Method of installing a passenger conveyer in a building and working method of constructing the building
Patent Information
- Application Number
- MYPI1998002043
- Authority / Receiving Office
- MY · MY
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 1998-05-07
- Publication Date
- 1998-11-12
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The conventional method of installing passenger conveyers like escalators in buildings is often delayed due to the progress of construction work, leading to extended installation times and impacting overall building construction timelines.
Assembling a passenger conveyer unit with step treads, a driving mechanism, and landing platforms within a main frame structure, which is then covered and transported through a building's ceiling opening during construction, allowing for early installation and use as a construction staircase, thus decoupling installation from construction progress.
This approach significantly reduces the installation time of passenger conveyers and shortens the overall building construction period by enabling the use of installed conveyers as construction staircases, improving construction efficiency.
Abstract
Description
TITLE OF THE INVENTIONMethod of installing a passenger conveyer in a building and working method of constructing the buildingBACKGROUND OF THE INVENTIONField of the InventionThe present invention relates to a method of installing a passenger conveyer such as an escalator or a moving pathway in a building, and particularly to a method of installing a passenger conveyer in a building under construction and a working method of constructing a building using the same.Description of the Related ArtIn most cases, a passenger conveyer is arranged almost in an inner central portion of a building.Therefore, a main frame structure of the passenger conveyer is installed in synchronism with progress of the construction of the building, and step treads and handrails are assembled in the main frame structure after completion of the main construction work of the building.Since the conventional method of installing a passenger conveyer described above is influenced by progress of the construction work of the building, there has been a problem in that the term of installation work becomes long.JP-A 53-101811 discloses a method of installing a passenger conveyer in a building, in which an escalator, which is already assembled in a unit, is installed in a completed building using a beam of the building.However, the aforesaid prior publication has no description on when and how the escalator is carried in the building, and hence the term of installation work of the escalator is not taken into consideration.SUMMARY OF THE INVENTIONAn object of the present invention is to provide a method of installing a passenger conveyer in a building, which is not influenced by progress of construction of the building, whereby the term of the installation work can be shortened.Another object of the present invention is to provide a constructing method of a building that much improves the building construction work, whereby the term of the construction work can be shortened.The aforesaid object can be attained by a method of installing a passenger conveyer in a building, wherein a passenger conveyer unit having at least step treads, a driving mechanism and landing platforms assembled in a main frame structure is covered by protecting material, which is carried through an opening provided in a ceiling of a building under construction and installed therein and the thus installed passenger conveyer is used as a staircase for construction work.With the above mentioned method, a nearly completed passenger conveyer can be installed within the construction term of a building, and the installed passenger conveyer can be used as a staircase for construction work of the building. Therefore, the installation term of the passenger conveyer can be shortened and the construction term of the building can be also shortened.BRIEF DESCRIPTION OF THE DRAWINGSFIG. 1 is a process diagram showing a method of installing a passenger conveyer according to an embodiment of the present invention;FIG. 2 shows a perspective view schematically showing an escalator before being carried in a building;FIG. 3 shows a cross sectional view of the escalator as shown in FIG. 2;FIG. 4 shows a perspective view of an inlet / outlet portion of a moving handrail in the escalator as shown in FIG. 2;FIG. 5 shows a perspective view showing an end portion of a main frame structure of the escalator as shown in FIG. 2;FIG. 6 shows a cross sectional view of the escalator of FIG. 2, which is covered by protective material for transportation and installation work;FIG. 7 shows a view showing the state of a transportation of a protected escalator by a trailer;FIG. 8 shows a view showing the state that an escalator is lifted up from the trailer and installed in accordance with the present invention;FIG. 9 shows a front view of the state as shown inFIG. 8;FIG. 10 shows the state that the escalator is lifted down and carried in a building by the installing method in accordance with the present invention;FIG. 11 shows a front view of the state as shown inFIG. 