AI Technical Summary

Technical Problem

Existing reinforcing bar binding technologies cannot run on reinforcing bars with different pitches without prior adjustment, limiting their versatility and efficiency in construction applications.

Method used

A reinforcing bar binding device equipped with wheels that can rotate and contact reinforcing bars, with a width larger than the difference between two pitches but smaller than 1.5 times and 0.5 times those pitches, allowing the device to run on bars with varying pitches without prior adjustment.

Benefits of technology

Enables the device to traverse and bind reinforcing bars with different pitches seamlessly, enhancing its adaptability and operational efficiency in construction environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure PI2025003940_DRAWING_001
    Figure PI2025003940_DRAWING_001
  • Figure PI2025003940_DRAWING_002
    Figure PI2025003940_DRAWING_002
  • Figure PI2025003940_DRAWING_003
    Figure PI2025003940_DRAWING_003
Patent Text Reader

Abstract

ABSTRACT REINFORCING-BAR-BUNDLING APPARATUS A reinforcing-bar-bundling apparatus that makes it possible for a plurality of reinforcing bars (R10) to travel at a first pitch and for a plurality of reinforcing bars (R20A) to travel at a second pitch higher than the first pitch, the reinforcing-bar-bundling apparatus comprising: roller parts (122a, 122c) via which the reinforcing bars are rotated, the roller parts (122a, 122c) having a width that is greater than the difference between the second pitch and the first pitch and less than the difference between 1.5 times the second pitch and 0.5 times the first pitch; roller parts (122b, 122d) on which other reinforcing bars rotate, the roller parts (122b, 122d) having a width that is greater than the difference between the second pitch and the first pitch and less than the difference between 1.5 times the second pitch and 0.5 times the first pitch; and a motor that drives the roller parts (122a to 122d). FIG. 13A
Need to check novelty before this filing date? Find Prior Art

Description

Rebar Binding Device

[0001] The present invention relates to a reinforcing bar binding device.

[0002] Conventionally, there have been studies on technologies for automating the work of tying reinforcing bars, for example, by using wires to tie the intersections of reinforcing bars extending in the vertical direction and reinforcing bars extending in the horizontal direction. For example, Patent Document 1 discloses a technology in which the valleys of V-shaped tapered drive wheels are brought into contact with the reinforcing bars extending in the vertical direction, so that the drive wheels run on the reinforcing bars.

[0003] Japanese Patent Application Publication No. 2019-39174

[0004] However, the technology described in Patent Document 1 had the problem that it was not possible to run diagonally in a direction that intersects with the extension direction of the reinforcing bars, and the tread width of the drive wheels had to be adjusted in advance to match the pitch of the reinforcing bars to be installed.

[0005] The present invention has been made in consideration of these circumstances, and aims to provide a rebar binding device that can run on multiple rebars with different pitches without requiring prior adjustment.

[0006] One aspect of the present disclosure is a rebar binding device configured to be able to run on a plurality of rebars arranged at a first pitch, and also configured to be able to run on a plurality of rebars arranged at a second pitch larger than the first pitch, comprising: a first wheel that rotates on the rebars and has a width that is larger than the difference between the second pitch and the first pitch and smaller than the difference between 1.5 times the second pitch and 0.5 times the first pitch; a second wheel that rotates on a different rebar from the first wheel and has a width that is larger than the difference between the second pitch and the first pitch and smaller than the difference between 1.5 times the second pitch and 0.5 times the first pitch; and a drive unit that drives the first wheel and second wheel to rotate.

[0007] According to the present disclosure, even when running over reinforcing bars with different pitches, it is possible to run over multiple reinforcing bars with different pitches without requiring prior adjustment.

[0008] FIG. 1 is an overall perspective view of a rebar bundling robot 100 according to an embodiment of the present disclosure, as viewed from diagonally above. FIG. 2 is an overall perspective view of a rebar bundling robot according to an embodiment of the present disclosure, as viewed from diagonally below. FIG. 3 is a plan view of the rebar bundling robot 100 as viewed from above (above in the Z direction). FIG. 4 is a plan view of the rebar bundling robot 100 as viewed from below (below in the Z direction). FIG. 5 is a perspective view of the rebar bundling robot 100 as viewed from diagonally above, with a rebar bundling unit 110 removed. FIG. 6 is a perspective view of the rebar bundling robot 100 as viewed from diagonally above, with a rebar bundling unit 110 removed. FIG. 7 is a diagram illustrating the functional block configuration of the rebar bundling robot 100. FIG. 8 is a view of the rebar bundling robot 100 as viewed from the Y direction while traveling along a first rebar R10. FIG. 9 is a view of the rebar bundling robot 100 as viewed from the X direction while traveling along a first rebar R10. Fig. 10 is a view of the rebar bundling robot 100, which has stopped traveling and is performing bundling work, as viewed from the Y direction. Fig. 11 is a view of the rebar bundling robot 100 performing bundling work as viewed from the X direction. Fig. 12 is a view of the rebar bundling robot 100 performing bundling work as viewed from below in the Z direction. Fig. 13A is a front view of the rebar bundling robot 100 as viewed from the Y direction. Fig. 13B is a front view of the rebar bundling robot 100 as viewed from the Y direction.

[0009] Hereinafter, the present embodiment will be described with reference to the accompanying drawings. To facilitate understanding of the description, the same components in the drawings will be denoted by the same reference numerals as much as possible, and duplicated descriptions will be omitted.

[0010] The configuration of a binding device 100 according to an embodiment of the present disclosure will be described below. In this embodiment, the binding device is a rebar binding device that binds multiple rebars arranged crossing each other, and may be, for example, a rebar binding robot. Below, the binding device 100 will be described using a rebar binding robot as an example, and the binding device 100 will also be referred to as a rebar binding robot 100. The drawings may also show an X-axis, a Y-axis, and a Z-axis. The X-axis, the Y-axis, and the Z-axis form a three-dimensional Cartesian coordinate system based on a right-handed system. Hereinafter, the direction of the X-axis arrow may be referred to as the forward X-axis, the +X direction, the right side of the X-axis, or the right side of the X-axis, and the direction opposite to the arrow may be referred to as the backward X-axis, the -X direction, the left side of the X-axis, or the left side of the X-axis. The same applies to the other axes. The forward Z-axis and the backward Z-axis may also be referred to as the "upper side" or "upper" and the "lower side" or "lower" respectively. Furthermore, planes perpendicular to the X-axis, Y-axis, or Z-axis may be called YZ planes, ZX planes, or XY planes, respectively. However, these directions are used for convenience to explain relative positional relationships. Therefore, these directions do not define absolute positional relationships.

[0011] FIG. 1 is an overall perspective view of a rebar bundling robot 100 according to an embodiment of the present disclosure, as viewed from diagonally above. FIG. 2 is an overall perspective view of the rebar bundling robot according to an embodiment of the present disclosure, as viewed from diagonally below. As shown in FIGS. 1 and 2 , the rebar bundling robot 100 according to an embodiment of the present disclosure includes a rebar bundling unit 110, a traveling unit 121, and a sensor unit 130. The rebar bundling robot 100 may further include other components, such as a main unit 140, a support bar 150, a control unit 160, reels 180 (first reel 180a and second reel 180b), batteries 182 (first battery 182a and second battery 182b), a lateral movement unit 146, and a memory device 198 (not shown).

