First information processing device, second information processing device, information processing method, and program

The information processing apparatus optimizes power supply and demand forecasting to reduce the need for large energy storage devices, addressing the cost issue in self-wheel power transmission by enhancing the accuracy of renewable energy utilization and sales strategies.

JP7954130B2Active Publication Date: 2026-11-19KYOCERA CORP
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2023171619
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2023-10-02
Publication Date
2026-11-19
Estimated Expiration
2043-10-02

AI Technical Summary

Technical Problem

The installation of a large power storage capacity in power generation facilities increases the installation cost for self-wheel power transmission.

Method used

An information processing apparatus and method that calculates predicted values of electricity generation and consumption based on weather and environmental information, adjusting power supply and demand to reduce the need for large energy storage devices by optimizing self-transmission and retail electricity sales.

Benefits of technology

Reduces the installation cost of large-capacity energy storage devices by improving the accuracy of power supply and demand forecasting, allowing for efficient utilization of renewable energy sources and reducing the discrepancy between planned and actual values.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007954130000001
    Figure 0007954130000001
  • Figure 0007954130000002
    Figure 0007954130000002
  • Figure 0007954130000003
    Figure 0007954130000003
Patent Text Reader

Abstract

To reduce installation cost for performing self consignment.SOLUTION: A first information processing device 10 comprises a controller 24 and a communication section 23. The controller 24 calculates a first prediction value on the basis of weather forecast information. The controller 24 calculates a second prediction value by subtracting an estimated error with respect to the first prediction value. The controller 24 calculates a third prediction value of a power amount used in a first power demand area 21 on the basis of environment information. The controller 24 calculates a fourth prediction value on the basis of the third prediction value. The controller 24 calculates a value obtained by cumulating the fourth prediction value in a time zone, in which the second prediction value exceeds the fourth prediction value, as a first supply power amount planned value. The controller 24 calculates a first demand power amount planned value on the basis of the first supply power amount planned value. The communication section 23 transmits the first supply power amount planned value and the first demand power amount planned value as information.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to an information processing apparatus, an information processing method, and a program.

Background Art

[0002] Conventionally, self-wheel power transmission is known as a mechanism for transmitting power output from a power generation facility to a demand facility from the power generation facility via a power system managed by a third-party entity (see Patent Document 1). To perform self-wheel power transmission, it is required to match the power generation plan or demand plan formulated in advance with the actual power generation performance or demand performance in units of 30 minutes. In a configuration applying a power source that generates power using renewable energy, it is conceivable to use a power storage device provided in the power generation facility to balance the difference between the planned amount of power to be generated and the actual result. In particular, in a configuration using a power source whose predicted power generation amount on average satisfies the expected power demand, a power storage device having a large power storage capacity is required.

Prior Art Documents

Patent Documents

[0003]

Patent Document 1

Summary of the Invention

Problems to be Solved by the Invention

[0004] However, the installation of a power storage device having a large power storage capacity increases the installation cost at the power generation facility.

[0005] Accordingly, an object of the present disclosure, which has been made in view of the problems of the related art as described above, is to provide an information processing apparatus, an information processing method, and a program that reduce the installation cost for performing self-wheel power transmission.

Means for Solving the Problems

[0006] In order to solve the aforementioned problems, the first information processing device from the first perspective is: Power is generated using renewable energy sources that are subject to management. all A first predicted value of the amount of electricity generated by the power source is calculated based on weather forecast information, a second predicted value is calculated by subtracting the estimation error from the first predicted value, a third predicted value of the amount of electricity used at at least one first power demand site to which electricity is supplied by the power source through self-transmission is calculated based on environmental information of the at least one first power demand site, and the third predicted value is calculated based on the all A controller that calculates a fourth predicted value of the amount of electricity to be supplied to at least one first electricity demand site at a power source, calculates a first planned power supply value by accumulating the fourth predicted value during the time periods in which the second predicted value exceeds the fourth predicted value within a plurality of time periods included in a unit time, and calculates the amount of electricity to be supplied to the first electricity demand site based on the first planned power supply value, The system includes a communication unit that transmits the first planned power supply value and the first planned power demand value as information. 。

[0007] Furthermore, the second information processing device from the second perspective is, Power is generated using renewable energy sources that are subject to management. all A first predicted value of the amount of electricity generated by the power source is calculated based on weather forecast information, a second predicted value is calculated by subtracting the estimation error from the first predicted value, a third predicted value of the amount of electricity used at at least one first power demand site to which electricity is supplied by the power source through self-transmission is calculated based on environmental information of the at least one first power demand site, and the third predicted value is calculated based on the allA controller that calculates a fourth predicted value of the amount of electricity to be supplied to at least one first power demand site at a power source, calculates a first planned power supply value by accumulating the fourth predicted value in the time periods in which the second predicted value exceeds the fourth predicted value among a plurality of time periods included in a unit time, and calculates the amount of electricity to be supplied to the first power demand site based on the first planned power supply value as a first planned power demand value; a communication unit that receives the first predicted value and the fourth predicted value as information from a first information processing device having: a controller that calculates a fourth predicted value of the amount of electricity to be supplied to the at least one first power demand site at a power source, calculates a first planned power supply value by accumulating the fourth predicted value in the time periods in which the second predicted value exceeds the fourth predicted value among a plurality of time periods included in a unit time, and calculates the amount of electricity to be supplied to the first power demand site based on the first planned power supply value as a first planned power demand value; and a communication unit that transmits the first planned power supply value and the first planned power demand value as information; The fifth predicted value obtained by subtracting the fourth predicted value from the first predicted value is calculated as the second planned power supply value, and sales are calculated prior to Electrical Recording The system includes a controller that calculates a second planned demand value for power supplied to at least one second power demand location from which power is supplied from a power source, based on the second planned supply value, and causes the controller to transmit the second planned supply value and the second planned demand value as information to the communication unit.

