GIS prefabricated cabin
The modular design of the GIS prefabricated module enables most of the installation and commissioning to be completed in the factory. The use of connecting structures such as pipes, hoses and flanges for rapid assembly solves the problem of difficult installation of GIS combined electrical appliances in large buildings, improves installation efficiency and equipment sealing, and ensures the safe operation of the equipment.
Patent Information
- Application Number
- CN202522460035.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-20
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-11-20
AI Technical Summary
In existing technologies, the installation of GIS modular electrical appliances needs to be carried out indoors in large buildings, which leads to transportation difficulties, numerous assembly procedures, long construction periods, and high complexity.
The modular GIS prefabricated cabin, including the cabin body and connectors, is mostly installed and commissioned in the factory before being hoisted to the site for assembly. It uses connecting structures such as pipes, hoses and flanges to achieve rapid splicing and sealing, and is equipped with a detection and alarm device to monitor SF6 leakage in real time.
This allows most of the installation and commissioning to be completed in the factory, shortening on-site installation time, reducing uncontrollable risks, improving installation efficiency and equipment sealing, and ensuring the safe operation of the equipment.
Smart Images

Figure CN225019872U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of substation technology, and in particular to a GIS prefabricated module. Background Technology
[0002] Currently, substations typically include electrical equipment such as transformers, switchgear, secondary control equipment, and gas-insulated substations (GIS). Among them, GIS typically includes live components such as circuit breakers, disconnectors, grounding switches, instrument transformers, surge arresters, busbars, and cable terminals. These live components are enclosed in metal pipes through optimized design, and the enclosed metal pipes are filled with SF6 insulating gas at a certain pressure.
[0003] Existing GIS switchgear is usually installed indoors in large buildings, which means that the equipment needs to be transported to the interior of the large building for installation. This is difficult and complicated, involves many assembly steps, and is difficult and time-consuming. Utility Model Content
[0004] In order to overcome at least one of the defects of the prior art, the present invention provides a wafer material rapid handling device to solve the problems of difficult and cumbersome transportation, numerous assembly procedures, high difficulty, and long construction period when installing in large buildings indoors.
[0005] The technical solution adopted by this utility model to solve its problem is: A prefabricated GIS module, comprising: The prefabricated module body has at least two components; The connector has one end connected to one prefabricated module body and the other end connected to another prefabricated module body; wherein, The connector includes a through pipe and a hose. One end of the through pipe is connected to one end of the hose, the other end of the through pipe is connected to a prefabricated cabin body, and the other end of the hose is connected to another prefabricated cabin body.
[0006] With the above solution, the prefabricated cabin body can be prefabricated in a standardized manner in the factory. After most of the GIS switchgear is installed and debugged in the factory, the whole unit is hoisted to the project site for assembly. It has a high degree of integration, a small footprint, a short installation cycle, and reduces the risk and uncontrollable factors brought about by on-site installation.
[0007] Furthermore, a first connecting pipe is provided on one side of the prefabricated cabin body, and a second connecting pipe is provided on the other side of the prefabricated cabin body. One of the first connecting pipes of the prefabricated cabin body is connected to one end of a through pipe, and the other of the second connecting pipes of the prefabricated cabin body is connected to one end of a flexible hose.
[0008] Through the above-mentioned further solutions, the modularly designed prefabricated cabin body can be quickly spliced together with pre-set connecting pipes and through pipes plus flexible hoses, which greatly shortens the on-site installation time.
[0009] Furthermore, a first flange is provided on the first connecting pipe of one of the prefabricated cabin bodies, and a third flange is provided at one end of the through pipe. The first flange and the third flange are flange-connected. A second flange is provided on the second connecting pipe of the other prefabricated cabin body, and a sixth flange is provided at one end of the flexible hose. The second flange and the sixth flange are flange-connected. A fourth flange is provided at the other end of the through pipe, and a fifth flange is provided at the other end of the flexible hose. The fourth flange and the fifth flange are flange-connected.