[0012] 1 and 2 also show a rebar group R including a plurality of rebars R10 (also referred to as "first rebars" or "vertical rebars" in this embodiment) extending in the Y direction. As shown in FIGS. 1 and 2, the rebar tying robot 100 is placed on the rebar group R so as to travel along the first rebars R10. In addition to the plurality of rebars R10, the rebar group R may also include a plurality of rebars (also referred to as "second rebars R20" or "horizontal rebars" in this embodiment) extending in the X direction.

[0013] In an embodiment of the present disclosure, the first rebar R10 is arranged so that its first extension direction is parallel to the Y direction. Furthermore, the second rebar R20 is arranged so that its second extension direction is parallel to the X direction. Therefore, in an exemplary embodiment of the present disclosure, the first rebar R10 and the second rebar R20 are arranged so that they are perpendicular to each other. Furthermore, the first rebar R10 and the second rebar R20 are arranged so that the plane formed by the first rebar R10 and the second rebar R20 (also referred to as the "rebar plane" in this embodiment) is parallel to the XY plane. Therefore, the plane formed by the first rebar R10 and the second rebar R20 is a horizontal plane in this embodiment. The arrangement of the first rebar R10 and the second rebar R20 is not limited to this. For example, the first rebar R10 and the second rebar R20 may be arranged so that they are non-orthogonal to each other. For example, the first reinforcing bars R10 and the second reinforcing bars R20 may be arranged so that the angle between the first reinforcing bars R10 and the second reinforcing bars R20 is, for example, 30°, 45°, 60°, or another angle. In the embodiment of the present disclosure, the first reinforcing bars R10 and the second reinforcing bars R20 are arranged so as to be perpendicular to each other, but they do not necessarily have to be perpendicular to each other depending on the intersection, and may be arranged so as to form an angle of, for example, 85° or more and less than 90°.

[0014] Furthermore, the first reinforcing bars R10 and the second reinforcing bars R20 may have a finite length, and the first reinforcing bars R10 or the second reinforcing bars R20 may be connected via joints in a first direction or a second direction, respectively. Furthermore, the first reinforcing bars R10 and the second reinforcing bars R20 may have ends.

[0015] The reinforcing bar binding unit 110 is configured to bind the intersection c12 (FIG. 6) of the first reinforcing bar R10 and the second reinforcing bar R20. The binding operation of the reinforcing bar binding unit 110 at the intersection c12 of the first reinforcing bar R10 and the second reinforcing bar R20 will be described in detail later.

[0016] 1 and 2, the traveling unit 121 may have four traveling units 121a, 121b, 121c, and 121d (in this embodiment, these are also referred to as the "first traveling unit," the "second traveling unit," the "third traveling unit," and the "fourth traveling unit," respectively). In the embodiment of the present disclosure, the traveling units 121 are arranged on the group of rebars R so that the rebar binding robot 100 moves in the Y direction. The first running unit 121a, the second running unit 121b, the third running unit 121c, and the fourth running unit 121d each have a first roller unit 122a, a second roller unit 122b, a third roller unit 122c, and a fourth roller unit 122d, and the first roller unit 122a, the second roller unit 122b, the third roller unit 122c, and the fourth roller unit 122d are configured to run on any one of the multiple first reinforcing bars R10 along the Y direction (first direction), which is the extension direction of the first reinforcing bars R10.

[0017] In this embodiment, the traveling unit 121 is an example of a moving unit (moving unit 120, which will be described later). The moving unit 120 may have the configuration of a moving unit other than the traveling unit 121, instead of or in addition to the traveling unit 121.

[0018] In the embodiment of the present disclosure, the first traveling unit 121a, the second traveling unit 121b, the third traveling unit 121c, and the fourth traveling unit 121d are described as being configured to travel in the Y direction, but the first traveling unit 121a, the second traveling unit 121b, the third traveling unit 121c, and the fourth traveling unit 121d may be configured to travel in a direction other than the Y direction. For example, the first traveling unit 121a, the second traveling unit 121b, the third traveling unit 121c, and the fourth traveling unit 121d may travel in a direction at an angle of several degrees to several tens of degrees from the Y direction. For example, even if the orientation of the rebar binding robot 100 is tilted due to the presence of a foreign object on the traveling first rebar R10, the rebar binding unit 110 of the rebar binding robot 100 can perform the binding operation at the intersection c12 of the first rebar R10 and the second rebar R20 by traveling so as to approximately follow the first rebar R10. Furthermore, even at a construction site where the first reinforcing bar R10 is arranged in a curved line, the first running unit 121a, the second running unit 121b, the third running unit 121c, and the fourth running unit 121d may be configured to move in a curved line so as to follow the curved first reinforcing bar R10, and in this case, the first direction, which is the extension direction of the first reinforcing bar R10, may be different for each point that constitutes the curve.

[0019] 1 and 2 and FIG. 3 described later, the sensor unit 130 has sensors 130a, 130b, 130c, and 130d (also referred to as the "first sensor," the "second sensor," the "third sensor," and the "fourth sensor" in this embodiment, respectively). The first sensor 130a and the second sensor 130b are arranged spaced apart from each other along the Y direction in FIGS. 1 and 2 (the direction in which a straight line connecting the first sensor 130a and the second sensor 130b extends is also referred to as the "third direction" in this embodiment). In addition, the fourth sensor 130d is arranged on the side opposite to the side on which the third sensor 130c of the rebar binding robot 100 is provided (the side on the far side of the paper in Figures 1 and 2), and the third sensor 130c and the fourth sensor 130d are arranged so as to be spaced apart from each other along a direction intersecting the Y direction in Figures 1 and 2 (the X direction in the example shown in Figures 1 and 2; in this embodiment, the direction in which the straight line connecting the third sensor 130c and the fourth sensor 130d extends is also referred to as the "fourth direction").

[0020] The first sensor 130a, the second sensor 130b, the third sensor 130c, and the fourth sensor 130d are configured to be capable of detecting the first rebar R10 and / or the second rebar R20. For example, the first sensor 130a and the second sensor 130b may be configured to be capable of detecting the first rebar R10, and the third sensor 130c and the fourth sensor 130d may be configured to be capable of detecting the second rebar R20. Alternatively, the first sensor 130a, the second sensor 130b, the third sensor 130c, and the fourth sensor 130d may all be configured to be capable of detecting the first rebar R10 and the second rebar R20.

[0021] Fig. 3 shows a plan view of the rebar binding robot 100 as seen from above (above in the Z direction), and Fig. 4 shows a plan view of the rebar binding robot 100 as seen from below (below in the Z direction).

[0022] As can be seen from FIGS. 3 and 4 , the first propulsion unit 121a and the second propulsion unit 121b may be arranged on one side and the other side of the fourth direction (X direction) relative to the first sensor 130a (the left and right sides, respectively, in the X direction in FIG. 3 ). Furthermore, the third propulsion unit 121c and the fourth propulsion unit 121d may be arranged on one side and the other side of the fourth direction (X direction) relative to the second sensor 130b. In other words, the first sensor 130a may be arranged between the first propulsion unit 121a and the second propulsion unit 121b in the fourth direction. Similarly, the second sensor 130b may be arranged between the third propulsion unit 121c and the fourth propulsion unit 121d in the fourth direction.

[0023] Furthermore, as shown in Figures 3 and 4, the third sensor 130c may be arranged between the first running unit 121a and the third running unit 121c in the third direction (the Y direction in Figures 3 and 4), and similarly, the fourth sensor 130d may be arranged between the second running unit 121b and the fourth running unit 121d in the third direction (the Y direction).