[0008] Furthermore, the information processing method from a third perspective is: Based on weather forecast information, the first predicted value of the amount of electricity generated by all power sources that use renewable energy under management is calculated. A second predicted value is calculated by subtracting the estimation error from the first predicted value. A third predicted value of the amount of electricity used at at least one first power demand site, which is supplied with electricity from all power sources by self-transmission, is calculated based on environmental information of the at least one first power demand site. Based on the third predicted value, a fourth predicted value is calculated for the amount of electricity to be supplied to the at least one first power demand site from all power sources. The first planned power supply value is calculated by accumulating the fourth predicted value over a unit time that includes multiple such time periods during the time period in which the second predicted value exceeds the fourth predicted value. Based on the first planned power supply amount, the amount of electricity supplied to the first power demand area is calculated as the first planned power demand amount. The first planned power supply amount and the first planned power demand amount are transmitted as information.

[0009] Furthermore, the program from the fourth perspective is: The first predicted value of the amount of electricity generated by all power sources that are managed using renewable energy is calculated based on weather forecast information, The process involves calculating a second predicted value obtained by subtracting the estimation error from the first predicted value, A third predicted value of the amount of electricity used at at least one first power demand site, which is supplied with electricity from all power sources by self-transmission, is calculated based on environmental information of the at least one first power demand site. Based on the third predicted value, a fourth predicted value of the amount of electricity to be supplied to the at least one first power demand site from all power sources is calculated, The first planned power supply value is calculated by accumulating the fourth predicted value over a unit time that includes multiple such time periods during the time period in which the second predicted value exceeds the fourth predicted value, The amount of electricity supplied to the first electricity demand area is calculated as the first electricity demand plan value based on the first planned electricity supply amount, The computer is instructed to perform an operation that includes transmitting the first planned power supply value and the first planned power demand value as information. [Effects of the Invention]

[0010] According to the information processing device, information processing method, and program described above, the installation cost of a large-capacity energy storage device for self-transmission is reduced. [Brief explanation of the drawing]

[0011] [Figure 1] This figure shows the network configuration of a power management system including a first information processing device according to this embodiment and a power supply and demand system managed by the power management system. [Figure 2]This is a block diagram showing a schematic configuration of the first information processing apparatus in FIG. 1. [Figure 3] This is a block diagram showing a schematic configuration of the second information processing apparatus in FIG. 1. [Figure 4] This is a flowchart for explaining the first transmission process executed by the controller in FIG. 2. [Figure 5] This is a flowchart for explaining the second transmission process executed by the controller in FIG. 2. [Figure 6] This is a flowchart for explaining the third transmission process executed by the controller in FIG. 3. [Mode for Carrying Out the Invention]

[0012] Hereinafter, embodiments of the information processing apparatus to which the present disclosure is applied will be described with reference to the drawings.

[0013] As shown in FIG. 1, a power management system 11 including a first information processing apparatus 10 according to an embodiment may be configured to include the first information processing apparatus 10, a second information processing apparatus 12, a third information processing apparatus 13, a fourth information processing apparatus 14, and a network 15. In FIG. 1, the first information processing apparatus 10, the second information processing apparatus 12, the third information processing apparatus 13, and the fourth information processing apparatus 14 may communicate information via the network 15. The power management system 11 may manage information for operating a power supply and demand system 19 including a plurality of power sources 16, a plurality of power demand sites 17, and a power transmission and distribution network 18.

[0014] The first information processing apparatus 10 is assumed to be used at least by a first operator who is a self-wheel-through power transmission operator. The first operator may treat at least one first power source 20 and at least one first power demand site 21 as management targets. The first operator may own the first power source 20 as an asset. The first operator may own the first power demand site 21 as an asset. The first operator may treat the power demand sites of other operators belonging to the same association as the first power demand sites 21 that are the management targets of the first operator. The first operator may also serve as a retail electricity operator.

[0015] At least one first power source 20 may include multiple first power sources 20. The first power source 20 is a power source 16 that generates electricity from renewable energy. The power source 16 may have an energy storage device. The first power demand area 21 is a power demand area 17 that is supplied with electricity from the first power source 20 by self-transmission.

[0016] The second information processing device 12 is intended to be used by a second business operator, which is a retail electricity business operator. The second business operator may purchase electricity from power generation businesses, including at least the first business operator, and sell the electricity to consumers. Consumers may include the second business operator itself. Consumers may have a second electricity demand area 22. The second electricity demand area 22 is under the management of the second business operator. Furthermore, the second electricity demand area 22 is an electricity demand area 17 that is supplied with electricity from various power sources 16, including the first power source 20, through sales from retail electricity businesses.

[0017] The third information processing device 13 is intended to be used by a third operator that performs supply and demand adjustment in the power supply and demand system 19. In Japan, for example, the third operator is OCCTO (Organization for Cross-regional Coordination of Transmission Operators).

[0018] The fourth information processing device 14 is intended to be used by a fourth business operator that forecasts the weather in the area where the first power source 20 is installed.

[0019] In the power supply and demand system 19, when the first operator uses the transmission and distribution network 18 for self-transmission, it is required to report to the third operator the planned values ​​of the amount of electricity demanded and supplied by self-transmission at predetermined time intervals (e.g., 30 minutes). Furthermore, it is required that the planned values ​​and actual values ​​at predetermined time intervals match. In addition, if there is a discrepancy between the planned values ​​and actual values, i.e., an imbalance occurs, a penalty (imbalance charge) will be imposed according to the imbalance. In the following explanation, the planned value of the amount of electricity demanded by self-transmission will also be referred to as the "first operator's planned demand amount." Similarly, the planned value of the amount of electricity supplied by self-transmission will hereafter be referred to as the "first operator's planned supply amount."

