A refrigeration machine surplus cold energy comprehensive utilization system
By designing a comprehensive system for utilizing surplus cooling capacity in refrigeration units, the problem of unused surplus cooling capacity in refrigeration units has been solved, achieving stable operation of refrigeration units, improving energy efficiency, and extending equipment life.
Patent Information
- Application Number
- CN202522581737.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-04
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-04
AI Technical Summary
In existing technologies, the excess cooling capacity of refrigeration units is not effectively utilized, resulting in energy waste and frequent start-ups and shutdowns of the refrigeration units, which reduces efficiency and service life.
A comprehensive system for utilizing surplus cooling capacity of a refrigeration unit was designed, including a refrigeration unit, water-using equipment, water pump, heat exchanger, control valve, and controller. Through pipeline connection and automated control, the system realizes the storage and distribution of surplus cooling capacity of the refrigeration unit. It adopts a Na2SO4·10H2O packed heat exchanger and an electromagnetic three-way valve, and is managed by a DCS or PLC controller.
It achieves efficient storage and distribution of the refrigeration unit's surplus cooling capacity, stabilizes the main system operation, avoids frequent start-ups and shutdowns of the refrigeration unit, extends equipment life, and improves energy utilization efficiency.
Smart Images

Figure CN225016916U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of refrigeration capacity utilization technology, specifically to a comprehensive utilization system for surplus refrigeration capacity. Background Technology
[0002] In large industrial parks, data centers, or large commercial complexes, central chiller stations are typically installed to provide cooling for process manufacturing (such as injection molding and chemical cooling) or building air conditioning. The selection of chiller types is usually based on meeting extreme summer loads, but in the following situations, a significant amount of "surplus cooling capacity" may be generated: During the transitional season and winter: ambient temperatures drop, and the cooling load of building air conditioning decreases significantly.
[0003] Nighttime or low-load conditions: Some production lines shut down, and the demand for process cooling decreases.
[0004] High-efficiency operating range of refrigeration units: Even in summer, when a refrigeration unit is operating at high efficiency under partial load, its cooling capacity output may momentarily exceed the actual demand.
[0005] Currently, the handling of this excess cooling capacity is very crude: either the excess heat is dissipated into the atmosphere through cooling towers, which is essentially a waste of electricity; or the units are manually shut down, leading to frequent start-ups and shutdowns of the chillers, reducing efficiency and lifespan. Existing technology lacks an effective system to collect this "waste cooling" and use it in other applications where needed, resulting in a huge waste of energy.
[0006] Therefore, there is an urgent need for new designs that can make reasonable use of the excess cooling capacity of refrigeration units. Utility Model Content
[0007] In view of the above-mentioned problems in the existing technology, the aim is to provide a system for comprehensive utilization of surplus cold energy in a refrigeration unit.
[0008] The specific technical solution is as follows: A system for comprehensively utilizing surplus cooling capacity of a refrigeration unit mainly includes: a refrigeration unit, water-using equipment, a water pump, a first control valve, a first pipeline, a second pipeline, a third pipeline, a fourth pipeline, a fifth pipeline, a heat exchanger, and a controller; The water inlet of the chiller is connected to the water pump through the first pipe, the water outlet of the chiller is connected to the water-using equipment through the second pipe, and the water-using equipment is connected to the water pump through the third pipe. One end of the heat exchanger is connected to the second pipeline through the fourth pipeline, and the other end of the heat exchanger is connected to the third pipeline through the fifth pipeline. The first control valve is installed on the fourth pipeline and is electrically connected to the controller.
[0009] The above-mentioned system for comprehensive utilization of surplus cooling capacity of a refrigeration unit also has the following features: it further includes a sixth pipeline, a seventh pipeline, a first three-way valve, a second three-way valve, and a second control valve. One end of the sixth pipeline is connected to the user's high-temperature water, and the other end of the sixth pipeline is connected to the first three-way valve. The first three-way valve is located in the fourth pipeline and between the first control valve and the heat exchanger. One end of the seventh pipeline is connected to the user's high-temperature water, and the other end of the seventh pipeline is connected to the second three-way valve, which is located on the fifth pipeline; The second control valve, the first three-way valve, and the second three-way valve are all connected to the user terminal.
[0010] The above-mentioned system for comprehensive utilization of surplus cold energy in a refrigeration unit also features a heat exchanger with Na2SO4·10H2O packing.
[0011] The above-mentioned system for comprehensive utilization of surplus cooling capacity in a refrigeration unit also has the following feature: both the first three-way valve and the second three-way valve are electromagnetic three-way valves.
