Sewing management system and sewing management method

The sewing management system addresses reduced worker capacity by calculating and comparing standard and current abilities, adjusting workloads, and suggesting breaks, ensuring productivity in sewing factories.

JP2026182456APending Publication Date: 2026-11-19JUKI CORP
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2025078706
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2025-05-09
Publication Date
2026-11-19

AI Technical Summary

Technical Problem

In sewing factories, workers may experience reduced work capacity due to poor physical condition, leading to decreased productivity if their diminished state is not addressed.

Method used

A sewing management system that calculates a worker's standard ability based on past performance, compares it with current ability, and outputs notifications if a significant reduction is detected, adjusting workload assignments and recommending breaks.

Benefits of technology

Enables recognition of reduced worker capacity, allowing for proactive measures to maintain productivity by adjusting workloads and encouraging breaks, thereby preventing productivity declines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2026182456000001_ABST
    Figure 2026182456000001_ABST
Patent Text Reader

Abstract

To recognize the current work capabilities of the workers. [Solution] The sewing management system includes: a standard ability calculation unit that calculates a standard ability indicating the worker's standard work ability based on the worker's work ability during a first period of working with a sewing machine; a current ability acquisition unit that acquires the current ability indicating the worker's work ability during a second period after the first period; a determination unit that determines whether the current ability is below the standard ability and whether the difference between the standard ability and the current ability is greater than or equal to a first specified amount, indicating a state of reduced ability; and an output unit that outputs notification data to a notification device when it is determined that the worker is in a state of reduced ability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The technology disclosed in the present specification relates to a sewing management system and a sewing management method.

Background Art

[0002] In the technical field related to sewing management systems, a sewing management system as disclosed in Patent Document 1 is known. In Patent Document 1, the sewing management system estimates the sewing skill of an operator based on production management information, and estimates the production capacity of the operator based on physical condition management information.

Prior Art Documents

Patent Documents

[0003]

Patent Document 1

Summary of the Invention

Problems to be Solved by the Invention

[0004] In a sewing factory, workers perform operations using sewing machines. For example, there is a possibility that a worker cannot demonstrate their usual work capacity due to poor physical condition. If a state where the current work capacity of a worker is reduced is left unaddressed, the productivity of the sewing factory may decrease.

[0005] The technology disclosed in the present specification aims to recognize the current work capacity of a worker.

Means for Solving the Problems

[0006] This specification discloses a sewing management system. The sewing management system includes: a standard ability calculation unit that calculates a standard ability representing the standard work ability of an operator based on the operator's work ability during a first period of operation using a sewing machine; a current ability acquisition unit that acquires the current ability representing the operator's work ability during a second period after the first period; a determination unit that determines whether the current ability is below the standard ability and the difference between the standard ability and the current ability is greater than or equal to a first specified amount, indicating a state of reduced ability; and an output unit that, if it is determined that the operator is in a state of reduced ability, outputs notification data to a notification device. [Effects of the Invention]

[0007] The technology disclosed herein makes it possible to recognize the current work capacity of an operator. [Brief explanation of the drawing]

[0008] [Figure 1] Figure 1 is a schematic diagram showing a sewing management system according to an embodiment. [Figure 2] Figure 2 is a block diagram showing a sewing machine, a management device, and an information terminal according to an embodiment of this model. [Figure 3] Figure 3 is a diagram illustrating the method for calculating standard capabilities according to the embodiment. [Figure 4] Figure 4 is a diagram illustrating the current capabilities according to this embodiment. [Figure 5] Figure 5 is a diagram illustrating the relationship between the standard production quantity, the target production quantity, and the current production quantity according to the embodiment. [Figure 6] Figure 6 shows a sewing control method according to an embodiment. [Figure 7] Figure 7 shows a sewing control method according to an embodiment. [Modes for carrying out the invention]

[0009] The following describes embodiments of this technology with reference to the drawings, but this technology is not limited to these embodiments. The components of the embodiments described below can be combined as appropriate. In addition, some components may not be used.

[0010] [Sewing Management System] Figure 1 is a schematic diagram showing a sewing management system 1 according to an embodiment. The sewing management system 1 manages a sewing factory that produces sewn products Pb. A sewing machine 2 is installed in the sewing factory. The sewing machine 2 operates in the sewing factory. The sewing machine 2 is an industrial sewing machine. The sewing machine 2 sews the material to be sewn Pa. By sewing the material to be sewn Pa with the sewing machine 2, sewn products Pb are produced. Fabric is an example of the material to be sewn Pa. Clothing is an example of the sewn product Pb.

[0011] Multiple sewing machines 2 are installed in the sewing factory. Sewn products Pb are produced through the cooperation of multiple sewing machines 2. Multiple types of sewing machines 2 may be installed in the sewing factory depending on their intended use. Examples of types of sewing machines 2 include a lockstitch sewing machine for sewing garment bodies together, a button-attaching sewing machine for attaching buttons to garment bodies, and a pocket-attaching sewing machine for attaching pockets to garment bodies. For the sake of simplicity, in this embodiment, it is assumed that there are three sewing machines 2 installed in the sewing factory. Sewing machines 2 include a first sewing machine 2A, a second sewing machine 2B, and a third sewing machine 2C.