[0020] Furthermore, in the power supply and demand system 19, when the second business operator uses the transmission and distribution network 18 for retail, it is required to report to the third business operator the planned values ​​of the demand and supply of electricity for retail in predetermined time units (e.g., 30 minutes). It is also required that the planned values ​​and actual values ​​for predetermined time intervals be matched. In the following explanation, the planned value of the electricity demand at the power demand area managed by the second business operator will also be referred to as the "second business operator's planned demand value." Furthermore, the planned value of the amount of electricity supplied to the power demand area managed by the second business operator will hereafter be referred to as the "second business operator's planned supply value."

[0021] In the power supply and demand system 19 of this embodiment, it is required to bring the actual values ​​in self-transmission closer to the planned values, and to bring the actual values ​​in retail closer to the planned values.

[0022] As shown in Figure 2, the first information processing device 10 is configured to include a communication unit 23 and a controller 24.

[0023] The communication unit 23 may include a communication module that communicates with the second information processing device 12, the third information processing device 13, and the fourth information processing device 14 via the network 15. The communication unit 23 may transmit and receive various information and commands. For example, the communication unit 23 may receive information on the amount of electricity generated from the first power source 20, which is managed by the first information processing device 10 used by the first business operator, at different time intervals. The communication unit 23 may also receive information on the amount of electricity consumed from the first power demand site 21, which is managed by the first information processing device 10 used by the first business operator, at different time intervals. Furthermore, the communication unit 23 may receive information on predicted values ​​of the amount of electricity purchased from power generation businesses other than the first business operator.

[0024] The controller 24 includes one or more processors and memory. The processors may include general-purpose processors that load specific programs and execute specific functions, and dedicated processors specialized for specific processing. Dedicated processors may include application-specific integrated circuits (ASICs). The processors may include programmable logic devices (PLDs). PLDs may include field-programmable gate arrays (FPGAs). The controller 24 may be either a system-on-a-chip (SoC) or a system-in-a-package (SiP) in which one or more processors work together.

[0025] The controller 24 calculates a first predicted value based on weather forecast information. The first predicted value is a predicted value of the amount of electricity generated by all first power sources 20 that generate electricity from renewable energy and are under the management of the first business operator, in other words, under the management of the first information processing device 10. The first power sources 20 that generate electricity from renewable energy are, for example, solar power sources and wind power sources. The weather forecast information is, for example, predicted values ​​of solar radiation and predicted values ​​of wind speed. The controller 24 calculates a first predicted value for the first power source 20 based on solar radiation forecast information in the installation area of ​​the first power source 20 that generates solar power. The controller 24 calculates a first predicted value for the first power source 20 based on wind speed forecast information in the installation area of ​​the first power source 20 that generates wind power. The controller 24 may, for example, obtain weather forecast information from the fourth information processing device 14 via the communication unit 23.

[0026] The controller 24 calculates a second predicted value by subtracting an estimation error from a first predicted value. The estimation error is the difference between the first predicted value and the lower limit of the estimated prediction range for the first predicted value. The estimation error may be, for example, the value obtained by multiplying the first predicted value by a predetermined coefficient less than 1, such as 0.9. Alternatively, the estimation error may be, for example, the lower limit of the range of actual values ​​taken for the same first predicted value in the past. Therefore, the second predicted value is a predicted value of the amount of electricity that is likely to be secured.

[0027] The controller 24 calculates a third predicted value based on environmental information of the first power demand area 21. The third predicted value is a predicted value for the amount of electricity used at the first power demand area 21. The environmental information includes, for example, a temperature forecast value at the first power demand area 21 and an operating forecast of the equipment at the first power demand area 21. The temperature forecast value improves the accuracy of forecasting the amount of electricity used by air conditioners, whose load fluctuates according to the temperature. The operating forecast improves the accuracy of forecasting the amount of electricity used by equipment such as factories, whose load fluctuates according to the operating conditions.

[0028] In a configuration where multiple first power demand locations 21 are managed by the first information processing device 10, the third predicted value may be the sum of the predicted values ​​of the amount of electricity used at each of the multiple first power demand locations 21.

[0029] The controller 24 calculates a fourth predicted value based on the third predicted value. The fourth predicted value is a predicted amount of electricity to be supplied from the first power source 20 to the first power demand area 21. Specifically, the fourth predicted value is the amount of electricity at the first power demand area 21 required to supply the third predicted value to the first power demand area 21. The controller 24 may calculate the fourth predicted value by dividing the third predicted value by a value obtained by subtracting the transmission loss rate from 1. The transmission loss rate may be the transmission loss rate between the first power source 20 and the first power demand area 21.

[0030] In a configuration where multiple first power demand locations 21 are managed by the first information processing device 10, the fourth predicted value may be the sum of predicted values ​​for the amount of electricity to be supplied from the first power source 20 to each of the multiple first power demand locations 21. The predicted value for the amount of electricity to be supplied from the first power source 20 to each of the multiple first power demand locations 21 may be based on predicted values ​​for the amount of electricity used at each of the multiple first power demand locations 21.

[0031] The controller 24 determines whether the second predicted value exceeds the fourth predicted value for each of several time periods included in a unit time. The unit time is, for example, one day. The controller 24 calculates the first planned power supply value by accumulating the fourth predicted value in the time periods in which the second predicted value exceeds the fourth predicted value over the unit time.

[0032] The controller 24 calculates a first planned power demand value based on a first planned power supply value. The first planned power demand value is a predicted value of the amount of electricity supplied to the first power demand site 21. The first planned power demand value is the amount of electricity corresponding to the first planned power supply value and is the amount of electricity transmitted to the first power demand site 21. The controller 24 may calculate the first planned power demand value by multiplying the first planned power supply value by a value obtained by subtracting the transmission loss rate from 1.

