Operation methods for hydrogen gas supply systems
By using inert gas to pressurize and discharge hydrogen gas multiple times, the method addresses the challenge of hydrogen gas's high diffusivity and permeability, achieving precise purging and leak prevention in fuel gas supply systems.
Patent Information
- Application Number
- JP2022125074
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2022-08-04
- Publication Date
- 2026-11-19
- Estimated Expiration
- 2042-08-04
AI Technical Summary
Hydrogen gas, with its high diffusivity and permeability, requires more accurate purging methods in fuel gas supply systems to prevent leaks and ensure safety.
A method involving the use of inert gas to increase the internal pressure of sealed areas in a hydrogen gas supply system, followed by opening these areas to discharge hydrogen gas with the inert gas, repeating this process multiple times for thorough purging.
Enables highly accurate purging, ensuring complete removal of hydrogen gas from the system and preventing leaks.
Smart Images

Figure 0007954023000001 
Figure 0007954023000002 
Figure 0007954023000003
Abstract
Description
Technical Field
[0001] The present disclosure relates to an operation method for a hydrogen gas supply system.
Background Art
[0002] In a fuel gas supply system that supplies fuel gas to burners of combustion facilities and the like, purging may be performed when the supply of fuel gas is stopped. When purging is performed, the fuel gas remaining inside the fuel gas supply system is pushed out by an inert gas or the like and discharged to the outside (see, for example, Patent Document 1 below).
Prior Art Documents
Patent Documents
[0003]
Patent Document 1
Summary of the Invention
Problems to be Solved by the Invention
[0004] By the way, in recent years, hydrogen gas, which does not generate carbon dioxide during combustion, has attracted attention as a fuel for combustion facilities such as boilers. However, hydrogen gas has higher diffusivity and permeability than other fuel gases such as natural gas. Therefore, in the hydrogen gas supply system, it is necessary to perform purging with higher accuracy than in other fuel gas supply systems.
[0005] Accordingly, the present disclosure aims to provide an operation method for a hydrogen gas supply system that is capable of performing highly accurate purging.
Means for Solving the Problems
[0006] A method for operating a hydrogen gas supply system according to one aspect of this disclosure involves supplying an inert gas to a sealed area to be purged in the hydrogen gas supply system to increase the internal pressure of the area to be purged, and then opening the area to be purged and discharging hydrogen gas from the area together with the inert gas, repeating this process multiple times in a continuous manner. [Effects of the Invention]
[0007] This configuration provides a method for operating a hydrogen gas supply system that enables highly accurate purging. [Brief explanation of the drawing]
[0008] [Figure 1] Figure 1 is a schematic diagram of the hydrogen gas supply system. [Figure 2] Figure 2 shows the hydrogen gas supply flow. [Figure 3] Figure 3 shows the first standby state of the hydrogen gas supply system. [Figure 4] Figure 4 is a diagram corresponding to step S1 of the hydrogen gas supply flow. [Figure 5] Figure 5 is a diagram corresponding to step S2 of the hydrogen gas supply flow. [Figure 6] Figure 6 is a diagram corresponding to step S3 of the hydrogen gas supply flow. [Figure 7] Figure 7 shows the diagram corresponding to step S4 of the hydrogen gas supply flow. [Figure 8] Figure 8 shows the diagram corresponding to step S5 of the hydrogen gas supply flow. [Figure 9] Figure 9 shows the flow of hydrogen gas supply shutdown. [Figure 10] Figure 10 is a diagram corresponding to step S11 of the hydrogen gas supply shutdown flow. [Figure 11] Figure 11 is a diagram corresponding to step S12 of the hydrogen gas supply shutdown flow. [Figure 12]FIG. 12 is a diagram corresponding to step S13 of the hydrogen gas supply stop flow. [Figure 13] FIG. 13 is a diagram corresponding to step S13 of the hydrogen gas supply stop flow. [Figure 14] FIG. 14 is a diagram corresponding to step S14 of the hydrogen gas supply stop flow. [Figure 15] FIG. 15 is a diagram corresponding to step S15 of the hydrogen gas supply stop flow. [Figure 16] FIG. 16 is a diagram corresponding to step S16 of the hydrogen gas supply stop flow. [Figure 17] FIG. 17 is a diagram corresponding to step S17 of the hydrogen gas supply stop flow. [Figure 18] FIG. 18 is a diagram corresponding to step S18 of the hydrogen gas supply stop flow. DETAILED DESCRIPTION OF EMBODIMENTS
[0009] (Overall Configuration of Hydrogen Gas Supply System) Hereinafter, the operation method of the hydrogen gas supply system 100 will be described. First, the overall configuration of the hydrogen gas supply system 100 will be described. FIG. 1 is a schematic diagram of the hydrogen gas supply system 100. The hydrogen gas supply system 100 of the present embodiment is a system that supplies hydrogen gas to a plurality of burners (first to third burners).