[0012] Manager Ma, worker Mb, and inspector Mc work in the sewing factory. Manager Ma manages sewing machine 2, worker Mb, and inspector Mc. Worker Mb operates sewing machine 2. Worker Mb works using sewing machine 2. Worker Mb sews the item to be sewn, Pa, using sewing machine 2.

[0013] Each of the multiple workers Mb performs their work using sewing machine 2. For the sake of simplicity, in this embodiment, we will assume that there are three workers Mb working in the sewing factory. The workers Mb include a first worker Mb1, a second worker Mb2, and a third worker Mb3. The first worker Mb1 performs the first sewing process using the first sewing machine 2A. The second worker Mb2 performs the second sewing process using the second sewing machine 2B. The third worker Mb3 performs the third sewing process using the third sewing machine 2C.

[0014] Inspector Mc inspects the sewn product Pa after it has been sewn by sewing machine 2. The inspection of the sewn product Pa includes an intermediate inspection of the sewn product Pa after some sewing processes have been completed, and a final inspection of the sewn product Pb after all sewing processes have been completed.

[0015] The sewing management system 1 includes a management device 3 that manages at least the sewing machines 2 and the workers Mb. In this embodiment, the management device 3 is installed in the sewing factory. However, the management device 3 may be installed outside the sewing factory.

[0016] The management device 3 comprises a display device 4 and an input device 5. The display device 4 displays display data. The display device 4 includes a flat panel display such as a liquid crystal display or an organic EL display. Input data is generated when the input device 5 is operated by the administrator Ma. The input device 5 may also be operated by the worker Mb or the inspector Mc. The input device 5 includes a touch panel (touch sensor) placed on the display screen of the display device 4. The input device 5 may be a computer keyboard, a mouse, or a voice input device.

[0017] The sewing machine 2 includes an operation panel 6 and a controller 7. The operation panel 6 includes a display device and an input device. The display device of the operation panel 6 includes a flat panel display such as a liquid crystal display or an organic EL display. The input device of the operation panel 6 includes at least one of a button, a computer keyboard, a touch panel (touch sensor), and a voice input device. Input data is generated when the input device of the operation panel is operated by the worker Mb.

[0018] The inspector Mc carries an information terminal 30. Examples of the information terminal 30 include a personal computer, a tablet terminal, and a smartphone. The information terminal 30 includes a display device and an input device. The display device of the information terminal 30 includes a flat panel display such as a liquid crystal display or an organic EL display. The input device of the information terminal 30 includes at least one of a touch panel (touch sensor), a computer keyboard, a mouse, and a voice input device. Input data is generated when the input device of the information terminal 30 is operated by the inspector Mc.

[0019] The management device 3 is shared by the plurality of sewing machines 2 and the information terminals 30 in a sewing factory. The number of the management devices 3 is smaller than the number of the sewing machines 2. The management device 3 can communicate with each of the sewing machines 2 and the information terminals 30. The management device 3 communicates with each of the controller 7 and the information terminal 30.

[0020] [Sewing Machine and Management Device] Figure 2 is a block diagram showing a sewing machine 2, a management device 3, and an information terminal 30 according to an embodiment. The management device 3 includes a computer. The management device 3 has a processor 8 such as a CPU (Central Processing Unit), a main memory 9 including volatile memory such as RAM (Random Access Memory), a storage 10 including non-volatile memory such as ROM (Read Only Memory), and an interface 11 including input / output circuits. The functions of the processor 8 are stored in the storage 10 as a computer program. The processor 8 reads the computer program from the storage 10, loads it into the main memory 9, and executes processing according to the computer program. The computer program may be distributed to the management device 3 via a network.

[0021] Sewing machine 2 includes a controller 7, an operation panel 6, a sewing machine motor 12, a pedal 13, and a sensor 14. The controller 7 controls sewing machine 2. The controller 7 includes a computer having a processor, main memory, storage, and interfaces.

[0022] The information terminal 30 includes a computer having a processor, main memory, storage, and interfaces.

[0023] The management device 3, the controller 7, and the information terminal 30 communicate via the network 15. Examples of the network 15 include a local area network (LAN), a wide area network (WAN), an intranet, and the internet. The management device 3, the controller 7, and the information terminal 30 may communicate wirelessly or via wired communication.

[0024] The sewing machine motor 12 is the main power source of the sewing machine 2. The sewing machine motor 12 drives the needle bar, balance wheel, and bobbin of the sewing machine 2. The sewing machine needle moves back and forth in an up-and-down direction while being held in the needle bar. The pedal 13 is operated by the foot of the operator Mb. When the pedal 13 is operated, the sewing machine motor 12 is driven. When the pedal 13 is released, the sewing machine motor 12 stops. The sensor 14 detects the operating conditions of the sewing machine 2. An example of the sensor 14 is a rotation sensor that detects the rotation data of the sewing machine motor 12. The rotation data of the sewing machine motor 12 includes the number of rotations or rotational speed of the sewing machine motor 12 per unit time.

