Lead-acid battery charging device
By using lithium iron phosphate battery clusters to replenish power to the UPS host in the energy storage system, combined with interlocking relays and lithium battery pack design, the problem of lead-acid battery depletion in the UPS host is solved, realizing a convenient, safe, and efficient power replenishment process, and improving the overall performance and safety of the system.
Patent Information
- Application Number
- CN202522783236.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-29
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-29
AI Technical Summary
In energy storage systems, the lead-acid batteries of UPS main units are prone to depletion after prolonged periods of inactivity, which can prevent them from starting normally. Furthermore, existing power replenishment methods suffer from difficulties in construction, high costs, and low safety.
A lead-acid battery charging device was designed, which uses lithium iron phosphate battery clusters from an energy storage system to charge the lead-acid batteries in the UPS host via a DC/AC inverter. Safety is ensured by an interlocking relay structure, and lithium battery packs are configured to cope with extreme situations, achieving intelligent voltage balancing and circuit protection.
It enables convenient and safe lead-acid battery recharging, improves operation and maintenance efficiency, reduces costs, extends battery pack life, and ensures operation and equipment safety.
Smart Images

Figure CN225020113U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of new energy storage and charging technology, specifically to a lead-acid battery charging device. Background Technology
[0002] With the rapid development of new energy technologies, energy storage systems are playing an increasingly important role in power peak shaving, new energy grid connection, and backup power. In energy storage systems, the UPS (Uninterruptible Power Supply) unit, as a crucial backup power device, undertakes the critical task of providing uninterrupted power to external environmental control equipment such as the BMS (Browser Management System), fire protection systems, and dehumidifiers. The UPS unit typically contains lead-acid batteries as the energy storage medium. When the mains power is normal, the UPS is charged by the mains power; when the mains power fails, the lead-acid batteries power critical loads.
[0003] However, in practical engineering applications, energy storage systems typically charge the batteries to a high level during factory commissioning and then directly connect them to the grid at the project site. Only after grid connection is complete is the mains power introduced. Since there is often a considerable time gap between the completion of factory commissioning and the completion of infrastructure construction at the project site, the lead-acid batteries in the UPS unit are prone to natural depletion during this period, especially in high-altitude and low-temperature areas. Once the lead-acid batteries are severely depleted, the UPS unit will fail to start normally, resulting in the BMS (Battery Management System) losing power. Since the BMS is the core control unit of the entire energy storage system, its failure to start will cause the entire energy storage system to lose control and fail to operate normally.
[0004] Furthermore, due to the inherent characteristics of the cells and manufacturing differences, containerized battery systems are prone to problems such as excessively large differences in total voltage between clusters after prolonged periods of charging and discharging, or large voltage differences between clusters due to insufficient cluster operation. When the voltage difference is too large and triggers the BMS protection, the system cannot be powered on simultaneously and can only be balanced by charging and discharging individual clusters, which is time-consuming and labor-intensive.
[0005] In existing technologies, the common method for replenishing lead-acid battery power is to run the live and neutral wires from the power distribution room to the UPS input. This method has several drawbacks: First, the power distribution room is often far from the energy storage container, requiring long and expensive power lines, which can lead to financial losses. Second, the complex terrain of the project area makes it difficult to run power lines without disrupting other workers' work, consuming considerable manpower. Third, standard wiring requires electricians to have electrician licenses, placing high demands on operators. Therefore, there is an urgent need for a lead-acid battery replenishment device to address the aforementioned shortcomings of existing technologies. Utility Model Content
[0006] The purpose of this utility model is to provide a lead-acid battery charging device to solve the technical problems mentioned in the background art, realize the safe and convenient charging of UPS lead-acid batteries using lithium iron phosphate battery clusters of energy storage system, and at the same time ensure electrical safety and voltage balance between lithium iron phosphate battery clusters during the charging process.
[0007] To achieve the above objectives, this utility model provides a lead-acid battery charging device, including a DC / AC inverter, a fuse, a switch, and a first relay. The DC circuit of the energy storage system is connected sequentially to the high-voltage DC terminal of the DC / AC inverter via the fuse and the switch. The AC terminal of the DC / AC inverter is connected to the AC distribution cabinet via the first relay. This device converts the DC power in the energy storage system's DC circuit into AC power via the DC / AC inverter, and then transmits it to the AC distribution cabinet via the first relay, thereby realizing the function of using the lithium iron phosphate battery clusters of the energy storage system to charge the lead-acid batteries in the UPS main unit.