[0024] Furthermore, for example, the camera constituting first sensor 130a may be disposed on a line passing through rotation axis 128a of first roller unit 122a constituting first traveling unit 121a and rotation axis 128b of second roller unit 122b constituting second traveling unit 121b, or forward of a line passing through rotation axis 128a and rotation axis 128b (+Y direction in FIG. 4). Similarly, the camera constituting second sensor 130b may be disposed on a line passing through rotation axis 128c of third roller unit 122c constituting third traveling unit 121c and rotation axis 128d of fourth roller unit 122d constituting fourth traveling unit 121d, or rearward of a line passing through rotation axis 128c and rotation axis 128d (-Y direction in FIG. 4).

[0025] 3 and 4, the first sensor 130a is disposed in front of the main unit 140 in the Y-axis direction (+Y direction). Similarly, the second sensor 130b is disposed behind the main unit 140 in the Y-axis direction (-Y direction). The third sensor 130c and the fourth sensor 130d are disposed on the left and right sides of the main unit 140 in the X-direction, respectively, when viewed from above in FIG. 3. That is, as can be seen from FIG. 4, for example, in this embodiment, the first sensor 130a, the second sensor 130b, the third sensor 130c, and the fourth sensor 130d are disposed on or inside the outer edge of an imaginary rectangle formed by connecting the approximate centers of the first traveling unit 121a, the second traveling unit 121b, the third traveling unit 121c, and the fourth traveling unit 121d in a plan view of the rebar binding robot 100. The virtual rectangle formed by the first to fourth propulsion units 121a to 121d may be a square, for example, if the spacing between the propulsion units in the X and Y directions is approximately equal. In this case, the first to fourth sensors 130a to 130d may be arranged on the outer edge of the virtual square or inside it. Depending on the arrangement of the first to fourth propulsion units 121a to 121d, the first to fourth propulsion units 121a to 121d may form a virtual quadrangle other than a rectangle or a square. In this case, the first to fourth sensors 130a to 130d may also be arranged on the outer edge of the virtual quadrangle or inside it.

[0026] 1 and 3 , the main body unit 140 may have a main body upper surface 142. The main body upper surface 142 may have, for example, a circular hole 144 formed near the center, and the rebar binding unit 110 may be arranged to pass through the hole 144.

[0027] In this embodiment, the rebar binding robot 100 may include, for example, two support bars 150 (a first support bar 150a and a second support bar 150b). The first support bar 150a and the second support bar 150b are bars extending in one direction and are arranged parallel to each other, for example, in a fourth direction (the X direction in FIGS. 1 to 4). Therefore, in the embodiment of the present disclosure, the first support bar 150a and the second support bar 150b are arranged parallel to each other, for example, in the horizontal direction. Furthermore, as shown in FIGS. 1 to 4, the first support bar 150a and the second support bar 150b may be arranged so as to be spaced apart from each other in the Y direction (the third direction). The first support bar 150a and the second support bar 150b may be configured to support the main unit 140 of the rebar binding robot 100, for example, when the rebar binding robot 100 moves laterally (the X direction in Figures 1 to 4, the fourth direction in the rebar binding robot 100).

[0028] FIG. 5 is a perspective view of the rebar tying robot 100 with the rebar tying unit 110 removed, as viewed from the diagonally rear right. FIG. 6 is a perspective view of the rebar tying robot 100 with the rebar tying unit 110 removed, as viewed from the diagonally front right. As shown in FIGS. 5 and 6 , the rebar tying unit 110 may be provided so as to be movable up and down (the Z direction in FIG. 1 ) while passing through the hole 144. This allows the rebar tying robot 100 to lower the rebar tying unit 110 and tie the intersection c12 of the first rebar R10 and the second rebar R20, for example, when the rebar tying robot 100 reaches the intersection c12 of the first rebar R10 and the second rebar R20. As shown in FIGS. 5 and 6 , the rebar tying robot 100 has reels 180 a and 180 b. The reels 180a and 180b contain wires used for bundling reinforcing bars, and when the reinforcing bar bundling unit 110 bundles the intersection c12 of the first reinforcing bar R10 and the second reinforcing bar R20, the wires contained in the reels 180a and / or 180b are pulled out to bundle the intersection c12. Although not described in detail, the reinforcing bar bundling unit 110 is provided with a wire twisting unit 114 ( FIG. 5 ) at one end (the lower end in the Z direction in FIG. 5 ) of the reinforcing bar bundling unit 110. The reinforcing bar bundling operation of the wire twisting unit 114 may be realized, for example, by a function similar to that of a known reinforcing bar bundling machine.

[0029] 7 is a diagram illustrating the functional block configuration of the rebar binding robot 100. As shown in Fig. 7, the rebar binding robot 100 may include a control unit 160, a lateral movement unit 146, and a storage device 198 in addition to the above-described components such as the rebar binding unit 110, the traveling unit 121, and the sensor unit 130.

[0030] The control unit 160 is configured to control the movement and binding work performed by the rebar binding robot 100. The control unit 160 may include a sensor detection result acquisition unit 162, a determination unit 164, an intersection point calculation unit 166 (also referred to as an "intersection point estimation unit" or an "intersection point estimation unit" in this embodiment), a rebar binding unit control unit 168, a rebar tracking control unit 170, a stop control unit 172, a movement amount calculation unit 174, a posture control unit 176, a motor control unit 178, and a foreign object detouring control unit 179.

[0031] 1, in the rebar binding robot 100 of this embodiment, the control unit 160 is disposed on the opposite side of the rebar binding unit 110 in the Y direction from the reels 180a and 180b. More specifically, as shown in FIG. 1, the reels 180a and 180b are disposed in the -Y direction of the rebar binding unit 110, whereas the control unit 160 is disposed in the +Y direction of the rebar binding unit 110. A reel wound with wire becomes relatively heavy, especially immediately after replacement, but by disposing the control unit 160 on the opposite side of the rebar binding unit 110, it is possible to balance the weight.

[0032] The lateral movement unit 146 ( FIG. 7 ) is configured to control the movement of the main unit 140 of the rebar binding robot 100. In the rebar binding robot 100 according to an embodiment of the present disclosure, the rebar binding robot 100 may be moved in the horizontal direction by the lateral movement unit 146. The lateral movement unit 146 may include a first lateral movement motor 146 a and a second lateral movement motor 146 b, and for example, when the rebar binding robot 100 moves laterally, the main unit 140 may be moved horizontally by the two motors 146 a and 146 b.

[0033] The storage device 198 may include, for example, a storage medium (e.g., a semiconductor memory device) or other media for non-transitory storage of one or more computer programs executed by the control unit 160, data used to control the rebar tying robot 100, and the like. The storage device 198 may also include, for example, a template database 198t. The template database 198t may store, for example, template images used to detect the first rebar R10 and / or the second rebar R20 using template matching based on the detection results of the sensor unit 130, or data obtained by performing image processing such as frequency analysis on the template images, based on the detection results of the sensor unit 130, as described below. The control unit 160 may also include a template data creation unit. For example, the control unit 160 may be configured to create template data based on images captured by the sensor unit 130 according to the site where the rebar tying work is to be performed, and store the template data in the template database 198t. The template data stored in the template database 198t may be accumulated, for example, whenever new template data is created, or may be deleted when bundling work at each construction site is completed. Alternatively, the created template data may be retained in the template database 198t of the storage device 198 for a certain period of time and then deleted, for example, periodically.