10; andFIG. 12 shows the state that escalators are completely installed in a building by the installing method in accordance with the present invention.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTSIn the following, an embodiment of the present invention will be described, referring to the accompanying drawings. The following description will be made, taking an escalator having an inclination angle of 30 degrees as an example of a passenger conveyer.As shown in figs. 2 and 3, escalator E is generally constructed as follows. First of all, main frame structure 1 is installed between an upper floor and a lower floor of a building. Various constituent parts necessary for the escalator are mounted on the main frame structure 1. The main frame structure 1 is composed of an upper horizontal frame 1A, a lower horizontal frame IB and a middle inclined frame 1C.Each of these frames 1A, IB, 1C is composed of a pair of side frames 2A, 2B and connecting members 3 for connecting them. The outside of the pair of side frames 2A, 2B are covered by outer panels 4A, 4B, and there is provided bottom plate 5 between lower ends of the side frames 2A, 2B of the main frame structure 1.At the end portions of, and integrally with the upper horizontal frame 1A and the lower horizontal frame IB of the main frame structure 1, support frames 6A, 6B are provided, respectively, to engage with beams in the upper floor and the lower floor of the building. Further, landing platforms 7A, 7B are detachably provided to the upper portions of the upper horizontal frame 1A and the lower horizontal frame IB, respectively.In the main frame structure 1 constructed as described above, a plurality of step treads 8, 8R linked by endless chains 9A, 9B are guided so as to circulate between the both landing platforms 7A, 7B. The step treads 8 move on the going side, and the step treads 8R turn over under the landing platforms 7A, 7B and move on the coming side.Each of the step treads 8, 8R runs on guide rails 12A, 12B and 13A, 13B provided in the main frame structure by a pair of right and left front wheels 10A, 10B and a pair of right and left rear wheels 11A, 11B. Further, all these four wheels are coupled to the chains 9A, 9B. The chains 9A, 9B are extended between sprockets (not shown) arranged under the landing platforms 7A, 7B. One of the sprockets is driven by a well-known drive unit. The drive unit, the sprockets and the chains 9A, 9B form a drive mechanism of the step treads 8, 8R.In the upper portion of the right and left side frames 2A, 2B, a pair of right and left handrails BL are arranged in a moving direction of the step treads. The handrails BL are composed of handrail panels 14A, 14B, outer decks 15A, 15B, inner decks 16A, 16B and skirt guards 17A, 17B.The handrail panels 14A, 14B are fixed by appropriate fixing member on the upper portion of the right and left side frames 2A, 2B in a moving direction of the step treads. The outer decks 15A, 15B provide the covering between the outer bottom portions of the handrail panels 14A, 14B and the upper portion of the outer panels 4A, 4B. The inner decks 16a, 16B cover the inner bottom portions of the handrail panels 14A, 14B. The skirt guards 17A, 17B are vertically fixed on appropriate immovable members within the main frame structure 1 to provide parting between the ends of the inner decks 16A, 16B and the side ends of each of the step treads 8.Moving handrails 18A, 18B are guided around the panels 14A, 14B of the handrail BL constructed as described above and move in synchronism with the step treads 8, 8R.In addition, although not shown, there are provided in the main frame structure 1 a handrail drive unit for driving the moving handrails 18A, 18B by obtaining power from the drive mechanism for the step treads 8, 8R, various kinds of safety units, control units, oil supply units, electric cables thereof, and so on.The escalator E as mentioned above is assembled in a factory and transported to an installation site after necessary inspections.In general, after the inspection, the escalator E is once disassembled into parts having size easily to be transported and carried in the installation site. The escalator E carried in is reassembled part by part in synchronism with progress of construction state of the building. Otherwise, after the construction of the building, the escalator E is reassembled without rest.In the present invention, however, an escalator E as it is, without any disassembling, is transported and installed in a building after completion of the inspections thereof.In the following, description will be done of processes from transportation to installation of an escalator E, after completion of the inspections, referring to FIG.l.[First Process] (1) Manufacturing processVarious parts necessary for an escalator E are manufactured in a manufacturing factory.