Continuous construction method for removing existing piles and installing new piles
The continuous construction method using bentonite water and cement grout for pile removal and installation addresses the extended construction period issue by allowing simultaneous operations, reducing noise and vibration, and ensuring pile verticality and stability.
Patent Information
- Application Number
- JP2023055845
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2023-03-30
- Publication Date
- 2026-11-19
- Estimated Expiration
- 2043-03-30
AI Technical Summary
Existing methods for removing foundation piles and constructing new piles require a lengthy wait for cement milk or fluidized treated soil to solidify, extending the construction period if immediate construction of a new building is desired.
A continuous construction method involving the use of bentonite water to fill extraction holes during pile removal, followed by drilling with a second casing to form an excavation hole, primary and secondary filling with cement grout, and inserting new piles into the excavation hole.
This method allows for a shortened construction period by enabling simultaneous pile removal and new pile installation, reducing noise and vibration, and ensuring the verticality and stability of the new piles.
Smart Images

Figure 0007954113000001 
Figure 0007954113000002 
Figure 0007954113000003
Abstract
Description
Technical Field
[0001] The present invention relates to a continuous construction method for removing existing piles and constructing new piles.
Background Art
[0002] When a building is to be demolished, existing foundation piles (hereinafter referred to as existing piles) are also removed. The removal of existing foundation piles is broadly divided into a separation and pulling-out method and a crushing and removal method, and the separation and pulling-out method can reduce noise and vibration. The following Patent Documents 1 and 2 disclose separation and pulling-out methods for existing piles. The hole remaining at the trace where the existing pile has been removed is backfilled with a backfill material such as low-proportion cement milk or fluidized treated soil so as to restore the original ground as much as possible. It usually takes about one month for low-proportion cement milk or fluidized treated soil to solidify and develop the expected strength.
Prior Art Documents
Patent Documents
[0003]
Patent Document 1
Patent Document 2
Summary of the Invention
Problems to be Solved by the Invention
[0004] There is no problem if construction of the next building is not carried out after the building is demolished, but if it is desired to construct the next building immediately, the construction period will be extended because it is necessary to wait for the low-proportion cement milk or fluidized treated soil to solidify. An object of the present invention is to provide a continuous construction method for removing existing piles and constructing new piles, which is capable of shortening the construction period when constructing new piles after removing existing piles.
Means for Solving the Problems
[0005] In the continuous method for removing existing piles and constructing new piles according to the present invention, the ground is drilled with a first casing to isolate the existing pile, the first casing is withdrawn, and while the existing pile is being withdrawn, bentonite water, a mixture of bentonite and water, is supplied into the extraction hole formed by the withdrawal of the existing pile to fill the extraction hole with the bentonite water, the ground is drilled with a second casing for the construction of the new pile so as to partially overlap with the extraction hole, the inside of the second casing embedded in the ground is excavated to form an excavation hole, cement grout is primaryly filled from the bottom to the top of the excavation hole, the second casing which is placed in the excavation hole is withdrawn, cement grout is secondaryly filled from the bottom to the top of the extraction hole which partially overlaps with the excavation hole to allow the remaining bentonite water to overflow, and the new pile is inserted into the excavation hole filled with cement grout and constructed. [Effects of the Invention]
[0006] According to the present invention, the construction period can be shortened when installing new piles after removing existing piles. [Brief explanation of the drawing]
[0007] [Figure 1] This is a cross-sectional view showing the first step in the continuous construction method for removing existing piles and installing new piles according to the embodiment. [Figure 2] This is a cross-sectional view showing the second step in the above construction method. [Figure 3] This is a cross-sectional view showing the third step in the above construction method. [Figure 4] This is a cross-sectional view showing the fourth step in the above construction method. [Figure 5] This is a plan view showing the fifth step in the above construction method. [Figure 6] This is a cross-sectional view showing the fifth step in the above construction method. [Figure 7] This is a cross-sectional view showing the sixth step in the above construction method. [Figure 8] This is a cross-sectional view showing the seventh step in the above construction method. [Figure 9] This is a cross-sectional view showing the eighth step in the above construction method. [Figure 10] This is a cross-sectional view showing the ninth step in the above construction method. [Figure 11] This is a cross-sectional view showing the tenth step in the above construction method. [Modes for carrying out the invention]
[0008] The continuous construction method for removing existing piles and installing new piles according to the embodiment will be explained with reference to Figures 1 to 11. Note that Figures 1 to 11 are schematic, and the aspect ratios of the piles and holes shown are not realistic.