[0034] The sensor detection result acquisition unit 162 acquires the detection results of the sensor unit 130. For example, the detection results of the first sensor 130a, the second sensor 130b, the third sensor 130c, and / or the fourth sensor 130d of the sensor unit 130 may be used to determine the positions of the first reinforcing bar R10 and / or the second reinforcing bar R20 by a first reinforcing bar determination unit 164a1 and / or a second reinforcing bar determination unit 164a2 of the determination unit 164 (described later). Furthermore, the detection results of the first sensor 130a, the second sensor 130b, the third sensor 130c, and / or the fourth sensor 130d may be used to determine the positions of the ends of the first reinforcing bar R10 and / or the second reinforcing bar R20 by a first reinforcing bar end determination unit 164b1 and / or a second reinforcing bar end determination unit 164b2 of the determination unit 164.

[0035] The determination unit 164 may include a first reinforcing bar determination unit 164a1, a second reinforcing bar determination unit 164a2, a first reinforcing bar end determination unit 164b1, a second reinforcing bar end determination unit 164b2, a posture determination unit 164c, an obstacle determination unit 164d, and a robot height calculation unit 164e. The first reinforcing bar determination unit 164a1 and the second reinforcing bar determination unit 164a2 determine the positions of the first reinforcing bar R10 and / or the second reinforcing bar R20 using, for example, the detection results of the first sensor 130a, the second sensor 130b, the third sensor 130c, and / or the fourth sensor 130d acquired by the sensor detection result acquisition unit 162. As described below, the first rebar determination unit 164a1 and the second rebar determination unit 164a2 may determine the position of the first rebar R10 and / or the second rebar R20 by performing template matching based on the captured images that are the detection results of the first sensor 130a to the fourth sensor 130d.

[0036] The first reinforcing bar end determination unit 164b1 and the second reinforcing bar end determination unit 164b2 determine the end of the first reinforcing bar R10 and / or the end of the second reinforcing bar R20, for example, using the detection results of the first sensor 130a, the second sensor 130b, the third sensor 130c, and / or the fourth sensor 130d acquired by the sensor detection result acquisition unit 162. The first reinforcing bar end determination unit 164b1 and the second reinforcing bar end determination unit 164b2 may also determine the position of the end of the first reinforcing bar R10 and / or the end of the second reinforcing bar R20 based on template matching, similar to the first reinforcing bar determination unit 164a1 and the second reinforcing bar determination unit 164a2.

[0037] The robot height calculation unit 164e may calculate the height of the rebar binding robot 100 from the group of rebars R, for example, based on the detection results of the first sensor 130a, the second sensor 130b, the third sensor 130c, and / or the fourth sensor 130d. For example, when the first rebar R10 and / or the second rebar R20 are imaged by the first sensor 130a, the second sensor 130b, the third sensor 130c, and / or the fourth sensor 130d (for example, when an area including the first rebar R10 and / or the second rebar R20 is imaged), the robot height calculation unit 164e may calculate the height of the rebar binding robot 100 from the group of rebars R by calculating the distance of the rebar binding robot 100 from the group of rebars R based on the relative size of the first rebar R10 and / or the second rebar R20 in the image of the imaged first rebar R10 and / or the second rebar R20.

[0038] The height of the rebar binding robot 100 from the group of rebars R may be calculated based on, for example, the angle of the traveling unit 121. As shown in Fig. 6, the traveling unit 121a may have a first main body link portion 125a connected to the main unit 140 and a first roller link portion 123a connected to the first roller portion 122a, and the first main body link portion 125a and the first roller link portion 123a may form a link mechanism. In this case, the link angle formed between the first main body link portion 125a and the first roller link portion 123a may be detected by the first link angle detection sensor 134a (Fig. 7) of the sensor unit 130, and the height of the first traveling unit 121a may be calculated based on the link angle.

[0039] Similarly, as shown in Figure 2, the second running unit 121b, the third running unit 121c, and the fourth running unit 121d have a second body side link portion 125b and a second roller side link portion 123b, a third body side link portion 125c and a third roller side link portion 123c, and a fourth body side link portion 125d and a fourth roller side link portion 123d, and the heights of the second running unit 121b, the third running unit 121c, and the fourth running unit 121d may be calculated by detecting the link angles formed by the second body side link portion 125b and the second roller side link portion 123b, the third body side link portion 125c and the third roller side link portion 123c, and the fourth body side link portion 125d and the fourth roller side link portion 123d using a second link angle detection sensor 134b, a third link angle detection sensor 134c, and a fourth link angle detection sensor 134d, respectively.

[0040] The robot height calculation unit 164e may calculate the height of the rebar binding robot 100 from the group of rebars R based on the calculated heights (heights from the group of rebars R) of the first traveling unit 121a, the second traveling unit 121b, the third traveling unit 121c, and the fourth traveling unit 121d. For example, the height of the rebar binding robot 100 may be calculated using the average value of some or all of the calculated heights of the first traveling unit 121a, the second traveling unit 121b, the third traveling unit 121c, and the fourth traveling unit 121d. Furthermore, for example, if the rebar binding robot 100 is positioned parallel or nearly parallel to a virtual plane formed by the group of rebars R, the height of the rebar binding robot 100 may be determined from any one of the heights of the first traveling unit 121a, the second traveling unit 121b, the third traveling unit 121c, and the fourth traveling unit 121d.

[0041] 7, the sensor unit 130 may include an inclination detection sensor 132 in addition to the first to fourth sensors 130a to 130d described above. The inclination detection sensor 132 may be, for example, a known inclination sensor or horizontal sensor, or any other sensor capable of detecting the inclination angle of the rebar binding robot 100. The sensor detection result acquisition unit 162 may also acquire the detection results of the inclination detection sensor 132. Based on the detection result of the inclination detection sensor 132, for example, the posture of the rebar binding robot 100 may be determined by the posture determination unit 164c of the determination unit 164, and based on the determination result of the posture determination unit 164c, the posture control unit 176 may drive the height change motors 126 of the running units 121 (the first height change motor 126a of the first running unit 121a, the second height change motor 126b of the second running unit 121b, the third height change motor 126c of the third running unit 121c, and / or the height change motor 126d of the fourth running unit 121d) to adjust the posture of the rebar binding robot 100.

[0042] The rebar binding robot 100 may drive the height change motor 126 based on the detection result of the inclination detection sensor 132 so that the main unit 140 is parallel to the surface formed by the first rebar R10 and / or the second rebar R20 (also referred to as the "rebar surface" in this embodiment). For example, if the first rebar R10 and the second rebar R20 are arranged so that the rebar surface extends horizontally and the rebar binding robot 100 is tilted in the X direction, the posture of the rebar binding robot 100 may be adjusted by changing the height of the first traveling unit 121a and the third traveling unit 121c, or the second traveling unit 121b and the fourth traveling unit 121d, among the first traveling unit 121a to the fourth traveling unit 121d.

[0043] The intersection point calculation unit 166 estimates the intersection point c12 by calculating the intersection point c12 of the first reinforcing bar R10 and the second reinforcing bar R20. For example, as described below, the intersection point calculation unit 166 may calculate the position of the intersection point c12 based on the positions of the first reinforcing bar R10 and the second reinforcing bar R20 determined by the first reinforcing bar determination unit 164a1 and the second reinforcing bar determination unit 164a2. Based on the calculated position of the intersection point c12, the reinforcing bar binding robot 100 may perform binding work using the reinforcing bar binding unit 110. Based on the estimated position of the intersection point c12, the motor control unit 178 may adjust the position of the reinforcing bar binding robot 100 using the first traveling unit 121a, the second traveling unit 121b, the third traveling unit 121c, and / or the fourth traveling unit 121d so that the reinforcing bar binding unit 110 is located over the intersection point c12.

