Marine LNG fuel tank container system

MYPI2025001737A0Undetermined Publication Date: 2024-05-11CRRC YANGTZE CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
MYPI2025001737
Authority / Receiving Office
MY · MY
Patent Type
Applications
Current Assignee / Owner
Priority Date
2022-11-11
Filing Date
2023-05-11
Publication Date
2024-05-11

AI Technical Summary

Technical Problem

The filling process of existing LNG fuel tank containers is difficult to connect, the pipelines are long, the liquid source is wasted, and the filling time is long.

Method used

A marine LNG fuel tank system is designed, including a detachable tank component, a filling gasification skid and a separated pipeline component, which allows the tank component and the pipeline component to be separated, disassembled and reconnected to achieve rapid replacement and Liquid filled.

Benefits of technology

Through this system, ships can quickly complete fuel replacement when docking without waiting for refueling, which improves the speed and efficiency of fuel supply.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure PI2025001737_DRAWING_001
    Figure PI2025001737_DRAWING_001
  • Figure PI2025001737_DRAWING_002
    Figure PI2025001737_DRAWING_002
Patent Text Reader

Abstract

A marine LNG fuel tank container system comprises: a tank container assembly (1) detachably disposed on a ship body; a refueling and gasification apparatus (2) disposed on the ship body; and a pipeline assembly (3), an end of which is detachably in communication with the tank container assembly (1) and another end of which is in communication with the refueling and gasification apparatus (2). Fig 1.
Need to check novelty before this filing date? Find Prior Art

Description

A marine LNG fuel tank system

[0001] CROSS-REFERENCE TO RELATED APPLICATIONS

[0002] This application claims priority to Chinese patent application No. 202211412067.7 filed on November 11, 2022, the entire contents of which are incorporated herein by reference. Technical Field

[0003] The present disclosure relates to the technical field of LNG fuel storage, and in particular to a marine LNG fuel tank system. Background Art

[0004] The development of LNG (Liquefied Natural Gas) powered ships has not seen any breakthroughs in more than a decade. Newly built or renovated ships have been out of service for a long time, mainly due to the supply of LNG fuel.

[0005] In existing technology, LNG fuel tank containers are fixed to ships. To refuel, they must dock at a dedicated coastal gas station or floating refueling pontoon. After connecting the filling pipeline through the above infrastructure equipment, LNG fuel can be refueled. However, this makes the LNG fuel tank container refueling process difficult to connect, the pipeline is long, the liquid source is wasted, and the filling time is long.

[0006] Summary of the Invention

[0007] The embodiments of the present disclosure provide a marine LNG fuel tank system, which solves or partially solves the technical problems in the prior art of LNG fuel tank containers, such as difficulty in docking during the filling process, long pipelines, large waste of liquid resources, and long filling time.

[0008] According to the present disclosure, a marine LNG fuel tank system is provided, comprising: a tank assembly detachably mounted on a ship hull; a filling and gasification skid mounted on the hull; and a pipeline assembly, one end of which is detachably connected to the tank assembly and the other end of which is connected to the filling and gasification skid. BRIEF DESCRIPTION OF THE DRAWINGS

[0009] To more clearly illustrate the technical solutions in the embodiments of the present disclosure, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present disclosure, and those skilled in the art can derive other drawings based on these drawings without inventive effort.

[0010] In order to more completely understand the present disclosure and its beneficial effects, the following description will be given in conjunction with the accompanying drawings. In the following description, the same reference numerals represent the same parts.

[0011] FIG1 is a schematic structural diagram of a marine LNG fuel tank system according to some embodiments of the present disclosure; and

[0012] FIG2 is a process flow diagram of the marine LNG fuel tank system in FIG1 . DETAILED DESCRIPTION

[0013] The following will be combined with the accompanying drawings in the embodiments of the present disclosure to clearly and completely describe the technical solutions in the embodiments of the present disclosure. Obviously, the embodiments described are only part of the embodiments of the present disclosure, not all of the embodiments. Based on the embodiments of the present disclosure, all other embodiments obtained by those skilled in the art without making any creative efforts are within the scope of protection of the present disclosure.