[0033] The controller 24 controls the communication unit 23 to transmit the calculated first planned power supply value and first planned power demand value as information. The first planned power supply value and first planned power demand value may be transmitted to the third information processing device 13 as planned values ​​from the first operator, which is a self-consignment operator. The first planned power supply value is the planned amount of electricity supplied from the first power source 20 to the transmission and distribution network 18 as self-consignment. The first planned power demand value is the planned amount of electricity supplied from the transmission and distribution network 18 to the first power demand area 21 as self-consignment.

[0034] The controller 24 may control the communication unit 23 to transmit the first predicted value and the fourth predicted value as information to the second information processing device 12.

[0035] The controller 24 may calculate a fifth predicted value obtained by subtracting a fourth predicted value from a first predicted value as the second planned power supply value. The controller 24 may calculate a second planned power demand value based on the second planned power supply value. The second planned power demand value may be the planned amount of power supplied to at least one second power demand location 22 that is supplied with power from the first power source 20 which is managed by the first information processing device 10. The second planned power demand value is the amount of power corresponding to the second planned power supply value and is the amount of power transmitted to the second power demand location 22. The controller 24 may calculate the second planned power demand value by multiplying the second planned power supply value by a value obtained by subtracting the transmission loss rate from 1.

[0036] The controller 24 may, when the first business operator purchases electricity from a power generation business operator other than the first business operator as a retail electricity business operator, add the predicted amount of electricity to be purchased from the said power generation business operator to the fifth predicted value to calculate the second planned supply amount and the second planned demand amount.

[0037] The controller 24 may control the communication unit 23 to transmit the calculated second planned power supply value and second planned power demand value as information. The second planned power supply value and second planned power demand value may be transmitted to the third information processing device 13 as planned values ​​from the first business operator, which is a retail electricity business operator. The second planned power supply value is the planned amount of electricity supplied from the first power source 20 to the transmission and distribution network 18 as retail sales. The second planned power demand value is the planned amount of electricity supplied from the transmission and distribution network 18 to the second power demand area 22 as retail sales.

[0038] Controller 24 may calculate a third actual value, which is the amount of electricity sold from the first business operator as a self-transmissioning business operator to the first business operator as a retail electricity business operator, as described below. Controller 24 may obtain a first actual value as information from the first power sources 20, which is the amount of electricity actually generated by all the first power sources 20. Controller 24 may obtain as information from the first power demand sites 21, which is the amount of electricity actually consumed by all the first power demand sites 21. Controller 24 may calculate a second actual value by dividing this amount of electricity by the transmission loss rate between the first power sources 20 and the first power demand sites 21 minus 1. Controller 24 may calculate the third actual value described above by subtracting the second actual value from the first actual value.

[0039] The controller 24 may associate environmental value information with the third actual value. The controller 24 may control the communication unit 23 to transmit the environmental value information. The environmental value information is information indicating that the electricity is generated from renewable energy. The environmental value information includes information that is issued in real time or information that is issued over time, such as non-fossil fuel certificates. The controller 24 may, for example, transmit the environmental value information to a consumer who purchases electricity from the first business operator as a retail electricity provider.

[0040] As shown in Figure 3, the second information processing device 12 is configured to include a communication unit 25 and a controller 26.

[0041] The communication unit 25 may include a communication module that communicates with the first information processing device 10 and the third information processing device 13 via the network 15. The communication unit 25 may transmit and receive various information and commands. For example, the communication unit 25 may receive a first predicted value and a fourth predicted value as information from the first information processing device 10. The communication unit 25 may also receive predicted values ​​of the amount of electricity to be purchased from power generation businesses other than the first business operator as information.

[0042] The controller 26 includes one or more processors and memory. The processors may include general-purpose processors that load specific programs and perform specific functions, and dedicated processors specialized for specific processing. The dedicated processor may include an ASIC. The processor may include a PLD. The PLD may include an FPGA. The controller 24 may be either an SoC in which one or more processors cooperate, or a SiP.

[0043] Controller 26 may calculate a fifth predicted value obtained by subtracting the fourth predicted value from the first predicted value as the second planned power supply value. Controller 26 may calculate a second planned power demand value based on the second planned power supply value. Controller 26 may calculate a second planned power demand value by multiplying the second planned power supply value by a value obtained by subtracting the transmission loss rate from 1. If the second operator purchases electricity from a power generator other than the first operator, Controller 26 may add the predicted amount of electricity to be purchased from the said power generator to the fifth predicted value to calculate the second planned power supply value and the second planned power demand value.

[0044] The controller 26 may control the communication unit 25 to transmit the calculated second planned power supply value and second planned power demand value as information. The second planned power supply value and second planned power demand value may be transmitted to the third information processing device 13 as planned values ​​from the second business operator, which is a retail electricity business operator. The second planned power supply value is the planned amount of electricity supplied to the transmission and distribution network 18 from the power source 16 managed by the second business operator, including the first power source 20, as retail sales. The second planned power demand value is the planned amount of electricity supplied to the second power demand area 22 from the transmission and distribution network 18 as retail sales.

[0045] Next, the first transmission process performed by the controller 24 of the first information processing device 10 in this embodiment will be explained using the flowchart in Figure 4. The first transmission process is initiated periodically, for example, at any point before the time when submission to the third business operator is stipulated.

[0046] In step S100, the controller 24 acquires weather forecast information for the area where the first power source 20 is installed. The weather forecast information may be the latest information previously acquired from the fourth information processing device 14. Alternatively, the weather forecast information may be read from the fourth information processing device 14. After acquisition, the process proceeds to step S101.

[0047] In step S101, the controller 24 calculates a first forecast value based on the weather forecast information acquired in step S100. After calculation, the process proceeds to step S102.

[0048] In step S102, the controller 24 calculates a second predicted value by subtracting the estimation error from the first predicted value calculated in step S101. After calculation, the process proceeds to step S103.

