Multi-layer electrode sealing device for calcium carbide furnace

By adopting a three-layer sealing structure and a downward pressure structure in the calcium carbide furnace, the problem of poor sealing effect is solved, smoke reduction and flame protection are achieved, and the service life of the calcium carbide furnace is extended.

CN225017140UActive Publication Date: 2026-11-24JUNZHENG (ORDOS CITY) CHEM CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522555717.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-02
Publication Date
2026-11-24
Estimated Expiration
2035-12-02

AI Technical Summary

Technical Problem

The existing sealing device for calcium carbide furnaces suffers from poor sealing performance due to prolonged wear during electrode operation, resulting in serious flue gas leakage. Furthermore, the flame burns the water hose, leading to abnormal furnace shutdowns.

Method used

It adopts a three-layer sealing structure, including a lower layer of refractory bricks, a middle layer of refractory bricks, and a sealing packing. Combined with the connection method of bolts, nuts, and insulating plates, it forms a multi-layer sealing device, which enhances the sealing effect and maintains the tight fit of the sealing packing through the downward pressure structure.

Benefits of technology

It effectively reduces flue gas leakage, prevents burn damage from flames, extends the service life of sealing devices, and ensures the stable operation of the calcium carbide furnace.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225017140U_ABST
    Figure CN225017140U_ABST
Patent Text Reader

Abstract

This utility model discloses a multi-layer electrode sealing device for a calcium carbide furnace, comprising three sealing structures arranged sequentially from bottom to top. The first sealing structure includes a lower sealing ring, the inner wall of which is lined with lower refractory bricks, and a lower flange. The second sealing structure includes a middle sealing ring, the bottom of which has a lower flange fixed to the lower flange, the inner wall of which is lined with middle refractory bricks, and the top outer wall of which has an upper flange. The third sealing structure includes an upper sealing ring, the bottom of which has an upper flange, one side of which is filled with three layers of sealing packing, and multiple bases fixed to the top outer wall of which each base has a pressing structure that moves up and down to press down the sealing packing. Advantages: The three-layer sealing structure prevents flue gas leakage. The pressing structure firmly compresses the sealing packing, making it less prone to loosening. The double-layer refractory bricks reduce the damage to the water pipe caused by flame jetting.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of machinery, specifically to a multi-layer electrode sealing device for a calcium carbide furnace. Background Technology

[0002] In calcium carbide smelting, electrodes are inserted into an electric arc furnace to heat ore raw materials, primarily calcium carbide. The electrodes are externally fixed with copper sleeves and pressure rings, and an outermost protective screen is fitted around them. This protective screen contacts the side wall of the furnace cover and enters the furnace through the furnace opening. The protective screen and the furnace cover experience dynamic friction. To prevent gas leakage through the gaps in contact, a fixed sealing device is typically installed on the furnace cover. This device has two internal layers: a bottom layer of refractory bricks and a top layer of insulating rock wool. However, during electrode operation, prolonged wear causes the rock wool to loosen and fall off, leading to increased gaps and a poorer seal. This not only makes gas leakage easier but also causes flames to shoot out and burn the surrounding cooling hoses when the furnace pressure rises, resulting in abnormal shutdowns of the calcium carbide furnace. Utility Model Content

[0003] The purpose of this invention is to provide a multi-layer electrode sealing device for a calcium carbide furnace.