[0014] Figure 1 is a schematic structural diagram of a marine LNG fuel tank system according to some embodiments of the present disclosure. As shown in Figure 1, a marine LNG fuel tank system according to an embodiment of the present disclosure includes: a tank assembly 1, detachably mounted on the ship's hull; a charging and gasification skid 2, mounted on the hull; and a piping assembly 3, one end of which is detachably connected to the tank assembly 1 and the other end of which is connected to the charging and gasification skid 2.

[0015] The pipeline assembly 3 is detachably connected to the charging and gasification skid 2, so that the pipeline assembly 3 can be easily replaced when damaged.

[0016] Because the tank assembly 1 is detachably mounted on the ship's hull, and the filling and gasification skid 2 is also mounted on the ship's hull, one end of the pipeline assembly 3 is detachably connected to the tank assembly 1, while the other end is connected to the tank assembly 1. Therefore, when the LNG fuel in the tank assembly 1 is exhausted, the pipeline assembly 3 can be removed from the tank assembly 1 and the tank assembly 1 can be hoisted away. The tank assembly 1, now filled with LNG fuel, is then hoisted onto the ship's hull, and the pipeline assembly 3 is connected to the tank assembly 1, allowing the LNG fuel to be delivered to the filling and gasification skid 2. The filling and gasification skid 2 delivers the LNG fuel to the equipment requiring it, allowing for refueling operations while the ship is docked and unloading, eliminating the need for waiting for refueling and ensuring a fast fuel supply.

[0017] In some embodiments, the tank container assembly 1 may not be lifted off the hull, but LNG fuel may be directly filled into the tank container assembly 1 through the filling and gasification skid 2 and the pipeline assembly 3 .

[0018] Figure 2 is a process flow diagram of the marine LNG fuel tank system in Figure 1. As shown in Figure 2, in some embodiments, the tank assembly 1 may include: a hoisting frame 1-1, a tank body 1-2, a cold box 1-3, a first gas phase pipe 1-4, a first delivery pipe 1-5, a second delivery pipe 1-6, and a third delivery pipe 1-7.

[0019] The tank body 1-2 can be arranged in the hoisting frame 1-1, and the tank body 1-2 can be supported by the hoisting frame 1-1. In some embodiments, the tank body 1-2 can be made of double-layer stainless steel to achieve high vacuum multi-layer insulation for storing LNG fuel.

[0020] The cold box 1-3 can be arranged in the hoisting frame 1-1 and connected to the tank body 1-2. The cold box 1-3 is provided with a first interface 1-31, a second interface 1-32 and a third interface 1-33 connected to the pipeline assembly 3, and the cold box 1-3 is supported by the hoisting frame 1-1.

[0021] The first gas phase pipe 1-4 can be arranged in the cold box 1-3 and communicate with the top of the tank body 1-2 and the first interface 1-31.

[0022] The first delivery pipe 1-5 can be arranged in the cold box 1-3, one end of the first delivery pipe 1-5 is connected to the top of the tank body 1-2, and the other end is connected to the bottom of the tank body 1-2.

[0023] The second delivery pipe 1-6 can be arranged in the cold box 1-3 and communicate with the first delivery pipe 1-5 and the second interface 1-32.

[0024] The third delivery pipe 1-7 can be provided in the cold box 1-3 and communicated with the bottom of the tank body 1-2 and the third interface 1-33. The third delivery pipe 1-7 is provided with a second temperature detector for detecting the temperature of the delivered LNG fuel.

[0025] In some embodiments, when gas is required, LNG fuel is delivered from the bottom of the tank 1-2 via the first delivery pipe 1-5, the second delivery pipe 1-6, the second port 1-32, and the pipeline assembly 3 to the filling and gasification skid 2. The filling and gasification skid 2 vaporizes the LNG fuel. The fuel is then delivered into the tank 1-2 via the pipeline assembly 3, the first port 1-31, and the first gas phase pipe 1-4, ensuring that the pressure within the tank 1-2 meets the required pressure. LNG fuel is delivered from the bottom of the tank 1-2 via the third delivery pipe 1-7, the third port 1-33, and the pipeline assembly 3 to the filling and gasification skid 2. The filling and gasification skid 2 vaporizes the LNG fuel and delivers it to the ship's equipment requiring fuel.