[0049] In step S103, the controller 24 acquires environmental information at the first power demand site 21. After acquisition, the process proceeds to step S104.

[0050] In step S104, the controller 24 calculates a third predicted value based on the environmental information acquired in step S103. After calculation, the process proceeds to step S105.

[0051] In step S105, the controller 24 calculates a fourth predicted value based on the third predicted value calculated in step S104 and the transmission loss rate between the first power source 20 and the first power demand site 21. After calculation, the process proceeds to step S106.

[0052] In step S106, the controller 24 calculates a first planned power supply value based on the second predicted value calculated in step S102 and the fourth predicted value calculated in step S105. After calculation, the process proceeds to step S107.

[0053] In step S107, the controller 24 calculates a first planned power demand value based on the first planned power supply value calculated in step S106 and the transmission loss rate between the first power source 20 and the first power demand site 21. After calculation, the process proceeds to step S108.

[0054] In step S108, the controller 24 controls the communication unit 23 to transmit the first planned power supply value calculated in step S106 and the first planned power demand value calculated in step S107 to the third information processing device 13. After transmission, the process proceeds to step S109.

[0055] In step S109, the controller 24 determines whether the system is configured to sell the electricity generated by the first power source 20 to a retail electricity provider. If it is configured to sell, the process proceeds to step S110. If it is not configured to sell, the process proceeds to step S111.

[0056] In step S110, the controller 24 controls the communication unit 23 to transmit the first predicted value calculated in step S101 and the fourth predicted value calculated in step S105 as information to the second information processing device 12. After transmission, the first transmission process ends.

[0057] In step S111, the controller 24 determines whether the first business operator is configured to be a retail electricity provider. If it is configured to be a retail electricity provider, the process proceeds to step S112. If it is not configured to be a retail electricity provider, the first transmission process ends.

[0058] In step S112, the controller 24 calculates a second planned power supply value based on the first predicted value calculated in step S101 and the fourth predicted value calculated in step S105. After calculation, the process proceeds to step S113.

[0059] In step S113, the controller 24 calculates a second planned demand value based on the second planned supply value calculated in step S112. After calculation, the process proceeds to step S114.

[0060] In step S114, the controller 24 controls the communication unit 23 to transmit the second planned power supply value calculated in step S112 and the second planned power demand value calculated in step S113 to the third information processing device 13. After transmission, the first transmission process ends.

[0061] Next, the second transmission process performed by the controller 24 of the first information processing device 10 in this embodiment will be explained using the flowchart in Figure 5. The second transmission process starts, for example, after the target date and time for which the first power supply plan value was created has elapsed.

[0062] In step S200, the controller 24 calculates a first actual value by summing the amount of electricity actually generated by the first power sources 20 at predetermined time intervals, which is obtained as information from all the first power sources 20 under management. After calculation, the process proceeds to step S201.

[0063] In step S201, the controller 24 sums up the amount of electricity consumed at each of the first power demand locations 21 for predetermined time intervals, which is obtained as information from all the first power demand locations 21 under management. By summing, the amount of electricity consumed at the date and time for which the first power supply plan value was created is calculated. After the calculation, the process proceeds to step S202.

[0064] In step S202, the controller 24 calculates a second actual value by dividing the amount of power calculated in step S201 by the value obtained by subtracting the transmission loss rate between the first power source 20 and the first power demand site 21 from 1. After calculation, the process proceeds to step S203.

[0065] In step S203, the controller 24 calculates a third actual value by subtracting the second actual value calculated in step S203 from the first actual value calculated in step S200. After calculation, the process proceeds to step S204.

[0066] In step S204, the controller 24 associates the environmental value information with the third actual value calculated in step S203. After the association, the process proceeds to step S205.

[0067] In step S205, the controller 24 controls the communication unit 23 to transmit environmental value information associated with the third actual value in step S205 to the customer. After transmission, the second transmission process ends.

[0068] Next, the third transmission process performed by the controller 26 of the second information processing device 12 in this embodiment will be explained using the flowchart in Figure 6. The third transmission process starts, for example, after receiving the first predicted value and the fourth predicted value as information from the first information processing device 10.

[0069] In step S300, the controller 26 calculates a second planned power supply value based on the received first and fourth predicted values. After calculation, the process proceeds to step S301.

[0070] In step S301, the controller 26 calculates a second planned power demand value based on the second planned power supply value calculated in step S300. After calculation, the process proceeds to step S302.

[0071] In step S302, the controller 26 controls the communication unit 25 to transmit the second planned power supply value calculated in step S300 and the second planned power demand value calculated in step S301 to the third information processing device 13. After transmission, the third transmission process ends.

[0072] The first information processing device 10 having the above configuration includes a controller 24 that calculates a first predicted value of the amount of electricity generated by all first power sources 20 based on weather forecast information, calculates a second predicted value by subtracting the estimation error from the first predicted value, calculates a third predicted value of the amount of electricity used at least one first power demand area 21 based on environmental information of the at least one first power demand area 21, calculates a fourth predicted value of the amount of electricity to be supplied to the at least one first power demand area 21 by all first power sources 20 based on the third predicted value, calculates a first planned power supply value by accumulating the fourth predicted value in the time periods in which the second predicted value exceeds the fourth predicted value among multiple time periods included in a unit time, and calculates the amount of electricity to be supplied to the first power demand area 21 based on the first planned power supply value as the first planned power demand value, and a communication unit 23 that transmits the first planned power supply value and the first planned power demand value as information. The accuracy of predicting the amount of electricity consumed at the electricity demand area 17 is higher than the accuracy of predicting the amount of electricity generated using renewable energy. Based on this fact, the first information processing device 10 calculates the planned amount of electricity to be supplied to the transmission and distribution network 18 (first planned supply amount) not based on the amount of electricity generated by the power source 16, but on the planned amount of electricity consumed at the electricity demand area 17 (first planned demand amount). Therefore, the first information processing device 10 can calculate a planned value (first planned supply amount) that reduces the difference from the actual value. As a result, the first information processing device 10 can reduce the size or omit the capacity of the energy storage device, thereby reducing installation costs.

