Construction management device and construction management program
The construction management device automates the assignment of construction processes by linking 3D model data with process items, addressing inefficiencies and errors in existing systems, facilitating efficient monitoring of construction progress.
Patent Information
- Application Number
- JP2022205548
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2022-12-22
- Publication Date
- 2026-11-19
- Estimated Expiration
- 2042-12-22
AI Technical Summary
Existing construction management systems require manual and time-consuming assignment of construction processes to components, leading to inefficiencies and potential input errors.
A construction management device and method that automates the assignment of construction processes by linking 3D model data with process items using a storage unit, quasi-process identification unit, and simulation unit, allowing for easy monitoring of construction progress.
Automates the assignment of construction processes, enabling efficient and error-free monitoring of construction progress through the use of 3D model data and process data linkage.
Smart Images

Figure 0007954059000001 
Figure 0007954059000002 
Figure 0007954059000003
Abstract
Description
Technical Field
[0001] The present invention relates to a construction management device, a construction management method, and a construction management program.
Background Art
[0002] In recent years, in the field of civil engineering public works such as bridges, tunnels, dams, earthworks, and rivers, when constructing various structures, business transformation through the shift from 2D drawings to 3D models, or front-loading that applies a load in the initial process (front stage) to conduct intensive examinations in advance to prevent rework that is likely to occur in subsequent processes, thereby enabling quality improvement and construction period reduction, has been promoted. For the purpose of accelerating consensus building, improving operational efficiency, enhancing quality, and ultimately improving productivity, the Ministry of Land, Infrastructure, Transport and Tourism has developed guidelines and is attempting systematic promotion to enable the smooth introduction of BIM / CIM (Building Information Modeling / Construction Information Modeling / Management). For this reason, various 3D model analysis programs and software for creating 3D CIM models have been developed.
[0003] Furthermore, unlike conventional methods in which a 2D drawing is created first, a 3D shape is assembled, and simulation is performed using CG, BIM / CIM models created by BIM / CIM have been developed, which allow designing in 3D from the beginning to generate a 3D model. Since a BIM / CIM model is an aggregate of 3D objects, it is possible to add attribute data such as cost, finishing, and management information to these objects, making it possible to utilize the information accumulated in the model throughout the entire life cycle of a building, from the design and construction of the building to its maintenance and management. Various 3D CAD software such as "ArchiCAD" and "Revit" are known as BIM / CIM tools capable of creating BIM / CIM models.
[0004] Furthermore, various project management software programs are known for managing the planning and implementation of projects, such as public works, to ensure that construction is completed within the set timeframe. In particular, project management software that employs Critical Chain Project Management (CCPM), developed from the perspective of overall optimization based on the concept of TOC (Theory of Constraints), has also been developed. Here, critical chain is a method that, in addition to the conventional method of critical path method which considers the dependency relationships in the work process when considering the execution order of each task in a project, also considers the dependency relationships that arise due to limited necessary resources. Project management is a practical method of project management that takes into account the human psychology and behavioral characteristics of personnel, as well as social and organizational problems, with the aim of shortening the construction period and adhering to deadlines. The safety margin removed from each task is aggregated and managed as a "buffer".
[0005] On the other hand, in construction work such as plant construction, construction progress management systems have been developed that allow for the confirmation of the progress of the work. For example, in the construction management device 10 described in Patent Document 1 below, in the process-model linking step S6 for simulation, process data is linked to a 3D design model of the building 30. In step S6, the worker repeatedly performs the task of selecting the design data of the part to which they want to link process items 33 from among the design data of multiple parts that make up the 3D design model, and assigning it to one or more process items 33 among the multiple process items that make up the process data, for all parts.