[0012] The above-mentioned system for comprehensive utilization of surplus cooling capacity of a refrigeration unit also has the following feature: the controller is a DCS controller or a PLC controller.
[0013] The above-mentioned system for comprehensive utilization of surplus cooling capacity of a refrigeration unit also has the following feature: it further includes a temperature transmitter, which is connected to the third pipeline and located in the section where the water-using equipment and the heat exchanger are connected in parallel, and the temperature transmitter is electrically connected to the controller. The positive effects of the above technical solution are: This utility model provides a comprehensive system for utilizing surplus cooling capacity from a refrigeration unit. It stores the low-cost surplus cooling capacity generated by the refrigeration unit at night or during winter, meeting some of the cooling demand from users during peak electricity consumption periods. Stable main system operation: It avoids frequent start-ups and shutdowns of the refrigeration unit due to load fluctuations, ensuring the main unit always operates within its high-efficiency range and extending equipment lifespan. The system features a reasonable structure, a high degree of automation, and the ability to collect, store, and distribute surplus cooling capacity generated by the refrigeration unit to end users, thereby maximizing energy efficiency. Attached Figure Description
[0014] Figure 1 This is a schematic diagram of a system for comprehensively utilizing surplus cooling capacity in a refrigeration unit, which is provided by this utility model. In the attached diagram: 1. Refrigeration unit; 2. Water-using equipment; 3. Water pump; 4. Heat exchanger; 5. Controller; 6. Temperature transmitter; 101. First control valve; 102. Second control valve; 201. First pipeline; 202. Second pipeline; 203. Third pipeline; 204. Fourth pipeline; 205. Fifth pipeline; 206. Sixth pipeline; 207. Seventh pipeline; 301. First three-way valve; 302. Second three-way valve. Detailed Implementation
[0015] To make the objectives, technical solutions, and advantages of this utility model clearer, the present utility model will be further described in detail below through embodiments and in conjunction with the accompanying drawings. It should be understood that the specific embodiments described herein are merely illustrative of the present utility model and are not intended to limit the present utility model.
[0016] The serial numbers assigned to components in this document, such as "first," "second," etc., are merely for distinguishing the described objects and have no sequential or technical meaning. The terms "connection" and "linkage" used in this application, unless otherwise specified, include both direct and indirect connections (linkages). In the description of this utility model, it should be understood that the terms "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," "clockwise," and "counterclockwise," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are used solely for the convenience of describing this utility model and for simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this utility model.
[0017] In this utility model, unless otherwise explicitly specified and limited, "above" or "below" the second feature can mean that the first feature is in direct contact with the second feature, or that the first feature is in indirect contact with the second feature through an intermediate medium. Furthermore, "above," "on top of," and "over" the second feature can mean that the first feature is directly above or diagonally above the second feature, or simply that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "under" the second feature can mean that the first feature is directly below or diagonally below the second feature, or simply that the first feature is at a lower horizontal level than the second feature.
[0018] Please see Figure 1Where A is the cooling water inlet, B is the cooling water outlet, C is the user's high-temperature water inlet, and D is the user's high-temperature water outlet. This utility model discloses a system for comprehensively utilizing surplus cooling capacity of a refrigeration unit. The system includes: a refrigeration unit 1, water-using equipment 2, a water pump 3, a first control valve 101, a first pipeline 201, a second pipeline 202, a third pipeline 203, a fourth pipeline 204, a fifth pipeline 205, a heat exchanger 4, and a controller 5.
[0019] The water inlet of the chiller 1 is connected to the water pump 3 through the first pipe 201, the water outlet of the chiller 1 is connected to the water-using equipment 2 through the second pipe 202, and the water-using equipment 2 is connected to the water pump 3 through the third pipe 203.
[0020] One end of the heat exchanger 4 is connected to the second pipe 202 via the fourth pipe 204, and the other end of the heat exchanger 4 is connected to the third pipe 203 via the fifth pipe 205. The first control valve 101 is installed on the fourth pipe 204 and is electrically connected to the controller 5. This allows for the initial utilization of the surplus cooling capacity of the refrigeration unit.
[0021] In this embodiment, the chilled water produced by the chiller 1 circulates in the main supply and return water pipelines. When the first control valve 101 detects that the return water temperature is too low or the supply and return water pressure difference is too large (indicating that the load demand is less than the cooling capacity supply), the controller 5 issues a command to open the bypass valve (first control valve 101) and introduce a portion of the excess low-temperature chilled water into the heat exchanger 4.