[0010] As shown in FIG. 1, the hydrogen gas supply system 100 includes a main pipe 10, a hydrogen gas header 20, and a plurality of branch pipes 30. Hereinafter, these constituent elements will be described in order.
[0011] <Main Pipe> The main pipe 10 is a pipe that guides the hydrogen gas supplied to the hydrogen gas supply system 100 to the hydrogen gas header 20. The main pipe 10 is provided with a fuel shutoff valve 11, a main shutoff section upstream valve 12, a main shutoff section downstream valve 13, and a flow rate adjustment valve 14.
[0012] The fuel shutoff valve 11 is located at the most upstream position of the hydrogen gas supply system 100. By opening the fuel shutoff valve 11, hydrogen gas is supplied to the hydrogen gas supply system 100. On the other hand, by closing the fuel shutoff valve 11, the supply of hydrogen gas to the hydrogen gas supply system 100 is stopped.
[0013] The main shutoff section upstream valve 12 is located downstream of the fuel shutoff valve 11. In the present embodiment, the area between the fuel shutoff valve 11 and the main shutoff section upstream valve 12 in the hydrogen gas supply system 100 is referred to as "upstream area 91". A first discharge pipe 41 is provided at the portion of the main pipe 10 corresponding to the upstream area 91.
[0014] The first discharge pipe 41 is a pipe that discharges the gas in the upstream area 91 to the outside of the hydrogen gas supply system 100. The first discharge pipe 41 is provided with a first discharge valve 42. By opening the first discharge valve 42, the gas in the upstream area 91 is discharged to the outside of the hydrogen gas supply system 100 via the first discharge pipe 41.
[0015] The main shutoff section downstream valve 13 is located downstream of the main shutoff section upstream valve 12. In the present embodiment, the section between the main shutoff section upstream valve 12 and the main shutoff section downstream valve 13 in the main pipe 10 is referred to as "main shutoff section 15". A main pressure gauge 16, a first inert gas supply pipe 51, and a second discharge pipe 43 are provided at the portion of the main pipe 10 corresponding to the main shutoff section 15.
[0016] The main pressure gauge 16 is a measuring instrument that measures the internal pressure of the main shutoff section 15.
[0017] The first inert gas supply pipe 51 is a pipe that supplies inert gas to the main shut-off section 15. The first inert gas supply pipe 51 connects the main shut-off section 15 to the inert gas header 50, and the first inert gas supply valve 52 is provided in the first inert gas supply pipe 51. By opening this first inert gas supply valve 52, inert gas is supplied from the inert gas header 50 to the main shut-off section 15 via the first inert gas supply pipe 51. Examples of inert gas include nitrogen gas.
[0018] The second discharge pipe 43 is a pipe that discharges the gas from the main shut-off section 15 to the outside of the hydrogen gas supply system 100. The second discharge pipe 43 is equipped with a second discharge valve 44. By opening the second discharge valve 44, the gas from the main shut-off section 15 is discharged to the outside of the hydrogen gas supply system 100 via the second discharge pipe 43.
[0019] The flow control valve 14 is located downstream of the main shut-off section downstream valve 13. In other words, the main shut-off section 15 is located upstream of the flow control valve 14. The flow control valve 14 is a valve that adjusts the hydrogen gas supply flow rate (in this embodiment, the hydrogen gas supply flow rate supplied to each burner). A third discharge pipe 45 is provided in the portion of the main piping 10 downstream of the flow control valve 14 (between the flow control valve 14 and the hydrogen gas header 20).
[0020] The third discharge pipe 45 is a pipe that discharges the gas downstream of the main shut-off section downstream valve 13 of the main pipe 10 to the outside of the hydrogen gas supply system 100. The third discharge pipe is equipped with a third discharge valve 46. By opening the third discharge valve 46, the gas downstream of the main shut-off section downstream valve 13 of the main pipe 10 is discharged to the outside of the hydrogen gas supply system 100 via the third discharge pipe 45.