(2) Assembling processThe parts manufactured in the manufacturing factory are gathered in an assembling factory, where the escalatorE is assembled in a state where the main frame structure 1 is horizontally laid as shown by the two-dot-dash line in FIG. 2, or in a state where the main frame structure 1 is inclined in the same angle of 30 degrees as the installation angle of the escalator. After assembly, various adjustments are performed.(3) Inspection processElectrical and mechanical inspections of the assembled escalator E are performed in the assembling factory.[Second Process] (4) Covering process with protective materialAfter completion of the inspections, the outer plates 4A, 4B and the bottom plate 5 are detached from the escalator E, and further, as shown in FIG. 4, the outer skirt guard 19, which is projected in the lateral direction near a gate for the moving handrail 18B, is detached from the side frame 2B (the side frame 2A is not shown in FIG. 4, however the same as mentioned above can also be applied thereto).The reason why the outer skirt guards 19 is detached is to prevent breakage of the outer skirt guard caused by contact with the surroundings of the building floor during a carry ing-'in process to be described later. Therefore, this is an important measure.Next, as shown in FIG. 5, auxiliary member 20 for transportation is fixed by bolts 21 to the support frames 6A, 6B of the upper and lower horizontal frames 1A, IB. Metal hook fittings 22 having a lope hole are attached by welding to the auxiliary member 20.After an escalator unit suitable for transportation is completed by detaching obstacles to transportation from an escalator E and by attaching the auxiliary members 20 for transportation thereto, the escalator unit is covered with hard protective members 23 to 27 such as plywood plates, which are fixed by adhesive tapes.The escalator unit to be covered for protection includes step surfaces of the step treads 8, on which passengers stand, the landing platforms 7A, 7B (FIG. 2), the upper surfaces of the outer decks 15A, 15B, the upper surfaces of the inner decks 16A, 16B, the upper surfaces of the moving handrails 18A, 18B, and the vicinity thereof.Thereafter, the step treads 8, which then appear on the going side, are covered with sheet protective member 28 in a stairs-shape so as to meet the shapes of the step surfaces and risers of the step tread. Further, the inner and the outer sides of the handrail BL including the moving handrails 18A, 18B are covered with sheet protective members 29, and the outer sides of the side frames 2A, 2B are also covered with sheet protective member 30. Waterproof and flameproof processed sheets are used for the sheet protective members 28 to 30 to protect the escalator from rain and snow during carrying process to be described later and to make the escalator withstand sparks caused by welding work during construction work around the escalator installed in the building.[Third Process] (5) Transportation processAs shown in FIG. 7, the escalator E protected as above is loaded on a trailer truck composed of power car 31 and load-carrying platform 32 trailed by the power car 31 to be transported to the installation site.The trailer truck travels on a common road to the installation site. However, since there are heightlimited sections such as pedestrian overpasses and tunnels in the common road, it is necessary that the escalator E is transported by lowering its height as low as possible.Firstly, in the present invention, therefore, the escalator E is loaded such that the lower horizontal frameIB of the escalator E faces the power car 31 and the upper horizontal frame 1A overhangs from the rear end 32E of the load-carrying platform 32.By loading the escalator E such that the lower horizontal frame IB of the escalator E faces the power car 31 as described above, an upper terminal portion BLa of the handrail BL is prevented to be raised up extremely high compared to the height of a lower terminal portion BLb thereof, and the height H from the ground level to the highest portion of the loaded escalator E can be reduced.Secondary, supporting stands 33A, 33B are interposed between the main frame structure 1 of the escalator E and the load-carrying platform 32 to raise the side of the upper horizontal frame 1A of the escalator E.Thereby, the height of the upper terminal portion BLa of the handrail BL from the ground level can be made equal to the height H of the lower terminal portion BLb thereof from the ground level. As a result, one of the sides of the upper terminal portion BLa and the lower terminal portion BLb does not extremely project from the other, whereby the total height H can be further lowered. [Fourth Process] (6) Carrying-in processThe trailer, which loads the escalator E as described above, travels to the building 34 under construction, in which the escalator is installed, and stopped beside it, as shown in FIGs. 8 and 9.The building 34 having plural floors 36 (or ceilings) is provided with opening 35 at each floor near the location thereof, at which the escalators E are to be installed. In general, the openings 36 for installing the escalator E are provided so as to overlap with each other over the plural stories almost near the center portion of the building 34. In floor (or