[0009] In the continuous construction method of this embodiment, the existing foundation piles, i.e., existing piles P1, are removed prior to the construction of the new foundation piles, i.e., the new piles P2. The new piles P2 in this embodiment are not cast-in-place concrete piles, but rather pre-fabricated piles. The existing piles P1 may be either pre-fabricated piles or cast-in-place concrete piles. The removal of the existing piles P1 is performed using the edge-cutting extraction method. First, in order to reduce friction with the ground 1 when the existing piles P1 are extracted, as shown in Figure 1, the ground 1 is drilled with the first casing 2, which is a round steel pipe, so that the first casing 2 is positioned around the existing piles P1, thereby performing what is called "edge-cutting". The first casing 2 drills into the ground 1 from the surface while rotating. At this time, a jet of water is sprayed from the tip of the first casing 2 to soften the ground 1. Instead of water, bentonite water may be used as a hole wall protective liquid. Bentonite water is a mixture of bentonite and water, and is also called bentonite solution or bentonite liquid. It does not contain solidifying components such as cement.
[0010] Figure 1 shows the state in which the first casing 2 has been embedded, and the process up to this point is a conventional procedure. Between the existing pile P1 and the first casing 2, muddy water, a mixture of injected jet water or bentonite water and the drilled ground 1, has accumulated. Next, as shown in Figure 2, the first casing 2 is pulled out from the ground 1. As a result, the existing pile P1 remains inside the extraction hole 5 drilled by the first casing 2, and muddy water remains around the existing pile P1.
[0011] Next, as shown in Figure 3, a wire rope 3 is wrapped around the top of the existing pile P1, and the existing pile P1 is removed by a so-called "ring toss" extraction method, which involves pulling the existing pile P1 upwards. While the removal of existing piles P1 by "ring toss" extraction is a conventional method, in this embodiment, bentonite water 4 is supplied to the interior from the top of the first casing 2 while the existing pile P1 is being pulled out. The supplied bentonite water 4 fills the extraction hole 5 formed in the area where the existing pile P1 has been pulled out. Note that Figure 3 shows the existing pile P1 partially pulled out, but once the existing pile P1 is completely pulled out, the bentonite water 4 fills the interior of the first casing 2 to the top, as shown in Figure 4. Bentonite water 4 has conventionally been used to protect borehole walls, forming an impermeable film on the inner surface of the borehole wall to prevent collapse of the borehole wall.
[0012] Normally, the extraction hole 5 would be backfilled with lean cement grout or fluidized soil to restore the original ground. However, in this embodiment, the construction of the new pile P2 has already been decided, and after the removal of the existing pile P1, the process immediately moves on to the construction of the new pile P2. First, the ground 1 is drilled by the second casing 6 to match the location where the new pile P2 will be installed. In this embodiment, the position of the new pile P2 is offset from the existing pile P1. Therefore, as shown in the plan view of Figure 5, the extraction hole 5 formed by the extraction of the existing pile P1 and filled with bentonite water 4 and the excavation hole 7 for the new pile P2, which will be formed inside the second casing 6, partially overlap.
