Connectors between frame elements of a temporary canopy, and methods for connecting frame elements.
Patent Information
- Application Number
- JP2025062815
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2025-04-04
- Publication Date
- 2026-10-16
- Estimated Expiration
- 2045-04-04
AI Technical Summary
【0012】 本発明によれば、ターンバックルを用いないので、取り付けに時間がかからない、という利点がある。
Smart Images

Figure 2026169099000001_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a connector between frame elements of a temporary shed, and a connection method thereof.
Background Art
[0002] As shown in Figures 4 and 5, in the conventional method for manufacturing a temporary shed, for example, in a factory or the like, two steel pipes 1, 1 arranged in parallel on one side and the other side are connected by beams 2, 2, a plurality of frame elements 3 formed in a rectangular frame shape for example are produced in a desired shape, and the plurality of produced frame elements 3 (3a, 3b, 3c, 3d) are transported to the site.
[0003] Then, at the site, joint pins 4 are inserted between the required left and right open ends of each of the plurality of frame elements 3 for connection, and the ends of a pulling tool such as a turnbuckle 7 are respectively engaged with the holes 6, 6 of the plate pieces 5 respectively provided at the opposing corners of each adjacent frame-shaped frame element 3, and the turnbuckle 7 is contracted to pull and fix the spaced frame elements 3, 3, thereby forming the frame of the temporary shed.
[0004] For example, Patent Document 1 discloses a related art as a connector for frame elements.
Prior Art Documents
Patent Documents
[0005]
Patent Document 1
Summary of the Invention
Problems to be Solved by the Invention
[0006] However, the above conventional method has a problem that it takes time to install the turnbuckle at the site.
[0007] Furthermore, the above method of connection had the disadvantage of low connection strength between frame elements.
[0008] This invention aims to eliminate the above-mentioned drawbacks. [Means for solving the problem]
[0009] The connector between frame elements of the temporary canopy of the present invention comprises a joint pin that connects adjacent first and second frame elements constituting the temporary canopy, a bolt portion that connects the first and second frame elements, and a brace provided between the first and second frame elements, each of the frame elements being formed in a frame shape by two parallel steel pipes and a beam connecting the first and second steel pipes, and the joint pin is made of the first and second steel pipes of the first frame element The first frame element and the second frame element are connected by inserting the bolt into the opening at one end of the pipe and the opening at the other end of the steel pipe on one and the other side of the second frame element, respectively. The bolt portion is composed of a bolt and a nut, and the connection is made by inserting the bolt into a bolt hole in a plate piece formed at the end of one of the steel pipes on one and the other side of the first frame element, respectively, and into a bolt hole in a plate piece formed at the end of the other steel pipe on one and the other side of the second frame element, respectively, and tightening the nut.
[0010] Furthermore, the brace is characterized by being connected by aligning the holes at both ends of the brace with the holes provided in the plate pieces formed at one end of each of the steel pipes of the first frame element and the second holes provided in the plate pieces formed at one end of each of the steel pipes of the second frame element, which are obliquely opposite to the first holes, inserting bolts, and tightening them with nuts.
[0011] Furthermore, the present invention provides a method for connecting frame elements of a temporary structure, comprising: a first step of creating a plurality of frame elements formed in a frame shape by connecting beams between two parallel steel pipes; a second step of inserting joint pins into one end opening of the first and second steel pipes of the first frame element and into the other end opening of the first and second steel pipes of the second frame element; a third step of inserting nuts into bolt holes in plate pieces formed at one end of the first and second steel pipes of the first frame element and into bolt holes in plate pieces formed at the other end of the first and second steel pipes of the second frame element; and a fourth step of providing bracing between the first and second frame elements. [Effects of the Invention]
[0012] According to the present invention, since turnbuckles are not used, there is the advantage that installation does not take much time.
[0013] Furthermore, the use of bracing increases the connection strength between frame elements.
[0014] Furthermore, the units can be connected using only bolts, improving work efficiency on site. [Brief explanation of the drawing]
[0015] [Figure 1] This is a plan view illustrating the connectors between frame elements of the erected canopy of the present invention. [Figure 2] This is a front view illustrating the connector between frame elements of the erected canopy according to the present invention. [Figure 3] This is a plan view illustrating the frame elements of the connecting device between frame elements of the erected canopy according to the present invention. [Figure 4] This is a perspective view illustrating the connectors between frame elements of a conventional temporary shelter. [Figure 5] This is a perspective view illustrating the connectors between frame elements of a conventional temporary shelter. [Modes for carrying out the invention]
[0016] Embodiments of the present invention will be described with reference to the following drawings. Note that the same reference numerals are assigned to the same parts as in the prior art, and descriptions thereof are omitted.
Example
[0017] As shown in Figures 1 to 3, the connector between the frame elements of the erected shed of the present invention comprises a joint pin 8 that connects the adjacent first frame element 3a and second frame element 3b, a bolt portion that connects the first frame element 3a and the second frame element 3b, and a brace 9 provided between the first frame element 3a and the second frame element 3b.
[0018] Each of the above frame elements 3 is formed, for example, in a frame shape formed by connecting two parallel steel pipes 1, 1 on one side and the other side with a plurality of beams 2, 2 by welding or the like.
