Construction vehicle operation management system

The construction vehicle operation management system addresses data entry inefficiencies and safety issues by employing GNSS-based geofencing and altitude sensing to provide real-time monitoring and accurate prediction of vehicle operations, improving safety and efficiency.

JP7954048B2Active Publication Date: 2026-11-19KONOIKE CONSTR LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2022195311
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2022-12-07
Publication Date
2026-11-19
Estimated Expiration
2042-12-07

AI Technical Summary

Technical Problem

Existing construction vehicle operation management systems face issues such as cumbersome data entry, potential for errors, terminal damage, and difficulty in operating communication devices in high-altitude or unloading conditions, especially for ready-mixed concrete trucks, leading to inefficiencies and safety concerns.

Method used

A construction vehicle operation management system utilizing GNSS-based geofencing to set up virtual boundaries along construction vehicle routes, capturing entry and exit times, and integrating location information with data management servers for real-time monitoring and sharing among construction personnel, including altitude and gradient data through angle and barometric pressure sensors.

Benefits of technology

Enables real-time monitoring and accurate prediction of vehicle operations, including speed, arrival times, and fuel consumption, while enhancing safety management and reducing errors, allowing for precise labor and fuel efficiency tracking and CO2 emission calculations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007954048000001
    Figure 0007954048000001
  • Figure 0007954048000002
    Figure 0007954048000002
  • Figure 0007954048000003
    Figure 0007954048000003
Patent Text Reader

Abstract

To provide a construction vehicle operation management system that manages operation of a ready-mixed concrete vehicle.SOLUTION: A construction vehicle operation management system includes: a data management server that accumulates operation data on a ready-mixed concrete vehicle 2; a position information transmission application that transmits position information on the ready-mixed concrete vehicle 2 to the data management server; and an operation management web application that verifies the operation data on the ready-mixed concrete vehicle 2 accumulated in the data management server. The position information transmission application is installed in a communication terminal 3 carried by a driver of the ready-mixed concrete vehicle 2; and the operation management web application is installed in a communication terminal 4 carried by a person in a construction site b who is concerned with construction. A geofence A is set at a point of a ready-mixed concrete plant a, a geofence B is set at a point of the construction site b, and geofences C and D are set at an intersection and a conjunction predicted point respectively between the ready-mixed concrete plant a and the construction site b. The construction vehicle operation management system is configured so that times when the ready-mixed concrete vehicle 2 which passes through the geofences A, B, C, and D enters and exits the geofences A, B, C, and D are registered in the communication terminal 3, and transmitted to and accumulated in the data management server.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present invention relates to a construction vehicle operation management system, and in particular, is configured to allow the operation status and the like of construction vehicles used at construction sites, such as ready-mixed concrete trucks that travel on roads not shown on maps including construction roads, dump trucks that transport surplus soil, or trucks that carry materials, to be grasped in real time and shared among construction personnel. BACKGROUND ART

[0002] In particular, placing concrete for building structural frames is an important process for creating high-quality concrete structures, and maximum safety and quality control are required while constantly checking the status of the placement location and the operation status of ready-mixed concrete trucks so that ready-mixed concrete can be placed smoothly.

[0003] For example, Patent Document 1 discloses an invention of a ready-mixed concrete delivery and placement management system that enables both a ready-mixed concrete plant and a construction site to share in real time the status of ready-mixed concrete shipment, delivery, placement, and the like.

[0004] Briefly described, the system is provided with a host computer having a database that accumulates operation data of ready-mixed concrete trucks, and a plurality of communication terminals that transmit the operation data of the ready-mixed concrete trucks to the database and check the operation data of the ready-mixed concrete trucks accumulated in the database, and the communication terminals are carried by personnel in charge at the ready-mixed concrete plant, drivers of the ready-mixed concrete trucks, construction site personnel, site office personnel, and further head office or branch office personnel and other construction-related personnel.

[0005] In addition to the specifications of the ready-mixed concrete, the operation data of the ready-mixed concrete trucks includes the ready-mixed concrete mixing start time, the shipment order of the ready-mixed concrete trucks at the ready-mixed concrete plant, the delivery time of the ready-mixed concrete at the construction site, the placement completion time, and the like.