[0026] In some embodiments, when the LNG fuel in the tank body 1-2 is used up, it is removed from the hull and transported to the onshore filling station, and LNG fuel is added to the tank body 1-2 through the second interface 1-32, the second delivery pipe 1-6 and the first delivery pipe 1-5. At this time, the external boosting equipment boosts the tank body 1-2 through the third interface 1-33 and the third delivery pipe 1-7.

[0027] In some embodiments, the cold box 1-3 can accommodate the first gas phase pipe 1-4, the first delivery pipe 1-5, the second delivery pipe 1-6 and the third delivery pipe 1-7, which can prevent the leaked LNG fuel from causing low-temperature damage to the tank body 1-2. At the same time, it can also prevent the leaked LNG fuel from spreading on the ship to ensure safety.

[0028] In some embodiments, the cold box 1-3 may be provided with a first vent 1-34, a first purge port 1-35, and a first sewage outlet 1-36.

[0029] The tank assembly 1 may further include: a detection pipe 1-9, a first vent pipe 1-10, a first purge pipe 1-11, a first sewage pipe 1-12, a second sewage pipe 1-13 and at least one overflow pipe 1-8.

[0030] At least one overflow pipe 1-8 can be located within the cold box 1-3 and connected to the tank 1-2. A first temperature detector can be provided on the overflow pipe 1-8. When LNG fuel is supplied to the tank 1-2, the LNG fuel enters the tank 1-2 and, after a certain period of filling, flows into the overflow pipe 1-8. The LNG fuel is relatively low in temperature. When the first temperature detector detects that the temperature on the overflow pipe 1-8 reaches a set threshold, indicating that the LNG fuel in the tank 1-2 has reached a set level, no further LNG fuel is added to the tank 1-2, thereby preventing overfilling of the LNG fuel.

[0031] When there are multiple overflow pipes 1 - 8 , the multiple overflow pipes 1 - 8 are spaced apart from top to bottom on the tank body 1 - 2 to detect different filling amounts of the tank body 1 - 2 .

[0032] A detection tube 1-9 may be provided in the cold box 1-3, with one end of the detection tube 1-9 communicating with the top of the tank 1-2 and the other end communicating with the bottom of the tank 1-2. The detection tube 1-9 may be provided with a pressure detector and a liquid level detector for detecting whether the pressure and liquid level in the tank 1-2 meet the requirements.

[0033] A first vent pipe 1-10 can be installed within the cold box 1-3. One end of the first vent pipe 1-10 is connected to the first gas phase pipe 1-4, the second delivery pipe 1-6, and the third delivery pipe 1-7, and the other end is connected to the first vent port 1-34. When the pressure within the marine LNG fuel tank system exceeds a set threshold, the gas is released through the first vent pipe 1-10 and the first vent port 1-34 to ensure that the pressure within the marine LNG fuel tank system meets the required level and avoid safety accidents. The first vent port 1-34 is connected to a connecting pipe 1-14 to transport the released gas to a set location to ensure safety.

[0034] A first purge pipe 1-11 is disposed within the cold box 1-3. One end of the first purge pipe 1-11 is connected to the first gas phase pipe 1-4, the second delivery pipe 1-6, and the third delivery pipe 1-7, and the other end is connected to the first purge port 1-35. When the tank 1-2 is to be filled with LNG fuel, inert gas from the outside is introduced into the first gas phase pipe 1-4, the second delivery pipe 1-6, and the third delivery pipe 1-7 through the first purge port 1-35 and the first purge pipe 1-11. The first gas phase pipe 1-4, the second delivery pipe 1-6, and the third delivery pipe 1-7 are purged to prevent air or residual LNG fuel from remaining in the first gas phase pipe 1-4, the second delivery pipe 1-6, and the third delivery pipe 1-7.

[0035] The first sewage pipe 1-12 can be arranged in the cold box 1-3 and connected to the first vent pipe 1-10, so as to discharge the sewage in the first vent pipe 1-10.

[0036] The second sewage pipe 1-13 can be connected to the first sewage outlet 1-36 to discharge the sewage in the cold box 1-3.

[0037] In some embodiments, the pipeline assembly 3 may include: a first tube 3-1, a second tube 3-2, and a third tube 3-3.

[0038] One end of the first tube 3 - 1 can be connected to the first interface 1 - 31 , and the other end is connected to the filling and gasification skid 2 , so as to connect the tank body 1 - 2 and the filling and gasification skid 2 .