ceiling) 36T (FIG. 9) of the highest story of the building 34, there is placed crane 37 for lifting up and down construction materials.The crane 37 is moved so that hook 38 is brought in the center position of the escalator E loaded on the trailer, and the hook 38 is lowered down so as to approach to the escalator E.Next, suspending lopes 39, 40 are made to pass through the lope holes of the hook metal fittings 22 of the auxiliary member 20 for transportation, which are hung at hooks 36. The suspending lope 39 has a certain length, and the suspending lope 40 is longer than the lope 39.The length of the lope 40 can be varied by lope length adjuster 41.Then, the hook 36 is once moved up to suspend the escalator E in a floating state from the trailer by operating the crane 37. With this floating state kept, an angle Θ of suspending the escalator E is determined by adjusting the length of the lope 40 using the adjuster 41. The suspending angle Θ is such an angle that the escalator E can be lifted down through the openings 35 without any contact of the auxiliary member 20 at the ends of the escalator E with the opening 35T provided in the floor 36T of the uppermost story of the building 34. This angle is larger than the usual installation angle of 30 degrees of the escalator.After the suspending angle Θ is determined, the escalator E is lifted up by operating the crane 37, and moved to a position just above the opening 35T provided in the floor 36T of the uppermost story. Then, the escalator E is lifted down to the lowermost portion of the installed position, as shown in FIGs. 10 and 11. Therein, since the escalator E is suspended with the suspending angle Θ larger than the usual installation angle of 30 degrees, the length Wa of the escalator when seeing from the top side is shorter than the lateral length W of each of the openings 35. Therefore, the periphery of each of the openings 34 does not become an obstacle, when the escalator E is lifted down.(7) Installation processAs the escalator E is lifted down to the desired position, the installation angle is adjusted to an appropriate value by using the adjuster 41 to vary the suspending angle of the escalator E, and the support frames 6A, 6B are engaged with beams in the periphery of the opening 35 of the building 34. Then, the lopes 39, 40 are released, and the installation of the escalator E-l is completed.By successively repeating the above mentioned working, the escalators E-2, E-3 are installed.Further, when the construction of the building 34 is progressed and a certain number of stories are further added upward, further escalators are installed by performing the above mentioned working corresponding to the number of the newly added floors.The thus installed escalators E-l, E-2, E-3 are still covered with the protective members 23 to 27, 28 to 30. However, such protective members do not need to be removed soon after completion of installation of the escalators to the building 34. That is, even if the installation of the escalators is completed, or even if the exterior structure of the building 34 is completed in synchronism with the installation of the escalators, works of furnishing the interior still remain and therefore the building 34 can still be under construction, as a whole. Therefore, the protective members, which are not yet removed, serves to prevent the escalators from being stained and damaged during such works.Further, stairs exclusively for the purpose of works are usually arranged in corner portions of the building. Therefore, there was such inconvenience that workers working in the building need to walk to the corner of the building to move between floors.According to the present invention, however, since the escalators E-l, E-2, E-3 installed in the center portions of the building and covered with the protective members 23 to 30 may be used as stairs for construction works, the workers can move between floors in the center portion of the building during working, and accordingly the efficiency of working can be improved.Furthermore, when work is done around the escalators E-l, E-2, E-3, scaffolding can be set up by making use of the escalators E-l, E-2, E-3 covered with the protective members 23 to 30. Therefore, there is no need to set up such scaffolding as closes the openings 34. In view of this point, the construction works can be simplified. [Fifth Process] (8) Protective member removing process (9) Final inspection processWhen the construction work and the interior finishing work of the building 34 are completed or nearly completed, the protective members 23 to 30 are removed from the escalator E, and various kinds of final inspections and adjustments are performed. Further, the outer plates 4A, 4B, the bottom plate 5 and the outer skirt guards 19, which have been detached before transportation, are attached again, and a gap between the escalator E and the opening 35 is closed. Thus, the installation work is completed.After completion of the above mentioned work, finally the whole escalator E is cleaned and made available for passengers.According to the embodiment of the present invention, as