[0044] The rebar binding unit control unit 168 controls the movement of the rebar binding unit 110 by controlling the rebar binding unit moving unit 168m. The rebar binding unit 110 can be positioned between a binding position where it performs a binding operation to bind the intersection c12 where the first rebar R10 and the second rebar R20 intersect, and a retracted position where it retreats after completing the binding operation and moves to the intersection c12 where the next binding operation will be performed. The rebar binding unit 110 moves in the -Z direction when moving from the retracted position to the binding position, and moves in the +Z direction when moving from the binding position to the retracted position. Such movement of the rebar binding unit 110 in the Z direction is achieved by the rebar binding unit moving unit 168m, which is configured, for example, by a motor. The rebar binding unit control unit 168 also controls the lifting and lowering operation of the rebar binding unit 110 in the Z direction by the rebar binding unit moving unit 168m.

[0045] The rebar binding unit control unit 168 also controls the binding operation of the rebar binding unit 110 at the intersection c12 after the rebar binding unit 110 has moved to the binding position. For example, the binding work performed by the rebar binding unit 110 using a wire drawn out from a wire reel 180 by a wire draw-out unit (described later) is controlled by the rebar binding unit control unit 168. For example, after the first traveling unit 121a, the second traveling unit 121b, the third traveling unit 121c, and / or the fourth traveling unit 121d have moved the rebar binding robot 100 so that the rebar binding unit 110 is positioned above the intersection c12, the rebar binding unit control unit 168 may control the rebar binding unit moving unit 168m to lower the rebar binding unit 110 to the binding position so as to approach the intersection c12, and then perform binding at the intersection c12.

[0046] The rebar following control unit 170 may, for example, use the motor control unit 178 to control the traveling unit 121 so that the rebar binding robot 100 follows the first rebar R10 while traveling, based on information such as the position of the first rebar R10 determined by the first rebar determination unit 164a1. For example, as shown in Fig. 5, when the rebar binding robot 100 travels between the first rebar R12 and the first rebar R14, the motor control unit 178 may drive the drive motors of the traveling unit 121 (the first wheel drive motor 124a that drives the first roller unit 122a, the second wheel drive motor 124b that drives the second roller unit 122b, the third wheel drive motor 124c that drives the third roller unit 122c, and / or the fourth wheel drive motor 124d that drives the fourth roller unit 122d) to prevent the rebar binding robot 100 from detaching from the first rebar R12 and the first rebar R14.

[0047] For example, the first wheel drive motor 124a and the third wheel drive motor 124c, which are the drive motors of the first traveling unit 121a and the third traveling unit 121c, among the first wheel drive motor 124a, the second wheel drive motor 124b, the third wheel drive motor 124c, and the fourth wheel drive motor 124d, which are arranged at the same position or approximately the same position in the X direction, may be accelerated or decelerated relative to the second wheel drive motor 124b and the fourth wheel drive motor 124d, which are the drive motors of the second traveling unit 121b and the fourth traveling unit 121d, which are arranged on the other side in the X direction, to adjust the position of the rebar binding robot 100 and make the rebar binding robot 100 travel to follow the first rebar R10.

[0048] Alternatively, the rebar tracking control unit 170 may adjust the rotation speed of the first wheel drive motor 124a, the second wheel drive motor 124b, the third wheel drive motor 124c, and / or the fourth wheel drive motor 124d, for example, to cause the rebar binding robot 100 to travel so as to follow the first rebar R10. For example, by setting one or more rotation speeds of the first wheel drive motor 124a, the second wheel drive motor 124b, the third wheel drive motor 124c, and the fourth wheel drive motor 124d to be different from the rotation speeds of the other wheel drive motors, or by setting the rotation speeds of all of the first wheel drive motor 124a, the second wheel drive motor 124b, the third wheel drive motor 124c, and the fourth wheel drive motor 124d to be different from one another, the rebar binding robot 100 can be made to flexibly follow the first rebar R10.

[0049] The stop control unit 172 is configured to control the stopping operation of the rebar binding robot 100. For example, as described below, when the first rebar end determination unit 164b1 and / or the second rebar end determination unit 164b2 determine that the rebar binding robot 100, which has traveled over the first rebar R12 and the first rebar R14, is near or approaching the end of the first rebar R13 based on the detection results of the first sensor 130a, the second sensor 130b, the third sensor 130c, and / or the fourth sensor 130d, the stop control unit 172 may control the motor control unit 178 to drive and stop the first wheel drive motors 124a to the fourth wheel drive motors 124d, thereby stopping the rebar binding robot 100. In addition, the rebar tying robot 100 may be stopped not only at the end of the first rebar R13, but also when it is determined that the rebar tying robot 100 is near the end of the first rebar R12 and / or the end of the first rebar R14, or is approaching the end, instead of or in addition to the end.

[0050] In addition, the stop control unit 172 may stop the rebar binding robot 100, for example, when the intersection point c12 of the first rebar R10 and the second rebar R20 is calculated by the above-mentioned intersection point calculation unit 166, in order to bind the intersection point c12 using the rebar binding unit 110.

[0051] As described below, the movement amount calculation unit 174 may be configured to calculate, for example, the amount of movement when the rebar binding robot 100 moves laterally (in the X direction). For example, as described above, when the first rebar end determination unit 164b1 and / or the second rebar end determination unit 164b2 determine that the rebar binding robot 100 is near or approaching the end of the first rebar R12 and the end of the first rebar R14, the rebar binding robot 100 completes the rebar binding work at the intersection c12 on the first rebar R13 located between the first rebar R12 and the first rebar R14, moves to another first rebar R10, and starts the rebar binding work at the intersection c12.

[0052] For example, if the rebar binding robot 100 completes the rebar binding work at the intersection c12 on the first rebar R13 and then performs the rebar binding work at the intersection c12 on the first rebar R14, the rebar binding robot 100 moves in the X direction by one interval for the X-direction spacing of the first rebars R10. At this time, the movement amount calculation unit 174 may calculate the movement amount based on the X-direction spacing between adjacent first rebars R10, based on information about the positions of the first rebars R10 determined by the first rebar determination unit 164a1. Similarly, when the rebar binding robot 100 performs the rebar binding work at the intersection c12 on first rebars R10 that are spaced apart by two or more in the X direction, the movement amount may be calculated based on the spacing between the first rebars R10. Furthermore, the lateral movement unit 146 may perform lateral movement (e.g., horizontal movement) of the main unit 140 during lateral movement based on the calculated movement amount. The movement amount calculation unit 174 may calculate the amount of movement in a direction other than the horizontal movement amount. For example, the movement amount calculation unit 174 may calculate the amount of vertical movement (movement in the first direction, Y direction) of the rebar binding robot 100 based on the detection results of the sensors 130a to 130d, the determination results of the rebar end determination unit 164b1 and / or the rebar end determination unit 164b2, etc.

[0053] The sensor unit 130 may be, for example, a camera capable of capturing two-dimensional or three-dimensional images. The location of a foreign object may be determined, for example, by the obstacle determination unit 164d of the determination unit 164 based on the detection results of the sensor unit 130. At a construction site where rebar is being assembled, for example, tools or other objects may be left on the surface of the rebar, or workers may be working on the rebar. These objects may be detected as foreign objects based on the detection results of the sensor unit 130. Based on the foreign object detection results, the foreign object detouring control unit 179 may be configured to detouring the foreign object by driving the first wheel drive motor 124a, the second wheel drive motor 124b, the third wheel drive motor 124c, and / or the fourth wheel drive motor 124d via the motor control unit 178. Alternatively, the rebar binding robot 100 may be configured to detouring the foreign object by performing lateral movement, which will be described later.