[0010] Furthermore, a first sealing gasket is provided between the first flange and the third flange, a second sealing gasket is provided between the second flange and the sixth flange, and a third sealing gasket is provided between the fourth flange and the fifth flange.
[0011] Through the above-mentioned further solutions, the flange connection can achieve a seal by pressing the sealing gasket tightly against the cover, preventing external moisture from entering the prefabricated cabin body and affecting the service life of the internal equipment of the prefabricated cabin body.
[0012] Furthermore, the hose includes a first connecting section, a telescopic section, and a second connecting section. A sixth flange is provided at one end of the first connecting section, and the other end of the first connecting section is connected to one end of the telescopic section. A fifth flange is provided at one end of the second connecting section, and the other end of the second connecting section is connected to the other end of the telescopic section.
[0013] Through the above-mentioned further solutions, the telescopic section has axial deformation capability, which can lengthen or shorten the overall length of the telescopic section, thereby adapting to the spacing between the two prefabricated cabin bodies, and has high adaptability.
[0014] Furthermore, the sixth flange has a plurality of evenly arranged first connecting ears on its outer circumference, and the fifth flange has a plurality of evenly arranged second connecting ears on its outer circumference. The number of first connecting ears is the same as the number of second connecting ears, and the positions of the first connecting ears correspond to the positions of the second connecting ears. Each of the plurality of first connecting ears and the plurality of second connecting ears is provided with a screw, and the screw is provided with a plurality of nuts. The plurality of nuts are used to clamp the first connecting ears and the second connecting ears.
[0015] The above-mentioned further solution involves adding connecting lugs and screw nuts to the outside of the flange, which can adjust, control, and fix the length of the expansion joint. The connecting lugs and screw nuts can also prevent the first and second connecting sections from shifting, effectively resisting bending moment, shear force, or eccentric load.
[0016] Furthermore, the first connecting section has a sixth flange with a first groove at one end, the second connecting section has a fifth flange with a second groove at one end, the through pipe has a first extension platform at one end and a third groove at the other end, the first extension platform is engaged in the second groove, the first connecting pipe has a second extension platform engaged in the third groove, and the second connecting pipe has a third extension platform engaged in the first groove.
[0017] Through the above-mentioned further solutions, the cooperation between the extension platform and the slot forms a mechanical guiding and limiting structure, which can realize automatic alignment and pre-positioning between the prefabricated cabin body, the through pipe and the hose before the flange bolts are tightened. This avoids the installation deviation or repeated adjustments caused by the difficulty of manual hole alignment in traditional flange connections, greatly shortens the on-site assembly time, and the snap-fit structure can bear part of the shear load, reduce the mechanical burden on the flange bolts, and prevent the bolts from loosening or fatigue fracture due to long-term excessive force.
[0018] Furthermore, the prefabricated cabin body is equipped with a detection alarm device.
[0019] Through the above-mentioned further measures, an online SF6 leakage monitoring and alarm device is installed inside the prefabricated cabin body, which can monitor the SF6 leakage situation inside each prefabricated cabin body in real time and will sound an alarm once a leakage occurs.
[0020] Compared with the prior art, the beneficial effects of this utility model are: The prefabricated cabin body can be prefabricated in a standardized manner in the factory. After most of the GIS switchgear is installed and commissioned in the factory, the whole unit is hoisted to the project site for assembly. It has a high degree of integration, a small footprint, a short installation cycle, and reduces the risks and uncontrollable factors brought about by on-site installation. Attached Figure Description
[0021] To more clearly illustrate the technical solutions of the embodiments of this utility model, the accompanying drawings used in the description of the embodiments will be briefly introduced below.
[0022] Figure 1 This is a schematic diagram of the overall structure of this utility model; Figure 2 This is a schematic diagram of the overall cross-sectional structure of this utility model; Figure 3 For the present utility model Figure 2 A magnified view of the structure at point A in the middle; Figure 4 For the present utility model Figure 2 A magnified schematic diagram of the structure at point B in the middle.
