Power source changeover system

The power switching system addresses the failure of existing systems to cut off power during commercial outages by using seismic control means and pseudo-earth leakage circuits to ensure safe load shutdown and continued power supply from distributed sources.

JP2024147694AActive Publication Date: 2024-10-16KAWAMURA ELECTRIC INC
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2024113585
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-10-16
Estimated Expiration
2039-06-05

Smart Images

  • Figure 2024147694000001_ABST
    Figure 2024147694000001_ABST
Patent Text Reader

Abstract

To provide a power supply changeover system that even in the case of occurence of an earthquake in a state in which a commercial power supply is stopped and a load operates using a distribution power supply, can cut off the load from the power supply.SOLUTION: A power supply changeover system comprises: a changeover switch 21 for performing changeover between a commercial power supply 4 and a storage battery 3 to supply power to a specific load; a seismoscope 23; and a control unit 24 for cutting off a power supply. The changeover switch 21 is connected with the secondary side of a trunk breaker 11 having the primary side to which the commercial power supply 4 is connected; and the specific load is connected to the output side of the changeover switch 21 via an earth leakage breaker 22. The control unit 24 includes: a relay 32 that makes both of the trunk breaker 11 and the earth leakage breaker 22 perform cut-off operation when sensing an earthquake; and a control section 35 for performing changeover control on the changeover switch 21. The control unit 24 receives supply of power from both of the commercial power supply 4 and the storage battery 3; and, when the commercial power supply 4 is stopped in a state in which the changeover switch 21 is connected to the commercial power supply 4, performs changeover of connection to the storage battery 3.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a power supply switching system that switches the power supply of a load between a commercial power supply and a distributed power supply, and more particularly to a power supply switching system having an earthquake-sensing cut-off function. [Background technology]

[0002] Conventionally, there has been a power supply switching system that allows the power supply of some loads to be switched between a commercial power supply and a distributed power supply, and further includes an earthquake-sensing relay (earthquake sensor) to cut off the load from the power supply in the event of an earthquake, thereby preventing the outbreak of an electrical fire. For example, in Patent Document 1, a distribution board is provided with a main breaker connected to a commercial power source and an earthquake-sensitive relay, and a distributed power source circuit section equipped with a switch that switches the power source between the commercial power source and the distributed power source, and when the earthquake-sensitive relay detects an earthquake, both the main breaker and the switch are shut off. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2015-177660 A Summary of the Invention [Problem to be solved by the invention]

[0004] The power supply switching system in Patent Document 1 was effective in preventing electrical fires by cutting off the load from the power supply when an earthquake occurred, but because the power supply for the earthquake-sensing relay was supplied from the commercial power supply, if an earthquake occurred when the commercial power supply was out of order, the earthquake-sensing relay did not operate. Therefore, if an earthquake occurred when the commercial power supply was out of order and the load was being driven by a distributed power supply, the power supply was not cut off, which resulted in a situation.

[0005] In consideration of these problems, the present invention aims to provide a power supply switching system that can disconnect a load from the power supply even if an earthquake occurs when the commercial power supply is interrupted and the load is operating on a distributed power supply. [Means for solving the problem]

[0006] In order to solve the above problem, the invention of claim 1 is a power supply switching system comprising a changeover switch that switches the power supplied to a specific load between a commercial power source and a distributed power source, and also comprising seismic control means that has a function of detecting earthquakes and cuts off the power supply to all loads when an earthquake occurs, wherein the changeover switch is connected to the secondary side of a main breaker, the primary side of which is connected to the commercial power source, to supply commercial power, and the output side of the changeover switch is connected to the specific load via a ground fault circuit interrupter, and further comprising a cutoff operation unit that cuts off both the main breaker and the ground fault circuit interrupter when an earthquake is detected, and a switching control unit that controls the changeover switch, and wherein the seismic control means receives power from both the commercial power source and the distributed power source, and when a power outage occurs in the commercial power source with the changeover switch connected to the commercial power source, performs control to switch the power supply of the specific load to the distributed power source. According to this configuration, since the earthquake sensing control means is supplied with power from both the commercial power source and the distributed power source, even if the commercial power source is interrupted and a specific load is being operated by the distributed power source, if an earthquake occurs, the earthquake sensing control means will detect it and perform cutoff control. Therefore, even if an earthquake occurs during a commercial power outage, all loads can be cut off from the power source, ensuring safety. In addition, when a commercial power outage occurs, the changeover switch performs a switching operation to switch the power source from the commercial power source to the distributed power source, so even if the changeover switch does not have the function to monitor the status of the commercial power source, the switching operation can be performed and power can continue to be supplied to a specific load.