[0006] Then, at the time of starting mixing of the ready-mixed concrete, at the time of shipment, at the time of delivery, and at the time of placing the ready-mixed concrete, the personnel in charge at the ready-mixed concrete plant and the drivers of the ready-mixed concrete trucks individually input each time by push button operation on their respective carried communication terminals.

[0007] The entered operational data is transmitted to and stored in the host computer's database. This data can then be accessed by construction sites, site offices, the head office, branches, and other construction personnel using their personal communication terminals, allowing for the sharing of progress regarding the shipment, delivery, and placement of ready-mix concrete. [Prior art documents] [Patent Documents]

[0008] [Patent Document 1] Patent No. 6709117 [Patent Document 2] Japanese Patent Publication No. 2014-233914 [Overview of the Initiative] [Problems that the invention aims to solve]

[0009] However, in the management system invention described in Patent Document 1, information such as the start time of mixing ready-mix concrete and the departure time of the ready-mix concrete truck from the plant is entered by the plant manager and the truck driver using push buttons on their respective communication terminals. This makes data entry cumbersome and prone to errors or omissions.

[0010] Furthermore, there were challenges such as the risk of dropping and damaging the communication terminal during work, and the fact that operating the communication terminal while unloading cargo was difficult, especially in high-altitude work situations.

[0011] Incidentally, there is a known method of confirming the current location of a vehicle by using location information from GNSS (GPS, etc.) to check entry and exit from geofences set on a map displayed on the screen of a mobile device, and recording and notifying departure and arrival times. This method is attracting attention, especially in the transportation industry, for its benefits in terms of improving operational efficiency, accident prevention, and working conditions.

[0012] The present invention was made to solve the above problems, and aims to provide a construction vehicle operation management system that enables real-time monitoring and sharing of the operation status of construction vehicles among construction personnel by setting up geofences using GNSS-based location information on the routes in which construction vehicles move, and confirming the entry and exit of construction vehicles into and from the geofences. [Means for solving the problem]

[0013] The present invention provides a construction vehicle operation management system comprising a data management server for accumulating operation data of construction vehicles, a location information transmission application for transmitting location information of construction vehicles to the data management server, and an operation management web application for checking the operation data accumulated on the data management server. The system is configured such that the location information transmission application is installed on a communication terminal carried by the driver of the construction vehicle, the operation management web application is installed on a communication terminal carried by the construction personnel, multiple geofences using GNSS location information are set at intervals along the route the construction vehicle travels, and each time the construction vehicle passes through a geofence, the entry and exit times of the construction vehicle to and from the geofence are transmitted to and stored on the data management server. This allows for real-time monitoring of the operation status of construction vehicles used on site, such as concrete mixer trucks, dump trucks transporting excavated soil, or trucks transporting materials, in geofenced sections, even on roads not shown on maps, such as construction roads, including the operating speed and estimated departure and arrival times of the construction vehicles, and to share this information among construction personnel.

[0014] Furthermore, by installing a location information transmission application on communication terminals carried by construction personnel within the construction site, setting up geofences using GNSS location information along the routes that the construction personnel move within the construction site, and configuring the system so that each time a construction worker enters or exits the geofence, the time of entry and exit of the geofence is captured by the communication terminal carried by the construction personnel and transmitted to the data management server for storage, for example, by setting up geofences in a certain area on the floor where ready-mix concrete is poured during the construction of a high-rise building, it is possible to automatically grasp the time when construction workers enter or exit the building floor or area where they are located, as well as the time they stay, and this can be used for managing the working hours and safety of construction workers.

[0015] Geofencing can be set up by specifying the location to be marked using latitude and longitude, and then defining an area (fence) with a virtual boundary line, such as a circle, centered on that location. The proximity of the marked locations can be adjusted by specifying the area.

[0016] The operational data of the aforementioned construction vehicles may include the height or gradient within each geofence. The height or gradient within each geofence can be determined by angle sensors and barometric pressure sensors equipped in the communication terminal, thereby allowing for the determination of elevation differences along the entire route and between geofences.