[0025] The processor 8 includes a standard capacity calculation unit 21, a current capacity acquisition unit 22, a determination unit 23, a production planning unit 24, and an output unit 25.

[0026] The standard capability calculation unit 21 calculates the standard capability Ws, which represents the standard work capability of worker Mb when working with the sewing machine 2. Standard capability Ws is worker Mb's usual work capability. Standard capability Ws is worker Mb's past standard work capability. The standard capability calculation unit 21 calculates the standard capability Ws based on worker Mb's past work capability in the first period Ea.

[0027] Figure 3 is a diagram illustrating the method for calculating the standard capacity Ws according to the embodiment. The standard capacity calculation unit 21 obtains the work capacity of worker Mb in the past first period Ea. The first period Ea can be arbitrarily determined. The first period Ea may be one week or one month.

[0028] The standard capacity calculation unit 21 acquires the work capacity for each unit time Ec in the first period Ea. The unit time Ec is shorter than the first period Ea. The unit time Ec can be arbitrarily determined. The unit time Ec may be 10 minutes, 1 hour, or the daily working hours of worker Mb (for example, 8 hours).

[0029] Work capacity includes the amount of work that a worker Mb can perform per unit time Ec. A worker Mb with high work capacity can perform a large amount of work. A worker Mb with low work capacity can perform a small amount of work.

[0030] Note that the workload may vary depending on the difficulty of the task. If the task is easy, the workload will be high, and if the task is easy, the workload will be low. If the task is easy, even a worker Mb with low work ability may be able to complete a large amount of work. If the task is difficult, even a worker Mb with high work ability may be able to complete a small amount of work. An example of an easy task is straight stitching. An example of an easy task is curved stitching.

[0031] In this embodiment, the workload of worker Mb is defined as the production quantity C, which represents the number of sewn objects Pa sewn by worker Mb using sewing machine 2. The production quantity C is the number of sewn objects Pa sewn per unit time Ec. When the difficulty level of the work is the same or similar, the production quantity C of worker Mb with high work ability will be high, and the production quantity C of worker Mb with low work ability will be low.

[0032] In this embodiment, the production quantity C of worker Mb is counted by inspector Mc. Inspector Mc counts the production quantity C of each of the multiple workers Mb (Mb1, Mb2, Mb3). Inspector Mc counts the production quantity C of each of the multiple workers Mb (Mb1, Mb2, Mb3) for each unit time Ec.

[0033] Inspector Mc operates the input device of information terminal 30 to input the production quantity C of each of the multiple workers Mb (Mb1, Mb2, Mb3) into information terminal 30. The production quantity C entered into information terminal 30 is transmitted to management device 3 via network 15. Standard capacity calculation unit 21 obtains the production quantity C of each of the multiple workers Mb (Mb1, Mb2, Mb3) from information terminal 30.

[0034] The standard capacity calculation unit 21 calculates the standard production quantity Cs for each of the multiple workers Mb (Mb1, Mb2, Mb3) as the standard capacity Ws, based on the production quantity C of each of the multiple workers Mb (Mb1, Mb2, Mb3) during the first period Ea, which is obtained from the information terminal 30. The standard production quantity Cs is an example of a standard workload.

[0035] In this embodiment, the standard production quantity Cs is the average value of multiple production quantities C obtained for each unit time Ec in the first period Ea. The standard capacity calculation unit 21 calculates the average value of multiple production quantities C obtained for each unit time Ec in the first period Ea as the standard production quantity Cs for worker Mb.

[0036] If the number of unit time periods Ec included in the first period Ea is N, and the production quantity C for each of the multiple unit time periods Ec is denoted as Ck, then the standard production quantity Cs is expressed by the following equation (1).

[0037]

number

[0038] The standard capacity calculation unit 21 may also exclude outliers from the multiple production quantities C obtained for each unit time Ec in the first period Ea. The standard capacity calculation unit 21 may also calculate the average value of the multiple production quantities C from which outliers have been excluded as the standard production quantity Cs for worker Mb. An outlier is a value that deviates significantly from the other values.

[0039] Note that the standard production quantity Cs may be the median of multiple production quantities C obtained for each unit time Ec in the first period Ea. The standard capacity Ws may be the median of multiple production quantities C after excluding outliers.

[0040] The standard production quantities Cs for each of the multiple workers Mb (Mb1, Mb2, Mb3) calculated by the standard capacity calculation unit 21 are stored in the standard capacity storage unit 26 of the storage unit 10.

[0041] The current ability acquisition unit 22 acquires the current ability Wc, which indicates the work ability of worker Mb in the second period Eb after the first period Ea. The second period Eb is an evaluation period for evaluating worker Mb's work ability. When evaluating worker Mb's work ability today, the second period Eb is at least a portion of today. When evaluating worker Mb's work ability at the present time, the second period Eb is a period that includes the present time. The second period Eb is shorter than worker Mb's daily working hours (e.g., 8 hours). The second period Eb can be arbitrarily determined. The second period Eb may be 10 minutes or 1 hour.