[0039] One end of the second tube 3 - 2 can be connected to the second interface 1 - 32 , and the other end is connected to the filling and gasification skid 2 , so as to connect the tank body 1 - 2 and the filling and gasification skid 2 .

[0040] One end of the third tube 3 - 3 can be connected to the third interface 1 - 33 , and the other end is connected to the filling and gasification skid 2 , so as to connect the tank body 1 - 2 and the filling and gasification skid 2 .

[0041] In some embodiments, the first tube 3 - 1 , the second tube 3 - 2 , and the third tube 3 - 3 are all metal hoses for ease of arrangement.

[0042] In some embodiments, the charging and gasification skid 2 may include: a tank 2-1, a vaporizer 2-2, a fourth delivery pipe 2-3, a fifth delivery pipe 2-4, a sixth delivery pipe 2-5, and a seventh delivery pipe 2-6.

[0043] The housing 2-1 may be provided with a fourth port 2-11, a fifth port 2-12, a sixth port 2-13, and an air supply port 2-14. The fourth port 2-11 may be connected to the first tube 3-1. The fifth port 2-12 may be connected to the second tube 3-2. The sixth port 2-13 may be connected to the third tube 3-3. The housing 2-1 may be provided with a ventilation inlet 2-22 and a ventilation outlet 2-23 for ventilating the interior of the housing 2-1.

[0044] The vaporizer 2-2 can be disposed in the housing 2-1. In some embodiments, the vaporizer 2-2 can be a water bath type, integrating a supercharger and a vaporizer in one, with a small size, and can stably vaporize the LNG fuel.

[0045] The fourth delivery pipe 2-3 can be provided in the box body 2-1. One end of the fourth delivery pipe 2-3 is connected to the vaporizer 2-2, and the other end is connected to the fourth interface 2-11.

[0046] The fifth delivery pipe 2-4 can be provided in the housing 2-1. One end of the fifth delivery pipe 2-4 is connected to the vaporizer 2-2, and the other end is connected to the fifth interface 2-12.

[0047] The sixth delivery pipe 2-5 can be provided in the box body 2-1. One end of the sixth delivery pipe 2-5 is connected to the vaporizer 2-2, and the other end is connected to the sixth interface 2-13.

[0048] The seventh delivery pipe 2-6 is provided in the housing 2-1. One end of the seventh delivery pipe 2-6 is connected to the vaporizer 2-2, and the other end is connected to the air supply port 2-14. A buffer tank 2-70 is provided on the seventh delivery pipe 2-6.

[0049] In some embodiments, when gas is supplied, the bottom of the tank 1-2 delivers LNG fuel to the vaporizer 2-2 through the first delivery pipe 1-5, the second delivery pipe 1-6, the second port 1-32, the second pipe 3-2, the fifth port 2-12, and the fifth delivery pipe 2-4. The vaporizer 2-2 vaporizes the LNG fuel and then delivers it into the tank 1-2 through the fourth delivery pipe 2-3, the fourth port 2-11, the first pipe 3-1, the first port 1-31, and the first gas phase pipe 1-4, ensuring that the pressure within the tank 1-2 meets the required pressure. The bottom of the tank 1-2 delivers LNG fuel to the vaporizer 2-2 through the third delivery pipe 1-7, the third port 1-33, the third pipe 3-3, the sixth port 2-13, and the sixth delivery pipe 2-5. After the vaporizer 2-2 vaporizes the LNG fuel, it is delivered to the ship's equipment requiring fuel through the seventh delivery pipe 2-6, the buffer tank 2-70, and the gas supply port 2-14.

[0050] In some embodiments, the box body 2-1 is provided with a seventh interface 2-15 and an eighth interface 2-16.

[0051] The charging and gasification skid 2 may further include: a second gas phase pipe 2-7 and an eighth delivery pipe 2-8.

[0052] The second gas phase pipe 2-7 can be arranged in the box body 2-1, and one end of the second gas phase pipe 2-7 is connected to the seventh interface 2-15, and the other end is connected to the fourth delivery pipe 2-3.

[0053] The eighth delivery pipe 2-8 can be arranged in the box body 2-1, and one end of the eighth delivery pipe 2-8 is connected to the eighth interface 2-16, and the other end is connected to the fifth delivery pipe 2-4.