[0023] In the diagram: 1. Prefabricated cabin body; 11. First connecting pipe; 111. First flange; 112. Second extension platform; 12. Second connecting pipe; 121. Second flange; 122. Third extension platform; 2. Connecting component; 21. Through pipe; 211. Third flange; 212. Fourth flange; 213. First extension platform; 214. Third slot; 22. Flexible hose; 221. Fifth flange; 222. Sixth flange; 223. First connecting section; 2231. First slot; 224. Telescopic section; 225. Second connecting section; 2251. Second slot; 3. First sealing gasket; 4. Second sealing gasket; 5. Third sealing gasket; 6. First connecting lug; 61. Screw; 62. Nut; 7. Second connecting lug. Detailed Implementation
[0024] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present utility model without creative effort are within the scope of protection of the present utility model.
[0025] In the description of this utility model, it should be noted that the terms "center," "upper," "lower," "left," "right," "vertical," "horizontal," "inner," and "outer," etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the accompanying drawings and are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and should not be construed as indicating or implying relative importance.
[0026] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances. Furthermore, the technical features involved in the different embodiments of this utility model described below can be combined with each other as long as they do not conflict with each other.
[0027] Example: refer to Figures 1-4As shown, a GIS prefabricated module includes a prefabricated module body 1, of which at least two are provided. A connector 2 is provided between the two prefabricated module bodies 1. The connector 2 is used to connect the two prefabricated module bodies 1. One end of the connector 2 is connected to one prefabricated module body 1, and the other end is connected to the other prefabricated module body 1. The prefabricated module body 1 can be prefabricated in a standardized manner in the factory. After most of the installation and commissioning of the GIS switchgear is completed in the factory, the whole module is hoisted to the project site for assembly. It has a high degree of integration, a small footprint, a short installation cycle, and reduces the risk and uncontrollable factors brought about by on-site installation.
[0028] The connector 2 includes a through pipe 21 and a hose 22. One end of the through pipe 21 is connected to one end of the hose 22, and the other end of the through pipe 21 is connected to one prefabricated cabin body 1. The other end of the hose 22 is connected to another prefabricated cabin body 1.
[0029] The prefabricated cabin body 1 has a first connecting pipe 11 on one side and a second connecting pipe 12 on the other side. One of the first connecting pipes 11 of the prefabricated cabin body 1 is connected to one end of the through pipe 21, and the other of the second connecting pipes 12 of the prefabricated cabin body 1 is connected to one end of the flexible hose 22. The modularly designed prefabricated cabin body 1 can be quickly spliced together with the pre-set connecting pipe, through pipe 21 and flexible hose 22, which greatly shortens the on-site installation time.
[0030] A first flange 111 is provided on the first connecting pipe 11 of one of the prefabricated cabin bodies 1, and a third flange 211 is provided at one end of the through pipe 21. The first flange 111 and the third flange 211 are flanged together. A second flange 121 is provided on the second connecting pipe 12 of the other prefabricated cabin body 1, and a sixth flange 222 is provided at one end of the flexible hose 22. The second flange 121 and the sixth flange 222 are flanged together. A fourth flange 212 is provided at the other end of the through pipe 21, and a fifth flange 221 is provided at the other end of the flexible hose 22. The fourth flange 212 and the fifth flange 221 are flanged together. A first sealing gasket 3 is provided between the first flange 111 and the third flange 211, a second sealing gasket 4 is provided between the second flange 121 and the sixth flange 222, and a third sealing gasket 5 is provided between the fourth flange 212 and the fifth flange 221. The flange connection is sealed by pressing the sealing gaskets tightly against the cover, which can achieve a seal and prevent external moisture from entering the prefabricated cabin body 1 and affecting the service life of the internal equipment of the prefabricated cabin body 1.