[0042] In this embodiment, the current capacity acquisition unit 22 acquires the current production quantity Cc, which is the production quantity C of worker Mb during the second period Eb, as the current capacity Wc. The current production quantity Cc is an example of the current workload. The current capacity acquisition unit 22 acquires the current production quantity Cc for each of the multiple workers Mb (Mb1, Mb2, Mb3).

[0043] In this embodiment, the current production quantity Cc of worker Mb is counted by inspector Mc. Inspector Mc counts the current production quantity Cc of each of the multiple workers Mb (Mb1, Mb2, Mb3). Inspector Mc counts the current production quantity Cc of each of the multiple workers Mb (Mb1, Mb2, Mb3) for each of the second period Eb.

[0044] Inspector Mc operates the input device of information terminal 30 to input the current production quantity Cc of each of the multiple workers Mb (Mb1, Mb2, Mb3) into information terminal 30. The current production quantity Cc entered into information terminal 30 is transmitted to management device 3 via network 15. Current capacity acquisition unit 22 acquires the current production quantity Cc of each of the multiple workers Mb (Mb1, Mb2, Mb3) from information terminal 30.

[0045] Figure 4 is a diagram illustrating the current capacity Wc according to the embodiment. Figure 4 shows the current production quantity Cc when worker Mb starts working with sewing machine 2 at 8:00 AM today. In the example shown in Figure 4, the second period Eb is 10 minutes long. The current production quantity Cc for the second period Eb from 8:00 AM to 8:10 AM is 10 pieces. The current production quantity Cc for the second period Eb from 8:10 AM to 8:20 AM is 10 pieces. The current production quantity Cc for the second period Eb from 8:20 AM to 8:30 AM, from 8:30 AM to 8:40 AM, and from 8:40 AM to 8:50 AM is 9 pieces. The current production quantity Cc for the second period Eb from 8:50 AM to 9:00 AM and for the second period Eb from 9:00 AM to 9:10 AM is 8 units. The current production quantity Cc for the second period Eb from 9:10 AM to 9:20 AM is 7 units. The current production quantity Cc for the second period Eb from 9:20 AM to 9:30 AM is 6 units.

[0046] The current capacity acquisition unit 22 acquires the current production quantity Cc for each of the multiple workers Mb (Mb1, Mb2, Mb3), as shown in Figure 4.

[0047] The determination unit 23 determines whether worker Mb is in a state of reduced ability, where the worker's current ability Wc is below the standard ability Ws and the difference between the standard ability Ws and the current ability Wc is equal to or greater than the first specified amount Da. The first specified amount Da is a predetermined value. The determination unit 23 determines whether each of the multiple workers Mb (Mb1, Mb2, Mb3) is in a state of reduced ability.

[0048] A worker Mb determined to be in a state of reduced performance is, for example, a worker Mb who is unable to perform their usual work tasks due to poor health. A worker Mb determined not to be in a state of reduced performance is a worker Mb who is able to perform their usual work tasks.

[0049] In this embodiment, the determination unit 23 determines whether the current production quantity Cc of worker Mb is below the standard production quantity Cs and whether the difference between the standard production quantity Cs and the current production quantity Cc is equal to or greater than the first specified amount Da, indicating a state of reduced capacity.

[0050] Furthermore, the first specified amount Da may be set for each worker Mb. The first specified amount Da may be set to a small value for workers Mb with high standard capacity Ws, and the first specified amount Da may be set to a large value for workers Mb with low standard capacity Ws.

[0051] Furthermore, the first specified amount Da may be determined according to the difficulty level of the work. The first specified amount Da may be set to a small value for workers Mb performing low-difficulty work, and to a large value for workers Mb performing high-difficulty work.

[0052] The production planning unit 24 calculates the target workload to be assigned to each of the multiple workers Mb(Mb1, Mb2, Mb3) based on the standard capacity Ws of each of the multiple workers Mb(Wa, Mb, Wc). In this embodiment, the production planning unit 24 calculates the target production quantity Cr to be assigned to each of the multiple workers Mb(Mb1, Mb2, Mb3) as the target workload. The target production quantity Cr calculated by the production planning unit 24 is stored in the target workload storage unit 27 of the storage 10.

[0053] Figure 5 is a diagram illustrating the relationship between the standard production quantity Cs, the target production quantity Cr, and the current production quantity Cc according to the embodiment. In the example shown in Figure 5, the standard production quantity Cs of the first worker Mb1 is 60 sheets per hour (10 sheets per 10 minutes). The standard production quantity Cs of the second worker Mb2 is 66 sheets per hour (11 sheets per 10 minutes). The standard production quantity Cs of the third worker Mb3 is 54 sheets per hour (9 sheets per 10 minutes).

