A perpendicularity calibration device
By using connecting ropes and floating marker components in the verticality calibration device for underwater steel pipe columns, the problem of high cost in underwater steel pipe column verticality calibration was solved, achieving efficient and low-cost verticality calibration and improving construction quality.
Patent Information
- Application Number
- CN202522653872.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-15
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-15
AI Technical Summary
In existing technologies, underwater steel pipe column verticality calibration equipment is costly and difficult to maintain accuracy in underwater environments, making it difficult to guarantee construction quality.
A verticality calibration device is adopted, which includes a first verticality measuring component, a second verticality measuring component, a first verticality adjustment component, and a second verticality adjustment component. The device uses a second connecting rope and a floating marker component to replace the traditional underwater positioning sensor. The device achieves coaxial setting by measuring and adjusting the verticality of the tool section and the underwater steel pipe column.
It significantly reduces calibration costs, improves the efficiency and accuracy of underwater steel pipe column verticality calibration, is simple to operate, highly adaptable, and reduces dependence on the environment and weather.
Smart Images

Figure CN225017425U_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of construction technology, and in particular to a verticality calibration device. Background Technology
[0002] With the rapid development of urban underground spaces, underground transportation hubs, and large-scale underground projects, the use of reverse construction methods and the installation of permanent steel pipe columns as structural support systems is becoming increasingly common. As a key component of the load-bearing system, the verticality and coaxiality of the steel pipe columns directly affect the stress safety of the superstructure and the quality of subsequent construction. Therefore, higher requirements are placed on the verticality calibration of steel pipe columns in underwater environments.
[0003] In existing construction methods, underwater steel pipe columns are typically installed using an HPE hydraulic vertical insertion machine in conjunction with tool sections. The tool sections are lowered together with the underwater steel pipe column after being connected via flange assemblies. However, due to factors such as manufacturing processes, processing errors, long-term use of the tool sections, wear and tear from flange assembly disassembly and assembly, and uneven stress during on-site hoisting, the flange assemblies are prone to deformation. This often makes it difficult to maintain ideal coaxiality between the flange connection surfaces of the tool section and the steel pipe column, leading to axial misalignment. Furthermore, the heavy weight of the steel pipe column makes it susceptible to slight deformation during hoisting and trenching due to uneven stress, making it difficult to maintain the original on-shore alignment accuracy in the underwater environment.
[0004] In actual underwater construction sites, installing precision verticality equipment such as laser measuring instruments and underwater sensors on the underwater bottom of underwater steel pipe columns presents the problem that these devices cannot be recovered, making them disposable consumables with high costs and unsuitable for large-scale construction. Utility Model Content
[0005] This application aims to solve at least one of the technical problems existing in the prior art. This application provides a verticality calibration device with a simple structure and low cost.
[0006] The verticality calibration device according to an embodiment of this application includes: A first perpendicularity measuring component is disposed on the tool section and is used to measure the first perpendicularity of the tool section; The second verticality measuring component is mounted on an underwater steel pipe column and is used to measure the second verticality of the underwater steel pipe column. The second verticality measuring component includes a second connecting rope and a floating marker component. The first end of the second connecting rope is connected to the underwater end of the underwater steel pipe column, and the second end of the second connecting rope is connected to the floating marker component. A first verticality adjustment component is disposed on the toolbar and is used to adjust the first verticality of the toolbar; The second verticality adjustment component is disposed between the tool section and the underwater steel pipe column, and is used to adjust the inclination of the tool section and the underwater steel pipe column so that the tool section and the underwater steel pipe column are set on the same axis.