[0021] <Hydrogen Gas Header> The hydrogen gas header 20 is located downstream of the main piping 10, and hydrogen gas is supplied from the main piping 10. The hydrogen gas header 20 has the function of temporarily holding the hydrogen gas supplied from the main piping 10 and distributing the held hydrogen gas to each branch piping 30. The hydrogen gas header 20 is also equipped with a hydrogen gas header pressure gauge 21 and a second inert gas supply pipe 53.
[0022] The hydrogen gas header pressure gauge 21 is a measuring instrument that measures the internal pressure of the hydrogen gas header 20.
[0023] The second inert gas supply pipe 53 is a pipe that supplies inert gas to the hydrogen gas header 20. The second inert gas supply pipe 53 connects the hydrogen gas header 20 and the inert gas header 50, and the second inert gas supply valve 54 is provided in the second inert gas supply pipe 53. By opening this second inert gas supply valve 54, inert gas is supplied from the inert gas header 50 to the hydrogen gas header 20 via the second inert gas supply pipe 53.
[0024] <Branch piping> The branch pipe 30 is a pipe that leads hydrogen gas from the hydrogen gas header 20 to the burner. The hydrogen gas supply system 100 in this embodiment has multiple (three in Figure 1) branch pipes 30. Each branch pipe 30 supplies hydrogen gas to the corresponding burner. Depending on the operating conditions of the combustion equipment including the burner, all branch pipes 30 may supply hydrogen gas to the burner, or only some of the branch pipes 30 may supply hydrogen gas to the burner.
[0025] Each branch pipe 30 is configured in the same way. Each branch pipe 30 is equipped with a branch shut-off valve 31, a branch shut-off valve 32, a check valve 33, and a flame arrestor 34.
[0026] The upstream valve 31 of the branch shut-off section is located on the upstream side of the branch piping 30. In this embodiment, the area between the upstream valve 12 of the main shut-off section and the upstream valve 31 of the branch shut-off section in the hydrogen gas supply system 100 is referred to as the "intermediate area 92". The area downstream of the upstream valve 31 of the branch shut-off section in the hydrogen gas supply system 100 is referred to as the "downstream area 93".
[0027] The downstream valve 32 of the branch shut-off section is located downstream of the upstream valve 31 of the branch shut-off section. In this embodiment, the section between the upstream valve 31 and the downstream valve 32 of the branch shut-off section in the branch piping 30 is referred to as the "branch shut-off section 35". A third inert gas supply pipe 55 is provided in the portion of the branch piping 30 corresponding to the branch shut-off section 35.
[0028] The third inert gas supply pipe 55 is a pipe that supplies inert gas to the branch shut-off section 35. The third inert gas supply pipe 55 connects the branch shut-off section 35 to the inert gas header 50, and the third inert gas supply pipe 55 is equipped with a third inert gas supply valve 56. By opening this third inert gas supply valve 56, inert gas is supplied from the inert gas header 50 to the branch shut-off section 35. In this embodiment, each of the third inert gas supply pipes 55 is partially connected, but each may also connect the branch shut-off section 35 and the inert gas header 50 independently.
[0029] Furthermore, a branch pressure gauge 36 is provided in the section between the branch shut-off section 35 of the third inert gas supply piping 55 and the third inert gas supply valve 56. The branch pressure gauge 36 is a measuring instrument that measures the internal pressure of the branch shut-off section 35.
[0030] The check valve 33 is located downstream of the branch shut-off valve 32. The check valve 33 allows the flow of hydrogen gas downstream (towards the burner) while prohibiting the flow of hydrogen gas upstream.
[0031] The flame arrester 34 is a device that prevents flames from entering the branch pipe 30 from the burner, and is installed as needed.
[0032] The above describes the overall configuration of the hydrogen gas supply system 100. In the above description, one inert gas supply valve 52, 54, and 56 are provided in each of the inert gas supply pipes 51, 53, and 55, which are pipes that supply inert gas to the hydrogen gas supply system 100. However, multiple inert gas supply valves 52, 54, and 56 may be provided in series in each of the inert gas supply pipes 51, 53, and 55.
[0033] (Hydrogen gas supply flow) Next, we will explain the hydrogen gas supply flow in the hydrogen gas supply system 100. Figure 2 shows the hydrogen gas supply flow. Here, we will explain the hydrogen gas supply flow in the hydrogen gas supply system 100 from when the hydrogen gas supply system 100 is in the "first standby state" until hydrogen gas is supplied to the burner.