[0008] Furthermore, the fuse is installed between the DC circuit of the energy storage system and the switch. That is, the DC circuit of the energy storage system first passes through the fuse, then through the switch, and finally connects to the high-voltage DC terminal of the DC / AC inverter. The fuse's installation ensures timely circuit disconnection in the event of a short circuit in the switching power supply, effectively preventing damage to the lithium iron phosphate battery clusters in the energy storage system from the short-circuit current, thus improving the safety and reliability of the device.
[0009] Furthermore, the AC power distribution cabinet includes a second relay, a UPS main unit, and a BMS main control unit. The mains power input line is connected to the input terminal of the second relay, the output terminal of the second relay is connected to the UPS main unit, and the coil of the second relay is connected to the BMS main control unit. This connection method allows the BMS main control unit to flexibly control the on / off state of the second relay according to the system status, realizing intelligent switching between mains power supply and supplementary power supply modes. The UPS main unit is equipped with a UPS battery, which is a lead-acid battery and is the supplementary power source for this device.
[0010] Furthermore, the DC circuit of the energy storage system includes a main positive copper busbar, a main negative copper busbar, a high-voltage box, and multiple lithium iron phosphate battery clusters. The lithium iron phosphate battery clusters are connected to the main positive and main negative copper busbars through the high-voltage box. In a specific embodiment of this utility model, a 12-in-1 energy storage system structure is adopted, which includes multiple sets of lithium iron phosphate battery clusters. The BMS main control is equipped with a CAN communication interface and a dry contact interface. The CAN communication interface is used to connect to the energy storage system and can monitor the voltage status of each lithium iron phosphate battery cluster in real time; the dry contact interface is used to connect to the UPS host and receive status feedback signals from the UPS host.
[0011] Furthermore, the first relay and the second relay are electrically connected to form an interlocking structure. This interlocking structure is an important safety feature of this invention. It ensures that in the supplementary power supply mode, the AC side of the switching power supply will not come into direct contact with the mains power, fundamentally eliminating the risk of phase-to-phase short circuits and significantly improving the operational safety of the device.
[0012] Furthermore, this invention also includes a lithium battery pack connected to the low-voltage DC terminal of the DC / AC inverter. The lithium battery pack is primarily configured to address extreme situations where the UPS lead-acid battery is severely depleted and unable to support the BMS master control startup. In such cases, the lithium battery pack provides a brief power supply to the UPS host via the DC / AC inverter, allowing the lead-acid battery to receive an initial charge until it can support the normal startup of the BMS master control. The lithium battery pack only serves a temporary wake-up function; one lithium battery pack can perform this operation for multiple containers within a day, offering convenience and high efficiency.
[0013] Furthermore, the output voltage of the energy storage system's DC circuit is 1500V DC, while the input voltage of the AC distribution cabinet is 220V AC. The DC / AC inverter is responsible for completing the high-voltage DC to AC voltage conversion, ensuring that the output voltage matches the rated input voltage of the AC distribution cabinet.
[0014] The lead-acid battery charging device provided by this utility model has the following beneficial effects: First, the device solves the problem of the inability to recharge the lead-acid batteries of the UPS in the energy storage system at the project site when they are depleted. It uses the energy storage system's own lithium iron phosphate battery clusters to charge the lead-acid batteries of the UPS, avoiding the complicated work of temporarily laying cables on site, improving operation and maintenance efficiency and reducing operation and maintenance costs.
[0015] Secondly, through the intelligent selection function of the BMS master control, voltage balance between lithium iron phosphate battery clusters in the energy storage system is achieved, effectively reducing the occurrence of inter-cluster circulating current, extending the battery pack's lifespan, and improving the overall system performance.
[0016] Third, the device is highly safe, equipped with a set of interlocking relays, which can effectively prevent the AC side of the switching power supply from directly contacting the mains power and causing a phase-to-phase short circuit during the power replenishment process, thus ensuring the safety of operators and equipment. Attached Figure Description
[0017] Figure 1 This is a schematic diagram of an embodiment of the lead-acid battery charging device of this utility model.