[0007] In addition, in the above configuration, it is also possible to adopt a configuration in which the circuit breaker operating unit is equipped with a first pseudo-earth leakage generating circuit that causes the earth leakage circuit breaker to perform an earth leakage circuit breaker operation, and a second pseudo-earth leakage generating circuit that causes the main breaker to perform an earth leakage circuit breaker operation, thereby generating a pseudo-earth leakage current and performing a circuit breaker operation. By adopting this configuration, the circuit breaker operates by utilizing the functions of the main breaker and earth leakage circuit breaker, so simple control is sufficient. In the above configuration, the seismic control means may be configured to energize the first pseudo-earth leakage current generating circuit immediately or after a certain period of time upon the occurrence of an earthquake, while having a leakage current control unit that energizes the second pseudo-earth leakage current generating circuit with a delay. By adopting this configuration, the load on the output side of the changeover switch is first cut off when an earthquake occurs, so if electrical equipment that is dangerous to shaking is placed on the output side of the changeover switch, it can be turned off instantly. Meanwhile, the main breaker does not immediately cut off the load, making it possible to secure an evacuation route. Effect of the Invention

[0008] According to the present invention, since the earthquake sensing control means is supplied with power from the output side of the changeover switch, even if the commercial power supply is interrupted and a specific load is operated by a distributed power supply, if an earthquake occurs, the earthquake sensing control means detects it and performs cutoff control. Therefore, even if an earthquake occurs during a commercial power supply interruption, all loads can be cut off from the power supply, ensuring safety. In addition, when a commercial power outage occurs, the changeover switch performs a switching operation to switch the power source from the commercial power source to the distributed power source, so even if the changeover switch does not have the function to monitor the status of the commercial power source, the switching operation can be performed and power can continue to be supplied to a specific load. [Brief description of the drawings]

[0009] [Figure 1] 1 is a configuration diagram showing an example of a power supply switching system according to the present invention; DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0010] Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings. Fig. 1 is a configuration diagram showing an example of a power supply switching system according to the present invention, which is configured to include a distribution board 1 that supplies power to loads using a commercial power supply 4 as a power source, a switching board 2 that is equipped with a changeover switch 21 and supplies power from a power source selected by the changeover switch 21 to a specific load, and a storage battery 3 as a distributed power source.

[0011] The distribution board 1 is equipped with a main breaker 11 and multiple branch breakers 12. A single-phase three-wire commercial power source 4 is connected to the main breaker 11, and the branch breakers 12 are connected to its secondary side. A load (not shown) is connected to each of the secondary sides of the branch breakers 12. The main breaker 11 is an ELB having a leakage current interruption function in addition to an overcurrent interruption function.

[0012] In addition to the changeover switch 21, the changeover panel 2 is equipped with an earth leakage breaker (ELB) 22, a seismometer 23 for detecting earthquakes, a control unit 24, and a plurality of branch breakers 25. A specific load (not shown) is connected to this branch breaker 25, and power selected by the changeover switch 21 is supplied to the branch breaker 25. The changeover switch 21 has two input terminals 21a and one output terminal 21b, and the two inputs are switched by operating a changeover handle (not shown), with one of the inputs being connected to the output terminal 21b. In addition, a switching control unit 21c is provided which switches the input upon receiving a switching signal from the outside, and is configured so that even if the commercial power source 4 experiences a power outage, a specific load connected to the branch breaker 25 continues to operate using the storage battery 3 as a power source.