[0019] Note that the beam 2 on the farthest one end side of the adjacent first frame element 3a and the beam 2 on the farthest other end side of the second frame element 3b are arranged such that when the first frame element 3a and the second frame element 3b are connected, a brace 9 can be provided between the beam 2 on the farthest one end side of the first frame element 3a and the beam 2 on the farthest other end side of the second frame element 3b, so they are provided at the inner end portion from the tip portion of each frame element 3.
[0020] The joint pin 8 is inserted into the one end openings 10a, 10a of the one and the other steel pipes 1, 1 of the first frame element 3a, and the other end openings 10b, 10b of the one and the other steel pipes 1, 1 of the second frame element 3b, respectively, so that the first frame element 3a and the second frame element 3b are connected.
[0021] The bolt portion described above is constituted by, for example, a bolt 11 and a nut 12. The bolt 11 is inserted into the bolt hole 14a of the plate piece 13a formed by welding or the like at one tip of each of the one and the other steel pipes of the first frame element 3a, and the bolt hole 14b of the plate piece 13b formed by welding or the like at the other tip of each of the one and the other steel pipes of the second frame element 3b, and the nut 12 is tightened, whereby the first frame element 3a and the second frame element 3b are connected to each other.
[0022] Further, the brace 9 described above has holes formed at both ends respectively, and the bolt 16 is inserted into each of the holes, the first hole for brace engagement provided in the plate piece 15a formed by welding or the like at one end of each of the one and the other steel pipes 1 of the first frame element 3a, and the second hole for brace engagement provided in the plate piece 15b formed by welding or the like at one end of each of the one and the other steel pipes of the second frame element 3b, which faces the first hole obliquely, and is tightened and connected by a nut.
[0023] Note that, as shown in FIG. 1, the brace 9 described above may be a single diagonal brace in addition to two crossed braces.
[0024] Since the connector between frame elements of the present invention is configured as described above, first, a plurality of frame elements 3 having a required shape are produced on site.
[0025] Then, these frame elements 3 are brought to the site, the plurality of frame elements 3 are arranged in the axial direction of the steel pipe 1 respectively, joint pins 8 are inserted and connected between the one and the other end openings 10a, 10b of each adjacent frame element 3, 3 respectively, the bolt 11 is inserted into the bolt hole 14a and the bolt hole 14b and tightened with the nut 12, and the holes of the brace 16 are overlapped with the first hole and the second hole respectively, the bolt 16 is inserted and tightened and fixed with a nut, thereby forming the frame of the temporary shed.
[0026] Furthermore, some or all of the multiple frame elements 3 may be manufactured by connecting them together at the factory.
[0027] According to the present invention, since turnbuckles are not used, installation time is reduced compared to conventional methods.
[0028] Furthermore, by using bracing, the connection strength between frame elements 3,3 can be increased.
[0029] Furthermore, the units can be connected using only bolts, improving work efficiency on site. [Explanation of symbols]
[0030] 1 Steel pipe 2 beams 3 Frame elements 3a Frame element 3b Frame element 3c frame element 3D frame element 4 Joint pins 5 plate pieces 6 holes 7 Turnbuckle 8 Joint pins 9. Diagonal bracing 10a One end opening 10b Other end opening 11 volts 12 nuts 13a plate piece 13b plate piece 14a Bolt hole 14b Bolt holes 15a plate piece 15b plate piece 16 volts
Claims
1. A joint pin connects adjacent first and second frame elements that constitute the temporary canopy, A bolt portion connecting the first frame element and the second frame element, It consists of a brace provided between the first frame element and the second frame element, Each of the above frame elements is formed in a frame shape by two parallel steel pipes, one on one side and the other on the other, and a beam connecting the two steel pipes. The joint pins are inserted into the openings at one end of the steel pipes on both sides of the first frame element and the openings at the other end of the steel pipes on both sides of the second frame element, thereby connecting the first frame element and the second frame element. The above-mentioned bolt portion is composed of a bolt and a nut, and the bolt is inserted into a bolt hole in a plate piece formed at one end of one of the first and other steel pipes of the first frame element, and into a bolt hole in a plate piece formed at the other end of the first and other steel pipes of the second frame element, and the connection is made by tightening the nut.
2. The brace is connected to the frame elements of a temporary structure according to claim 1, characterized in that the holes at both ends of the brace are aligned with holes provided in plate pieces formed at one end of each of the steel pipes of the first frame element and second holes provided in plate pieces formed at one end of each of the steel pipes of the second frame element, which are obliquely opposite to the first holes, and bolts are inserted and tightened with nuts.
3. The first step involves creating multiple frame elements by connecting beams between two parallel steel pipes, one on one side and the other on the other, to form a frame-like structure. A second step involves inserting joint pins into one end opening of the first frame element and into the other end opening of the first and other steel pipes of the second frame element, respectively. A third step involves inserting a plate piece into a bolt hole formed at one end of one of the steel pipes of the first frame element, and into a bolt hole formed at the other end of the steel pipe of the second frame element, and then tightening a nut. A method for connecting frame elements of a temporary structure, characterized by comprising a fourth step of providing a brace between the first frame element and the second frame element.
Citation Information
Patent Citations
Rib connector for temporary cover
JP1998266579A