[0022] Furthermore, it also includes a sixth pipe 206, a seventh pipe 207, a second control valve 102, a first three-way valve 301, and a second three-way valve 302. One end of the sixth pipe 206 is connected to the user's high-temperature water, and the other end is connected to the first three-way valve 301. The first three-way valve 301 is located on the fourth pipe 204 and between the first control valve 101 and the heat exchanger 4. One end of the seventh pipe 207 is connected to the user's high-temperature water, and the other end is connected to the second three-way valve 302. The second three-way valve 302 is located on the fifth pipe 205. The second control valve 102, the first three-way valve 301, and the second three-way valve 302 are all connected to the user end (not shown in the figure). This allows for the secondary utilization of the surplus cooling capacity of the chiller.
[0023] In this embodiment, when a user at the end of the system has a cooling demand, the system will prioritize using heat exchanger 4 as a cold source for heat exchange based on the user's control signal. If the user's heat exchange demand is met, the second control valve 102 will be closed. Specifically, the user sends a signal to the second control valve 102, the first three-way valve 301, and the second three-way valve 302 to send the user's high-temperature water into the heat exchanger 4 for cooling and then back to the user.
[0024] Optionally, the heat exchanger may be a heat exchanger filled with Na2SO4·10H2O.
[0025] Optionally, both the first three-way valve 301 and the second three-way valve 302 are electromagnetic three-way valves.
[0026] Optionally, the controller is a DCS controller or a PLC controller.
[0027] Furthermore, it also includes a temperature transmitter 6, which is connected to the third pipeline 203 and located in the section where the water-using equipment 2 and the heat exchanger 4 are connected in parallel, and the temperature transmitter 6 is electrically connected to the controller 5.
[0028] This utility model provides a comprehensive system for utilizing surplus cooling capacity from a refrigeration unit. It stores the low-cost surplus cooling capacity generated by the refrigeration unit at night or during winter, meeting some of the cooling demand from users during peak electricity consumption periods. Stable main system operation: It avoids frequent start-ups and shutdowns of the refrigeration unit 1 due to load fluctuations, ensuring the main unit always operates within its high-efficiency range and extending equipment lifespan. The system features a reasonable structure, high degree of automation, and the ability to collect, store, and distribute the surplus cooling capacity generated by the refrigeration unit 1 to end users, thereby maximizing energy efficiency. The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0029] The embodiments described above are merely illustrative of several implementations of this utility model, and while the descriptions are relatively specific and detailed, they should not be construed as limiting the scope of this utility model patent. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of this utility model, and these all fall within the protection scope of this utility model. Therefore, the protection scope of this utility model patent should be determined by the appended claims.
Claims
1. A system for comprehensively utilizing surplus cooling capacity of a refrigeration unit, characterized in that, include: Refrigeration unit, water-using equipment, water pump, first control valve, first pipeline, second pipeline, third pipeline, fourth pipeline, fifth pipeline, heat exchanger and controller; The water inlet of the chiller is connected to the water pump through the first pipe, the water outlet of the chiller is connected to the water-using equipment through the second pipe, and the water-using equipment is connected to the water pump through the third pipe. One end of the heat exchanger is connected to the second pipeline through the fourth pipeline, and the other end of the heat exchanger is connected to the third pipeline through the fifth pipeline. The first control valve is installed on the fourth pipeline and is electrically connected to the controller.
2. The system for comprehensive utilization of surplus cooling capacity in a refrigeration unit according to claim 1, characterized in that, It also includes a sixth pipeline, a seventh pipeline, a first three-way valve, a second three-way valve, and a second control valve. One end of the sixth pipeline is connected to the user's high-temperature water, and the other end of the sixth pipeline is connected to the first three-way valve. The first three-way valve is located in the fourth pipeline and between the first control valve and the heat exchanger. One end of the seventh pipeline is connected to the user's high-temperature water, and the other end of the seventh pipeline is connected to the second three-way valve, which is located on the fifth pipeline; The second control valve, the first three-way valve, and the second three-way valve are all connected to the user terminal.
3. The system for comprehensive utilization of surplus refrigeration capacity of a refrigeration unit according to claim 2, characterized in that, The heat exchanger uses Na2SO4·10H2O packing.
4. The system for comprehensive utilization of surplus refrigeration capacity of a refrigeration unit according to claim 2, characterized in that, Both the first three-way valve and the second three-way valve are electromagnetic three-way valves.
5. The refrigeration surplus cooling capacity comprehensive utilization system according to any one of claims 1 to 4, characterized in that, The controller is a DCS controller or a PLC controller.
6. The refrigeration surplus cooling capacity comprehensive utilization system according to any one of claims 1 to 4, characterized in that, It also includes a temperature transmitter, which is connected to the third pipeline and located in the section where the water-using equipment and the heat exchanger are connected in parallel, and the temperature transmitter is electrically connected to the controller.