[0054] The production planning unit 24 calculates the target production quantity Cr to be assigned to each of the multiple workers Mb (Mb1, Mb2, Mb3) based on the standard production quantity Cs of each of the multiple workers Mb (Mb1, Mb2, Mb3). The production planning unit 24 calculates the target production quantity Cr so that the target production quantity Cr does not exceed the standard production quantity Cs. The production planning unit 24 may also calculate the target production quantity Cr so that the target production quantity Cr matches the standard production quantity Cs. The production planning unit 24 may also calculate the target production quantity Cr so that the target production quantity Cr is less than the standard production quantity Cs and the difference between the standard production quantity Cs and the target production quantity Cr is less than the first specified quantity Da. In the example shown in Figure 5, the target production quantity Cr for the first worker Mb1 is 9 sheets per 10 minutes. The target production quantity Cr for the second worker Mb2 is 10 sheets per 10 minutes. The target production quantity for worker Mb3 is 8 pieces per 10 minutes.

[0055] The current capacity acquisition unit 22 acquires the current production quantity Cc for each of the multiple workers Mb (Mb1, Mb2, Mb3). In the example shown in Figure 5, the current production quantity Cc for the first worker Mb1 is 7 sheets per 10 minutes. The current production quantity Cc for the second worker Mb2 is 10 sheets per 10 minutes. The current production quantity Cc for the third worker Mb3 is 8 sheets per 10 minutes.

[0056] The determination unit 23 determines whether the current production quantity Cc is below the standard production quantity Cs and whether the difference between the standard production quantity Cs and the current production quantity Cc is equal to or greater than the first specified quantity Da, indicating a state of reduced capacity. In the example shown in Figure 5, if the first specified quantity Da is 2, the determination unit 23 determines that the first worker Mb1 is in a state of reduced capacity. The determination unit 23 determines that the second worker Mb2 and the third worker Mb3 are not in a state of reduced capacity.

[0057] The production planning unit 24 changes the target production quantity Cr, which is the target workload, if it determines that at least one of the multiple workers Mb (Mb1, Mb2, Mb3) is in a state of reduced capacity. The production planning unit 24 changes the target production quantity Cr so that the target production quantity Cr of the first worker Mb1, which is determined to be in a state of reduced capacity, decreases, and the target production quantity Cr of at least one of the second worker Mb2 and the third worker Mb3, which are determined not to be in a state of reduced capacity, increases.

[0058] The production planning unit 24 changes the target production quantity Cr so that the target production quantity Cr of workers Mb whose current production quantity Cc is below the target production quantity Cr is preferentially increased if there are workers Mb whose current production quantity Cc is below the target production quantity Cr. In the example shown in Figure 5, the current production quantity Cc of the second worker Mb2 and the third worker Mb3 are both below the target production quantity Cr. The production planning unit 24 changes the target production quantity Cr to the target production quantity Ca so that the target production quantity Cr of the second worker Mb2 and the third worker Mb3, whose current production quantity Cc is below the target production quantity Cr, is preferentially increased. When the target production quantity Cr is changed to the target production quantity Ca, the target work amount storage unit 27 updates the target production quantity Cr to the target production quantity Ca.

[0059] The production planning unit 24 changes the target production quantity Cr to target production quantity Ca so that the revised target production quantity Ca does not exceed the standard production quantity Cs. Alternatively, the production planning unit 24 may change the target production quantity Cr to target production quantity Ca so that the revised target production quantity Ca exceeds the standard production quantity Cs, and the difference between the standard production quantity Cs and the revised target production quantity Ca does not exceed a predetermined second specified quantity Db. The second specified quantity Db may be the same value as the first specified quantity Da or a value smaller than the first specified quantity Da.

[0060] The output unit 25 outputs notification data to the notification device when it is determined that worker Mb is in a state of reduced ability. In this embodiment, the display device 4, the operation panel 6, and the information terminal 30 are each examples of notification devices. Outputting notification data to the notification device includes displaying display data on the display device 4. Outputting notification data to the notification device includes displaying display data on at least one of the display devices of the operation panel 6 and the information terminal 30. If at least one of the display device 4, the operation panel 6, and the information terminal 30 includes an audio output device, outputting notification data to the notification device includes outputting audio data to the audio output device.

[0061] The notification data includes recommendation data suggesting that the first worker Mb1, who has been determined to be in a state of reduced ability, should take a break. The output unit 25 causes the display device on the operation panel 6 of the first sewing machine 2A, for example, to display data prompting the first worker Mb1 to take a break.

[0062] The notification data may include reducing the target production quantity Cr for the first worker Mb1, who is determined to be in a state of reduced capacity, and increasing the target production quantity Cr for at least one of the second worker Mb2 and the third worker Mb3, who are determined not to be in a state of reduced capacity.

[0063] For example, instruction data instructing the first worker Mb1 to decrease the target production quantity Cr, and instruction data instructing at least one of the second worker Mb2 and the third worker Mb3 to increase the target production quantity Cr, may be displayed on the display device 4.

[0064] For example, the revised target production quantity Ca for the first worker Mb1 may be displayed on the display device of the operation panel 6 of the first sewing machine 2A, the revised target production quantity Ca for the second worker Mb2 may be displayed on the display device of the operation panel 6 of the second sewing machine 2B, and the revised target production quantity Ca for the third worker Mb3 may be displayed on the display device of the operation panel 6 of the third sewing machine 2C.