[0006] Furthermore, in the above-mentioned construction management device 10, process data and status are linked in the process / status linking step S5 for simulation purposes. In step S5, the worker repeatedly performs the following task for all process items: specifying a process item 33, setting the material status 33a during the process period of the specified process item 33, and then setting the material status 33b after the process period of the specified process item 33 has elapsed. [Prior art documents] [Patent Documents]
[0007] [Patent Document 1] Japanese Patent Publication No. 2021-21983 [Overview of the Initiative] [Problems that the invention aims to solve]
[0008] However, in the technology described in Patent Document 1, there were a considerable number of components at each construction site, and it was necessary to assign each process to one by one. Furthermore, since there were multiple processes for each component, a considerable number of assignment tasks had to be performed in total. As a result, the technology described in Patent Document 1 required a considerable amount of time and, due to the possibility of input errors, was a very inefficient process.
[0009] The present invention aims to provide a construction management device, a construction management method, and a construction management program that automate assignment tasks and allow for easy monitoring of construction progress. [Means for solving the problem]
[0010] To achieve the above objective, the present invention includes the following embodiments.
[0011] [1] A storage unit that stores three-dimensional model data that makes it possible to identify each part of a building and the members that make up each part, member master data to which standard process items that are standard process items performed on each member are associated, and process data that identifies the name of the process item, the member associated with the process item and the part made up of the member, and the order of each of a plurality of process items, and a mark that identifies the combination of each part of the three-dimensional model data, the members that make up the part and the standard process performed on the member by referring to the three-dimensional model data and the member master data A construction management device comprising: a quasi-process identification unit; a construction linking unit that links the 3D model data to the process items of the process data; and a simulation unit that displays the 3D model data linked to the process items on a screen in a state corresponding to the construction stage of the process items, wherein the construction linking unit links the member of the 3D model data to the process items of the process data in which the combination of the part, the member and the name of the process item matches the combination of the part, the member and the name of the standard process in the 3D model data identified by the standard process identification unit.
[0012] [2] The storage unit stores the 3D model data as a file for each component, with the strings of the name of the part and the name of the component in the file name, and the standard process identification unit extracts the strings of the name of the part and the name of the component from the file name to identify the component for each part of the 3D model data, as described in [1].
[0013] [3] The construction management device according to [1] or [2], wherein the storage unit stores process data in which each of the plurality of process items is associated with a string of the name of the part and the name of the member, and a string of an alias can be set for the member, and the construction linking unit links the member of the 3D model data to the process item using the string of the alias for the member for process items in which a string of an alias for the member is associated in the process data,
[0014] [4] The storage unit further stores standard process master data that associates each of the standard processes with a status corresponding to the construction stage of the standard process, and the construction linking unit links the status associated with the standard process in the standard process master data to the process item in the process data that has the same name as the standard process. The construction management device according to any one of [1] to [3].
[0015] [5] A storage step that stores three-dimensional model data that makes it possible to identify each part of a building and the members that make up each part, member master data to which standard processes, which are standard process items performed on each member, are associated, and process data that identifies the name of the process item, the member associated with the process item, and the part made up of the member, and the order of each of a plurality of process items; and a standard process identification step that identifies the combination of each part of the three-dimensional model data, the members that make up the part, and the standard process performed on the member by referring to the three-dimensional model data and the member master data. A construction management method comprising: a step; a construction linking step that links the 3D model data to the process items of the process data; and a simulation step that displays the 3D model data linked to the process items on a screen in a state corresponding to the construction stage of the process items, wherein the construction linking step links the member of the 3D model data to the process item among the process items of the process data, where the combination of the part, the member and the name of the process item matches the combination of the part, the member and the name of the standard process in the 3D model data identified in the standard process identification step.