[0013] In Figure 5, the solid line indicates the positional relationship between the extraction hole 5 and the second casing 6 (excavation hole 7) in the present embodiment. The positional relationship indicated by the dotted line in Figure 5 will be described later. In the plan view shown in Figure 5, O1 is the center of the extraction hole 5, O2 is the center of the excavation hole 7, and the two Qs are the intersection points between the inner periphery of the extraction hole 5 and the outer periphery of the second casing 6. In other words, the two Qs are the intersection points between the inner periphery of the extraction hole 5 and the inner periphery of the excavation hole 7 formed by the second casing 6. The hole formed by drilling with the first casing 2 and extracting the first casing 2 and the existing pile P1 is the extraction hole 5. Similarly, the hole formed by drilling with the second casing 6, excavating the inside thereof (described later), and removing the second casing 6 is the excavation hole 7.
[0014] In the plan view shown in Figure 5, of the entire circumference of the excavation hole 7, the arc portion overlapping with the extraction hole 5 is defined as an overlapping arc C. That is, the portion between the two intersection points Q is the overlapping arc C. In the present embodiment, the ground 1 is drilled by the second casing 6 such that the centers O1 and O2 are located on opposite sides of the straight line passing through the two intersection points Q. When drilling with the second casing 6, the drilling resistance of the ground 1 does not act on the portion of the overlapping arc C, and the drilling resistance is biased along the circumferential direction of the second casing 6. For this reason, it is necessary to pay attention to the verticality of the drilled hole when drilling with the second casing 6. Usually, a drilled (excavated) hole tends to incline toward the side with lower excavation resistance.
[0015] If the ratio of overlapping arcs C to the entire circumference of the second casing 6, i.e., the borehole 7, becomes large, the bias in circumferential drilling resistance increases, and the verticality of the drilled borehole 7 deteriorates. For this reason, the size (diameter) of the second casing 6 is set so that the ratio of overlapping arcs C to the entire circumference of the borehole 7 is 1 / 2 or less, preferably 1 / 3 or less. The position of the center O2 of the second casing 6 (borehole 7) coincides with the center of the newly installed pile P2. If the ratio of overlapping arcs C exceeds 1 / 2, as described above, the verticality of the borehole 7, and consequently the verticality of the newly installed pile P2 constructed within the borehole 7, deteriorates. In particular, to achieve accurate verticality, it is preferable that the ratio of overlapping arcs C be 1 / 3 or less in order to further reduce the bias in circumferential drilling resistance. The verticality of a foundation pile is extremely important, and it is important to drill with the second casing 6 in such a way that the ratio of overlapping arcs C is satisfied.
[0016] As described above, in this embodiment, drilling by the second casing 6 is performed such that the proportion of overlapping arcs C is 1 / 2 or less, under the condition that the centers O1 and O2 are located on opposite sides of the straight line passing through the two intersections Q. However, as shown by the dotted line in Figure 5, even under the condition that the centers O1 and [O2] are located on the same side of the straight line passing through the two intersections [Q], it may be possible to make the proportion of overlapping arcs C 1 / 2 (preferably 1 / 3) or less. In this case, the drilled hole [7] relative to the extraction hole 5 is shown by the dotted line in Figure 5, and the center [O2] of the drilled hole [7] and the two intersections [Q] with the extraction hole 5 are also shown. Thus, even when the drilled hole [7] is formed so as to overlap most of the extraction hole 5, the proportion of overlapping arcs C can be made 1 / 2 (preferably 1 / 3) or less. As a result, even if there is a large overlap between the extraction hole 5 and the excavated hole [7], the verticality of the excavated hole [7] can be ensured by securing a sufficient drilling length in the ground 1 by the second casing 6 and suppressing the unevenness of the circumferential drilling resistance.
[0017] As shown in Figure 4, the ground 1 is drilled by the second casing 6 so as to partially overlap with the extraction hole 5 filled with bentonite water 4 as shown in Figure 5. Figure 6 shows a state where the drilling by the second casing 6 is completed. At this time, jet water is jetted from the tip of the second casing 6 to soften the ground 1. Bentonite water may be jetted instead of water, but the hole wall of the extraction hole 5 is already protected by bentonite water 4, and the drilled hole 7 formed by the second casing 6 is filled with cement milk 9 before the second casing 6 is removed, so the significance of using bentonite water is low.