[0018] In the diagram: 1-DC / AC inverter; 2-fuse; 3-switch; 4-first relay; 5-AC distribution cabinet; 6-second relay; 7-UPS main unit; 8-BMS main control; 9-lithium battery pack; 10-UPS battery; 11-main positive copper busbar; 12-main negative copper busbar; 13-high voltage box; 14-lithium iron phosphate battery cluster. Detailed Implementation
[0019] The present invention will now be described in further detail with reference to the accompanying drawings and specific embodiments. The following embodiments are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0020] like Figure 1 As shown, this utility model provides a lead-acid battery charging device. The device includes a DC / AC inverter 1 and a lithium battery pack 9. The DC / AC inverter 1 has a high-voltage DC terminal, a low-voltage DC terminal, and an AC terminal. In terms of circuit connection, the DC circuit of the energy storage system is connected to the high-voltage DC terminal of the DC / AC inverter 1 sequentially through a fuse 2 and a switch 3. The AC terminal of the DC / AC inverter 1 is connected to the AC distribution cabinet 5 through a first relay 4. This connection method constitutes the basic circuit topology of the device, realizing the power transmission path from the DC side of the energy storage system to the AC distribution cabinet 5.
[0021] The energy storage system adopts a 12-to-1 structure, with its DC circuit including a main positive copper busbar 11, a main negative copper busbar 12, multiple high-voltage boxes 13, and multiple sets of lithium iron phosphate battery clusters 14. Each lithium iron phosphate battery cluster 14 is connected to the main positive copper busbar 11 and the main negative copper busbar 12 through a corresponding high-voltage box 13, forming the DC bus of the energy storage system. In this embodiment, the output voltage of the energy storage system's DC circuit is 1500V DC voltage. This high-voltage DC voltage passes through fuse 2 and switch 3 in sequence before entering DC / AC inverter 1. After conversion by DC / AC inverter 1, it outputs 220V AC voltage, matching the rated input voltage of AC distribution cabinet 5. Fuse 2 is installed between the energy storage system and switch 3. When a short circuit fault occurs in the switching power supply, fuse 2 can promptly melt and disconnect the circuit, effectively preventing the short-circuit current from damaging the lithium iron phosphate battery clusters 14 of the energy storage system.
[0022] The internal structure of the AC power distribution cabinet 5 includes a second relay 6, a UPS main unit 7, and a BMS main control unit 8. The mains power input line is connected to the input terminal of the second relay 6, the output terminal of the second relay 6 is connected to the UPS main unit 7, and the coil of the second relay 6 is connected to the BMS main control unit 8. The UPS main unit 7 houses a UPS battery 10, which is a lead-acid battery and serves as the power replenishment device. The BMS main control unit 8, as the intelligent control hub of the system, is equipped with a CAN communication interface and a dry contact interface. The CAN communication interface is used to connect to the energy storage system and can monitor the status parameters of each lithium iron phosphate battery cluster 14 in real time. The dry contact interface is used to connect to the UPS main unit 7, receive status feedback signals from the UPS main unit 7, and perform intelligent scheduling according to a preset control strategy.
[0023] A key safety feature of this device is the interlocking structure formed by the electrical connection between the first relay 4 and the second relay 6. This interlocking structure ensures that in the supplementary power mode, when the first relay 4 is energized, the second relay 6 is de-energized, cutting off the connection between the mains power and the UPS host 7. This interlocking structure ensures that the AC side of the switching power supply will never be in direct contact with the mains power at any time, fundamentally eliminating the risk of phase-to-phase short circuits.
[0024] This device is also equipped with a lithium battery pack 9, which is connected to the low-voltage DC terminal of the DC / AC inverter 1. The main function of the lithium battery pack 9 is to handle extreme situations where the UPS battery 10 is severely depleted, in which case the UPS battery 10 can no longer provide sufficient starting power for the BMS main control 8. At this time, the lithium battery pack 9, input through the low-voltage DC terminal of the DC / AC inverter 1, provides temporary power to the UPS host 7, allowing the UPS battery 10 to receive an initial charge until it can support the normal startup of the BMS main control 8. This functional design fully considers the extreme operating conditions that may be encountered in actual engineering, improving the applicability and reliability of the device.
[0025] The operation of this device can be divided into the following situations: In the first scenario, when the mains power supply is normal, the second relay 6 is in the energized state, and the mains power supplies the UPS host 7 through the second relay 6, while simultaneously performing float charging on the UPS battery 10. At this time, the device is in standby mode, switch 3 remains open, and the first relay 4 is in the deactivated state.