[0016] [6] A computer has a storage unit that stores three-dimensional model data that makes it possible to identify each part of a building and the members that make up each part, member master data to which standard process items that are standard process items performed on each member are associated, and process data that identifies the order of each of a plurality of process items, including the name of the process item, the member associated with the process item, and the part made up of the member, and by referring to the three-dimensional model data and the member master data, a unit that identifies the combination of each part of the three-dimensional model data, the members that make up the part, and the standard process performed on the member. A construction management program comprising: a standard process identification unit; a construction linking unit that links the 3D model data to the process items of the process data; and a simulation unit that displays the 3D model data linked to the process items on a screen in a state corresponding to the construction stage of the process items, wherein the construction linking unit links the member of the 3D model data to the process items in the process data whose combination of the part, the member and the name of the process item matches the combination of the part, the member and the name of the standard process in the 3D model data identified by the standard process identification unit. [Effects of the Invention]
[0017] According to the present invention, it is possible to provide a construction management device, a construction management method, and a construction management program that automate assignment tasks and allow for easy confirmation of the progress of construction work. [Brief explanation of the drawing]
[0018] [Figure 1] This is a functional block diagram of an example of a construction management device according to an embodiment. [Figure 2] This figure shows an example of a 3D model of a building included in the 3D model data according to the embodiment. [Figure 3] This figure shows an example of component master data according to the embodiment. [Figure 4] This figure shows an example of standard process master data for an embodiment. [Figure 5] It is a diagram showing an example of display settings for each status according to the embodiment. [Figure 6] It is a diagram showing an example of process data according to the embodiment. [Figure 7] It is a flowchart of an operation example of the construction management device according to the embodiment. [Figure 8] It is an explanatory diagram of automatic status setting processing during and after a period by the construction association unit according to the embodiment. DETAILED DESCRIPTION OF EMBODIMENTS
[0019] Hereinafter, modes for carrying out the present invention (hereinafter referred to as embodiments) will be described with reference to the drawings.
[0020] Figure 1 shows a functional block diagram of an example of the construction management device 100 according to the embodiment. The construction management device 100 includes a storage unit 10, a standard process identification unit 12, a construction association unit 14, a simulation unit 16, a display unit 18, an editing unit 19, and a CPU 20, and is configured as a computer that controls the entire device and performs various calculations. The CPU 20 may include an accelerator such as a GPU in addition to the CPU.
[0021] The CPU 20 functions as the standard process identification unit 12, the construction association unit 14, the simulation unit 16, the editing unit 19, and the like. Each of the above functions is realized by, for example, the CPU 20 and a program that controls the processing operations of the CPU 20.
[0022] Furthermore, the storage unit 10 is composed of non-volatile memory such as a hard disk drive or solid-state drive (SSD), and stores the above-mentioned data and information necessary for each process performed by the construction management device 100, such as programs for operating the CPU 20. The storage unit 10 may also use a digital versatile disk (DVD), compact disk (CD), magneto-optical disk (MO), flexible disk (FD), magnetic tape, electrically erasable and rewritable read-only memory (EEPROM), flash memory, etc. Preferably, the storage unit 10 includes random access memory (RAM) which primarily functions as a workspace for the CPU 20, and read-only memory (ROM) which stores control programs such as the BIOS and other data used by the CPU 20. The storage unit 10 may also include external storage devices.
[0023] The storage unit 10 stores three-dimensional model data that allows for the identification of the shape and arrangement of each part of a building and all the components that make up each part, component master data that associates standard processes performed on each component, and process data that identifies the names of process items and the order of each of multiple process items, including the components associated with the process items and the parts that make up those components. Furthermore, the storage unit 10 may also store standard process master data.
[0024] Here, 3D model data refers to data relating to the 3D model of a building that is the subject (also called the managed object) of construction work. It includes the names of each part and component that make up the building, the 3D model data for each component, and the placement information of each component. In other words, the 3D model data includes a collection of 3D model data for each component. This 3D model data is created in advance using CAD software and stored in the storage unit 10 as a group of files for each part or component. The file containing the 3D model data for each component includes a string or identification code of the name of each part and component as the file name. This allows for the identification of parts and components by extracting strings from the file name.
[0025] Component master data is information that associates standard processes to be performed for each component of a building. It is created in advance using spreadsheet software or the like and stored in the storage unit 10 as a file containing the standard processes for each component. A standard process is a set of process items that are pre-defined as standard construction processes from among the process items performed for each component, and one or more standard processes are performed (associated) for a single component. For example, for a component called a "column," it would consist of "rebar work," "formwork work," "concrete pouring work," "curing work," "deformation," etc. Thus, component master data may include the association of multiple standard processes for a single component. Alternatively, it may include a standard process common to the construction of different components. Therefore, component master data may include the association of a common standard process for multiple components. As a concrete example, the beginning of the component name may be a common name (for example, Column 1st stage, Column 2nd stage, etc.), in which case the common standard process "Column" may be applied. Standard process information includes, for example, component names (names of components) and standard process names (names of standard processes).