[0054] The control unit 160 is, for example, a processor such as a CPU (Central Processing Unit) that corresponds to a calculation unit, and is a control unit that controls the execution of computer programs stored in the storage device 198 and calculates and processes data. The processor is a calculation unit that executes programs that perform operations of the rebar binding robot 100 (rebar tracking and traveling, lateral movement (e.g., horizontal movement), rebar binding work, etc.) using each piece of detection data, etc. The processor executes the programs stored in the storage device 198, thereby realizing each unit of the control unit (e.g., sensor detection result acquisition unit 162, etc.).

[0055] The storage device 198 may include, for example, a RAM (Random Access Memory) and a ROM (Read Only Memory). The RAM is a memory unit that allows data to be rewritten and may be configured, for example, with a semiconductor memory element. The RAM may store programs executed by the processor and data required for executing the programs (for example, template data used to determine the position of rebar based on the detection results of the sensor unit 130, as described below). Note that these are merely examples, and the RAM may store other data or may not store some of the data.

[0056] The ROM is a memory from which data can be read and may be configured, for example, by a semiconductor memory element. The ROM may store, for example, programs executed by the control unit 160 and data that is not rewritten.

[0057] The program executed by the control unit 160 may be provided by being stored in a computer-readable storage medium such as the storage device 198 (e.g., RAM or ROM), or if the rebar binding robot 100 according to this embodiment has a communication unit (not shown), the program may be provided via a communication network connected by the communication unit.

[0058] The above physical configuration is an example, and in the rebar binding robot 100 according to the embodiment of the present disclosure, the control unit 160 and the storage device 198 do not necessarily have to be independent. For example, the rebar binding robot 100 may be equipped with an LSI (Large-Scale Integration) that integrates a processor and memory. The rebar binding robot 100 may also be equipped with a GPU (Graphical Processing Unit) as the control unit 160, and the GPU may execute programs to realize the various operations described above.

[0059] Next, the traveling operation of the rebar bundling robot 100 on rebars will be described with reference to FIGS. 8 and 9 . FIG. 8 is a view of the rebar bundling robot 100 traveling along the first rebar R10, as viewed from the Y direction (−Y direction). FIG. 9 is a view of the rebar bundling robot 100 traveling along the first rebar R10, as viewed from the X direction (+X direction). In FIGS. 8 and 9 , the rebar bundling robot 100 travels in a first direction (Y direction). As shown in FIGS. 8 and 9 , the rebar bundling robot 100 travels such that the third roller 122c of the third traveling unit 121c is on the first rebar R12 and the fourth roller 122d of the fourth traveling unit 121d is on the first rebar R14. As shown in Fig. 9, the second roller portion 122b of the second traveling unit 121b also travels on the first rebar R14, similar to the fourth roller portion 122d of the fourth traveling unit 121d. Although not shown in Figs. 8 and 9, the first roller portion 122a of the first traveling unit 121a also travels on the first rebar R12, similar to the third roller portion 122c of the third traveling unit 121c. In this way, when the rebar tying robot 100 according to an embodiment of the present disclosure runs along the first rebar R10, it runs, for example, between a certain first rebar R10 (first rebar R12) and a first rebar R10 (first rebar R14) located two rebars away from the certain first rebar R12, and ties the intersection c12 of the first rebar R10 and the second rebar R20 located on the first rebar R13, which is the first rebar R10 located between the running first rebar R12 and the first rebar R14.

[0060] Next, the rebar bundling robot 100 during rebar bundling work will be described with reference to FIGS. 10, 11, and 12. FIG. 10 is a view of the rebar bundling robot 100 performing bundling work, viewed from the Y direction (-Y direction), with the robot 100 having stopped traveling. FIG. 11 is a view of the rebar bundling robot 100 performing bundling work, viewed from the X direction (+X direction). FIG. 12 is a view of the rebar bundling robot 100 performing bundling work, viewed from below in the Z direction (-Z direction). FIGS. 10, 11, and 12 show an example in which the rebar bundling robot 100 binds the intersection c12 of the first rebar R13 and the second rebar R20. When performing bundling work, the rebar bundling robot 100 stops traveling (FIG. 10) and lowers the rebar bundling unit 110 to perform bundling (FIGS. 11 and 12).

[0061] Next, we will explain the arrangement and configuration of the first roller portion 122a (an example of a "first wheel"), second roller portion 122b (an example of a "second wheel"), third roller portion 122c (an example of a "third wheel"), and fourth roller portion 122d (an example of a "fourth wheel") of the rebar binding robot 100 according to this embodiment.

[0062] The inventors of the present application focused on the fact that the pitch of the first rebars R10 on which the rebar tying robot 100 travels may vary depending on the type of reinforced concrete structure, and devised a wheel arrangement and configuration for traveling on multiple types of rebars arranged at different pitches. Figures 13A and 13B are front views of the rebar tying robot 100 traveling on multiple first rebars R10 arranged at a pitch of 130 mm (an example of the "first pitch P1") and a pitch of 220 mm (an example of the "second pitch P2"), as seen from the +Y direction, which is the traveling direction of the rebar tying robot 100. The wheel arrangement and configuration will be described in detail below.

[0063] The first roller unit 122a is configured to be able to travel on one first rebar R10 (e.g., first rebar R12) by rotating while in contact with the first rebar R10. As described above, the first roller unit 122a is rotationally driven by the first wheel drive motor 124a (FIG. 7) of the first traveling unit 121a.

[0064] Here, the first roller unit 122a is formed in a cylindrical shape with a central axis extending in a direction (e.g., X direction) perpendicular to the direction of travel (e.g., +Y direction). With this configuration, the first roller unit 122a and the rebar binding robot 100 are configured to be able to travel on the first rebar R10 regardless of the position in the width direction (X direction) of the first roller unit 122a that the first rebar R12 is in contact with.

[0065] As shown in the figure, a pair of flanges 122aX may be formed on both ends of the first roller portion 122a in the width direction (X direction) so as to protrude in the vertical direction when viewed from the front in the +Y direction. By forming the flanges 122aX, it is possible to prevent the first roller portion 122a from coming off the first reinforcing bar R12 and running off.

[0066] [Width of Roller Unit] Here, the width W1 of the first roller unit 122a (the width of the area in the X direction, which is perpendicular to the direction of travel, where the first roller unit 122a can travel by rotating while in contact with the first rebar R10) is formed to be larger than the difference between the two pitches at which the rebar binding robot 100 is expected to travel, i.e., the difference between the second pitch P2 and the first pitch P1. For example, if the second pitch P2 is 220 mm and the first pitch P1 is 130 mm, the difference between the second pitch P2 and the first pitch P1 is 90 mm. Therefore, the width of the first roller unit 122a is formed to be larger than 90 mm.