described above, since an escalator can be transported in an assembled state from a factory and installed in a building under construction, installation of the escalator can be performed without being influenced by progress of the construction work of the building. Accordingly, the actual term of work installing an escalator can be shortened.Further, since escalators installed in the center portions of a building under construction may be used as stairs for construction works of workers, the efficiency of the construction works can be improved, whereby the construction term of a building can be shortened.In addition to the above, since during transportation of an escalator, it is loaded such that the upper horizontal frame 1A overhangs from the rear end 32E of the load-carrying platform 32, the height of the thus loaded escalator can be reduced, and accordingly transportation of the escalator with sufficient allowance can be realized.In the above mentioned embodiment, the escalator E is assembled in the factory, and can be transported beside the building 34 as an installation site in the assembled state without disassembling after inspections. Then, the escalator is carried in the building 34 through the opening 35 provided in the floor (or ceiling) 36 of the building.However, there are some cases where an escalator cannot be transported in the state of one unit due to transportation problem by all means. Such cases occur in a long span escalator having a long main frame structure, an escalator with special specification and so on.In such cases, it is preferable to do the works in accordance with disassembling process (10), carrying-out process (5'), reassembling process (2') and protecting process, instead of the path of protecting process (4) and carrying-out process (5). In other words, the escalator E is once disassembled after inspections (disassembling process (10)). The disassembled escalator E is transported to an appropriate location, such as a location near an installation site of a building, a construction yard, if it has a sufficient space, a ceiling of a building under construction, if such yard has no sufficient space, or to a warehouse, if there is such near the construction site (carrying-out process (5’)).Then, the escalator E is reassembled (reassembling process (2')) and the protecting process (4') is performed in the location near the installation site, on the ceiling or in the warehouse. Then, the works are prepared for the Fourth and the Fifth Processes.The escalator E reassembled in the installation site or in the warehouse is transported beside the building 34 under construction. The transported escalator E or the escalator E reassembled on the ceiling of the building 34 is lifted up using the crane 37 with a desired angle and lifted down inside the building through the opening 35T.Further, the object of the present invention, as already mentioned before, can be attained by another embodiment in accordance with the present invention as described hereinbelow.The above mentioned protecting process shows an example that the protection work is performed to an escalator in the state in which the moving handrails 18A, 18B are guided in the peripheries of the handrails 14A, 14B. However, if there is fear that the moving handrails 18A, 18B of rubber products are damaged in progress of the construction work of a building, the protection work may be performed by removing the moving handrails 18A, 18B.In this case, the moving handrails 18A, 18B may be attached during the protective member removing process.Further, an escalator unit can be formed in such a manner that at least the plural step treads 8 endlesslylinked and the drive mechanism are assembled within the main frame structure 1 of the escalator, to which the landing platforms 7A, 7B are attached. The thus 'constructed escalator unit is covered by protective material and thereafter can be carried in a building through an opening provided in a ceiling.It might be thought that the drive mechanism is not necessary to be assembled in the escalator unit as mentioned above. However, in order that such escalator unit can be used as a stairs for construction works, portions of the landing platforms 7A, 7B are necessary to be closed for safety of workers. If the portions of the landing platforms 7A, 7B are closed, it is preferred to assemble the drive mechanism therein in advance.Even if such a semifinished escalator is installed, remaining constituent parts are small and rather insignificant ones and in addition, they can be attached to the escalator unit by making use of already aligned parts as the reference. Therefore, such works become simple.In each of the above mentioned embodiments, description has been made of an example, in which an escalator as a passenger conveyor is installed in a building. However, the application of the present invention is not limited to the escalator. There is no need to say that the present invention can be applied to an inclined moving path having the smaller inclination angle than an escalator or to a moving path horizontally installed within a building.