[0026] Process data is information that identifies the sequence of multiple process items to be carried out for a managed building. Process items are items of work carried out to construct the building, and the process data consists of combinations of process items carried out for each component that makes up a part of the building. In addition to the sequence of process items, the process data also includes the name of the process item, information on the part to which the process item applies, and information on the components that make up the part. This process data also includes information on the planned start date and planned end date to identify the sequence of work for each process item. During the construction period or after completion, information on the actual start date and actual end date may also be included. Furthermore, the planned start date and planned end date may change during the construction period. In that case, the original plan may be kept separately as the initial start date and initial end date, and the planned start date and planned end date may be updated as needed. The process data is created in advance using process management software and stored in the storage unit 10, for example, as a file for each component.
[0027] Standard process master data is information that associates multiple standard processes with statuses defined as information representing their construction stages. This data is created in advance using spreadsheet software or the like and stored in the storage unit 10. The status represents the construction state of the components during, after, and initially (before construction) of the standard process. When the simulation unit 16 simulates and displays the 3D model, the display color of each component is set according to its status, and the status of each component at that date and time can be confirmed by the color display. The standard process master data is created, for example, as a CSV file listing status information for each standard process, and includes information such as the standard process name (name of the standard process), status during the period (status during construction), status after the period (status after construction), and initial model status (status before construction).
[0028] The standard process identification unit 12 identifies combinations of parts of the 3D model data, the members constituting those parts, and the standard processes performed on those members by referring to the 3D model data and member master data. Specifically, the standard process identification unit 12 reads the 3D model data and member master data of the building to be managed from the storage unit 10, searches the member master data using the name of the member included in the file name of the read 3D model data as a key, and identifies the standard processes performed on each member, thereby identifying combinations of names of parts of the 3D model data, the members constituting those parts, and the one or more standard processes performed on those members. The standard process identification unit 12 writes each identified combination of names to the storage unit 10 for storage.
[0029] The construction linking unit 14 links the 3D model data to the process items in the process data. Specifically, the construction linking unit 14 reads and references the process data from the storage unit 10, and links the process items in the process data that match the combination of part, member, and process item name with the combination of part, member, and one or more standard process names identified by the standard process identification unit 12 in the 3D model data to the member in the 3D model data. The construction linking unit 14 writes the information of the linked process items and members in the 3D model data to the storage unit 10 for storage. Furthermore, the construction linking unit 14 also performs the process of linking the statuses defined in the standard process master data—period, after period, and initial (before construction)—to each of the process items in the process data as information representing the progress of the construction. This process is performed by linking the status associated with the standard process in the standard process master data to the process items in the process data that have the same name as the standard process.
[0030] The simulation unit 16 displays each component included in the 3D model data linked to the process item on the screen in a state corresponding to the construction stage of the process item, according to the process data. Specifically, the simulation unit 16 reads the linked process data and 3D model data information from the storage unit 10, prompts the user to specify a date and time, compares that date and time with the planned start date and planned end date of each process item to determine the progress of the construction at that date and time (i.e., whether each process item is within or after the period), and displays each component of the 3D model data corresponding to the planned progress of the construction at that date and time on the display unit 18 screen in a color corresponding to the specified status.
[0031] The display unit 18 is composed of a liquid crystal display device or other appropriate display device and its control device, and displays a 3D model and status, etc., according to the progress of the construction work at the specified date and time, based on the instructions of the simulation unit 16.
[0032] The editorial unit 19 adds or modifies information stored in the memory unit 10. Examples include editing the content of the 3D model data described later, or editing process data such as adding the actual start date and actual end date, or changing the planned start date and planned end date.