[0034] First, let's explain the "first standby state." Figure 3 shows the first standby state of the hydrogen gas supply system 100. In Figure 3, thick lines indicate areas filled with hydrogen gas, dashed lines indicate areas filled with inert gas, white valve symbols indicate that the valve is open, and black valve symbols indicate that the valve is closed. The same applies to Figures 4 to 8 and 10 to 18, which will be discussed later.
[0035] As shown in Figure 3, when the hydrogen gas supply system 100 is in the first standby state, the fuel shut-off valve 11, the main shut-off section upstream valve 12, the main shut-off section downstream valve 13, the branch shut-off section upstream valve 31, the branch shut-off section downstream valve 32, and the inert gas supply valves 52, 54, and 56 are closed, while all other valves are open. When the hydrogen gas supply system 100 is in the first standby state, there is no hydrogen gas (more precisely, a combustible amount of hydrogen gas) downstream of the fuel shut-off valve 11 (inside the hydrogen gas supply system 100). Furthermore, since the branch shut-off section upstream valve 31 and the branch shut-off section downstream valve 32 are closed, the branch shut-off section 35 is shut off.
[0036] When the hydrogen gas supply flow is started from the first standby state of the hydrogen gas supply system 100, as shown in Figure 2, an inert gas is first supplied to the main shut-off section 15 (step S1). Specifically, as shown in Figure 4, the second discharge valve 44 is closed, and then the first inert gas supply valve 52 is opened. This supplies inert gas to the main shut-off section 15. After that, the internal pressure of the main shut-off section 15 is raised to a predetermined main shut-off pressure or higher, and then the first inert gas supply valve 52 is closed and maintained in that state. In this state, the internal pressure of the main shut-off section 15 is measured using the main pressure gauge 16 to confirm that there are no leaks. Note that the above-mentioned "main shut-off pressure" is higher than the pressure of the hydrogen gas supplied to the main shut-off section 15.
[0037] After step S1 is performed, hydrogen gas is supplied to the upstream area 91 (step S2). Specifically, as shown in Figure 5, the first discharge valve 42 is closed and then the fuel shut-off valve 11 is opened. This supplies hydrogen gas to the upstream area 91. In this embodiment, the state shown in Figure 5 is referred to as the "second standby state".
[0038] After step S2 is performed, inert gas is supplied to the branch shut-off section 35 (step S3). Specifically, as shown in Figure 6, the third inert gas supply valve 56 is opened. This supplies inert gas to the branch shut-off section 35. Then, the internal pressure of the branch shut-off section 35 is raised to a predetermined branch shut-off pressure or higher, and then the third inert gas supply valve 56 is closed and maintained in that state. In this state, the internal pressure of the branch shut-off section 35 is measured using the branch pressure gauge 36 to confirm that there are no leaks. Note that the above-mentioned "branch shut-off pressure" is higher than the pressure of the hydrogen gas supplied to the branch shut-off section 35.
[0039] After step S3 is performed, hydrogen gas is supplied to the intermediate area 92 (step S4). Specifically, as shown in Figure 7, after closing the third discharge valve 46, the main shut-off section upstream valve 12 and the main shut-off section downstream valve 13 are opened. This supplies hydrogen gas to the intermediate area 92. In this state, the internal pressure of the intermediate area 92 is measured using the hydrogen gas header pressure gauge 21 to confirm that there are no leaks.
[0040] After step S4 is performed, hydrogen gas is supplied to the downstream area 93 (step S5). Note that here, hydrogen gas is not supplied to all of the multiple downstream areas 93, but only to the downstream area 93 corresponding to the burner to which hydrogen gas is to be supplied. For example, if it is to be supplied only to the first burner, the upstream valve 31 and downstream valve 32 of the branch shut-off section of the downstream area 93 corresponding to the first burner are opened, as shown in Figure 8. As a result, hydrogen gas is supplied only to the first burner.
[0041] On the other hand, in the downstream area 93 corresponding to the second and third burners, the upstream valve 31 and downstream valve 32 of the branch shut-off section remain closed, and the branch shut-off section 35 is filled with inert gas. Moreover, the pressure of the inert gas in the branch shut-off section 35 (above the branch shut-off pressure) is higher than the pressure of the hydrogen gas supplied to the branch shut-off section 35. Therefore, in the downstream area 93 corresponding to the second and third burners, even if there were a gap in the upstream valve 31 of the branch shut-off section that would allow highly permeable hydrogen gas to pass through, the hydrogen gas cannot pass through the branch shut-off section 35. In other words, hydrogen gas will not leak to the second and third burners. The above explains the hydrogen gas supply flow in the hydrogen gas supply system 100.