[0067] The distance between any first reinforcing bars R10 (FIG. 13A) arranged at the first pitch P1 and any first reinforcing bars R10 (FIG. 13B) arranged at the second pitch P2 is equal to or less than the difference between the two pitches. For example, as shown in FIGS. 13A and 13B, when a first reinforcing bar R13, which is a first reinforcing bar R10 to be tied to a second reinforcing bar R20, is located between the first roller portion 122a and the second roller portion 122b in the width direction (X direction), the distance between the first reinforcing bar R12 adjacent to the first reinforcing bar R13 in FIG. 13A and the first reinforcing bar R12 adjacent to the first reinforcing bar R13 in FIG. 13B is 90 mm, which is the difference between the two pitches. Therefore, by forming the width W1 of the first roller portion 122a to be greater than 90 mm, the first roller portion 122a can run on the first reinforcing bar R12 adjacent to the first reinforcing bar R13 to be bundled, whether the first reinforcing bar R12 is arranged at the first pitch P1 (Figure 13A), the second pitch P2 (Figure 13B), or any pitch greater than the first pitch P1 and less than the second pitch P2.

[0068] More specifically, when the first reinforcing bars R10 are arranged at a first pitch P1, the first roller portion 122a can run on the first reinforcing bars R12 with the area inside the widthwise center of the first roller portion 122a in contact with the first reinforcing bars R12, and when the first reinforcing bars R10 are arranged at a second pitch P2, the first roller portion 122a can run on the first reinforcing bars R12 with the area outside the widthwise center of the first roller portion 122a in contact with the first reinforcing bars R12.

[0069] Here, the second pitch P2 may be set in the specifications as the pitch of rebars that the rebar bundling robot R100 can bundle, or may be the maximum value at which the rebar bundling robot R100 can reasonably travel, and the first pitch P1 may be set in the specifications as the pitch of rebars that the rebar bundling robot R100 can bundle, or may be the minimum value at which the rebar bundling robot R100 can reasonably travel. For example, the second pitch P2 may be greater than 1.5 times and less than 2.5 times the first pitch P1.

[0070] On the other hand, the width W1 of the first roller portion 122a is configured to be smaller than the difference between 1.5 times the second pitch P2 and 0.5 times the first pitch P1. For example, if the second pitch P2 is 220 mm and the first pitch P1 is 130 mm, the difference between 1.5 times the second pitch P2 (330 mm) and 0.5 times the first pitch P1 (65 mm) is 265 mm. Therefore, the width W1 of the first roller portion 122a is configured to be smaller than 265 mm. With this configuration, whether the first reinforcing bars R10 are arranged at the first pitch P1 or the second pitch P2, when the first reinforcing bar R13, which is the first reinforcing bar R10 to be tied to the second reinforcing bar R20, is located midway between the first roller unit 122a and the second roller unit 122b in the width direction (X direction), the first roller unit 122a can run on one reinforcing bar, that is, the first reinforcing bar R12, which is adjacent to the first reinforcing bar R13 to be tied. This makes it possible to run on reinforcing bars with different pitches P1 and P2 without requiring prior adjustment.

[0071] Here, the width W1 of the first roller unit 122a may be less than twice the first pitch P1 (i.e., less than 260 mm in this embodiment). With this configuration, even if the first reinforcing bars R10 are arranged at the first pitch P1, when a first reinforcing bar R13, which is the first reinforcing bar R10 to be tied to a second reinforcing bar R20, is located midway between the first roller unit 122a and the second roller unit 122b in the width direction (X direction), the first roller unit 122a can run over a single first reinforcing bar R12 adjacent to the first reinforcing bar R13 to be tied at the center in the width direction.

[0072] The second roller unit 122b, the third roller unit 122c, and the fourth roller unit 122d may have the same configuration as the first roller unit 122a, and therefore detailed description thereof will be omitted. That is, the second roller unit 122b, the third roller unit 122c, and the fourth roller unit 122d are configured to be able to run on the first rebar R14, the first rebar R12, and the first rebar R14, respectively, by rotating on the first rebar R10 while in contact with the first rebar R10. The width of each roller unit, including the width W2 of the second roller unit 122b (FIGS. 13A and 13B), is configured to be greater than the difference between the two pitches at which the rebar binding robot 100 is expected to run, i.e., the difference between the second pitch P2 and the first pitch P1, but smaller than the difference between 1.5 times the second pitch P2 and 0.5 times the first pitch P1.

[0073] The first roller unit 122a and the third roller unit 122c arranged in the front-rear direction each rotate and run on the same rebar (e.g., the first rebar R12), and the second roller unit 122b and the fourth roller unit 122d arranged in the front-rear direction each rotate and run on the same rebar (e.g., the first rebar R14). The configuration including the first wheel drive motor 124a that drives the first roller unit 122a and the second wheel drive motor 124b that drives the second roller unit 122b may be collectively referred to as a drive unit.

[0074] [Gap Between Roller Portions] Next, the gap SP between the first roller portion 122a and the second roller portion 122b will be described. The gap SP between the first roller portion 122a and the second roller portion 122b is preferably larger than the first pitch P1.

[0075] With this configuration, it is possible to move the rebar binding robot 100 so that at least one first rebar R10 (first rebar R13 in FIGS. 13A and 13B ) is present in the region between the region where the first roller unit 122a is provided and the region where the second roller unit 122b is provided in the X direction, which is perpendicular to the traveling direction. Therefore, the first sensor 130a (an example of a "detection unit") and the second sensor 130b (an example of a "detection unit") provided between the first roller unit 122a and the second roller unit 122b can detect the first rebar R13 located between the first rebar R12 with which the first roller unit 122a comes into contact and the first rebar R14 with which the second roller unit 122b comes into contact.

[0076] Therefore, the rebar binding robot 100 is configured such that the first sensor 130a and the second sensor 130b detect the first rebar R13, which is the middle first rebar R10 of three adjacent first rebars R10, and the first roller unit 122a runs while rotating over the adjacent first rebar R12 on the one hand, and the second roller unit 122b runs while rotating over the adjacent first rebar R14 on the other hand. The drive unit, including the first wheel drive motor 124a and the second wheel drive motor 124b, is configured to rotate the first roller unit 122a and the second roller unit 122b based on the position of the middle first rebar R13 detected by the first sensor 130a and / or the position of the middle first rebar R13 detected by the second sensor 130b.

[0077] With this configuration, the sensor unit 130 can detect the first rebar R10 immediately adjacent to the first rebar R10 that the two rollers, the first roller unit 122a and the second roller unit 122b, are traveling over, and the first roller unit 122a and the second roller unit 122b can be driven to rotate based on the detection results, thereby enabling the rebar binding robot 100 to travel with high precision. Furthermore, the first rebar R10 detected by the sensor unit 130 is bound using the rebar binding unit 110 (an example of a "binding unit"), making it possible to detect the binding position with high precision.

[0078] Furthermore, the interval SP between the first roller portion 122a and the second roller portion 122b (the distance between the inner end of the first roller portion 122a and the inner end of the second roller portion 122b) is preferably smaller than twice the first pitch P1.

[0079] If the interval SP between the first roller unit 122a and the second roller unit 122b were greater than twice the first pitch P1, there would be a possibility that the first sensor 130a and the second sensor 130b would detect two or more first rebars R10. However, by making the interval SP smaller than twice the first pitch P1, it becomes possible to identify that the first rebar R10 detected by the first sensor 130a and the second sensor 130b is the middle first rebar R13. In this embodiment, the first pitch P1 is 130 mm, so it is preferable that the interval SP between the first roller unit 122a and the second roller unit 122b be greater than 130 mm and less than 260 mm.

[0080] In addition, when each roller part, including the first roller part 122a, has an inner surface as in this embodiment, it can be said that it is preferable that the distance between the inner surface (the side facing inward) of the first roller part 122a and the inner surface (the side facing inward) of the second roller part 122b is greater than 130 mm and less than 260 mm.