[0073] Furthermore, in order to increase the certainty of generating electricity exceeding the planned amount of electricity to be supplied by the first power source, a first power source 20 with a relatively large generation capacity compared to the expected demand is used. By selling the remaining electricity, obtained by subtracting the electricity supplied to the first electricity demand area 21 from the electricity generated by the first power source 20, to a retail electricity business operator, the first power source 20 owned by the first business operator can be effectively utilized. Retail electricity business operators generally receive electricity from multiple power sources 16 distributed over a wide area, compared to self-transmission operators. Therefore, the forecast of electricity generated by the power sources 16 distributed over a wide area is averaged out overall, so the ratio of the difference between the planned value and the actual value to the actual value is relatively small. Consequently, the difference between the forecast and actual values ​​of electricity generated by a self-transmission operator can be absorbed by the forecast and actual values ​​of electricity generated by all power sources managed by the retail electricity business operator.

[0074] Furthermore, the first information processing device 10 calculates a fifth predicted value obtained by subtracting a fourth predicted value from a first predicted value as the second planned power supply value, calculates a second planned power demand value to be supplied to at least one second power demand location 22 from which power is supplied from the power source through sales, based on the second planned power supply value, and transmits the second planned power supply value and the second planned power demand value as information. With this configuration, the first information processing device 10 can transmit planned values ​​for power supply and power demand as a retail electricity business operator (the second planned power supply value and the second planned power demand value).

[0075] Furthermore, the first information processing device 10 associates environmental value information with a third actual value obtained by subtracting a second actual value, which is obtained by dividing the amount of electricity actually consumed by at least one first power demand site 21 by the transmission loss rate between the first power source 20 and the first power demand site 21 minus 1, from a first actual value of the amount of electricity actually generated by all first power sources 20, and transmits the environmental value information. With this configuration, the first information processing device 10 can add environmental value information as added value to the electricity that the first business operator, as a retail electricity business operator, sells to consumers.

[0076] Non-fossil fuel certificates included in environmental value information are issued based on the actual meter readings (electricity received) for each power plant. In the case of multiple power plants, each belonging to a retail power generation balancing group and a self-transmission power generation balancing group, it is preferable to allocate each power plant to either the retail power generation balancing group or the self-transmission power generation balancing group. This is because it makes it easier to certify the amount of electricity received by the power plant. The ease of certification is explained below. A meter installed by a general transmission and distribution company, of which only one is installed at each power plant (power generation site), can measure the entire amount of electricity generated (also called electricity received). As mentioned above, in a configuration where multiple power plants belong to retail and self-transmission power generation balancing groups, by allocating any power plant to self-transmission and another power plant to retail, the amount for retail is measured, making it easier to certify non-fossil fuel certificates. This is because, under the current system in Japan, the value measured by the meter at the power plant is certified as a non-fossil fuel certificate. Furthermore, the control to determine whether each power plant will be used for retail sales or self-consignment may be performed by the first information processing device 10 in Figure 1.

[0077] However, if any single operator owns only one power plant, it is not possible to separate the amount of electricity received into a retail power balancing group and a self-transmission power balancing group. This is because only one meter is installed, which can only measure the amount of electricity generated (received) from that single power plant, and as a result, it is not physically possible to measure whether the electricity is for self-transmission or retail.

[0078] To address the aforementioned issues, the calculation of the retail portion of electricity, based on the planned power generation values ​​and partial supply notification values ​​separated into self-consignment and retail, is used as the target of environmental value information. Even if a predetermined period is required for electricity quantity certification and conversion into non-fossil fuel certificates, the information can be linked in real time, and the environmental value of the retail portion calculated by this invention can be immediately estimated.

[0079] Furthermore, in the first information processing device 10, at least one first power demand location 21 includes a plurality of first power demand locations 21, the third predicted value is the sum of predicted values ​​for the amount of electricity used in each of the plurality of first power demand locations 21, and the fourth predicted value is the sum of predicted values ​​for the amount of electricity to be supplied to each of the plurality of first power demand locations 21 by the first power source 20, based on the predicted values ​​for the amount of electricity used in each of the plurality of first power demand locations 21. With this configuration, the first information processing device 10 can transmit a first planned supply amount of electricity and a first planned demand amount of electricity for self-transmission to the plurality of power demand locations 17.

[0080] The second information processing device 12, having the configuration described above, includes a communication unit 25 that receives the first predicted value and the fourth predicted value as information from the first information processing device 10, and a controller 26 that calculates the fifth predicted value obtained by subtracting the fourth predicted value from the first predicted value as the second planned power supply value, calculates the second planned power demand value to be supplied to at least one second power demand site 22 based on the second planned power supply value, and causes the second planned power supply value and the second planned power demand value to be transmitted to the communication unit 25 as information. With this configuration, the second information processing device 12 can transmit planned values ​​for power supply and power demand as a retail electricity business operator (second planned power supply value and second planned power demand value).

[0081] In one embodiment, (1) the first information processing device is A controller that calculates a first predicted value of the amount of electricity generated by all power sources that generate electricity from renewable energy sources under management, based on weather forecast information, calculates a second predicted value by subtracting the estimation error from the first predicted value, calculates a third predicted value of the amount of electricity used at least one first power demand site to which electricity is supplied by the power sources through self-transmission, based on environmental information of the at least one first power demand site, calculates a fourth predicted value of the amount of electricity to be supplied to the at least one first power demand site by all power sources based on the third predicted value, calculates a first planned power supply value by accumulating the fourth predicted value during the time periods in which the second predicted value exceeds the fourth predicted value within a plurality of time periods included in a unit time, and calculates the amount of electricity to be supplied to the first power demand site based on the first planned power supply value, The system includes a communication unit that transmits the first planned power supply value and the first planned power demand value as information.

