Bidet

MYPI2025003976A0Undetermined Publication Date: 2024-06-29COWAY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
MYPI2025003976
Authority / Receiving Office
MY · MY
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-08-29
Filing Date
2023-08-29
Publication Date
2024-06-29

AI Technical Summary

Technical Problem

Existing bidet designs require a water level sensor, which increases manufacturing costs and complexity, and can lead to issues like continuous heating without water, due to the need for magnetoresistive sensors and complex circuitry, and difficulties in distinguishing between sensor and nozzle valve failures.

Method used

A bidet that detects water presence using temperature sensors at the inlet and outlet, allowing the control device to determine water levels without a traditional water level sensor, thereby reducing costs and simplifying the configuration.

Benefits of technology

Enables effective water level detection and prevents unnecessary heating, reducing costs and improving reliability by using temperature differences to assess water presence within the bidet.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure PI2025003976_DRAWING_001
    Figure PI2025003976_DRAWING_001
  • Figure PI2025003976_DRAWING_002
    Figure PI2025003976_DRAWING_002
  • Figure PI2025003976_DRAWING_003
    Figure PI2025003976_DRAWING_003
Patent Text Reader

Abstract

A bidet includes: a spray nozzle assembly with a spray hole; a water body having an inlet for receiving water from a water supply source, and an outlet through which water flows to the spray hole; a sensor unit for measuring the temperature of the water body; a valve module that opens / closes to allow water to flow into or out of the water body; and a controller that controls the spray nozzle assembly, the water body, and the valve module. The controller performs water detection control to determine the presence / absence of water in the water body, determines the presence / absence of water in the water body on the basis of the relationship between a first temperature measured before controlling the valve module, and a second temperature measured after performing the water detection control, and controls the valve module based on the presence / absence of water in the water body.
Need to check novelty before this filing date? Find Prior Art

Description

Bidet

[0001] The present invention relates to a bidet.

[0002] Typically installed above the toilet, a bidet is a device used to cleanse the user's body. These bidets include a cleansing nozzle capable of spraying cleansing water toward the user, and can cleanse the user's body by spraying the water at a predetermined pressure.

[0003] Additionally, the bidet is equipped with a water tank for temporarily storing cleansing water, and a water level sensor is installed within the water tank to detect the water level contained therein. This water level sensor maintains the cleansing water within the water tank at a predetermined level, and when cleansing water is discharged, cleansing water flows into the water tank up to the predetermined level.

[0004] The applicant's Korean Patent Publication No. 10-0814966 "Bidet water level detection device" (Patent Document 1) discloses a water level detection device capable of detecting the water level in a water tank.

[0005] However, the water level detection device of Patent Document 1 includes a magnetic resistance sensor and a magnet for water level detection, which increases the manufacturing cost. In addition, a water level detection float including a weight balance is required to prevent the water level detection device from becoming unbalanced due to the magnet, which complicates the configuration of the water level detection device. In addition, the circuit of the printed circuit board must be more complex, which increases the manufacturing cost of the printed circuit board. In addition, if the water level detection device of Patent Document 1 breaks down, there is a risk that the water level detection device will not properly detect the water level, causing the heater to continuously heat the water tank even if there is no water inside the water tank.

[0006] Accordingly, a bidet is being developed that can determine whether the water level detection device is broken when the water level detection device is broken.

[0007] Korean Patent Publication No. 10-2014-0061157, "Bidet malfunction inspection method, bidet expected power consumption calculation method, and bidet using the same" (Patent Document 2) of the present applicant, discloses a bidet capable of determining whether a water level sensor is abnormal. In addition, the bidet of Patent Document 2 controls a nozzle valve that supplies cleaning water stored in a water tank to a nozzle unit in a predetermined pattern, and determines whether the water level sensor detects this pattern to determine whether the water level sensor is abnormal.

[0008] However, in the bidet of Patent Document 2, if the nozzle valve malfunctions, the operating pattern of the nozzle valve itself may be incorrect, making it difficult to determine whether the water level sensor or the nozzle valve is malfunctioning. Furthermore, to determine whether the water level sensor is malfunctioning, other components, such as the nozzle valve, must be included in the bidet, increasing costs.