[0018] The second casing 6 cuts the hole wall of the extraction hole 5, but since the hole wall of the extraction hole 5 is protected by the bentonite water filled inside, it will not collapse due to the drilling by the second casing 6. In addition, the extraction hole 5 remains filled with bentonite water 4, and the head pressure of the bentonite water also acts on the hole wall of the extraction hole 5, so that collapse is further suppressed. The cut portion of the hole wall of the extraction hole 5 by the second casing 6 is also protected by the bentonite water 4 in the extraction hole 5. In the present embodiment, the second casing 6 drills deeper than the bottom of the extraction hole 5. The advantages of this will be described later. Note that there is no problem even if part of the bentonite water 4 in the extraction hole 5 seeps into the drilled portion formed by the second casing 6.
[0019] Next, as shown in Figure 7, the inside of the buried second casing 6 is excavated by the screw auger 8, forming a borehole 7. In the state shown in Figure 7, the second casing 6 is still inside the borehole 7. This borehole 7 is the hole for the new pile P2. When the borehole 7 is excavated by the screw auger 8, the bentonite water that filled the overlapping area with the excavated ground 1 and the withdrawal hole 5 is removed from the top of the borehole 7. In the state shown in Figure 7, the lower end head of the screw auger 8 is located at the bottom of the formed borehole 7. From this state, the screw auger 8 is withdrawn while cement grout 9 is filled into the borehole 7 from the head of the screw auger 8. Figure 8 shows the state in the middle of this process. By the time the screw auger 8 is completely withdrawn from the borehole 7, the cement grout 9 is filled from the bottom to the top of the borehole 7. This filling of the borehole 7 with cement grout 9 is the primary filling of cement grout 9.
[0020] The cement milk 9 will eventually solidify and firmly hold the newly installed pile P2, which will be inserted into the excavation hole 7 later, within the ground 1. As is done in conventional construction methods, the cement milk 9 consists of two components: a "foundation strengthening liquid" that is filled into the lower part of the excavation hole 7 and a "pile perimeter fixing liquid" that is filled into the upper part of the excavation hole 7, and is filled sequentially from the bottom to the top of the excavation hole 7.
[0021] Next, the second casing 6, which is still in place in the borehole 7, is withdrawn and removed. Figure 9 shows the state after the second casing 6 has been withdrawn and completely removed. The specific gravity of the cement grout 9 is greater than that of the bentonite water 4. Therefore, when the bottom of the borehole 7 and the bottom of the withdrawal hole 5 come into contact during the process of withdrawing the second casing 6, the hydrostatic pressure of the cement grout 9 inside the second casing 6 also acts, causing some of the cement grout 9 to flow into the bottom of the withdrawal hole 5. The bentonite water 4, which has a lower specific gravity, is moved upward by the cement grout 9, which has a higher specific gravity. Once the movement of the lower part of the cement grout 9 stabilizes, the cement grout 9 that escapes downward from the lower end of the second casing 6 as it is withdrawn will rest on top of its lower part. Also, when the second casing 6 is withdrawn, the hydrostatic pressure of the cement grout 9 acts sufficiently near the bottom of the borehole 7, so the borehole wall of the borehole 7 can be protected more stably.
[0022] The extraction hole 5 and the drilled hole 7 partially overlap to form one large hole. Since the extraction hole 5 was filled with bentonite water 4, some bentonite water 4 remains in this large hole. The new pile P2 will be installed in the drilled hole 7 later, but it is necessary to replace the bentonite water 4 in this large hole with cement grout 9. Therefore, a screw auger 8 or the like is used to secondarily fill the extraction hole 5 from the bottom to the top with cement grout 9. This secondary filling with cement grout 9 causes the bentonite water 4 to overflow, filling the large hole formed by the extraction hole 5 and the drilled hole 7 with cement grout 9. Figure 10 shows the state during the secondary filling of the extraction hole 5 with cement grout 9. As mentioned above, the specific gravity of cement grout 9 is greater than that of bentonite water 4, so the bentonite water 4 that remained near the extraction hole 5 is moved upward by the cement grout 9 and reliably overflows from both the extraction hole 5 and the drilled hole 7.