[0082] (2) In the first information processing device described in (1) above, The controller calculates the fourth predicted value by dividing the third predicted value by the value obtained by subtracting the transmission loss rate between the power source and the first power demand site from 1.

[0083] (3) In the first information processing device described in (1) or (2) above, The controller calculates a fifth predicted value obtained by subtracting the fourth predicted value from the first predicted value as the second planned power supply value, and calculates a second planned power demand value to be supplied to at least one second power demand location from which power is supplied from the power source by sale, based on the second planned power supply value. The communication unit transmits the second planned power supply value and the second planned power demand value as information.

[0084] (4) In the first information processing device described in (3) above, The controller associates environmental value information with a third actual value obtained by subtracting a second actual value, which is obtained by dividing the amount of electricity actually consumed by at least one first power demand site by the transmission loss rate between the power source and the first power demand site minus 1, from a first actual value of the amount of electricity actually generated by all power sources. The communication unit transmits the environmental value information.

[0085] (5) In any of the first information processing devices described in (1) to (4) above, The aforementioned at least one first power demand site includes a plurality of first power demand sites, The third predicted value is the sum of the predicted values ​​of the amount of electricity used in each of the plurality of first electricity demand locations. The fourth predicted value is the sum of predicted values ​​of the amount of electricity to be supplied from the power source to each of the multiple first power demand sites, based on predicted values ​​of the amount of electricity used at each of the multiple first power demand sites.

[0086] (6) A communication unit that receives the first predicted value and the fourth predicted value as information from the first information processing device of (1) or (2) above, The system includes a controller that calculates a fifth predicted value obtained by subtracting the fourth predicted value from the first predicted value as a second planned power supply value, calculates a second planned power demand value to be supplied to at least one second power demand location from which power is supplied from all power sources through sales, based on the second planned power supply value, and causes the controller to transmit the second planned power supply value and the second planned power demand value as information to the communication unit.

[0087] In one embodiment, (7) the information processing method is Based on weather forecast information, the first predicted value of the amount of electricity generated by all power sources that use renewable energy under management is calculated. A second predicted value is calculated by subtracting the estimation error from the first predicted value. A third predicted value of the amount of electricity used at at least one first power demand site, which is supplied with electricity from all power sources by self-transmission, is calculated based on environmental information of the at least one first power demand site. Based on the third predicted value, a fourth predicted value is calculated for the amount of electricity to be supplied to the at least one first power demand site from all power sources. The first planned power supply value is calculated by accumulating the fourth predicted value over a unit time that includes multiple such time periods during the time period in which the second predicted value exceeds the fourth predicted value. Based on the first planned power supply amount, the amount of electricity supplied to the first power demand area is calculated as the first planned power demand amount. The first planned power supply amount and the first planned power demand amount are transmitted as information.

[0088] In one embodiment, (8) the program is The first predicted value of the amount of electricity generated by all power sources that are managed using renewable energy is calculated based on weather forecast information, The process involves calculating a second predicted value obtained by subtracting the estimation error from the first predicted value, A third predicted value of the amount of electricity used at at least one first power demand site, which is supplied with electricity from all power sources by self-transmission, is calculated based on environmental information of the at least one first power demand site. Based on the third predicted value, a fourth predicted value of the amount of electricity to be supplied to the at least one first power demand site from all power sources is calculated, The first planned power supply value is calculated by accumulating the fourth predicted value over a unit time that includes multiple such time periods during the time period in which the second predicted value exceeds the fourth predicted value, The amount of electricity supplied to the first electricity demand area is calculated as the first electricity demand plan value based on the first planned electricity supply amount, The computer is instructed to perform an operation that includes transmitting the first planned power supply value and the first planned power demand value as information.

[0089] While embodiments of the first information processing device 10 have been described above, embodiments of the present disclosure may also include not only methods or programs for implementing the device, but also a storage medium on which a program is recorded (for example, an optical disc, magneto-optical disc, CD-ROM, CD-R, CD-RW, magnetic tape, hard disk, or memory card).

[0090] Furthermore, the implementation form of the program is not limited to application programs such as object code compiled by a compiler or program code executed by an interpreter, but may also be in the form of a program module embedded in an operating system. In addition, the program may or may not be configured so that all processing is performed only on the CPU on the control board. The program may also be configured so that some or all of its processing is performed by another processing unit implemented on an expansion board or expansion unit attached to the board, as needed.

[0091] The diagrams illustrating the embodiments described herein are schematic. Dimensions and proportions shown in the drawings do not necessarily correspond to actual dimensions.

[0092] While embodiments relating to this disclosure have been described based on the drawings and examples, it should be noted that those skilled in the art can make various modifications or alterations based on this disclosure. Therefore, it should be noted that these modifications or alterations are within the scope of this disclosure. For example, the functions and other elements included in each component can be rearranged in a logically consistent manner, and multiple components can be combined into one or separated.

[0093] All of the constituent elements described in this disclosure, and / or all of the disclosed methods or steps of processing, can be combined in any combination except for any combination in which these features are mutually exclusive. Furthermore, each of the features described in this disclosure can be replaced by an alternative feature that works for the same, equivalent, or similar purposes, unless expressly disregarded. Thus, unless expressly disregarded, each of the disclosed features is merely an example of a comprehensive set of identical or equivalent features.

[0094] Furthermore, the embodiments relating to this disclosure are not limited to any specific configuration of the embodiments described above. The embodiments relating to this disclosure can be extended to all novel features or combinations thereof described herein, or all novel methods or processing steps or combinations thereof described herein.