[0007] The verticality calibration device according to the embodiments of this application has at least the following beneficial effects: The verticality calibration device of this application includes a first verticality measuring component, a second verticality measuring component, a first verticality adjusting component, and a second verticality adjusting component. The first verticality measuring component is mounted on the tool section and can measure the first verticality of the tool section in its current state. The second verticality measuring component is mounted on the underwater steel pipe column and can measure the second verticality of the underwater steel pipe column. The second verticality measuring component includes a second connecting rope and a floating marker component. The first end of the second connecting rope is fixedly connected to the underwater end of the underwater steel pipe column, and the floating marker component can float in the water. The second end of the second connecting rope is fixedly connected to the floating marker component. When the underwater steel pipe column is underwater, the floating marker component can form a clear floating marker point on the water surface, with the floating marker point offset L2 relative to the wall of the underwater steel pipe column. The first verticality adjusting component is mounted on the tool section. Based on the first verticality parameter value of the tool section measured by the first verticality measuring component, the first verticality of the tool section is adjusted by the first verticality adjusting component to correct the verticality of the tool section, making the tool section longitudinally vertical. The second verticality adjustment component is installed between the tool section and the underwater steel pipe column. After the tool section is calibrated, the second verticality of the underwater steel pipe column is adjusted by the second verticality adjustment component according to the second verticality parameter value of the underwater steel pipe column measured by the second verticality measuring component, so as to correct the verticality of the underwater steel pipe column, making the underwater steel pipe column longitudinally vertical, and aligning the first central axis of the tool section with the second central axis of the underwater steel pipe column.
[0008] The verticality calibration device of this application replaces the use of traditional underwater positioning sensors with a second verticality measuring component that includes only a second connecting rope and a floating marker component, which significantly reduces the calibration cost of tool sections and underwater steel pipe columns; the second verticality measuring component of this application can instantly reflect the verticality offset of the underwater steel pipe column after underwater installation, thereby improving calibration efficiency.
[0009] According to some embodiments of this application, the first verticality measuring component includes a first connecting rope and a plumb bob marker component, a first end of the first connecting rope being connected to a tool section, and a second end of the first connecting rope being connected to the plumb bob marker component.
[0010] According to some embodiments of this application, a plane is provided at a first preset distance away from the underwater bottom surface of the underwater steel pipe column, and the first end of the second connecting rope is fixedly disposed on the plane.
[0011] According to some embodiments of this application, a first fixed end is provided at the first central axis of the tool section, and a second fixed end is provided at the second central axis of the underwater steel pipe column. The first end of the first connecting rope is connected to the first fixed end, and the first end of the second connecting rope is connected to the second fixed end.
[0012] According to some embodiments of this application, the first preset distance is set to 0.5m to 2m.
[0013] According to some embodiments of this application, when both the first connecting rope and the second connecting rope are vertical, the plumb bob marker component and the floating marker component are separated by a second preset distance, which is set to 3mm to 5mm.
[0014] According to some embodiments of this application, the second verticality adjustment assembly includes a flange assembly and a bolt assembly, and the tool section is connected to the underwater steel pipe column through the cooperation of the flange assembly and the bolt assembly.
[0015] According to some embodiments of this application, the flange assembly includes a first flange and a second flange, the first flange being connected to a tool section and the second flange being connected to an underwater steel pipe string, and the first flange and the second flange being detachably connected by the bolt assembly.
[0016] According to some embodiments of this application, the second verticality adjustment assembly further includes a rubber gasket disposed between the first flange and the second flange.
[0017] According to some embodiments of this application, the second connecting rope is configured as a fishing line, and the floating marker component is configured as a fishing float. Attached Figure Description
[0018] The present application will be further described below with reference to the accompanying drawings and embodiments, wherein: Figure 1 This is a schematic diagram of a structure in which both the tool section and the underwater steel pipe column are in an uncorrected state according to an embodiment of this application; Figure 2 This is a schematic diagram of the underwater steel pipe column in an embodiment of this application, after the tool section has been corrected and is in an uncorrected state. Figure 3 This is a schematic diagram of the structure of an embodiment of this application, in which both the tool section and the underwater steel pipe column are in a state of completed calibration.