[0054] In some embodiments, when the LNG fuel in tank 1-2 is depleted and needs to be refilled on the hull, external LNG fuel is added to tank 1-2 via the eighth port 2-16, the eighth delivery pipe 2-8, the fifth delivery pipe 2-4, the fifth port 2-12, the second pipe 3-2, the second port 1-32, the second delivery pipe 1-6, and the first delivery pipe 1-5. At this time, some LNG fuel is delivered to the vaporizer 2-2 via the fifth delivery pipe 2-4. The vaporizer then vaporizes the LNG fuel and pressurizes it into tank 1-2 through the sixth delivery pipe 2-5, the sixth port 2-13, the third pipe 3-3, the third port 1-33, and the third delivery pipe 1-7. The seventh port 2-15 is connected to the first gas phase pipe 1-4 via the second gas phase pipe 2-7, the fourth delivery pipe 2-3, the fourth port 2-11, the first pipe 3-1, and the first port 1-31, ensuring pressure balance within tank 1-2.

[0055] In some embodiments, the box body 2-1 may be provided with a second vent 2-17, a second purge port 2-18, and a second sewage outlet 2-19.

[0056] The charging and gasification skid 2 may further include: a second vent pipe 2-9, a second purge pipe 2-10 and at least one third sewage pipe 2-30.

[0057] A second relief pipe 2-9 can be installed within the tank 2-1. One end of the second relief pipe 2-9 is connected to the second relief port 2-17, and the other end is connected to the fourth delivery pipe 2-3, the fifth delivery pipe 2-4, the sixth delivery pipe 2-5, the seventh delivery pipe 2-6, the second gas phase pipe 2-7, and the eighth delivery pipe 2-8. When the pressure within the marine LNG fuel tank system exceeds a set threshold, the gas is released through the second relief pipe 2-9 and the second relief port 2-17 to ensure that the pressure within the marine LNG fuel tank system meets the required level and avoid safety accidents. The second relief port 2-17 is connected to the connecting pipe 1-14 to transport the released gas to a set location to ensure safety.

[0058] A second purge pipe 2-10 is disposed within the housing 2-1. One end of the second purge pipe 2-10 communicates with the second purge port 2-18, and the other end communicates with the second gas phase pipe 2-7, the eighth delivery pipe 2-8, and the seventh delivery pipe 2-6. When the tank 1-2 is to be filled with LNG fuel using the filling and gasification skid 2, inert gas from the outside is introduced into the second gas phase pipe 2-7, the eighth delivery pipe 2-8, and the seventh delivery pipe 2-6 through the second purge pipe 2-10 and the second purge port 2-18, thereby purging the second gas phase pipe 2-7, the eighth delivery pipe 2-8, and the seventh delivery pipe 2-6 to prevent air or residual LNG fuel from remaining in the second gas phase pipe 2-7, the eighth delivery pipe 2-8, and the seventh delivery pipe 2-6.

[0059] At least one third sewage pipe 2-30 is connected to the second sewage outlet 2-19 and is used to discharge the sewage in the box body 2-1.

[0060] In some embodiments, the first gas-phase pipe 1-4, the first delivery pipe 1-5, the third delivery pipe 1-7, the fourth delivery pipe 2-3, the fifth delivery pipe 2-4, the sixth delivery pipe 2-5, the seventh delivery pipe 2-6, the second gas-phase pipe 2-7, and the eighth delivery pipe 2-8 are each provided with a pneumatic control valve 4. The pneumatic control valve 4 is used to control the opening and closing of the first gas-phase pipe 1-4, the first delivery pipe 1-5, the third delivery pipe 1-7, the fourth delivery pipe 2-3, the fifth delivery pipe 2-4, the sixth delivery pipe 2-5, the seventh delivery pipe 2-6, the second gas-phase pipe 2-7, and the eighth delivery pipe 2-8.

[0061] The marine LNG fuel tank system may further include a filling control valve group 5 connected to the pneumatic control valve 4, and the opening and closing of the pneumatic control valve is controlled by the filling control valve group 5. In some embodiments, the filling control valve group 5 controls the opening and closing of the pneumatic control valve 4 through compressed gas.