[0004] This utility model is implemented by the following technical solution: A multi-layer electrode sealing device for a calcium carbide furnace includes three sealing structures arranged sequentially from bottom to top. The first sealing structure includes a lower sealing ring, the bottom of which is fixed to the top of the furnace cover. A lower refractory brick with a cross-section of "7" extending to the inner wall of the furnace cover is built on the inner wall of the lower sealing ring. A lower flange is fixed to the top of the lower sealing ring. The second sealing structure includes a middle sealing ring, a lower flange fixed to the bottom of the middle sealing ring, an insulating plate sandwiched between the lower flange and the lower flange, and the lower flange and the lower flange connected and fixed by bolts and nuts. The inner wall of the middle sealing ring is built with middle refractory bricks, and an upper flange is fixed to the top outer wall of the middle sealing ring. The third sealing structure includes an upper sealing ring, with an upper flange fixed to the bottom of the upper sealing ring. An insulating plate is sandwiched between the upper flange and the middle upper flange, and the upper flange and the middle upper flange are connected and fixed by bolts and nuts. Three layers of sealing packing are filled on one side of the inner wall of the upper sealing ring. Multiple bases are circumferentially fixed on the top outer wall of the upper sealing ring, and each base has a pressing structure that moves up and down to press down the sealing packing.

[0005] Preferably, the bolt is fitted with an insulating sleeve, and there are insulating gaskets between the bolt and nut and the upper flange, the lower flange, the upper middle flange, or the lower middle flange.

[0006] Preferably, the pressing structure includes a screw, an L-shaped frame, and a pressure plate. The bottom end of the screw is fixed to the base. One end of the L-shaped frame is horizontally sleeved on the screw, and a nut is screwed to the top end of the screw. The other end of the L-shaped frame extends to one side of the inner wall of the upper sealing ring and is fixed to the pressure plate. The pressure plate presses down on the top of the uppermost sealing packing.

[0007] The advantages of this utility model are: during the electrode operation, its protective screen is in close contact and sealed with the lower layer of refractory bricks, the middle layer of refractory bricks, and the sealing packing of the three-layer sealing structure. The lower layer of refractory bricks and the middle layer of refractory bricks prevent some of the smoke from leaking out, can insulate heat, isolate flames, and also provide insulation. The sealing packing is in soft contact with the protective screen and fits tightly, further reducing smoke leakage.

[0008] Multiple pressing structures compress the three-layer sealing packing tightly between the upper sealing ring and the protective screen, reducing the possibility of loosening and falling off. The pressing structure is easy to disassemble, which also facilitates the maintenance and replacement of the packing, thereby reducing the chance of gaps increasing and improving the sealing effect.

[0009] The double-layer refractory brick insulation reduces the occurrence of water hose damage from flames. The upper flange is fixed to the top outer wall of the middle sealing ring. Removing the third sealing structure directly exposes the middle refractory brick, which facilitates maintenance and replacement of damaged middle refractory bricks, promotes long-term maintenance and use, ensures sealing effect, and extends service life. Attached Figure Description

[0010] To more clearly illustrate the technical solutions in the embodiments of this utility model or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0011] Figure 1 This is a schematic diagram of the overall structure of this utility model.

[0012] Figure 2 yes Figure 1 A magnified view of part A in the diagram.

[0013] Figure 3 yes Figure 1 Top view.

[0014] In the diagram: 1. Lower sealing ring; 2. Furnace cover; 3. Lower refractory brick; 4. Lower flange; 5. Middle sealing ring; 6. Middle and lower flange; 7. Insulating plate; 8. Bolt; 9. Nut; 10. Middle refractory brick; 11. Middle and upper flange; 12. Upper sealing ring; 13. Upper flange; 14. Sealing packing; 15. Base; 16. Lower pressure structure; 16. Screw; 16.1. L-shaped frame; 16.2. Pressure plate; 16.3. Insulating sleeve; 17. Insulating gasket; 18. Detailed Implementation

[0015] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0016] like Figure 1 , Figure 2 , Figure 3 As shown, a multi-layer electrode sealing device for a calcium carbide furnace includes three sealing structures arranged sequentially from bottom to top. The first sealing structure includes a lower sealing ring 1, the bottom of which is fixed to the top of the furnace cover 2. A lower refractory brick 3 with a cross-section of "7" extending to the inner wall of the furnace cover 2 is built on the inner wall of the lower sealing ring 1. A lower flange 4 is fixed to the top of the lower sealing ring 1. The lower layer of refractory bricks 3 is arranged at the bottom layer and sealed on the top of the furnace cover 2. A ring is built around the inner wall of the lower layer sealing ring 1. The gap between the lower layer sealing ring 1 and the protective screen is limited. When the electrode moves, it contacts the protective screen to prevent some flue gas from leaking out. It can also insulate heat and isolate flames. The lower layer of refractory bricks 3 is made of first-grade high-alumina refractory bricks and can also provide insulation.