[0065] The notification data may include recommendation data suggesting that the work of the first worker Mb1, who has been determined to be in a state of reduced capacity, be assigned to at least one of the second worker Mb2 and the third worker Mb3, who have been determined not to be in a state of reduced capacity.

[0066] [Sewing management method] Figures 6 and 7 are flowcharts illustrating a sewing control method according to an embodiment. Figure 6 is a flowchart of the standard capacity calculation phase, in which the standard capacity Ws is calculated. Figure 7 is a flowchart of the current capacity evaluation phase, in which the current capacity Wc is evaluated based on the standard capacity Ws.

[0067] The standard capacity calculation phase will be explained with reference to Figure 6. In the first period Ea of the standard capacity calculation phase, the standard capacity calculation unit 21 acquires the work capacity of worker Mb for each unit time Ec. In this embodiment, the standard capacity calculation unit 21 acquires the production quantity C of worker Mb for each unit time Ec. The standard capacity calculation unit 21 acquires the production quantity C of each of the multiple workers Mb (Mb1, Mb2, Mb3) (step SA1).

[0068] The standard capacity calculation unit 21 calculates the standard production quantity Cs as the standard capacity Ws of worker Mb based on the production quantity C of worker Mb in the first period Ea. As shown in equation (1), the standard production quantity Cs may also be the average value of multiple production quantities C obtained for each unit time Ec in the first period Ea (step SA2).

[0069] The standard capacity calculation unit 21 calculates the standard production quantity Cs for each of the multiple workers Mb (Mb1, Mb2, Mb3). The standard production quantity Cs for each worker Mb calculated by the standard capacity calculation unit 21 is stored in the standard capacity storage unit 26 of the storage 10 (step SA3).

[0070] The production planning unit 24 calculates the target production quantity Cr to be assigned to each of the multiple workers Mb (Mb1, Mb2, Mb3) based on the standard production quantity Cs of each of the multiple workers Mb (Mb1, Mb2, Mb3) (step SA4).

[0071] The target production quantity Cr calculated in the production planning unit 24 is stored in the target workload storage unit 27 of the storage unit 10 (step SA5).

[0072] Next, the current capacity evaluation phase will be explained with reference to Figure 7. The current capacity acquisition unit 22 acquires the current capacity Wc, which indicates the work capacity of worker Mb in the second period Eb after the first period Ea. In this embodiment, the current capacity acquisition unit 22 acquires the current production quantity Cc of worker Mb in the second period Eb. The current capacity acquisition unit 22 acquires the current production quantity Cc for each of the multiple workers Mb (Mb1, Mb2, Mb3) (step SB1).

[0073] The determination unit 23 determines for each of the multiple workers Mb (Mb1, Mb2, Mb3) whether they are in a state of reduced capacity where the current production quantity Cc is below the standard production quantity Cs and the difference between the standard production quantity Cs and the current production quantity Cc is equal to or greater than the first specified amount Da. In other words, the determination unit 23 determines whether there are any workers Mb in a state of reduced capacity (step SB2).

[0074] If it is determined in step SB2 that there is a worker Mb in a state of reduced capacity (step SB2: Yes), the production planning unit 24 changes the target production quantity Cr for each of the multiple workers Mb (Mb1, Mb2, Mb3) (step SB3).

[0075] The production planning unit 24 changes the target production quantity Cr to target production quantity Ca so that the target production quantity Cr decreases for workers Mb determined to be in a state of reduced capacity, and the target production quantity Cr increases for workers Mb determined not to be in a state of reduced capacity. If there are workers Mb whose current production quantity Cc is below the target production quantity Cr, the production planning unit 24 changes the target production quantity Cr to target production quantity Ca so that the target production quantity Cr of workers Mb whose current production quantity Cc is below the target production quantity Cr is increased preferentially. In the target workload storage unit 27, the target production quantity Cr is updated to target production quantity Ca.

[0076] If the output unit 25 determines that there is a worker Mb in a state of reduced performance, it causes the notification device to output notification data (step SB4). The notification data includes recommendation data that suggests taking a break for the worker Mb determined to be in a state of reduced performance. The output unit 25 causes the display device on the operation panel 6 of the sewing machine 2, for example, to display data prompting the worker Mb in a state of reduced performance to take a break. The notification data may also include recommendation data that suggests reducing the target production quantity Cr for the worker Mb determined to be in a state of reduced performance, or recommendation data that suggests assigning the work of the worker Mb determined to be in a state of reduced performance to a worker Mb determined not to be in a state of reduced performance.

[0077] If it is determined in step SB2 that there are no workers Mb in a reduced capacity state (step SB2: No), the target production quantity Cr is not changed. Worker Mb continues to work using sewing machine 2 based on the target production quantity Cr.

[0078] [effect] As described above, according to the embodiment, the processor 8 of the management device 3 includes a standard ability calculation unit 21 that calculates a standard ability Ws indicating the standard work ability of worker Mb based on the work ability of worker Mb in a first period Ea working with the sewing machine 2; a current ability acquisition unit 22 that acquires the current ability Wc indicating the work ability of worker Mb in a second period Eb after the first period Ea; a determination unit 23 that determines whether or not the current ability Wc is below the standard ability Ws and the difference between the standard ability Ws and the current ability Wc is greater than or equal to a first specified amount Da, indicating a reduced ability state; and an output unit 25 that outputs notification data to a notification device when it is determined that worker Mb is in a reduced ability state.