[0031] The hose 22 includes a first connecting section 223, a telescopic section 224, and a second connecting section 225. A sixth flange 222 is provided at one end of the first connecting section 223, and the other end of the first connecting section 223 is connected to one end of the telescopic section 224. A fifth flange 221 is provided at one end of the second connecting section 225, and the other end of the second connecting section 225 is connected to the other end of the telescopic section 224. The telescopic section 224 has axial deformation capability, which can lengthen or shorten the overall length of the telescopic section 224, thereby adapting to the spacing between the two prefabricated cabin bodies 1, and has high adaptability.
[0032] The sixth flange 222 has a plurality of evenly arranged first connecting ears 6 on its outer circumference, and the fifth flange 221 has a plurality of evenly arranged second connecting ears 7 on its outer circumference. The number of first connecting ears 6 is the same as the number of second connecting ears 7, and the positions of the first connecting ears 6 and the second connecting ears 7 correspond to the positions of the second connecting ears 7. Each of the plurality of first connecting ears 6 and the plurality of second connecting ears 7 is provided with a screw 61, and the screw 61 is provided with a plurality of nuts 62. The plurality of nuts 62 are used to clamp the first connecting ears 6 and the second connecting ears 7. The addition of connecting ears, screw 61 and nuts 62 on the outside of the flange can adjust, control and fix the length of the expansion segment 224. The connecting ears, screw 61 and nuts 62 can also prevent the first connecting segment 223 and the second connecting segment 225 from shifting, effectively resisting bending moment, shear force or eccentric load.
[0033] The first connecting section 223 has a sixth flange 222 with a first groove 2231 at one end; the second connecting section 225 has a fifth flange 221 with a second groove 2251 at one end; the through pipe 21 has a first extension platform 213 at one end and a third groove 214 at the other end; the first extension platform 213 is engaged in the second groove 2251; the first connecting pipe 11 has a second extension platform 112, which is engaged in the third groove 214; the second connecting pipe 12... The upper part is provided with a third extension platform 122, which is snapped into the first slot 2231. The cooperation between the extension platform and the slot constitutes a mechanical guiding and limiting structure, which can realize automatic alignment and pre-positioning between the prefabricated cabin body 1, the through pipe 21 and the hose 22 before the flange bolts are tightened. This avoids the installation deviation or repeated adjustment caused by the difficulty of manual hole alignment in traditional flange connection, and greatly shortens the on-site assembly time. The snap-fit structure can bear part of the shear load, reduce the mechanical burden on the flange bolts, and prevent the bolts from loosening or fatigue fracture due to long-term excessive force.
[0034] The prefabricated cabin body 1 is equipped with a detection and alarm device and an exhaust fan. The detection and alarm device is an online SF6 leakage monitoring alarm, which can monitor the SF6 leakage situation inside each prefabricated cabin body 1 in real time. Once a leakage occurs, an alarm will be triggered, and the prefabricated cabin exhaust fan will be activated simultaneously to exhaust air and ensure the safety of operating personnel.
[0035] In a further extension of this embodiment, the prefabricated cabin body 1 is also equipped with monitoring methods such as online monitoring of partial discharge of GIS switch, monitoring of SF6 gas pressure and micro-water, online monitoring of surge arrester, and video surveillance to monitor the equipment operation status in real time and ensure the safe operation of the equipment.
[0036] The installation process in this embodiment is as follows: First, the prefabricated module body 1 is hoisted to the corresponding installation point and fixedly installed. Adjust nut 62 to shorten the length of hose 22 and engage the second slot 2251 on hose 22 with the first extension platform 213 on pipe 21, so that hose 22 is connected to pipe 21 to form connector 2. The hoisting connector 2 is flush with the first connecting pipe 11 and the second connecting pipe 12. First, the third slot 214 on the connector 2 is engaged with the second extension platform 112 on the first connecting pipe 11, so that one end of the connector 2 is connected to the first connecting pipe 11. The length of the hose 22 is stretched, and the first slot 2231 on the connector 2 is engaged with the third extension platform 122 on the second connecting pipe 12, so that the other end of the connector 2 is connected to the second connecting pipe 12. Finally, the flange is connected with bolts, making installation simple and convenient.