[0019] Figure label: Tool section 1; First central axis 11; First fixed end 12; 2. Underwater steel pipe column; 21. Plane; 22. Second central axis; 23. Second fixed end; First verticality measuring component 3; First connecting rope 31; Plumb bob marking component 32; Second verticality measuring component 4; Second connecting rope 41; Fishing line 411; Floating marker component 42; Fishing float 421; First verticality adjustment component 5; HPE hydraulic vertical insertion device 51; Second verticality adjustment component 6; flange assembly 61. Detailed Implementation
[0020] The embodiments of this application are described in detail below. Examples of these embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals denote the same or similar elements or elements having the same or similar functions throughout. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain this application, and should not be construed as limiting this application.
[0021] In the description of this application, it should be understood that the use of terms such as "center," "middle," "longitudinal," "transverse," "length," "width," "thickness," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," "axial," "radial," and "circumferential" to indicate orientation or positional relationships is based on the orientation or positional relationships shown in the accompanying drawings and is only for the convenience of describing this application and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this application. Furthermore, features defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this application, unless otherwise stated, "a plurality of" means two or more.
[0022] In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installation," "connection," and "linking" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection between two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.
[0023] The following reference Figures 1 to 3 Describe the verticality calibration device in the embodiments of this application.
[0024] according to Figures 1 to 3As shown, an embodiment of the verticality calibration device of this application includes a first verticality measuring component 3, a second verticality measuring component 4, a first verticality adjusting component 5, and a second verticality adjusting component 6. The first verticality measuring component 3 is mounted on the tool section 1 and is capable of measuring the first verticality of the tool section 1 in its current state. The second verticality measuring component 4 is mounted on the underwater steel pipe column 2 and is capable of measuring the second verticality of the underwater steel pipe column 2 in its current state. The second verticality measuring component 4 includes a second connecting rope 41 and a floating marker component 42. The first end of the second connecting rope 41 is fixedly connected to the underwater end of the underwater steel pipe column 2. The buoyancy force on the floating marker component 42 is greater than its weight, allowing it to float in the water. The second end of the second connecting rope 41 is fixedly connected to the floating marker component 42. The first verticality adjusting component 5 is mounted on the tool section 1 and is used to adjust the attitude of the tool section 1 to adjust its first verticality. The second verticality adjustment component 6 is installed between the tool section 1 and the underwater steel pipe column 2 to adjust the relative inclination of the tool section 1 and the underwater steel pipe column 2, so that the first central axis 11 of the tool section 1 is aligned and coincides with the second central axis 22 of the underwater steel pipe column 2, thereby achieving coaxial setting.
[0025] In use, S1. The first verticality of tool section 1 is obtained through the first verticality measuring component 3; the floating mark component 42 is installed on the underwater end of the underwater steel pipe column 2 through the second connecting rope 41, the floating mark component 42 floats up and forms a clear floating mark point on the water surface, and the second verticality of the underwater steel pipe column 2 can be obtained by the offset L2 of the floating mark point relative to the wall of the underwater steel pipe column 2.
[0026] S2. Determine whether tool section 1 is tilted based on the first perpendicularity of tool section 1 measured by the first perpendicularity measuring component 3.
[0027] See Figure 1 If tool section 1 is tilted, the posture of tool section 1 is adjusted by the first verticality adjustment component 5 to correct the first verticality of tool section 1 and make tool section 1 vertical in the longitudinal direction.
[0028] See Figure 2 If tool section 1 is in a vertical state, proceed to the next step S3.
[0029] S3. After tool section 1 is calibrated, determine whether the underwater steel pipe column 2 is tilted based on the second verticality measured by the second verticality measuring component 4.
[0030] See Figure 2If the underwater steel pipe column 2 is tilted, the attitude of the underwater steel pipe column 2 is adjusted by the second verticality adjustment component 6 to correct the second verticality of the underwater steel pipe column 2, so that the underwater steel pipe column 2 is vertical in the longitudinal direction, and the first central axis 11 of the tool section 1 and the second central axis 22 of the underwater steel pipe column 2 are aligned and coincident (see...). Figure 3 ).
[0031] See Figure 3 If the underwater steel pipe column 2 is in a vertical position, no adjustment is required.