[0033] Figure 2 shows an example of a 3D model of a building included in 3D model data. In the example in Figure 2, a building is depicted in which a rectangular structure 28 is placed on a framework 26 composed of piles 22 and beams 24, and the whole constitutes a single part. This part consists of the framework 26 composed of piles 22 and beams 24 and the rectangular structure 28. The 3D model data includes 3D model data of the parts and members that make up the building, as well as placement information of each member, and the names of the parts and the members that make up each part.
[0034] Figure 3 shows an example of member master data. In the example in Figure 3, the member master data includes the member name and standard process names 1 to 4. For example, since pile 22 is constructed as a cast-in-place pile, "Cast-in-place pile construction" is associated with the member name "Cast-in-place pile" as standard process 1. The number of standard process names can be set arbitrarily; for example, 10 standard process names (standard process names 1 to 10) can be set. In Figure 3, the member master data is created as a CSV file in which the standard process names are listed for each member for multiple members.
[0035] Figure 4 shows an example of standard process master data. In the example in Figure 4, the standard process master data includes the items of standard process name, status during the period, status after the period, and initial model (pre-construction) status. For example, for the standard process 1 "cast-in-place pile work" of member name "cast-in-place pile" associated with pile 22 which is constructed as a cast-in-place pile, the "status during the period" is "pile driving work", the "status after the period" is "completed", and the "initial model status" is "not started". "Status during the period" is a display setting that the simulation unit 16 uses to indicate in the simulation that the process item of the target member is within the construction period, "status after the period" is a display setting that the simulation unit 16 uses to indicate in the simulation that the process item of the target member is after the construction period (after construction is completed), and "initial model status" is a display setting that the simulation unit 16 uses to indicate in the simulation that the process item of the target member is in the state before the construction period.
[0036] Figure 5 shows examples of display settings for each status. Display settings include the display / hide distinction and display color set for each standard process of each component so that each component of the 3D model can be displayed by the simulation unit 16. For example, for the component name "cast-in-place pile," the standard process is "cast-in-place pile work," and the "period status" of "pile driving work" is associated with the "display" of the component in that status and the display color "orange." For the "post-period status" of "completed," the "display" of the component in that status and the display color "gray" are associated. In that case, when the process item "cast-in-place pile work" is determined to be within the construction period, the simulation unit 16 draws the 3D model of the pile 22 as the component "cast-in-place pile" corresponding to the process item "cast-in-place pile work" in "orange" and displays a figure with "pile driving work" as the attribute information of the status. Similarly, when the relevant process item "cast-in-place pile construction" is determined to be after the construction period, the simulation unit 16 draws a 3D model of the pile 22 as a "cast-in-place pile" in "gray" and displays a figure with the status attribute information "completed". Also, since "not started" is associated with the "initial model status" of "cast-in-place pile construction", when the relevant process item "cast-in-place pile construction" is determined to be before the construction period, the simulation unit 16 displays a figure in which, for example, the 3D model of the pile 22 as a "cast-in-place pile" is "hidden".
[0037] Figure 6 shows an example of process data. In the example in Figure 6, the process data includes name, planned start date, planned end date, actual start date, actual end date, status during the period, status after the period, block name, component name, and process item name.
[0038] The name field contains the name of each process item. The process items have a hierarchical structure and include both actual process items and classification process items that represent groups of actual process items. To represent this, in the example in Figure 6, each process item is associated with its position within the hierarchy (the position determines the order and depth) and a flag F (referred to as the task type) that identifies whether or not it is an actual process item. The actual process items are identified by their part name (block name in Figure 6) so that the construction target can be identified. Therefore, the part name can be identified for each actual process item in the process data.
[0039] Furthermore, in the process data, in order to enable automatic assignment, information that identifies the components constituting a part (component name) is associated with each actual process item, along with the name of the process item performed on that part. Process items are identified by the name of the process item.
[0040] Furthermore, the planning start date is the start of construction at the planning stage for each process item, and the planning end date is its end. The actual start date is the start of the actual construction period for each process item, and the actual end date is its end. The actual start date and actual end date are entered during or after construction.