[0013] The seismometer 23 has a built-in acceleration sensor, and outputs an earthquake detection signal when it detects shaking of, for example, a seismic intensity of 5 or more. This earthquake detection signal is transmitted to the control unit 24 via the transmission line S1. The seismometer 23 is supplied with power from the power line S4 connected to the secondary side of the earth leakage breaker 22.

[0014] The control unit 24 includes two relays 32 (a first relay 32a and a second relay 32b) that constitute a cut-off operation section, a signal input section 33 to which a detection signal is input, a sensor section 34 that detects the circuit voltage, and a control section 35 consisting of a microcomputer that controls the relays 32 and the change-over switch 21. The relay 32 has an a-contact, the first relay 32a is arranged in parallel with the earth leakage breaker 22 to form a first pseudo earth leakage generating circuit W1 that generates a pseudo earth leakage, and the second relay 32b is arranged in parallel with the main breaker 11 to form a second pseudo earth leakage generating circuit W2 that generates a pseudo earth leakage. Thus, when the first relay 32a is turned on, the first pseudo earth leakage generating circuit W1 is energized, and the earth leakage breaker 22 determines that an earth leakage has occurred and performs an earth leakage interruption. Also, when the second relay 32b is turned on, the second pseudo earth leakage generating circuit W1 is energized, and the main breaker 11 determines that an earth leakage has occurred and performs an earth leakage interruption.

[0015] The sensor unit 34 is a terminal for detecting the voltages of two power supply circuits, and is connected to a detection line S2 for detecting a specified line voltage of the secondary circuit S5 of the main breaker 11 to which commercial power is supplied, and a detection line S3 for detecting a specified line voltage of the output circuit S6 of the storage battery 3. Incidentally, power is supplied to the control unit 24 via the detection lines S2 and S3.

[0016] The power supply switching system configured as above operates as follows when an earthquake occurs. When an earthquake of a magnitude equal to or greater than a preset seismic intensity occurs, the seismometer 23 detects it and outputs an earthquake detection signal. This earthquake detection signal is transmitted to the control unit 24 via the transmission line S1. When the control unit 35 receives the earthquake detection signal via the signal input unit 33, it starts the following control. First, the first relay 32a is immediately turned on. As a result, a pseudo earth leakage current is generated on the secondary side of the earth leakage circuit breaker 22, and the earth leakage circuit breaker 22 performs an interruption operation.

[0017] On the other hand, the control unit 35 has a built-in timer, which counts a predetermined time when it receives an earthquake detection signal from the seismometer 23, and turns on the second relay 32b when the predetermined time has elapsed. As a result, a false earth leakage occurs on the secondary side of the main breaker 11, causing the main breaker 11 to perform an interruption operation. In other words, a delay operation is implemented in which the main breaker 11 performs an interruption operation when a certain time has elapsed since the occurrence of an earthquake.

[0018] Furthermore, if the sensor unit 34 detects a power outage of the commercial power source 4 while the changeover switch 21 has selected the commercial power source 4, the control unit 35 outputs a changeover signal to the changeover control unit 21c of the changeover switch 21 to change the power source connected to the output terminal 21b from the commercial power source 4 to the storage battery 3. Furthermore, if the commercial power source 4 is restored while switched to the storage battery 3, the sensor unit 34 detects this and controls the connection of the input terminal 21a of the changeover switch 21 back to the commercial power source 4.