[0017] Furthermore, PCs, tablets, or smartphones can be used as communication terminals carried by the drivers of the construction vehicles and other construction personnel. [Effects of the Invention]

[0018] The present invention has the following effects. (1) By setting up multiple geofences using GNSS location information on roads not shown on maps, such as construction roads, it is possible to check the operation status of construction vehicles used on site, such as concrete mixer trucks, dump trucks transporting excavated soil, or trucks transporting materials, and share this information among construction personnel.

[0019] For example, by setting up multiple geofences at intervals along the route of construction vehicles and tracking the time it takes for construction vehicles to pass through the geofences, it is possible to determine the operating speed and estimated arrival and departure times of construction vehicles within the geofenced sections.

[0020] While conventional car navigation systems alert drivers to speeding or driving economically based on tire rotation, geofencing allows for the management of construction vehicle operations using only communication devices such as smartphones.

[0021] (2) By setting up geofences at intersections and congestion-prone areas on public roads, the time that construction vehicles spend within the geofences can be monitored, allowing for real-time prediction of congestion locations and arrival times (information is available every second, so there is no wasted time). While typical car navigation systems rely on information from VICS (registered trademark), setting up geofences allows for this determination to be made using only communication devices such as smartphones.

[0022] (3) By setting up multiple geofences at regular intervals on public roads, etc., the time of passage of construction vehicles passing through each geofence can be confirmed. Therefore, the operating interval can be calculated from the time difference when the preceding vehicle passes (the operating interval time is calculated from the time difference, the operating speed is calculated from the operating interval time and the distance between geofence sections, and the operating interval distance with the preceding vehicle is calculated), thus preventing tandem driving. Note that regular car navigation systems cannot obtain information on other vehicles.

[0023] (4) By setting geofences not only within the site premises but also at pinpoint locations such as near concrete pump trucks, the placement start time of ready-mixed concrete trucks can be accurately predicted (the placement starts a few minutes after entering the area, e.g., 3 minutes after area entry, and the placement end time is almost identical to the area exit time).

[0024] (5) By setting the geofence setting area to be narrow, the range of applications can be expanded. Normally, there are systems where a responsible person presses a placement start button at the start of concrete placement, or a distance sensor is installed on a pump truck or the like to detect arrival and start of placement when a ready-mixed concrete truck approaches a predetermined distance, but the present arrangement can be implemented using only a communication terminal.

[0025] (6) Mobile terminals (smartphones) have a built-in barometric pressure sensor that can determine the altitude of the mobile terminal. With these, the horizontal X-Y direction and the vertical Z direction of the communication terminal can be determined. For example, by setting a geofence in the ready-mixed concrete placement area during the construction of a high-rise building, it is possible to automatically confirm the floor or area where the construction worker carrying the communication terminal is located, the time when the worker entered the relevant floor or area, and the time when the worker exited the relevant floor or area, which can be utilized for labor time management and safety management of workers. Ordinary geofences only use horizontal X-Y coordinates, but by adding a height dimension, management in three directions, namely the horizontal X-Y direction and the vertical Z direction, can be performed.

[0026] (7) By setting geofences at regular intervals on the travel route of construction vehicles, the section speed between each geofence and the estimated arrival time can be determined. In particular, by using the angle sensor and barometric pressure sensor that are normally installed in smartphones, the elevation difference between geofences can be determined. This makes it possible to grasp the elevation difference along the entire route and between geofences.

[0027] (8) Each construction vehicle driver has their own unique driving habits, including those related to weather conditions and road conditions (for example, driving too fast on flat ground, revving the engine too much on uphill slopes, driving too fast even when there is snow or rain, etc.), so the arrival time will differ for each driver. Therefore, it is possible to calculate the speed and driving time from the distance (including height) between geofences for each driver, both when the vehicle is loaded with ready-mix concrete and when it is empty. This allows us to understand the characteristics of each driver and estimate the expected arrival time.

[0028] Once the characteristics of each driver are entered, the system can accurately predict their route even if it changes, taking those characteristics into account. Furthermore, because excessive speed near houses and around curves varies from driver to driver, it can be used for safe driving education (safety messages can be registered on the map for each driver, and voice messages can be sent). Conventional car navigation systems do not take driver habits into account.