Claims
1. A method of installing a passenger conveyer, characterised by: covering with a protective member (23 - 27; 28 - 30) a passenger 5 conveyer unit, in which at least step treads (8, 8R) and landing platforms (7A, 7B) are assembled in a main frame structure (1); and carrying in the thus covered passenger conveyer unit in a building (34) under construction through an opening (35) provided at a ceiling of the building which position corresponds to a position where the passenger io conveyer is to be installed and installing the passenger conveyer unit in the building.
2. A method of installing a passenger conveyer in a building, characterised by: assembling a passenger conveyer outside the building (34) under 15 construction, in which the passenger conveyer is to be installed; covering the assembled passenger conveyer with a protective member (23 -27; 28-30); carrying the passenger conveyer covered with the protective member (23 - 27; 28 - 30) in the building (34) under construction through an opening 20 (35) provided at a ceiling of the building which position corresponds to a position where the passenger conveyer is to be installed and installing the passenger conveyer in the building; and removing the protective member (23 - 27; 28 - 30) from the installed passenger conveyer after completion of construction of the building (34). -223. A method of installing a passenger conveyer in a building, characterised by: forming a semi-finished passenger conveyer unit, in which at least a 5 plurality of step treads (8, 8R) and landing platforms (7A, 7B) are assembled in a main frame structure (1) of a passenger conveyer unit; covering the passenger conveyer unit with a protective member (23 - 27; 28-30); installing the passenger conveyer unit covered with the protective member io (23 - 27; 28 - 30) at a predetermined position in a building (34) under construction after carrying in the passenger conveyer unit through an opening (35) provided at a ceiling of the building which position corresponds to a position where the passenger conveyer is to be installed; and 15 removing the protective member (23 - 27; 28 - 30) from the installed passenger conveyer unit when remaining constituent parts are assembled in the passenger conveyer unit.
4. A method of installing a passenger conveyer in a building, characterised by: 20 assembling a passenger conveyer in a factory; covering the assembled passenger conveyer with a protective member (23 - 27; 28 - 30) and attaching auxiliary members (20) for transportation to the passenger conveyer; -23transporting the passenger conveyer covered with the protective member (23 - 27; 28 - 30) to a building (34) under construction, in which the passenger conveyer is to be installed;5 lifting up the transported passenger conveyer outside the building (34) and lifting down the passenger conveyer in an installation site through an opening (35) provided at a ceiling of the building which position corresponds to a position where the passenger conveyer is to be installed; installing the lifted-down passenger conveyer at a predetermined position io and removing the auxiliary members (20) for transportation; and removing the protective member (23 - 27; 28 - 30) from the installed passenger conveyer after completion of construction of the building (34).
5. A method of transporting a passenger conveyer, wherein when a 15 passenger conveyer unit having at least a plurality of step treads (8, 8R) and landing platforms (7A, 7B) assembled in a main frame structure (1) of the passenger conveyer unit is transported, a trailer truck is loaded with the passenger conveyer unit such that an upper horizontal portion (1A) of said main frame structure (1) is overhung downward from a rear end (32E) 20 of a load-carrying platform (32) of the trailer truck.
6. A method of transporting a passenger conveyer, wherein when a passenger conveyer having step treads (8, 8R) and handrails (BL) assembled in a main frame structure (1) is transported, a trailer truck is loaded with the passenger conveyer such that an upper horizontal portion 25 (1A) of said main frame structure (1) is overhung downward from a rear end (32E) ofa load-carrying platform (32) of the trailer truck and the height of the handrails (BL) on the upper floor side from the ground level is made equal to the height of handrails (BL) on the lower floor side from the ground level. -247. A method of carrying a passenger conveyer in a building, characterised by: lifting up the passenger conveyer assembled with step treads (8, 8R) and 5 handrails (BL) assembled in a main frame structure (1) from a loadcarrying platform (32) of a trailer truck by means of a crane (37); in such a state, adjusting an angle of suspending the passenger conveyer so that the angle becomes larger than an angle of the passenger conveyer being actually installed in the building (34); and io further lifting up the passenger conveyer on the outside of the building (34) and then lifting down the passenger conveyer into the building through an opening (35) provided at a ceiling of the building which position corresponds to a position where the passenger conveyer is to be installed.