ratio of the lead of the spiral channel to the tube bundle height is 1:1.
2.
6. The high-efficiency heat exchange single-tube once-through boiler according to claim 1, characterized in that: The smoke chamber shell (4) is composed of a smoke chamber cylinder (401) and an expansion ring (402). The expansion ring (402) is formed by stamping a whole steel plate into an L-shaped ring with a longitudinal section. The long side of the L-shape is welded to the smoke chamber cylinder (401), and the short side of the L-shape is welded to the lower annular header (7).