[0029] (9) Summarize the relationship between the distance traveled, speed, stopping time, and total fuel consumption on flat ground and uphill, with and without concrete loaded, between each geofence (including height), and calculate the fuel consumption according to each operating condition. Repeating these steps will improve the accuracy of the fuel consumption calculation. This will allow you to calculate the fuel consumption from the speed of the construction vehicle along its route, and further calculate the CO2 emissions, which can be used for fuel-efficient driving and CO2 emission reduction.

[0030] The Ministry of Land, Infrastructure, Transport and Tourism's standard method for calculating CO2 emissions is based on vehicle size and mileage, and does not take into account conditions such as whether the vehicle is loaded with ready-mix concrete, or whether it is driving on flat ground or uphill when empty. The management system of the present invention can calculate fuel consumption by taking route conditions into account, and therefore can accurately calculate CO2 emissions. Furthermore, even if the route changes, CO2 emissions can be calculated accurately if the elevation difference of the route and the driving speed are known. [Brief explanation of the drawing]

[0031] [Figure 1]This is a schematic diagram illustrating one embodiment of the construction vehicle operation management system of the present invention. [Figure 2] Figure 1 is an explanatory diagram illustrating the operation of the construction vehicle operation management system. [Figure 3] Figure 1 is an explanatory diagram illustrating the operation of the construction vehicle operation management system. [Modes for carrying out the invention]

[0032] Figure 1 is a schematic diagram showing one embodiment of the construction vehicle operation management system of the present invention, and Figures 2 and 3 are explanatory diagrams showing its operation method.

[0033] In the diagram, reference numeral 1 denotes a host computer into which a data management server that stores data such as operational information of the construction vehicle (hereinafter referred to as "concrete mixer truck") 2 is installed. Reference numeral 3 denotes a communication terminal that transmits location information of the concrete mixer truck 2 to the host computer 1, and has the concrete mixer truck 2 location information transmission application installed. Reference numeral 4 denotes a communication terminal that checks data such as operational information of the concrete mixer truck 2 stored in the host computer 1, and has the concrete mixer truck 2 operation management web application installed.

[0034] Communication terminal 3 uses smartphones, tablets, etc., and is carried by workers at the ready-mix concrete plant and the drivers of the ready-mix concrete truck 2. In addition, communication terminal 4 uses personal computers, etc., in addition to smartphones and tablets, and is carried by site supervisors and related personnel at construction sites, the construction management headquarters at the head office and branches, and other construction-related personnel such as clients and design offices.

[0035] On the maps displayed on the screens of communication terminals 3 and 4, geofence A is set to enclose the location of concrete plant a and a certain area including the location of concrete plant a, and geofence B is set to enclose the location of construction site b and a certain area including the location of construction site b.

[0036] Furthermore, geofences C and D are set up on the road along which the concrete mixer truck 2 travels between the location of concrete plant a and the location of construction site b. These geofences include intersections c and areas where congestion is predicted, respectively.

[0037] Geofences A, B, C, and D are set to the most suitable shape, such as a circle or rectangle, to match the intricate road network and other features within their respective geofence areas. Additionally, geofence B is set on a road that does not appear on the map.

[0038] In this configuration, each time the concrete mixer truck 2 passes through geofences A, B, C, and D, the arrival time at each geofence A, B, C, and D, and the departure time from geofences A, B, C, and D are automatically registered in the communication terminal 3 carried by the driver of the concrete mixer truck 2. The registered data is then transmitted to the host computer 1 and automatically stored in the data management server of the host computer 1.

[0039] Furthermore, the maps displayed on the screens of communication terminals 3 and 4 show real-time information representing the operational status of the concrete mixer trucks 2, such as the vehicle position of each truck. In addition, necessary information representing the concrete pouring status, such as the planned amount of concrete to be poured, the amount poured, and the remaining amount, are displayed in real time (see Figure 3).

[0040] This information, representing the concrete placement status, is entered by personnel at the ready-mix concrete plant and drivers of the ready-mix concrete truck 2 using their own portable communication terminals 3, and is also displayed automatically or via button operation on the screens of communication terminals 3 and 4.