[0032] The verticality calibration device of this application acquires the verticality of tool section 1 and underwater steel pipe column 2 through a first verticality measuring component 3 and a second verticality measuring component 4, respectively. Based on the verticality parameters, the axial deviation of tool section 1 and underwater steel pipe column 2 is adjusted sequentially through a first verticality adjusting component 5 and a second verticality adjusting component, ensuring coaxial alignment. This verticality calibration device replaces the traditional underwater positioning sensor with a second verticality measuring component 4, which only includes a second connecting rope 41 and a floating marker component 42, significantly reducing the calibration cost of tool section 1 and underwater steel pipe column 2. The second verticality measuring component 4 can instantly reflect the verticality offset of underwater steel pipe column 2 after underwater installation, thereby improving calibration efficiency. The verticality calibration device of this application has a simple structure and is easy to operate, requiring less expertise from operators, possessing superior practicality, and is unaffected by construction environment, weather, or temperature.
[0033] according to Figures 1 to 3 As shown, in one embodiment of this application, the first verticality measuring component 3 includes a first connecting rope 31 and a plumb bob marker component 32. The first end of the first connecting rope 31 is connected to the tool section 1, and the second end of the first connecting rope 31 is connected to the plumb bob marker component 32. The plumb bob marker component 32 is installed on the upper end of the tool section 1 via the first connecting rope 31. The plumb bob marker component 32 can hang naturally under gravity, and the first connecting rope 31 is vertically taut. The first verticality of the tool section 1 can be obtained by the offset L1 of the plumb bob marker component 32 relative to the wall of the tool section 1.
[0034] When in use, after tool section 1 is calibrated, S3. determine whether the underwater steel pipe column 2 is tilted based on the second verticality measured by the second verticality measuring component 4.
[0035] See Figure 2If the underwater steel pipe column 2 is in an inclined state, the difference L3 between the floating marker component 42 and the plumb bob marker component 32 is obtained. By comparing the offset value L2 with the difference L3, the difference between the central axis of the tool section 1 and the underwater steel pipe column 2 is determined. The attitude of the underwater steel pipe column 2 is adjusted by the second verticality adjustment component 6 to correct the second verticality of the underwater steel pipe column 2, so that the underwater steel pipe column 2 is vertical in the longitudinal direction, and the first central axis 11 of the tool section 1 and the second central axis 22 of the underwater steel pipe column 2 are aligned and coincident.
[0036] In some embodiments, the plumb bob marker component 32 and / or the float marker component 42 may be provided with visible markings.
[0037] In some embodiments, the plumb bob marker component 32 may be configured as a plumb bob (not shown).
[0038] according to Figures 1 to 3 As shown, in one embodiment of this application, the second connecting rope 41 is configured as a fishing line 411, and the floating marker component 42 is configured as a fishing float 421.
[0039] In the verticality calibration device of this application, the operator only needs to visually determine the offset of the tool section 1 and the underwater steel pipe column 2 by cooperating the plumb bob marker component 32 with the first connecting rope 31 and the floating marker component 42 with the second connecting rope 41. The operation and structure are extremely simple, and it has strong scalability and practicality. In addition, the fishing line 411 and the float 421 are extremely low in cost, about 10 yuan, and are easy to purchase, which can further enhance the practicality of the verticality calibration device of this application.
[0040] In some other embodiments, the first verticality measuring component 3 can be configured as a verticality sensing device, optical device, laser device, etc., for obtaining the verticality of tool section 1, but the above-mentioned devices are expensive and difficult to use widely.
[0041] according to Figures 1 to 3 As shown, in one embodiment of this application, the underwater steel pipe column 2 has a plane 21 located at a first preset distance d away from its underwater bottom surface. A second fixed end 23 is provided on this plane 21, and the first end of the second connecting rope 41 is fixedly installed on the second fixed end 23 on this plane 21. In one embodiment of this application, the first preset distance d is set to 0.5m to 2m. Compared to directly installing the second fixed end 23 on the underwater bottom surface, installing the second fixed end 23 on the plane 21 at a first preset distance d above the bottom surface can prevent the underwater steel pipe column 2 from accidentally colliding with the bottom surface and damaging the second fixed end 23 during descent, thereby preventing damage to the second verticality measuring component 4.