[0062] In some embodiments, the charging and gasification skid 2 may further include: a regulating pipe 2 - 40 .

[0063] The regulating pipe 2-40 is arranged in the box body 2-1. One end of the regulating pipe 2-40 is connected to the fourth delivery pipe 2-3, and the other end is connected to the sixth delivery pipe 2-5. A pressure regulating valve 2-41 is provided on the regulating pipe 2-40. The pressure regulating valve 2-41 is opened and closed to realize the connection and disconnection of the regulating pipe 2-40 and the fourth delivery pipe 2-3 and the sixth delivery pipe 2-5 to ensure pressure balance.

[0064] In some embodiments, the box body 2-1 may be provided with a circulating water inlet 2-20 and a circulating water outlet 2-21.

[0065] The charging and gasification skid 2 may further include: a first water pipe 2-50 and a second water pipe 2-60.

[0066] The first water pipe 2-50 can be arranged in the box body 2-1. One end of the first water pipe 2-50 is connected to the circulating water inlet 2-20, and the other end is connected to the vaporizer 2-2.

[0067] The second water pipe 2-60 may be disposed in the housing 2-1. One end of the second water pipe 2-60 is connected to the circulating water outlet 2-21, and the other end is connected to the vaporizer 2-2.

[0068] In some embodiments, when LNG fuel is to be vaporized, external circulating water enters the vaporizer 2-2 through the circulating water inlet 2-20 and the first water pipe 2-50, exchanges heat with the LNG fuel to vaporize the LNG fuel, and the circulating water after heat exchange is discharged in turn through the second water pipe 2-60 and the circulating water outlet 2-21.

[0069] According to the technical solutions of some embodiments of the present disclosure, the tank assembly is detachably mounted on the hull, the filling and gasification skid is mounted on the hull, one end of the pipeline assembly is detachably connected to the tank assembly, and the other end is connected to the tank assembly. Therefore, when the LNG fuel in the tank assembly is used up, the pipeline assembly is removed from the tank assembly and the tank assembly can be lifted away. The tank assembly filled with LNG fuel is then hoisted onto the hull, and the pipeline assembly is connected to the tank assembly filled with LNG fuel, so that the LNG fuel can be transported to the filling and gasification skid. The LNG fuel is transported to the equipment that needs gas by the filling and gasification skid, and the reloading operation can be completed when the ship docks and unloads, without the need for waiting time for refueling, and the fuel supply is fast.

[0070] Finally, it should be noted that the above specific implementation methods are only used to illustrate the technical solutions of the present disclosure and are not limiting. Although the present disclosure has been described in detail with reference to examples, those skilled in the art should understand that the technical solutions of the present disclosure can be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present disclosure, which should all be included in the scope of the claims of the present disclosure.

Claims

1. A marine LNG fuel tank system, comprising: A tank container assembly is detachably mounted on the hull; A charging and gasification skid, provided on the hull; and A pipeline assembly has one end detachably connected to the tank assembly and the other end connected to the filling and gasification skid.

2. The marine LNG fuel tank system according to claim 1, wherein: The tank container assembly comprises: Lifting frame; A tank body is arranged in the hoisting frame; A cold box is provided in the hoisting frame and connected to the tank body, and the cold box is provided with a first interface, a second interface and a third interface connected to the pipeline assembly; a first gas phase pipe, disposed in the cold box and connected to the top of the tank and the first interface; a first delivery pipe, disposed in the cold box, wherein one end of the first delivery pipe is connected to the top of the tank body, and the other end of the first delivery pipe is connected to the bottom of the tank body; a second delivery pipe, disposed in the cold box and communicating with the first delivery pipe and the second interface; and The third delivery pipe is arranged in the cold box and is communicated with the bottom of the tank body and the third interface.