[0042] (Flowchart for stopping hydrogen gas supply) Next, we will explain the supply shutdown flow in the hydrogen gas supply system 100. Here, we will explain the flow from the state of the hydrogen gas supply system 100 shown in Figure 8 to the first standby state or second standby state, where the supply of hydrogen gas to the burner is stopped.
[0043] Figure 9 shows the hydrogen gas supply shutdown flow. As shown in Figure 9, when the hydrogen gas supply shutdown flow begins, the intermediate area 92 and the downstream area 93 are first depressurized (step S11). Specifically, as shown in Figure 10, after closing the main shut-off section upstream valve 12, the main shut-off section downstream valve 13, the branch shut-off section upstream valve 31, and the branch shut-off section downstream valve 32, the second discharge valve 44 and the third discharge valve 46 are opened. As a result, the internal pressure of the intermediate area 92 and the downstream area 93 (the downstream area 93 corresponding to the first burner) decreases, and the intermediate area 92 and the downstream area 93 are depressurized.
[0044] After step S11 is performed, the downstream area 93 is purged (step S12). Specifically, as shown in Figure 11, after opening the branch shut-off section downstream valve 32, the third inert gas supply valve 56 of each downstream area 93 is opened. As a result, the hydrogen gas present inside the downstream area 93 is discharged to the outside of the hydrogen gas supply system 100 via each burner. In other words, the downstream area 93 is purged.
[0045] After step S12 is performed, the intermediate area 92 is purged (step S13). Specifically, as shown in Figure 12, the branch shut-off section downstream valve 32, the third inert gas supply valve 56, the second discharge valve 44, and the third discharge valve 46 are closed, and then the first inert gas supply valve 52 and the second inert gas supply valve 54 are opened. This supplies inert gas to the intermediate area 92, causing the internal pressure of the intermediate area 92 to rise (accumulate). Then, as shown in Figure 13, the first inert gas supply valve 52 and the second inert gas supply valve 54 are closed, and the second discharge valve 44 and the third discharge valve 46 are opened. This opens the intermediate area 92, and hydrogen gas is discharged from the intermediate area 92 along with the inert gas via the second discharge pipe 43 and the third discharge pipe 45. The process shown in Figures 12 and 13 is then repeated multiple times in succession. This ensures that hydrogen gas is effectively discharged from the intermediate area 92, even though the intermediate area 92, which is the area to be purged, has a complex shape. In other words, it allows for highly accurate purging.
[0046] After step S13 is performed, the main shut-off section 15 is shut off (step S14). Specifically, as shown in Figure 14, the second discharge valve 44 is closed. This shuts off the main shut-off section 15.
[0047] After step S14 is performed, inert gas is supplied to the main shut-off section 15 (step S15). Specifically, as shown in Figure 15, the first inert gas supply valve 52 is opened. This supplies inert gas to the main shut-off section 15. After that, the internal pressure of the main shut-off section 15 is raised to above the aforementioned main shut-off pressure, and then the first inert gas supply valve 52 is closed and maintained in that state. As a result, the hydrogen gas supply system 100 enters the second standby state. In other words, the hydrogen gas supply system 100 enters the state shown in Figure 5 above. In this case, even if there is a gap in the main shut-off section upstream valve 12 that would allow highly permeable hydrogen gas to pass through, the hydrogen gas cannot pass through the main shut-off section 15.
[0048] If the hydrogen gas supply system 100 is kept in a "second standby state" until the hydrogen gas supply is resumed, the hydrogen gas supply shutdown flow ends here. In this case, when resuming the hydrogen gas supply, the process starts from step S3 in Figure 2. For example, if the time until the hydrogen gas supply is to be resumed is relatively short, the hydrogen gas supply system 100 can be kept in a second standby state.
[0049] On the other hand, if the hydrogen gas supply system 100 is to be kept in a "first standby state" until the hydrogen gas supply is resumed, step S15 is performed and then the process proceeds to step S16. For example, if the time until the hydrogen gas supply is to be resumed is relatively long, the hydrogen gas supply system 100 can be kept in a first standby state.
[0050] In step S16, the upstream area 91 is depressurized. Specifically, as shown in Figure 16, the fuel shut-off valve 11 is closed, and then the first discharge valve 42 is opened. This reduces the internal pressure of the upstream area 91, and the upstream area 91 is depressurized.