[0026] In the second scenario, when there is a mains power failure but the UPS battery 10 can support the startup of the BMS main control unit 8, the operator manually closes switch 3 and selects the power replenishment function through the human-machine interface of the BMS main control unit 8. The BMS main control unit 8 then scans the voltage status of each lithium iron phosphate battery cluster 14 in the energy storage system via the CAN communication interface, automatically selecting the cluster with the highest total voltage to connect to the DC circuit of the energy storage system. During this process, the BMS main control unit 8 controls the first relay 4 to close and the second relay 6 to open, establishing a power replenishment path from the energy storage system to the UPS host 7, and the lithium iron phosphate battery cluster 14 of the energy storage system begins to charge the UPS battery 10.
[0027] During the power replenishment process, the BMS main control 8 continuously monitors the total voltage of the currently connected lithium iron phosphate battery cluster 14 and compares it with the average total voltage of the remaining lithium iron phosphate battery clusters 14. When the total voltage of the current cluster is detected to be lower than the average total voltage of the remaining clusters, the BMS main control 8 will automatically switch to other lithium iron phosphate battery clusters 14 with higher voltages to continue charging and discharging operations, thereby achieving dynamic voltage balance between clusters. When the UPS host 7 detects that the UPS battery 10 has finished charging, it transmits charging termination information to the BMS main control 8 through a dry contact signal. After receiving this signal, the BMS main control 8 controls the second relay 6 to close and the first relay 4 to open, cutting off power to the connected lithium iron phosphate battery cluster 14 and restoring the circuit to its initial standby state.
[0028] In the third scenario, when there is a mains power failure and the UPS battery 10 is severely depleted and unable to support the startup of the BMS master control 8, lithium battery pack 9 is required for auxiliary wake-up. Lithium battery pack 9 is connected to the low-voltage DC terminal of DC / AC inverter 1. The low-voltage DC output from lithium battery pack 9 is converted to AC power by DC / AC inverter 1 to provide temporary power to the UPS host 7. With the assistance of lithium battery pack 9, the UPS battery 10 gradually charges. When its charge is sufficient to support the startup of the BMS master control 8, lithium battery pack 9 can be disconnected, and the normal power replenishment process of the second scenario can begin. Lithium battery pack 9 only plays a temporary wake-up role in this process. A single lithium battery pack 9 can perform this wake-up operation for multiple containerized energy storage systems within a day, offering high efficiency and convenience.
[0029] The above-described embodiments are merely one implementation of this utility model, and while the descriptions are specific and detailed, they should not be construed as limiting the scope of this utility model patent. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of this utility model, and these all fall within the protection scope of this utility model. Therefore, the protection scope of this utility model patent should be determined by the appended claims.
Claims
1. A lead-acid battery charging device, characterized in that, include: The DC / AC inverter (1), fuse (2), switch (3) and first relay (4) are connected in sequence through the fuse (2) and the switch (3) to the high voltage DC terminal of the DC / AC inverter (1), and the AC terminal of the DC / AC inverter (1) is connected to the AC distribution cabinet (5) through the first relay (4).
2. The lead-acid battery charging device according to claim 1, characterized in that, The AC power distribution cabinet (5) includes a second relay (6), a UPS host (7) and a BMS main control (8); the mains power input line is connected to the input terminal of the second relay (6), the output terminal of the second relay (6) is connected to the UPS host (7), and the coil of the second relay (6) is connected to the BMS main control (8).
3. The lead-acid battery charging device according to claim 2, characterized in that, The UPS host (7) is equipped with a UPS battery (10), which is a lead-acid battery.
4. The lead-acid battery charging device according to claim 2, characterized in that, The first relay (4) and the second relay (6) are electrically connected to form an interlocking structure.
5. The lead-acid battery charging device according to claim 2, characterized in that, The BMS main control (8) is equipped with a CAN communication interface and a dry contact interface. The CAN communication interface is used to connect with the energy storage system, and the dry contact interface is used to connect with the UPS host (7).
6. The lead-acid battery charging device according to claim 1, characterized in that, The DC circuit of the energy storage system includes a total positive copper busbar (11), a total negative copper busbar (12), a high voltage box (13), and multiple lithium iron phosphate battery clusters (14). The lithium iron phosphate battery clusters (14) are connected to the total positive copper busbar (11) and the total negative copper busbar (12) through the high voltage box (13).
7. The lead-acid battery charging device according to claim 1, characterized in that, It also includes a lithium battery pack (9), the low-voltage DC terminal of the DC / AC inverter (1) being connected to the lithium battery pack (9).
8. The lead-acid battery charging device according to claim 1, characterized in that, The output voltage of the DC circuit of the energy storage system is 1500V DC voltage, and the input voltage of the AC distribution cabinet (5) is 220V AC voltage.