[0017] The second sealing structure includes a middle sealing ring 5, a lower flange 6 fixed to the bottom of the middle sealing ring 5, an insulating plate 7 sandwiched between the lower flange 6 and the lower flange 4, and the lower flange 6 and the lower flange 4 are connected and fixed by bolts 8 and nuts 9. A middle layer of refractory bricks 10 are built on the inner wall of the middle sealing ring 5, and an upper flange 11 is fixed to the top outer wall of the middle sealing ring 5. The middle layer refractory bricks 10 are arranged in the middle layer, and a ring is built around the inner wall of the middle layer sealing ring 5. The distance between the middle layer sealing ring 5 and the protective screen is limited. When the electrode moves, it contacts the protective screen to prevent some smoke from leaking out. It can also insulate heat and isolate flames. The middle layer refractory bricks 10 are made of first-grade high-alumina refractory bricks, which can also provide insulation.

[0018] The upper flange 11 is fixed to the top outer wall of the middle sealing ring 5. The third sealing structure is removed, directly exposing the middle refractory brick 10, which facilitates maintenance and replacement of the burned middle refractory brick 10, and is conducive to long-term maintenance and use, ensuring sealing effect and extending service life.

[0019] The third sealing structure includes an upper sealing ring 12, an upper flange 13 fixed to the bottom of the upper sealing ring 12, an insulating plate 7 sandwiched between the upper flange 13 and the middle upper flange 11, and the upper flange 13 and the middle upper flange 11 are connected and fixed by bolts 8 and nuts 9. Three layers of sealing packing 14 are filled on one side of the inner wall of the upper sealing ring 12. Multiple bases 15 are circumferentially fixed on the top outer wall of the upper sealing ring 12. The top of each base 15 has a pressing structure 16 that presses down the sealing packing 14.

[0020] The sealing packing 14 is a commercially available packing, also called sealing filler. It is made of expanded graphite yarn through braiding and is commonly used in most applications except for strong oxidizers. It can be used for boiling water, high temperature, high pressure steam, heat exchange media, oils, acids, alkalis, hydrogen, ammonia, organic solvents, hydrocarbons, cryogenic liquids, and other media. The sealing packing 14 is arranged on the top layer, circumferentially surrounding the inner wall of the upper sealing ring 12, between the upper sealing ring 12 and the protective screen. Because it is a braided material, it is soft and can fit tightly with the protective screen. When the electrode moves, it comes into contact with the protective screen. With the first and second layer sealing structures already preventing most of the smoke leakage, providing heat insulation, and isolating flames, further reducing smoke leakage greatly improves the effect. The three-layer structure also ensures better performance. Multiple downward pressing structures 16 press down and tighten the three-layer sealing packing 14, pressing it firmly between the upper sealing ring 12 and the protective screen, reducing the possibility of loosening and falling off.

[0021] An insulating sleeve 17 is fitted on the bolt 8. An insulating gasket 18 is placed between the bolt 8, the nut 9 and the upper flange 13, the lower flange 4, the upper middle flange 11 or the lower middle flange 6.

[0022] The protective screen and the three-layer sealing structure are insulated with refractory bricks and packing. The connection between the three-layer sealing structures is also insulated with insulating board 7, insulating sleeve 17, and insulating gasket 18.