[0079] According to the embodiment, the processor 8 can determine whether or not there are workers Mb who are in a state of reduced ability and unable to perform their usual work performance by comparing the standard ability Ws with the current ability Wc. If there are workers Mb who are in a state of reduced ability and unable to perform their usual work performance, the processor 8 causes the notification device to output notification data. As a result of the notification data being output from the notification device, at least some of the managers Ma, workers Mb, and inspectors Mc can recognize the current work performance of the workers Mb. Once the existence of workers Mb with reduced work performance is recognized, measures can be taken to suppress the decline in productivity of the sewing factory. For example, workers Mb with reduced work performance can be encouraged to take a break, the workload of workers Mb with reduced work performance can be reduced, or the workload of workers Mb whose work performance has not decreased can be increased.

[0080] By calculating the standard capacity Ws of each of the multiple workers Mb, the production planning unit 24 can calculate the target workload to be assigned to each of the multiple workers Mb based on their standard capacity Ws. When formulating a production plan for sewn products Pb in a sewing factory, an appropriate production plan is formulated based on the standard capacity Ws of the workers Mb. For example, the production plan is formulated so that the target workload assigned to workers Mb with high standard capacity Ws is high, and the target workload assigned to workers Mb with low standard capacity Ws is low. Also, for example, the production plan is formulated so that workers Mb with high standard capacity Ws are assigned high-difficulty tasks, and workers Mb with low standard capacity Ws are assigned low-difficulty tasks. For example, if a worker Mb with high standard capacity Ws is unable to perform at their usual level due to poor health, the decline in productivity of the sewing factory can be suppressed by assigning some or all of the work of the worker Mb who is unable to perform at their usual level to other workers Mb.

[0081] [Other embodiments] In the above embodiment, the production quantity C of worker Mb is counted by inspector Mc. However, the production quantity C of worker Mb may be counted by worker Mb. Worker Mb may also input their own production quantity C into the operation panel 6 by operating the input device of the operation panel 6. The production quantity C input into the operation panel 6 may be transmitted to the management device 3 via the network 15.

[0082] In the above embodiment, the processor 8 may calculate the workload of worker Mb based on the detection data of the sensor 14. If the sensor 14 is a rotation sensor that detects the rotation data of the sewing machine motor 12, the processor 8 can calculate the workload of worker Mb based on the detection data of the sensor 14. As described above, the rotation data of the sewing machine motor 12 includes the number of rotations or rotational speed of the sewing machine motor 12 per unit time. If the sensor 14 detects the rotation of the sewing machine motor 12, the processor 8 can determine that the sewing machine motor 12 is running. The processor 8 can calculate the number of stitches of the sewing machine 2 based on the rotation data of the sewing machine motor 12 detected by the sensor 14. The number of stitches of the sewing machine 2 refers to the number of times the sewing machine needle, which is held in the needle bar and moves back and forth in the vertical direction, has penetrated the sewing target Pa. The lower the rotation speed or rotational speed of the sewing machine motor 12, the fewer stitches the sewing machine 2 will have, and the higher the rotation speed or rotational speed of the sewing machine motor 12, the more stitches the sewing machine 2 will have. The fewer the number of stitches on sewing machine 2, the less work operator Mb does, and the more stitches on sewing machine 2, the more work operator Mb does. If correlation data showing the relationship between the rotation data of sewing machine motor 12, the number of stitches on sewing machine 2, and the work operator Mb does has been derived in advance, the processor 8 can calculate the work operator Mb does based on the detection data of sensor 14 and the correlation data.

[0083] Furthermore, the rotation data of the sewing machine motor 12 detected by the sensor 14 correlates with the operation state of the pedal 13 by the worker Mb. The operation state of the pedal 13 includes the number of operations or the operation time. If correlation data showing the relationship between the rotation data of the sewing machine motor 12, the operation state of the pedal 13, and the amount of work done by the worker Mb has been derived in advance, the processor 8 may calculate the amount of work done by the worker Mb based on the data detected by the sensor 14 and the correlation data.

[0084] In the above embodiment, if the worker Mb's work status is captured by a camera, the processor 8 may calculate the amount of work done by worker Mb based on the image data captured by the camera. The processor 8 can determine whether or not worker Mb is sewing the sewing target Pa by processing the image data.