[0095] In this disclosure, the designations "First," "Second," etc., are identifiers used to distinguish the configurations. Configurations distinguished by the designations "First," "Second," etc., in this disclosure may have their numbers swapped. For example, the first information processing device may swap the identifiers "First" and "Second" with those of the second information processing device. The swapping of identifiers occurs simultaneously. The configurations remain distinguishable even after the swapping of identifiers. Identifiers may be deleted. Configurations from which identifiers have been deleted are distinguished by codes. The designations "First," "Second," etc., in this disclosure should not be used alone to interpret the order of the configurations or to justify the existence of smaller numbered identifiers. [Explanation of Symbols]

[0096] 10. First Information Processing Device 11 Power Management System 12. Second Information Processing Device 13. Third Information Processing Device 14. The fourth information processing device 15 Network 16 Power source 17 Electricity demand area 18 Power transmission and distribution network 19. Power supply and demand system 20. First power source 21. Primary electricity demand area 22 Second largest electricity demand area 23 Communications Department 24 controllers 25 Communications Department 26 Controllers

Claims

1. A controller that calculates a first predicted value of the amount of electricity generated by all power sources that generate electricity from renewable energy sources under management, based on weather forecast information, calculates a second predicted value by subtracting the estimation error from the first predicted value, calculates a third predicted value of the amount of electricity used at least one first power demand site to which electricity is supplied by the power sources through self-transmission, based on environmental information of the at least one first power demand site, calculates a fourth predicted value of the amount of electricity to be supplied to the at least one first power demand site by all power sources based on the third predicted value, calculates a first planned power supply value by accumulating the fourth predicted value in the time periods in which the second predicted value exceeds the fourth predicted value within a plurality of time periods included in a unit time, and calculates the amount of electricity to be supplied to the first power demand site based on the first planned power supply value, The system includes a communication unit that transmits the first planned power supply value and the first planned power demand value as information. The first information processing device.

2. In the first information processing apparatus according to claim 1, The controller calculates the fourth predicted value by dividing the third predicted value by the value obtained by subtracting the transmission loss rate between the power source and the first power demand site from 1. The first information processing device.

3. In the first information processing apparatus according to claim 1 or 2, The controller calculates a fifth predicted value obtained by subtracting the fourth predicted value from the first predicted value as the second planned power supply value, and calculates a second planned power demand value to be supplied to at least one second power demand location from which power is supplied from the power source by sale, based on the second planned power supply value. The communication unit transmits the second planned power supply value and the second planned power demand value as information. The first information processing device.

4. In the first information processing apparatus according to claim 3, The controller associates environmental value information with a third actual value obtained by subtracting a second actual value, which is obtained by dividing the amount of electricity actually consumed by at least one first power demand site by the transmission loss rate between the power source and the first power demand site minus 1, from a first actual value of the amount of electricity actually generated by all the power sources. The communication unit transmits the environmental value information. The first information processing device.

5. In the first information processing apparatus according to claim 1 or 2, The aforementioned at least one first power demand site includes a plurality of first power demand sites, The third predicted value is the sum of the predicted values ​​of the amount of electricity used in each of the plurality of first electricity demand locations. The fourth predicted value is the sum of predicted values ​​of the amount of electricity to be supplied from the power source to each of the multiple first power demand sites, based on predicted values ​​of the amount of electricity used at each of the multiple first power demand sites. The first information processing device.

6. A communication unit that receives the first predicted value and the fourth predicted value as information from the first information processing device described in claim 1 or 2, The system includes a controller that calculates a fifth predicted value obtained by subtracting the fourth predicted value from the first predicted value as a second planned power supply value, calculates a second planned power demand value to be supplied to at least one second power demand location from which power is supplied by the power source through sales, based on the second planned power supply value, and transmits the second planned power supply value and the second planned power demand value as information to the communication unit. The second information processing device.

7. Based on weather forecast information, the first predicted value of the amount of electricity generated by all power sources that use renewable energy under management is calculated. A second predicted value is calculated by subtracting the estimation error from the first predicted value. A third predicted value of the amount of electricity used at at least one first power demand site, which is supplied with electricity from all power sources by self-transmission, is calculated based on environmental information of the at least one first power demand site. Based on the third predicted value, a fourth predicted value is calculated for the amount of electricity to be supplied to the at least one first power demand site from all power sources. The first planned power supply value is calculated by accumulating the fourth predicted value over a unit time that includes multiple such time periods during the time period in which the second predicted value exceeds the fourth predicted value. Based on the first planned power supply amount, the amount of electricity supplied to the first power demand area is calculated as the first planned power demand amount. The first planned power supply value and the first planned power demand value are transmitted as information. Information processing methods.

8. The first predicted value of the amount of electricity generated by all power sources that are managed using renewable energy is calculated based on weather forecast information, The process involves calculating a second predicted value obtained by subtracting the estimation error from the first predicted value, A third predicted value of the amount of electricity used at at least one first power demand site, which is supplied with electricity from all power sources by self-transmission, is calculated based on environmental information of the at least one first power demand site. Based on the third predicted value, a fourth predicted value of the amount of electricity to be supplied to the at least one first power demand site from all power sources is calculated, The first planned power supply value is calculated by accumulating the fourth predicted value over a unit time that includes multiple such time periods during the time period in which the second predicted value exceeds the fourth predicted value, Based on the first planned power supply amount, the amount of electricity supplied to the first power demand area is calculated as the first planned power demand amount, The computer is made to perform an operation that includes transmitting the first planned power supply value and the first planned power demand value as information. program.

Citation Information

Patent Citations

  • Generation power controller of self-consignment system

    JP2005261056A

  • Power storage facility management device and power storage facility management method

    JP2020058141A

  • Self consignment system and self consignment method

    JP2021052557A

  • Power control system and power control apparatus

    JP2023095550A