[0041] Furthermore, the process data includes "status during the period" and "status after the period" linked from the standard process master data, which correspond to the construction stage of each process item, indicating how each component is displayed when the simulation unit 16 simulates and displays the 3D model of each component.
[0042] Figure 7 shows a flowchart illustrating an example of the operation of the construction management device 100 according to the embodiment. In Figure 7, as described above, standard process master data created in advance using spreadsheet software or the like is stored in the storage unit 10, and the construction management device 100 acquires this data (S1). In this case, the data is stored in the storage unit 10 using the functions of the spreadsheet software or the like.
[0043] Next, component master data, which has been created in advance using spreadsheet software or the like, is stored in the storage unit 10, and the construction management device 100 acquires this data (S2). In this case, the data is stored in the storage unit 10 using the functions of the spreadsheet software or the like.
[0044] Next, process data created in advance using process management software is stored in the storage unit 10, and the construction management device 100 acquires this data (S3). In this case, the process management software's functions cause the data to be stored in the storage unit 10.
[0045] The construction linking unit 14 reads the process data and standard process master data from the storage unit 10, searches for the status in the standard process master data using the name of the process item in the process data as a key, and links the status corresponding to that standard process in the standard process master data to the process item in the process data that has the same name as the standard process in the standard process master data (S4). This allows the status during and after the period to be automatically set for each process item. The set status is written to and stored in the process data stored in the storage unit 10.
[0046] Figure 8 shows an explanatory diagram of the automatic setting process for the status during and after the construction period by the construction linking unit 14. In Figure 8, the process of searching the standard process master data using the name of the process item in the process data as a key is indicated by the word "key". In the example in Figure 8, the standard process names "rebar worker", "formwork worker", and "demolition" are used as keys. Based on these keys, "rebar worker / pressure welding" is set as the status during the period and "formwork worker" is set as the status after the period in the standard process master data for the corresponding process item in the process data. Also in the example in Figure 8, "formwork worker" is set as the status during the period and "concrete pouring" is set as the status after the period in the standard process master data for the corresponding process item in the process
[0047] Next, 3D model data created in advance using CAD software is stored in the storage unit 10, and the construction management device 100 acquires the data (S5). In this case, the CAD software's functions are used to store the data in the storage unit 10.
[0048] The standard process identification unit 12 reads the 3D model data from the storage unit 10, extracts the names of parts and components from the file name of the 3D model data, and identifies the component names of the 3D model for each part (S6).
[0049] Next, the standard process identification unit 12 reads the member master data from the storage unit 10 and, using the member name of the 3D model identified in S6 as a key, searches the member master data shown in Figure 3, for example, to identify the standard process to be performed on the member of the 3D model (S7). This identifies the combination of the part of the 3D model included in the 3D model data, the member constituting that part, and the standard process performed on each of those members.
[0050] Furthermore, the user can set an alias for the member name of the 3D model by editing the contents of the 3D model data using the editing unit 19 as needed, and store the alias in the storage unit 10 in association with the corresponding member of the 3D model data (S8). Here, "as needed" refers to cases such as when there is a discrepancy between the member name in the 3D model data and the name in the process data.
[0051] The process of setting an alias for a component name is performed, for example, as follows: When the user specifies the editing start command for the editing unit 19, the editing unit 19 reads the 3D model data from the storage unit 10 and displays the "block name," "component name 1," and "component name 2" for each 3D model written in the 3D model data on the display unit 18, and also accepts input for "component name 2," which is the alias setting field. The user enters an alias in the "component name 2" field, and the editing unit 19 writes that alias to the 3D model data. When the user finishes inputting and specifies the editing end command for the editing unit 19, the editing unit 19 transfers the "component name 1" of 3D models for which an alias was not set in the 3D model data to "component name 2." From then on, the string in the "component name 2" field is used as the component name.