[0023] In this embodiment, secondary filling of the cement grout 9 is performed solely by the "pile-peripheral fixing liquid". Since the new pile P2 is installed in the excavation hole 7, the lower end of the new pile P2 is firmly fixed by the "foundation-reinforcing liquid" filled at the bottom of the excavation hole 7. Therefore, there is no need to fill the bottom of the extraction hole 5 with foundation-reinforcing liquid, and in this embodiment, secondary filling of the cement grout 9 is performed solely by the pile-peripheral fixing liquid. In particular, in this embodiment, as described above, the bottom of the excavation hole 7 is deeper than the bottom of the extraction hole 5, so the bottom of the excavation hole 7 is firmly filled with foundation-reinforcing liquid, and the difference in height prevents the foundation-reinforcing liquid in the excavation hole 7 from escaping to the bottom of the extraction hole 5.
[0024] Furthermore, since the lower end of the newly installed pile P2 needs to be firmly fixed, the entire perimeter of the lower end of the newly installed pile P2 should be firmly surrounded by the ground 1. If the bottom of the extraction hole 5 is deeper than the bottom of the excavation hole 7, an overlapping portion with the extraction hole 5 will be formed at the bottom of the excavation hole 7, which may raise concerns regarding the fixing strength. For this reason, in this embodiment, by making the bottom of the excavation hole 7 deeper than the bottom of the extraction hole 5, the lower end of the newly installed pile P2 can be firmly fixed. Moreover, since the specific gravity of the root reinforcement liquid is usually greater than that of the pile-peripheral fixing liquid, in the secondary filling of cement milk 9 shown in Figure 10, the root reinforcement liquid filled at the bottom of the excavation hole 7 does not move to the extraction hole 5 due to the secondary filling of cement milk 9. Note that in the secondary filling of cement milk 9, the two components, "root reinforcement liquid" and "pile-peripheral fixing liquid," may also be sequentially filled from the bottom to the top of the extraction hole 5.
[0025] Next, as shown in Figure 11, the new pile P2 is inserted vertically into the excavation hole 7. At this time, a portion of the cement grout 9 overflows from the extraction hole 5 and the excavation hole 7. After this, if the cement grout 9 is allowed to solidify as usual, the new pile P2 will be firmly fixed to the ground 1. In this embodiment, considering quality, the bentonite water 4 was completely overflowed during the secondary filling of the cement grout 9. However, considering the overflow when inserting the new pile P2 into the excavation hole 7, it may be planned to leave a small amount of bentonite water 4 while allowing most of it to overflow during the secondary filling of the cement grout 9. This remaining bentonite water 4 should all be overflowed when inserting the new pile P2 into the excavation hole 7.
[0026] According to the continuous construction method of the above embodiment, the removal of existing piles and the construction of new piles are carried out in the following steps: (1) The ground 1 is drilled with the first casing 2 to isolate the area around the existing pile P1, and then the first casing 2 is withdrawn. (2) While withdrawing the existing pile P1, bentonite water 4, a mixture of bentonite and water, is supplied into the withdrawal hole 5 formed by the withdrawal of the existing pile P1, and the withdrawal hole 5 is filled with bentonite water 4. (3) The ground 1 is drilled with the second casing 6 for the construction of the new pile P2, so as to partially overlap with the withdrawal hole 5. (4) The inside of the second casing 6 embedded in the ground 1 is excavated to form a borehole 7. (5) Cement grout 9 is primaryly filled into the borehole 7 from the bottom to the top. (6) The second casing 6, which is placed in the borehole 7, is withdrawn. (7) Cement grout 9 is secondaryly filled into the withdrawal hole 5, which partially overlaps with the borehole 7, from the bottom to the top, causing the remaining bentonite water 4 to overflow. (8) The new pile P2 is inserted into the excavated hole 7 filled with cement grout 9 and then installed.