[0019] In this way, since the seismic sensor 23 receives power from the output side of the changeover switch 21, it can detect an earthquake even if the commercial power supply 4 has failed and certain loads are operating on the storage battery 3, and since the control unit 24 receives power from the commercial power supply 4 and the storage battery 3, it controls to shut off the main breaker 11 and earth leakage circuit breaker 22 when it receives an earthquake detection signal from the seismic sensor 23. Therefore, even if an earthquake occurs during a power outage in the commercial power supply 4, all loads can be shut off from the power supply, ensuring safety. In addition, since the circuit breaker 11 and the earth leakage breaker 22 are used to perform the circuit breaker operation, there is no need to incorporate a new circuit, and simple control is sufficient. In addition, since the load on the output side of the changeover switch 21 is first cut off in response to an earthquake, electrical equipment that is dangerous to shaking can be instantly turned off by connecting it as a specific load. On the other hand, since the main breaker 11 does not immediately cut off the load, it is possible to secure an evacuation route. Furthermore, in response to a power outage of the commercial power source 4, the changeover switch 21 performs a changeover operation to switch the power source of the specific load from the commercial power source 4 to the storage battery 3. Therefore, even if the changeover switch 21 does not have a function for monitoring the state of the commercial power source 4, the changeover switch 21 can perform a changeover operation and continue to supply power to the specific load.

[0020] In the above embodiment, the earth leakage breaker 22 is immediately shut off when an earthquake detection signal is received from the seismometer 23, but the earth leakage breaker 22 may also be shut off after a certain time has elapsed since the occurrence of an earthquake. When the earth leakage breaker 22 and the main breaker 11 are shut off with a delay in this manner, the seismometer 23 itself may be operated with a delay to output an earthquake detection signal a certain time after detecting an earthquake. Also, although the seismic sensor 23 and the control unit 24 are separate bodies, they may be integrated. If the main breaker 11 and the earth leakage breaker 22 have a signal input section for separately performing a cutoff operation, a signal output section for outputting a cutoff signal to the signal input section may be provided instead of the first relay 32a and the second relay 32b. Furthermore, although the distributed power source is the storage battery 3, it may be a power generation facility such as a solar power generation device or a fuel cell. Furthermore, the changeover switch 21 and the control unit 24 are housed in the changeover board 2 that is separate from the distribution board 1, but the changeover board 2 may be integrated with the distribution board 1 and all may be assembled to the distribution board 1. [Explanation of symbols]

[0021] 1··Distribution board, 2··Switchboard, 3··Storage battery (distributed power source), 4··Commercial power source, 11··Main breaker, 12··Branch breaker, 21··Switching switch, 22··Earth leakage circuit breaker, 23··Seismic sensor (seismic control means), 24··Control unit (seismic control means), 25··Branch breaker, 32··Relay (breaker operation section), 33··Signal input section, 34··Sensor section, 35··Control section (earth leakage control section, switching control section), W1··First pseudo-earth leakage current generation circuit, W2··Second pseudo-earth leakage current generation circuit.

Claims

[Claim 1] A power supply switching system including a changeover switch for switching the power supplied to a specific load between a commercial power supply and a distributed power supply, and also including an earthquake sensing control means having a function of detecting an earthquake and cutting off the power supply to all loads when an earthquake occurs, The changeover switch is connected to a secondary side of a main breaker to which the commercial power source is connected on its primary side, so that commercial power is supplied, and the specific load is connected to an output side of the changeover switch via a ground fault circuit interrupter, Furthermore, the earthquake-sensing control means has a shutoff operation unit that shuts off both the main breaker and the earth leakage circuit breaker when it detects an earthquake, and a switching control unit that controls the switching of the changeover switch, and the earthquake-sensing control means receives power from both the commercial power source and the distributed power source, and when the commercial power source experiences a power outage while the changeover switch is connected to the commercial power source, performs control to switch the power source of the specific load to the distributed power source. This power source switching system is characterized in that it

Citation Information

Patent Citations

  • Interconnection system and changeover switch

    JP2015142487A

  • System-interconnection system

    JP2015177660A

  • Automatic transfer switch module

    US20100141038A1