[0081] On the other hand, it is preferable that the distance between the outer end of the first roller portion 122a and the outer end of the second roller portion 122b in a direction (e.g., X direction) perpendicular to the direction of travel (e.g., +Y direction) be greater than twice the second pitch P2, i.e., 440 mm, and less than three times the second pitch P2, i.e., 660 mm.

[0082] When the distance between the outer end (outer surface) of the first roller portion 122a and the outer end (outer surface) of the second roller portion 122b is greater than 440 mm and less than 660 mm, when arranged at the second pitch P2, there will always be three first reinforcing bars R10 between the outer end (outer surface) of the first roller portion 122a and the outer end (outer surface) of the second roller portion 122b.

[0083] Therefore, in the rebar binding robot 100, the first sensor 130a and the second sensor 130b detect the first rebar R13, which is the middle first rebar R10 of three adjacent first rebars R10, and the first roller unit 122a runs while rotating over the adjacent first rebar R12, and the second roller unit 122b runs while rotating over the other adjacent first rebar R14. Therefore, based on the position of the middle first rebar R13 detected by the first sensor 130a and / or the position of the middle first rebar R13 detected by the second sensor 130b, the drive unit including the first wheel drive motor 124a and the second wheel drive motor 124b can drive and rotate the first roller unit 122a and the second roller unit 122b.

[0084] The above-described arrangement and configuration of the first roller unit 122a and the second roller unit 122b are the same for the third roller unit 122c and the fourth roller unit 122d, and therefore detailed description thereof will be omitted. However, the first roller unit 122a and the second roller unit 122b of the rebar binding robot 100 do not have to have the same configuration as the third roller unit 122c and the fourth roller unit 122d. For example, the rebar binding robot may have any of the configurations of the first roller unit 122a and the second roller unit 122b described above as the third roller unit 122c and the fourth roller unit 122d, but may not have configurations corresponding to the first roller unit 122a and the second roller unit 122b. For example, this rebar binding robot may have a tricycle configuration including a third roller unit that runs on the single middle first rebar R10, i.e., the first rebar R13, instead of the first roller unit 122a and the second roller unit 122b.

[0085] As shown in Figures 13A and 13B, the rebar binding robot 100 configured as described above is configured to be able to run on a plurality of first rebars R10 arranged at a pitch of 130 mm (first pitch P1), and is also configured to be able to run on a plurality of first rebars R10 arranged at a pitch of 220 mm (second pitch P2), which is larger than the 130 mm pitch.

[0086] The rebar binding robot 100 having the above-described configuration can also travel continuously between a first travel area where a plurality of first rebars R10 are arranged at a first pitch P1 of 130 mm and a second travel area where a plurality of first rebars R10 are arranged at a second pitch P2 of 220 mm. Here, the rebar binding robot 100 can also travel over a plurality of first rebars R10 arranged at any pitch larger than the first pitch P1 and smaller than the second pitch P2, so it can travel while binding rebars even in an area where the arrangement pitch varies to connect the first and second travel areas.

[0087] The above-described embodiments are intended to facilitate understanding of the present invention and are not intended to limit the scope of the present invention. The present invention may be modified or improved without departing from its spirit, and equivalents are also included within the scope of the present invention. In other words, designs modified by those skilled in the art as appropriate are also encompassed within the scope of the present invention as long as they incorporate the characteristics of the present invention. For example, the elements and their arrangements, materials, conditions, shapes, sizes, etc. of the embodiments are not limited to those illustrated and can be modified as appropriate. Furthermore, the embodiments are merely examples, and partial substitutions or combinations of the configurations shown in different embodiments are naturally possible. These are also encompassed within the scope of the present invention as long as they incorporate the characteristics of the present invention.

[0088] This application is a Japanese patent application filed on January 20, 2023 (Patent Application No. 2023-007172), a Japanese patent application filed on January 20, 2023 (Patent Application No. 2023-007174), a Japanese patent application filed on January 20, 2023 (Patent Application No. 2023-007176), a Japanese patent application filed on January 20, 2023 (Patent Application No. 2023-007177), a Japanese patent application filed on January 20, 2023 (Patent Application No. 2023-007182), a Japanese patent application filed on January 20, 2023 (Patent Application No. 2023-007187), and a Japanese patent application filed on August 10, 2023 (Patent Application No. 2023-131031), the contents of which are incorporated by reference into this application.

[0089] The reinforcing bar binding device according to the present disclosure can improve tracking performance even when running over multiple reinforcing bars with different pitches.

[0090] REFERENCE SIGNS LIST 100...Rebar tying robot (rebar tying device) 110...Rebar tying unit (tying section) 122a...First roller section (first wheel) 122b...Second roller section (second wheel) 122c...Third roller section (first wheel) 122d...Fourth roller section (second wheel) 124a...First wheel drive motor (drive section) 124b...Second wheel drive motor (drive section) 124c...Third wheel drive motor (drive section) 124d...Fourth wheel drive motor (drive section) 130a, 130b...Sensor (detection section)

Claims

1. A steel bar bundling device configured to be able to travel on a plurality of steel bars arranged at a first pitch and also configured to be able to travel on a plurality of steel bars arranged at a second pitch greater than the first pitch, the steel bar bundling device comprising: a first wheel that rotates on the steel bars and has a width greater than the difference between the second pitch and the first pitch and less than the difference between 1.5 times the second pitch and 0.5 times the first pitch; a second wheel that rotates on the steel bars different from the first wheel and has a width greater than the difference between the second pitch and the first pitch and less than the difference between 1.5 times the second pitch and 0.5 times the first pitch; and a drive unit that rotationally drives the first wheel and the second wheel.

2. The steel bar bundling device according to claim 1, wherein the second pitch is less than 2.5 times the first pitch.

3. The steel bar bundling device according to claim 1, wherein the distance between the first wheel and the second wheel is greater than the first pitch and less than 2 times the first pitch.

4. The steel bar bundling device according to claim 1, further comprising a detection unit configured to be able to detect a steel bar located between the steel bar in contact with the first wheel and the steel bar in contact with the second wheel.

5. The steel bar bundling device according to claim 4, wherein the drive unit rotationally drives the first wheel and the second wheel based on the position of the steel bar detected by the detection unit.

6. The steel bar bundling device according to claim 5, wherein the drive unit rotationally drives the first wheel and the second wheel so that the first wheel and the second wheel move in the width direction based on the position of the steel bar detected by the detection unit.

7. The steel bar bundling device according to claim 1, wherein the steel bar bundling device is configured to be able to continuously travel on a first traveling area where a plurality of steel bars are arranged at the first pitch and a second traveling area where a plurality of steel bars are arranged at the second pitch.

8. The steel bar bundling device according to claim 1, wherein the width of the first wheel and the width of the second wheel are greater than 90 mm and less than 265 mm.

9. The steel bar bundling device according to claim 1, wherein the distance between the outer surfaces of the first wheel and the second wheel is greater than 440 mm and less than 660 mm, and the distance between the inner surfaces of the first wheel and the second wheel is greater than 130 mm and less than 260 mm.

10. The reinforcing bar binding device according to claim 1, wherein the first wheel and the second wheel are columnar and extend in a direction intersecting the traveling direction of the reinforcing bar binding device.

11. The reinforcing bar binding device according to claim 4, further comprising a binding portion provided between the first wheel and the second wheel and configured to be able to bind a reinforcing bar detected by the detection portion to another reinforcing bar intersecting the reinforcing bar.