[0027] This continuous construction method allows for a smooth and continuous process from the removal of existing piles P1 to the installation of new piles P2, thereby shortening the construction period. Furthermore, it offers the following advantages: Since existing piles P1 are removed using the edge-cutting extraction method, it generates less noise and vibration. The continuous construction method can be carried out smoothly while protecting the hole wall of the extraction hole 5 formed by the extraction of existing piles P1 with bentonite water 4. The amount of cement grout 9 can be reduced compared to when the extraction hole 5 is backfilled. Specifically, when the hole is backfilled, the cement grout 9 in the overlapping portion of the extraction hole 5 and the excavation hole 7 is wasted because it is removed when the excavation hole 7 is excavated after it has solidified.
[0028] Furthermore, according to the continuous drilling method of the above embodiment, the second casing 6 drills the borehole 7 such that the ratio of the length of the overlapping arc C of the borehole 7 that overlaps with the extraction hole 5 to the total circumference of the borehole 7 is 1 / 2 or less. This reduces the circumferential bias of the drilling resistance when drilling with the second casing 6, and ensures the verticality of the drilling by the second casing 6. Consequently, it is possible to ensure the verticality of the newly installed pile P2 constructed inside the borehole 7 formed by drilling with the second casing 6.
[0029] Furthermore, according to the continuous construction method of the above embodiment, the excavation hole 7 is excavated such that its bottom is deeper than the bottom of the extraction hole 5. Therefore, the lower end of the newly installed pile P2 located at the bottom of the excavation hole 7 is securely fixed by being surrounded all around by the ground 1. In addition, the lower end of the newly installed pile P2 is securely fixed to the bottom of the excavation hole 7 by the root-reinforcing liquid component in the primary filling of the excavation hole 7 with cement grout 9.
[0030] The present invention is not limited to the embodiments described above, and the components can be modified and implemented in practice without departing from the spirit of the invention. Furthermore, various inventions can be formed by appropriately combining the multiple components disclosed in the above embodiments. [Explanation of symbols]
[0031] 1 ground 2. First casing 4 Bentonite water 5. Pull-out hole 6. Second casing 7. Borehole 9. Cement Milk C overlapping arcs P1 Existing pile P2 New Pile Installation
Claims
1. A continuous construction method for removing existing piles and installing new piles, After drilling into the ground with the first casing to isolate the existing pile, the first casing is withdrawn. While pulling out the existing pile, bentonite water, a mixture of bentonite and water, is supplied to the inside of the extraction hole formed by the extraction of the existing pile, filling the extraction hole with the bentonite water. The ground is drilled using a second casing for the construction of the new pile so as to partially overlap with the aforementioned extraction hole. The inside of the second casing embedded in the ground is excavated to form a borehole. The aforementioned borehole is first filled with cement grout from the bottom to the top. The second casing, which is placed in the aforementioned borehole, is withdrawn. The extraction hole, which has a portion overlapping with the aforementioned excavation hole, is secondarily filled with cement grout from the bottom to the top, causing the remaining bentonite water to overflow. A continuous construction method for removing existing piles and installing new piles, comprising inserting the new piles into the excavated hole filled with cement grout.
2. The continuous method for removing existing piles and constructing new piles according to claim 1, wherein, in a plan view, the excavation hole is drilled by the second casing such that the ratio of the length of the overlapping arc of the excavation hole that overlaps with the extraction hole to the total circumference of the excavation hole is 1 / 2 or less.
3. The continuous method for removing existing piles and constructing new piles according to claim 1 or 2, wherein the excavated hole is excavated such that its bottom is deeper than the bottom of the extraction hole.
Citation Information
Patent Citations
Method for continuous lap drilling by leader auger machine and device used therefor
JP2000319881A
Composition for injection liquid and injection liquid for drilling
JP2012149107A
Pile construction method
JP2015183374A
Existing pile pulling out method
JP2020023788A
Pile pull-out method
JP2022070362A