[0023] The pressing structure 16 includes a screw 16.1, an L-shaped frame 16.2, and a pressure plate 16.3. The bottom end of the screw 16.1 is fixed to the base 15. One end of the L-shaped frame 16.2 is horizontally sleeved on the screw 16.1, and a nut 9 is screwed to the top end of the screw 16.1. The other end of the L-shaped frame 16.2 extends to one side of the inner wall of the upper sealing ring 12 and is fixed to the pressure plate 16.3. The pressure plate 16.3 presses down on the top of the uppermost sealing packing 14.

[0024] Tightening nut 9 downwards compresses the L-shaped frame 16.2, which, along with the pressure plate 16.3 (made of stainless steel), moves up and down on the screw 16.1, pressing down the uppermost sealing packing 14.

[0025] Working principle: When this utility model is in use, the protective screen of the electrode moves up and down, and will fit and seal with the lower refractory brick 3, the middle refractory brick 10 and the three-layer sealing packing 14 of the three-layer sealing structure. The lower refractory brick 3 and the middle refractory brick 10 prevent some smoke from leaking out, and can also insulate heat and isolate flames. They are all made of first-grade high-alumina refractory bricks and can also provide insulation.

[0026] The sealing packing 14 makes soft contact with the protective screen, fitting tightly to further reduce smoke leakage and greatly improve the effect. The three-layer structure also ensures better performance.

[0027] Multiple pressing structures 16 press the three-layer sealing packing 14 tightly between the upper sealing ring 12 and the protective screen, reducing the possibility of loosening and falling off.

[0028] The upper flange 11 is fixed to the top outer wall of the middle sealing ring 5. The third sealing structure is removed, directly exposing the middle refractory brick 10, which facilitates maintenance and replacement of the burned middle refractory brick 10, and is conducive to long-term maintenance and use, ensuring sealing effect and extending service life.

[0029] The above description is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present utility model should be included within the protection scope of the present utility model.

Claims

1. A multi-layer electrode sealing device for a calcium carbide furnace, characterized in that, It includes a three-layer sealing structure arranged from bottom to top. The first layer sealing structure includes a lower sealing ring. The bottom of the lower sealing ring is fixed to the top of the furnace cover. A lower refractory brick with a "7" shaped cross section is built on the inner wall of the lower sealing ring and extends to the inner wall of the furnace cover. A lower flange is fixed to the top of the lower sealing ring. The second sealing structure includes a middle sealing ring, a lower flange fixed to the bottom of the middle sealing ring, an insulating plate sandwiched between the lower flange and the lower flange, and the lower flange and the lower flange connected and fixed by bolts and nuts. The inner wall of the middle sealing ring is built with middle refractory bricks, and an upper flange is fixed to the top outer wall of the middle sealing ring. The third sealing structure includes an upper sealing ring, with an upper flange fixed to the bottom of the upper sealing ring. An insulating plate is sandwiched between the upper flange and the middle upper flange, and the upper flange and the middle upper flange are connected and fixed by bolts and nuts. Three layers of sealing packing are filled on one side of the inner wall of the upper sealing ring. Multiple bases are circumferentially fixed on the top outer wall of the upper sealing ring, and each base has a pressing structure that moves up and down to press down the sealing packing.

2. The multi-layer electrode sealing device for a calcium carbide furnace according to claim 1, characterized in that: The bolt is fitted with an insulating sleeve, and there are insulating gaskets between the bolt and nut and the upper flange, the lower flange, the upper middle flange, or the lower middle flange.

3. The multi-layer electrode sealing device for a calcium carbide furnace according to claim 1, characterized in that: The pressing structure includes a screw, an L-shaped frame, and a pressure plate. The bottom end of the screw is fixed to the base. One end of the L-shaped frame is horizontally sleeved on the screw, and a nut is screwed to the top end of the screw. The other end of the L-shaped frame extends to one side of the inner wall of the upper sealing ring and is fixed to the pressure plate. The pressure plate presses down on the top of the uppermost sealing packing.