[0037] The above description is merely a specific embodiment of this utility model, but the protection scope of this utility model is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the technical scope disclosed in this utility model should be included within the protection scope of this utility model. Therefore, the protection scope of this utility model should be determined by the protection scope of the claims.
Claims
1. A GIS prefabricated cabin, characterized in that, include: The prefabricated module body (1) has at least two; A connector (2) has one end connected to a prefabricated module body (1) and the other end connected to another prefabricated module body (1); wherein, The connector (2) includes a through pipe (21) and a hose (22). One end of the through pipe (21) is connected to one end of the hose (22), and the other end of the through pipe (21) is connected to a prefabricated cabin body (1). The other end of the hose (22) is connected to another prefabricated cabin body (1).
2. The GIS prefabricated cabin according to claim 1, characterized in that: The prefabricated cabin body (1) is provided with a first connecting pipe (11) on one side and a second connecting pipe (12) on the other side. One of the first connecting pipes (11) of the prefabricated cabin body (1) is connected to one end of the through pipe (21), and the other of the second connecting pipes (12) of the prefabricated cabin body (1) is connected to one end of the hose (22).
3. A GIS prefabricated cabin according to claim 2, characterized in that: A first flange (111) is provided on the first connecting pipe (11) of one of the prefabricated cabin bodies (1), and a third flange (211) is provided at one end of the through pipe (21). The first flange (111) and the third flange (211) are flanged together. A second flange (121) is provided on the second connecting pipe (12) of another prefabricated cabin body (1). A sixth flange (222) is provided at one end of the hose (22). The second flange (121) and the sixth flange (222) are flanged together. A fourth flange (212) is provided at the other end of the through pipe (21), and a fifth flange (221) is provided at the other end of the hose (22). The fourth flange (212) and the fifth flange (221) are flanged together.
4. A GIS prefabricated cabin according to claim 3, characterized in that: A first sealing gasket (3) is provided between the first flange (111) and the third flange (211), a second sealing gasket (4) is provided between the second flange (121) and the sixth flange (222), and a third sealing gasket (5) is provided between the fourth flange (212) and the fifth flange (221).
5. A GIS prefabricated cabin according to claim 3, characterized in that: The hose (22) includes a first connecting section (223), a telescopic section (224), and a second connecting section (225). A sixth flange (222) is provided at one end of the first connecting section (223), and the other end of the first connecting section (223) is connected to one end of the telescopic section (224). A fifth flange (221) is provided at one end of the second connecting section (225), and the other end of the second connecting section (225) is connected to the other end of the telescopic section (224).
6. A GIS prefabricated cabin according to claim 5, characterized in that: The sixth flange (222) has a plurality of evenly arranged first connecting ears (6) on its outer circumference, and the fifth flange (221) has a plurality of evenly arranged second connecting ears (7) on its outer circumference. The number of first connecting ears (6) is the same as the number of second connecting ears (7), and the positions of the first connecting ears (6) and the second connecting ears (7) correspond to each other. Each of the plurality of first connecting ears (6) and the plurality of second connecting ears (7) is provided with a screw (61), and the screw (61) is provided with a plurality of nuts (62). The plurality of nuts (62) are used to clamp the first connecting ears (6) and the second connecting ears (7).
7. A GIS prefabricated cabin according to claim 5, characterized in that: The first connecting section (223) is provided with a sixth flange (222) and a first slot (2231) is provided at one end. The second connecting section (225) is provided with a fifth flange (221) and a second slot (2251) is provided at one end. The through pipe (21) is provided with a first extension platform (213) at one end and a third slot (214) at the other end. The first extension platform (213) is engaged in the second slot (2251). The first connecting pipe (11) is provided with a second extension platform (112) and the second extension platform (112) is engaged in the third slot (214). The second connecting pipe (12) is provided with a third extension platform (122) and the third extension platform (122) is engaged in the first slot (2231).
8. A GIS prefabricated cabin according to claim 4, characterized in that: The prefabricated cabin body (1) is equipped with a detection alarm device.