[0052] Next, the construction linking unit 14 reads from the storage unit 10 the combination of each part of the 3D model data identified by the standard process identification unit 12, the members constituting that part, and the name of the standard process performed on that member, along with the standard process master data. Using the name of the standard process associated with each 3D model included in the 3D model data as a key, it searches the standard process master data, identifies the initial status of the standard process whose name matches the key in the standard process master data, and writes the identified initial status to the 3D model data as the initial status of the corresponding 3D model (S9). Note that the processing in S9 may be performed by identifying the initial status in step S4, similar to the status during and after the period, and writing it to the process data.
[0053] The construction linking unit 14 reads and references process data from the storage unit 10, and if the combination of part, material and name of process item among the process items in the process data matches the combination of part, material and name of standard process in the 3D model data identified by the standard process identification unit 12, it links the material from the 3D model data to each of the process items (S10). In this case, the construction linking unit 14 uses the combination of "block name (part name)", "member name 1 (if no alias is set) or member name 2 (if an alias is set)", and "standard process name" that constitute the name of the part in the 3D model data as a key to search for "block name (part name)", "member name", and "process item name" in the process data. In the process data, if the "block names (part names)" are an exact match and an alias is set, then "member name 2" in the 3D model data matches the "member name" in the process data by prefix (allowing the process data string to be longer). If no alias is set, then "member name 1" in the 3D model data matches the "member name" in the process data by prefix (allowing the process data string to be longer), and the "standard process name" in the 3D model data matches the "process item name" in the process data by prefix (allowing the process data string to be longer). The construction linking unit 14 links each component of the 3D model data to the process data by writing the correspondence between the identified process data record and the keyed 3D model data record to the storage unit 10.
[0054] Next, in S10, the user uses the editing unit 19 to link all the components of the 3D model data to the process data, for example, by adding or editing "Component Name 2" or changing the component name in the process data for each component of the 3D model data that was not subject to linking (automatic assignment) to the process data (S11).
[0055] Furthermore, after construction has commenced or completed, users can use the editorial department 19 to record the actual start and end dates for each process item in accordance with the progress of the construction. Alternatively, if the planned start date or planned end date changes, the initially set planned start date or planned end date may be changed. In that case, the initially set planned start date or planned end date may be used as the original start date and original end date.
[0056] Next, the simulation unit 16 prompts the user to specify a date and time, compares that date and time with the planned start and end dates of each process item, and determines the progress of the construction at that date and time (i.e., whether each process item is within the planned period or after it has ended). Based on the above, a 3D model and status, etc., corresponding to the progress of the planned construction at that date and time are displayed on the screen (S12).
[0057] The program for performing each step in Figure 7 described above can be stored on a recording medium, or it may be provided by means of communication. In that case, for example, the program described above may be considered as an invention of a "computer-readable recording medium on which a program is recorded" or an invention of a "data signal".
[0058] In the embodiments described above, an example was shown in which information about the members of the 3D model data can be identified by the file name of the 3D model data. However, it may also be possible to identify them by data within the file, such as the file header, or by a list file that describes the correspondence between the file name of the 3D model and the member.
[0059] In Figure 7 above, step S8, "Setting an alias for the member name of the 3D model data," an example was shown where "Member Name 2" is set in the 3D model data using the editing function of the editorial department 19. However, "Member Name 2" can also be set by using a file. Doing so may streamline the setting process by allowing the use of editing functions of spreadsheet software, etc.
[0060] In other words, the user uses a predetermined command of the editorial unit 19 to output the "block name (part name)", "part name 1", "part name 2", and "standard process name 1" to "standard process name 10", which are associated with each 3D model and written to the storage unit 10 by the processing of S6 and S7, as a CSV file. The user edits the CSV file using spreadsheet software or the like and writes "part name 2", which is a different alias from "part name 1" and can be linked to the part name in the process item data, to the row of "part" of the 3D model for which an alias is to be set. The user also transfers "part name 1" of 3D models for which an alias was not set to "part name 2". After that, the user specifies the CSV file using a predetermined command of the editorial unit 19 and writes the data represented by the CSV file back to the storage unit 10.
