Water exchange storage facility construction method and storage facility

JP2024544363AActive Publication Date: 2024-11-29CCCC FIRST HARBOR ENGINEERING CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2024529496
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Priority Date
2022-10-21
Filing Date
2023-09-01
Publication Date
2024-11-29
Estimated Expiration
2043-09-01

AI Technical Summary

Technical Problem

Conventional storage facility construction methods result in reduced enclosure space due to submerged fill materials, converting water environments into anhydrous grounds, leading to inefficient use of space and increased costs.

Method used

A method involving constructing a water-stop enclosure, draining the enclosed area, forming a stacking yard with terraces, and using cylindrical steel plates and riprap mounds to create a watertight structure that replaces land filling, allowing for expanded storage space and cost-effective construction.

Benefits of technology

The method enhances storage capacity, reduces landfill costs, and accelerates construction by utilizing a watertight enclosure that maintains a dry construction environment, optimizing space utilization and cost-effectiveness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024544363000001_ABST
    Figure 2024544363000001_ABST
Patent Text Reader

Abstract

The present application provides a water exchange storage construction method, including the steps of: constructing a water stop enclosure; constructing a drainage channel after enclosing, in which after enclosing the water stop enclosure, drain the water within the enclosed range of the water stop enclosure to expose the pit and form a dry construction state; constructing a stacking yard, in which under the dry construction state, the stacking yard is constructed in the pit, including constructing a lower low terrace and an upper high terrace, the low terrace is lower than the average water level outside the water stop enclosure, the high terrace can be used to move a stacking / removal device, and the stacking / removal device can transport materials between the warehouse; and constructing a warehouse, in which the warehouse is constructed on the low terrace.
Need to check novelty before this filing date? Find Prior Art

Citation Information

Patent Citations

  • Construction method of underground structures of seacoasts and artificial islands

    CN102345300A

  • Construction method for coastal reclamation based on basement utilization

    CN110080169A

  • Automatic container port and construction and installation method

    CN110921342A

  • The base structure and the method of forming a road

    JP1990504050A

  • Construction method of reclaiming land from the sea based on basement utilization

    US20200318306A1