3. The marine LNG fuel tank system according to claim 2, wherein: The cold box is provided with a first vent, a first purge port and a first sewage outlet; The tank container assembly further comprises: at least one overflow pipe, disposed in the cold box and connected to the tank, wherein the overflow pipe is provided with a first temperature detector; A detection tube is provided in the cold box, one end of the detection tube is connected to the top of the tank body, and the other end is connected to the bottom of the tank body, and the detection tube is provided with a pressure detector and a liquid level detector; a first vent pipe, disposed in the cold box, wherein one end of the first vent pipe is connected to the first gas phase pipe, the second delivery pipe, and the third delivery pipe, and the other end of the first vent pipe is connected to the first vent port; a first purge pipe, disposed in the cold box, wherein one end of the first purge pipe is connected to the first gas phase pipe, the second delivery pipe, and the third delivery pipe, and the other end of the first purge pipe is connected to the first purge port; a first sewage pipe, disposed in the cold box and connected to the first vent pipe; and The second sewage pipe is connected to the first sewage outlet.

4. The marine LNG fuel tank system according to claim 2, wherein: The pipeline assembly includes: a first pipe, one end of which is connected to the first interface and the other end of which is connected to the filling and gasification skid; a second pipe, one end of which is connected to the second interface and the other end of which is connected to the filling and gasification skid; and The third tube has one end connected to the third interface and the other end connected to the filling and gasification skid.

5. The marine LNG fuel tank system according to claim 4, wherein: The filling and gasification skid comprises: The box body is provided with a fourth interface, a fifth interface, a sixth interface and an air supply port, the fourth interface is connected to the first pipe, the fifth interface is connected to the second pipe, and the sixth interface is connected to the third pipe; a vaporizer, disposed in the housing; a fourth delivery pipe, disposed in the housing, wherein one end of the fourth delivery pipe is connected to the vaporizer, and the other end is connected to the fourth port; a fifth delivery pipe, disposed in the housing, wherein one end of the fifth delivery pipe is connected to the vaporizer, and the other end is connected to the fifth port; a sixth delivery pipe, disposed in the housing, wherein one end of the sixth delivery pipe is connected to the vaporizer, and the other end is connected to the sixth port; and A seventh delivery pipe is provided in the box body, one end of the seventh delivery pipe is connected to the vaporizer, and the other end is connected to the air supply port, and a buffer tank is provided on the seventh delivery pipe.

6. The marine LNG fuel tank system according to claim 5, wherein: The box body is provided with a seventh interface and an eighth interface; The filling and gasification skid further comprises: a second gas phase pipe, disposed in the box body, wherein one end of the second gas phase pipe is connected to the seventh interface, and the other end is connected to the fourth delivery pipe; An eighth delivery pipe is provided in the box body, one end of the eighth delivery pipe is communicated with the eighth interface, and the other end of the eighth delivery pipe is communicated with the fifth delivery pipe.

7. The marine LNG fuel tank system according to claim 6, wherein: The box body is provided with a second vent, a second purge port and a second sewage outlet; The filling and gasification skid further comprises: a second discharging pipe, disposed in the box body, wherein one end of the second discharging pipe is connected to the second discharging port, and the other end is connected to the fourth delivery pipe, the fifth delivery pipe, the sixth delivery pipe, the seventh delivery pipe, the second gas phase pipe, and the eighth delivery pipe; a second purge pipe, disposed in the housing, one end of the second purge pipe being connected to the second purge port, and the other end of the second gas phase pipe, the eighth delivery pipe, and the seventh delivery pipe; and At least one third sewage pipe is connected to the second sewage outlet.

8. The marine LNG fuel tank system according to claim 6, wherein: The first gas phase pipe, the first delivery pipe, the third delivery pipe, the fourth delivery pipe, the fifth delivery pipe, the sixth delivery pipe, the seventh delivery pipe, the second gas phase pipe and the eighth delivery pipe are all provided with a pneumatic control valve; The marine LNG fuel tank system further includes a filling control valve group connected to the pneumatic control valve.

9. The marine LNG fuel tank system according to claim 5, wherein: The filling and gasification skid further comprises: A regulating pipe is arranged in the box body, one end of the regulating pipe is connected to the fourth delivery pipe, and the other end is connected to the sixth delivery pipe. A pressure regulating valve is provided on the regulating pipe.

10. The marine LNG fuel tank system according to claim 5, wherein: The box body is provided with a circulating water inlet and a circulating water outlet; The filling and gasification skid further comprises: A first water pipe is provided in the housing, one end of the first water pipe is connected to the circulating water inlet, and the other end is connected to the vaporizer; and The second water pipe is arranged in the box body, one end of the second water pipe is connected to the circulating water outlet, and the other end is connected to the vaporizer.