[0061] In the example shown in Figure 7 above, in step S8, "Setting an alias for the member name of the 3D model data," "Member Name 1," which does not require an alias setting, is transferred to "Member Name 2," and in step S10, "Linking the 3D model to the process data," the linking is performed using "Member Name 2" as the key. However, the transfer may be omitted. In that case, in step S10, "Linking the 3D model to the process data," for 3D models where "Member Name 2" is not empty, the linking is performed using "Member Name 2" as the key, and for 3D models where "Member Name 2" is empty, the linking is performed using "Member Name 1" as the key.
[0062] While an example of representing a part using "block name" has been shown, a part can also be represented by combining two items: "block name" and "construction phase." Construction phase refers to information that identifies construction phases, such as "Phase 1 construction" and "Phase 2 construction," when construction is divided into phases. In this case, the process data will have the item "construction phase" added, the 3D model data will have a string representing "construction phase" added to the file name, etc., and the construction linking unit 14 will use a combination of "block name" and "construction phase" as the part name for searching and assigning. [Explanation of Symbols]
[0063] 10 Memory unit, 12 Standard process identification unit, 14 Construction linking unit, 16 Simulation unit, 18 Display unit, 19 Editing unit, 20 CPU, 22 Piles, 24 Beams, 26 Frame, 28 Rectangular structure, 100 Construction management device.
Claims
1. A storage unit that stores three-dimensional model data that makes it possible to identify each part of a building and the members that make up each part, member master data to which standard process items, which are standard process items performed on each member, are associated, and process data that identifies the name of the process item, the member associated with the process item, and the part made up of the member, and the order of each of the multiple process items, A standard process identification unit that identifies combinations of each part of the 3D model data, the member constituting the part, and the standard process performed on the member by referring to the 3D model data and the member master data, A construction linking unit that links the three-dimensional model data to the process items of the process data, A simulation unit that displays the three-dimensional model data linked to the process item on a screen in a state corresponding to the construction stage of the process item, according to the process data. Equipped with, The construction linking unit links the member of the 3D model data to the process item in the process data where the combination of the part, the member, and the name of the process item matches the combination of the part, the member, and the name of the standard process in the 3D model data identified by the standard process identification unit. Construction management device.
2. The storage unit stores the 3D model data as a file for each component, with the string of the name of the part and the name of the component included in the file name. The standard process identification unit extracts the strings of the part name and the member name from the file name to identify the member for each part of the 3D model data. The construction management device according to claim 1.
3. The storage unit stores the process data in which each of the plurality of process items is associated with a string of the name of the part and the name of the component, and a string of an alias can be set for the component. The construction linking unit, for process items to which the string of the alias of the member is associated in the process data, uses the string of the alias of the member to link the member in the 3D model data to the process item. A construction management device according to claim 1 or claim 2.
4. The memory unit further stores standard process master data that associates each of the standard processes with a status corresponding to the construction stage of the said standard process. The construction linking unit links the status associated with the standard process in the standard process master data to the process item in the process data that has the same name as the standard process. A construction management device according to claim 1 or claim 2.
5. Computers, A storage unit that stores three-dimensional model data that makes it possible to identify each part of a building and the members that make up each part, member master data to which standard process items, which are standard process items performed on each member, are associated, and process data that identifies the name of the process item, the member associated with the process item, and the part made up of the member, and the order of each of the multiple process items. A standard process identification unit that identifies combinations of each part of the 3D model data, the member constituting the part, and the standard process performed on the member by referring to the 3D model data and the member master data. A construction linking unit that links the three-dimensional model data to the process items of the process data. A simulation unit that displays the three-dimensional model data linked to the process item on the screen in a state corresponding to the construction stage of the process item, according to the process data. To make it function as, The construction linking unit links the member of the 3D model data to the process item in the process data where the combination of the part, the member, and the name of the process item matches the combination of the part, the member, and the name of the standard process in the 3D model data identified by the standard process identification unit. Construction management program.
Citation Information
Patent Citations
Management method, management system, management device, computer program and recording medium