[0042] according to Figures 1 to 3As shown, in one embodiment of this application, a first fixed end 12 is provided at the first central axis 11 of the tool section 1, and the first fixed end 12 is used to connect to the first end of the first connecting rope 31. A second fixed end 23 is provided at the second central axis 22 of the underwater steel pipe column 2, and the second fixed end 23 is used to connect to the first end of the second connecting rope 41. Since the first fixed end 12 and the second fixed end 23 are respectively located on the central axes of the tool section 1 and the underwater steel pipe column 2, when the plumb bob marker component 32 and the floating marker component 42 (the first connecting rope 31 and the second connecting rope 41) are aligned, that is, the tool section 1 and the underwater steel pipe column 2 are coaxially aligned; otherwise, when they are not aligned, that is, the tool section 1 and the underwater steel pipe column 2 are not coaxially aligned. The verticality calibration device of this application can intuitively and quickly reflect the calibration status of the tool section 1 and the underwater steel pipe column 2 through the setting of the central axis. Even if there is a slight tilt, it can be quickly identified, which is convenient for detection.
[0043] according to Figures 1 to 3 As shown, in one embodiment of this application, when both the first connecting rope 31 and the second connecting rope 41 are vertical, the plumb bob marker component 32 and the floating marker component 42 are separated by a second preset distance, which is set to 3mm to 5mm. This allows the operator to more intuitively observe whether the first connecting rope 31 and the second connecting rope 41 are coaxially arranged and obtain the difference L3 between the floating marker component 42 and the plumb bob marker component 32.
[0044] In some embodiments, the first verticality measuring component 3 further includes a first rope length adjusting component (not shown), and / or the second verticality adjusting component 6 further includes a second rope length adjusting component (not shown). The first rope length adjusting component and the second rope length adjusting component are respectively capable of adjusting the lengths of the first connecting rope 31 and the second connecting rope 41 to limit the distance between the plumb bob marker component 32 and the floating marker component 42 within a second preset distance.
[0045] In some embodiments, the first verticality adjustment component 5 may be configured as an HPE hydraulic vertical insertion device 51 or other device for adjusting the posture of tool section 1.
[0046] according to Figures 1 to 3 As shown, in one embodiment of this application, the second verticality adjustment assembly 6 includes a flange assembly 61 and a bolt assembly (not shown). The flange has several through holes (not shown) for inserting bolts. The tool section 1 is connected to the underwater steel pipe string 2 through the cooperation of the flange assembly 61 and the bolt assembly. By tightening or loosening the through holes in different orientations using the bolt assembly, the angle between the tool section 1 and the underwater steel pipe string 2 changes, thereby adjusting the tilt direction and angle.
[0047] according to Figures 1 to 3As shown, in one embodiment of this application, the flange assembly 61 includes a first flange (not shown) and a second flange (not shown). The first flange is connected to the tool section 1, and the second flange is connected to the underwater steel pipe string 2. The first flange and the second flange are detachably connected by a bolt assembly.
[0048] according to Figures 1 to 3 As shown, in one embodiment of this application, the second verticality adjustment component 6 further includes a rubber gasket (not shown). The rubber gasket is disposed between the first flange and the second flange. The rubber gasket has a buffering effect, which can prevent the first integral consisting of the first flange and the tool section 1 from being rigidly connected to the second integral consisting of the second flange and the underwater steel pipe string 2, thus avoiding stress concentration. The rubber gasket can improve the service life of the second verticality adjustment component 6 of this application, and further improve the service life of the verticality calibration device.