[0051] After step S16 is performed, the upstream area 91 is purged (step S17). Specifically, as shown in Figure 17, the first inert gas supply valve 52 and the main shut-off section upstream valve 12 are opened. As a result, inert gas flows into the upstream area 91, and hydrogen gas is discharged to the outside of the hydrogen gas supply system 100 via the first discharge pipe 41 along with the inert gas.
[0052] After step S17 is performed, the hydrogen gas supply system 100 is put into the first standby state (step S18). Specifically, as shown in Figure 18, the main shut-off section upstream valve 12 is closed, then the first inert gas supply valve 52 is closed, and then the second discharge valve 44 is opened. In other words, the hydrogen gas supply system 100 is put into the state shown in Figure 3. In this case, when restarting the hydrogen gas supply, the process starts from step S1 in Figure 2. The above is an explanation of the hydrogen gas supply shutdown flow in the hydrogen gas supply system 100.
[0053] (summary) The first item disclosed herein is a method for operating a hydrogen gas supply system, which involves supplying an inert gas to a sealed area to be purged to increase the internal pressure of the area, and then opening the area to be purged and releasing hydrogen gas from the area along with the inert gas, and repeating this process multiple times in a series of steps to perform purging of the area to be purged.
[0054] This method allows for the thorough removal of hydrogen gas from the purging area, enabling highly accurate purging.
[0055] The second item disclosed herein is a method for operating the hydrogen gas supply system described in the first item, which involves forming a shut-off section in the hydrogen gas supply system, supplying an inert gas to the shut-off section to raise the internal pressure of the shut-off section to a predetermined shut-off pressure or higher, and maintaining the internal pressure of the shut-off section at or above the shut-off pressure to prevent hydrogen gas from passing through the shut-off section.
[0056] According to this method, hydrogen gas cannot pass through the barrier section, thus blocking the flow of hydrogen gas at the barrier section.
[0057] A third item disclosed herein is a method for operating the hydrogen gas supply system described in the second item, wherein the hydrogen gas supply system is provided with a flow control valve for adjusting the hydrogen gas supply flow rate, and the shut-off section is formed upstream of the flow control valve.
[0058] This method allows the flow of hydrogen gas to be blocked upstream of the flow control valve.
[0059] A fourth item disclosed herein is a method of operating the hydrogen gas supply system described in item 2 or 3, wherein the hydrogen gas supply system includes a plurality of branch pipes that supply hydrogen gas to a corresponding burner, and the shut-off section is formed in each of the plurality of branch pipes.
[0060] With this configuration, the flow of hydrogen gas can be blocked in each branch pipe. [Explanation of Symbols]
[0061] 14 Flow control valve 15 Main Blocked Section (Blocked Section) 30 branch pipes 35 Branching section (blocked section) 92 Intermediate area (area subject to purging) 100 Hydrogen gas supply system
Claims
1. In a hydrogen gas supply system, the process of supplying an inert gas to a sealed area to be purged to increase the internal pressure of the area, then opening the area to be purged and releasing hydrogen gas along with the inert gas from the area is repeated multiple times in a continuous manner to perform purging of the area. In a hydrogen gas supply system, a shut-off section is formed, an inert gas is supplied to the shut-off section to raise the internal pressure of the shut-off section to above a predetermined shut-off pressure, and the internal pressure of the shut-off section is maintained above the shut-off pressure, thereby preventing hydrogen gas from passing through the shut-off section. The aforementioned interruption section includes the main interruption section. The hydrogen gas supply system is provided with a flow control valve for adjusting the hydrogen gas supply flow rate, and a pair of valves located upstream of the flow control valve and adjacent to it without a branching point in the piping. The pair of valves forms the main shut-off section upstream of the flow control valve. A method for operating a hydrogen gas supply system, wherein the purging target area includes the main shutoff section, the section between the main shutoff section and the flow control valve, and the section downstream of the flow control valve.
2. The interruption section includes a branch interruption section, The hydrogen gas supply system according to claim 1, wherein the hydrogen gas supply system includes a plurality of branch pipes that supply hydrogen gas to a corresponding burner, and the branch shut-off section is formed in each of the plurality of branch pipes.
Citation Information
Patent Citations
Pressure relief and replacement device and method for hydrogen loading and unloading connector
CN115560243A
Lorry shipping method of lng
JP2001324093A
Abnormality detection method for gas turbine fuel supply device
JP2002013418A
Hydrogen combustion boiler
JP2018200166A
Combustion device
JP2022016933A