[0085] In the above embodiment, the worker Mb's work capacity is defined as the production quantity C, which represents the amount of work done by worker Mb. The worker Mb's work capacity may also be defined as the defect rate F of the sewn objects Pa after worker Mb has sewn them using the sewing machine 2. The defect rate F is the ratio of defective products to the total number of sewn objects Pa sewn per unit time Ec. Workers Mb with high work capacity have a low defect rate F, and workers Mb with low work capacity have a high defect rate F. The defect rate F of each of multiple workers Mb may be counted by inspector Mc or by worker Mb. The standard capacity calculation unit 21 calculates the standard defect rate Fs as the standard capacity Ws. The current capacity acquisition unit 22 acquires the current defect rate Fc as the current capacity Wc. If the current capacity Wc is less than the standard capacity Ws, it means that the current defect rate Fc is greater than the standard defect rate Fs. The determination unit 23 determines whether the current defect rate Fc is greater than the standard defect rate Fs and whether the difference between the standard defect rate Fs and the current defect rate Fc is greater than or equal to a predetermined third specified amount Dc, which indicates a reduced capacity state. If the production planning unit 24 determines that at least one worker Mb is in a reduced capacity state, it changes the target workload so that the target workload for the worker Mb determined to be in a reduced capacity state decreases and the target workload for the worker Mb determined not to be in a reduced capacity state increases. If the output unit 25 determines that a worker Mb is in a reduced capacity state, it outputs notification data to the notification device.

[0086] In the above embodiment, the worker Mb's work ability is counted by the inspector Mc and transmitted from the information terminal 30 to the management device 3. The administrator Ma may also count the worker Mb's work ability. The administrator Ma may also input the worker Mb's work ability to the processor 8 by operating the input device 5.

[0087] In the embodiments described above, standard work time may be used as the standard capacity Ws. Work time refers to the time it takes for a worker with a standard level of proficiency to perform a task using standard procedures, methods, and conditions. The current capacity Wc may be the net time required for worker Mb to perform the task. [Explanation of symbols]

[0088] 1...Sewing management system, 2...Sewing machine, 2A...First sewing machine, 2B...Second sewing machine, 2C...Third sewing machine, 3...Management device, 4...Display device, 5...Input device, 6...Operation panel, 7...Controller, 8...Processor, 9...Main memory, 10...Storage, 11...Interface, 12...Sewing machine motor, 13...Pedal, 14...Sensor, 15...Network, 21...Standard capacity calculation unit, 22...Current capacity acquisition unit, 23...Determination unit, 24...Production planning unit, 25...Output unit, 26...Standard capacity storage unit, 27...Eye Standard work quantity memory unit, 30... Information terminal, C... Production quantity, Ca... Target production quantity, Cc... Current production quantity, Cr... Target production quantity, Cs... Standard production quantity, Da... First specified quantity, Db... Second specified quantity, Dc... Third specified quantity, Ea... First period, Eb... Second period, Ec... Unit time, F... Defect rate, Fc... Current defect rate, Fs... Standard defect rate, Ma... Manager, Mb... Worker, Mb1... First worker, Mb2... Second worker, Mb3... Third worker, Mc... Inspector, Pa... Sewing target, Pb... Sewn product, Wc... Current capacity, Ws... Standard capacity.

Claims

1. A standard ability calculation unit calculates a standard ability that indicates the standard work ability of a worker based on the worker's work ability during a first period of working with a sewing machine, A current ability acquisition unit that acquires the current ability of the worker in the second period after the first period, A determination unit that determines whether the current capacity is below the standard capacity and whether the difference between the standard capacity and the current capacity is greater than or equal to a first specified amount, The system includes an output unit that outputs notification data to a notification device when it is determined that the worker is in the state of reduced ability. Sewing management system.

2. The notification data includes recommendation data suggesting that the worker be given a break. The sewing management system according to claim 1.

3. The aforementioned workers include a first worker who is determined to be in the state of reduced ability and a second worker who is determined not to be in the state of reduced ability. The notification data includes recommendation data that suggests reducing the target workload of the first worker and increasing the target workload of the second worker, or assigning the work of the first worker to the second worker. The sewing management system according to claim 1.

4. The production planning unit includes a unit that calculates a target workload to be assigned to each of the multiple workers based on the aforementioned standard capacity. The production planning department shall change the target workload if it determines that at least one worker is in the reduced capacity state. The sewing management system according to claim 1.

5. The production planning unit modifies the target workload so that the target workload for workers determined to be in a state of reduced capacity decreases, and the target workload for workers determined not to be in a state of reduced capacity increases. The sewing management system according to claim 4.

6. The aforementioned current capacity includes the current workload of the worker, The production planning department changes the target workload so that the target workload increases for workers whose current workload falls below the target workload. The sewing management system according to claim 5.

7. The standard capacity calculation unit acquires the work capacity for each unit time of the first period, The standard capacity is the average or median of the multiple work capacities acquired for each unit of time. The sewing management system according to claim 1.

8. The work capacity includes at least one of the production number, which indicates the number of items sewn by the worker using the sewing machine, and the defect rate of the items sewn after being sewn using the sewing machine. The sewing management system according to claim 1.

9. To calculate a standard ability that indicates the standard work ability of a worker based on the worker's work ability during the first period when the worker is working with a sewing machine, To obtain the current capabilities of the worker in the second period after the first period, To determine whether the current capacity is below the standard capacity and whether the difference between the standard capacity and the current capacity is greater than or equal to the first specified amount, If the worker is determined to be in the state of reduced ability, the notification device outputs notification data, including: Sewing management method.