[0041] This information can then be viewed in real time by workers at the ready-mix concrete plant, drivers of the ready-mix concrete truck 2, site supervisors and personnel at the construction site, the construction management headquarters at the head office and branches, and other construction-related personnel such as clients and design offices, using their respective portable communication terminals 3 and 4.

[0042] This allows us to track the passage times of concrete mixer truck 2 through geofences A, B, C, and D as it moves between the concrete plant and the construction site. This enables real-time monitoring of operational status, such as operating speed and estimated arrival / departure times, for each geofenced section, and allows this information to be shared among construction personnel. Furthermore, by checking the dwell time of concrete mixer truck 2 at each geofenced location, it is possible to predict congestion points and arrival times in real time.

[0043] For example, since the passing times of concrete mixer truck 2 as it passes each geofence A, B, C, and D can be confirmed, the operating interval can be calculated from the time difference when the preceding concrete mixer truck 2 passes (the operating interval time is calculated from the time difference, and the operating speed is calculated from the operating interval time and the distance between each geofence A, B, C, and D to calculate the operating interval distance between the preceding concrete mixer truck 2 and the following concrete mixer truck 2), thus preventing consecutive operation.

[0044] Furthermore, by setting up geofences not only within the construction site but also at specific points such as near the concrete pump truck, the start time of concrete pouring by concrete mixer truck 2 can be accurately predicted. Typically, concrete pouring begins after concrete mixer truck 2 enters the area, such as 3 minutes after entering the geofence, and the end time is almost the same as the time it leaves the area.

[0045] Furthermore, if communication terminals 3 and 4 are equipped with a barometric pressure sensor and an angle sensor, the elevation difference between the geofence A, B, C, and D designated sections can be calculated, thereby allowing the elevation difference between the entire route traveled by the concrete mixer truck 2 and between each geofence A, B, C, and D designated point to be determined. [Industrial applicability]

[0046] This invention enables real-time monitoring and sharing of the operating status of construction vehicles used at construction sites, such as concrete mixer trucks traveling on roads not shown on maps (e.g., construction roads), dump trucks transporting excavated soil, or trucks carrying materials, among construction personnel. [Explanation of symbols]

[0047] 1 Host computer 2. Ready-mix concrete truck (construction vehicle) 3. Communication terminals 4. Communication terminals A, B, C, D Geofence a. Ready-mix concrete plant b construction site c intersection d Traffic congestion predicted locations

Claims

1. A construction vehicle operation management system comprising: a data management server for accumulating operation data of construction vehicles; a location information transmission application for transmitting location information of construction vehicles to the data management server; and an operation management web application for checking the operation data of construction vehicles accumulated on the data management server, wherein the location information transmission application is installed on a communication terminal carried by the driver of the construction vehicle, and the operation management web application is installed on a communication terminal carried by construction personnel, and a plurality of geofences using GNSS location information are set at intervals along the route on which the construction vehicle moves, and each time the construction vehicle passes through a geofence, the time of entry and exit of the geofence of the construction vehicle is transmitted to and stored on the data management server.

2. A construction vehicle operation management system according to claim 1, characterized in that a location information transmission application is installed on a communication terminal carried by a construction worker at a construction site to transmit the location information of the construction worker, a geofence using GNSS location information is set up on the route that the construction worker moves along within the construction site, and each time the construction worker enters or exits the geofence, the time of entry or exit of the geofence by the construction worker is captured on the communication terminal carried by the construction worker and transmitted to the data management server for storage.

3. A construction vehicle operation management system according to claim 2, characterized in that the communication terminals carried by the drivers of the construction vehicles and the construction personnel at the construction site are PCs, tablets, or smartphones.

4. A construction vehicle operation management system according to claim 1 or 2, characterized in that the operation data of the construction vehicle includes height or gradient within each geofence.

Citation Information

Patent Citations

  • Vehicle operation management system

    JP2008210087A

  • Vehicle operation management system

    JP2012221227A

  • Ready mixed concrete misdelivery prevention program and system

    JP2014233914A

  • Ready-mixed concrete delivery and pouring management system

    JP6709117B2