[0049] The verticality calibration device of this application first sets a first connecting rope 31 and a fishing line 411 on the central axis of the tool section 1 and the underwater steel pipe column 2, respectively, so that the plumb bob and the float 421 form a vertical reference line that can be coaxially aligned under the action of gravity and buoyancy, respectively. Further, by fixing the fishing line 411 to a preset plane 21 above the underwater end of the underwater steel pipe column 2, the float 421 forms a stable and reliable floating marker point, thereby simultaneously, independently, and in real time reflecting the verticality of the tool section 1 and the underwater steel pipe column 2. Secondly, when the plumb bob and the float 421 are both in a vertical state with the connecting rope, a small second preset distance is maintained, so that the axial consistency between the upper and lower reference points can be visualized with millimeter-level accuracy, allowing for a more intuitive judgment of the coaxial deviation between the tool section 1 and the underwater steel pipe column 2. In addition, by adopting a detachable connection structure including a first flange, a second flange, and a bolt assembly, and by setting a rubber gasket between the two flanges, the flange connection is not completely rigid, which can improve the service life of the verticality calibration device.
[0050] In the description of this specification, the use of terms such as "an embodiment," "some examples," "some embodiments," "illustrative embodiment," "example," "specific example," or "some examples" indicates that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of this application. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples.
[0051] The embodiments of this application have been described in detail above with reference to the accompanying drawings. However, this application is not limited to the above embodiments. Within the scope of knowledge possessed by those skilled in the art, various changes can be made without departing from the spirit of this application.
Claims
1. A verticality calibration device, characterized in that: include A first perpendicularity measuring component is disposed on the tool section and is used to measure the first perpendicularity of the tool section; The second verticality measuring component is mounted on an underwater steel pipe column and is used to measure the second verticality of the underwater steel pipe column. The second verticality measuring component includes a second connecting rope and a floating marker component. The first end of the second connecting rope is connected to the underwater end of the underwater steel pipe column, and the second end of the second connecting rope is connected to the floating marker component. A first verticality adjustment component is disposed on the toolbar and is used to adjust the first verticality of the toolbar; The second verticality adjustment component is disposed between the tool section and the underwater steel pipe column, and is used to adjust the inclination of the tool section and the underwater steel pipe column so that the tool section and the underwater steel pipe column are set on the same axis.
2. The verticality calibration device according to claim 1, characterized in that: The first verticality measuring component includes a first connecting rope and a plumb bob marker component. The first end of the first connecting rope is connected to a tool section, and the second end of the first connecting rope is connected to the plumb bob marker component.
3. The verticality calibration device according to claim 1, characterized in that: A flat surface is provided at a first preset distance away from the underwater bottom surface of the underwater steel pipe column, and the first end of the second connecting rope is fixedly set on the flat surface.
4. The verticality calibration device according to claim 2, characterized in that: The tool section has a first fixed end at the first central axis and a second fixed end at the second central axis of the underwater steel pipe column. The first end of the first connecting rope is connected to the first fixed end, and the first end of the second connecting rope is connected to the second fixed end.
5. The verticality calibration device according to claim 3, characterized in that: The first preset distance is set to 0.5m to 2m.
6. The verticality calibration device according to claim 4, characterized in that: When both the first connecting rope and the second connecting rope are vertical, the plumb bob marker and the floating marker are separated by a second preset distance, which is set to 3mm to 5mm.
7. The verticality calibration device according to claim 1, characterized in that: The second verticality adjustment assembly includes a flange assembly and a bolt assembly, and the tool section is connected to the underwater steel pipe column through the cooperation of the flange assembly and the bolt assembly.
8. The verticality calibration device according to claim 7, characterized in that: The flange assembly includes a first flange and a second flange. The first flange is connected to a tool section, and the second flange is connected to an underwater steel pipe column. The first flange and the second flange are detachably connected by the bolt assembly.
9. The verticality calibration device according to claim 8, characterized in that: The second verticality adjustment assembly also includes a rubber gasket, which is disposed between the first flange and the second flange.
10. The verticality calibration device according to claim 1, characterized in that: The second connecting rope is set as a fishing line, and the floating marker component is set as a fishing float.