[0009] Therefore, there is a need for a bidet that can detect the water level contained within the bidet without a water level detection sensor.

[0010] One embodiment of the present invention was invented with the above background in mind, and aims to provide a bidet capable of detecting the water level contained in the bidet without a water level detection sensor.

[0011] In addition, one embodiment of the present invention seeks to provide a bidet that can reduce the cost required for a water level detection sensor by not having a water level detection sensor.

[0012] According to one embodiment of the present invention, a bidet capable of detecting the presence or absence of water inside by measuring the temperature of water comprises: a spray nozzle assembly having a spray hole formed to spray water onto a user's body; a water body having an inlet for introducing water from an external water source and an outlet for introducing water toward the spray hole; a sensor unit for measuring the temperature of the water body; a valve module for opening and closing to allow water to be introduced into or discharged from the water body; And a control device that controls at least one of the spray nozzle assembly, the water body, and the valve module, wherein the control device executes water detection control to determine the presence or absence of water in the water body, and controls the valve module to allow water to flow in the water body based on a relationship between a first temperature, which is a temperature of the water body measured by the sensor unit before controlling the valve module, and a second temperature, which is a temperature of the water body measured by the sensor unit after executing the water detection control, to determine the presence or absence of water in the water body, and controls the valve module according to the presence or absence of water in the water body.

[0013] In addition, the water detection control includes a water supply control that controls the valve module to allow water to flow into the water body through the inlet for a preset water supply time, and the control device obtains the first temperature, which is the temperature of the water body measured by the sensor unit before executing the water supply control, and obtains the second temperature, which is the temperature of the water body measured by the sensor unit after executing the water supply control, so as to determine the presence or absence of water in the water body based on the relationship between the first temperature and the second temperature.

[0014] Additionally, the control device can determine that water exists in the water body if the difference between the first temperature and the second temperature is greater than a preset value.

[0015] In addition, the sensor unit includes an inlet temperature sensor for measuring the temperature of the inlet, and the first temperature and the second temperature can be measured by the inlet temperature sensor.

[0016] In addition, the water detection control includes a drain control that controls the valve module to allow water that has flowed into the inside of the water body to flow out of the water body through the outlet, and the control device obtains the first temperature, which is the temperature of the water body measured by the sensor unit before executing the drain control, and obtains the second temperature, which is the temperature of the water body measured by the sensor unit after executing the drain control, so as to determine the presence or absence of water in the water body based on the relationship between the first temperature and the second temperature.

[0017] Additionally, the control device can determine that water exists in the water body if the difference between the first temperature and the second temperature is greater than a preset value.

[0018] In addition, the control device may additionally perform the drain control if the difference between the first temperature and the second temperature is less than a preset value, and determine the presence or absence of water in the water body based on the relationship between the first re-measured temperature obtained from the sensor unit before the additional drain control is performed and the second re-measured temperature obtained from the sensor unit after the additional drain control is performed.

[0019] Additionally, the control device can determine that water exists in the water body if the difference between the first re-measured temperature and the second re-measured temperature is greater than a preset value.

[0020] In addition, the sensor unit includes an outlet temperature sensor for measuring the temperature of the outlet, and the first temperature and the second temperature can be measured by the outlet temperature sensor.

[0021] Additionally, the control device can execute the drain control when the first temperature is greater than a predetermined value.

[0022] In addition, the water body further includes a heater capable of heating water, and the water detection control includes a heating control for operating the heater for a predetermined time, and the control device can obtain the first temperature, which is the temperature of the water body measured by the sensor unit before executing the heating control, and obtain the second temperature, which is the temperature of the water body measured by the sensor unit after executing the heating control.

[0023] Additionally, the control device can determine that water exists in the water body if the difference between the first temperature and the second temperature is less than a preset value.

[0024] In addition, the control device may additionally perform the heating control if the difference between the first temperature and the second temperature is greater than a preset value, and may determine the presence or absence of water in the water body based on a relationship between a first re-measured temperature acquired from the sensor unit before the additional heating control is performed and a second re-measured temperature acquired from the sensor unit after the additional heating control is performed.

[0025] Additionally, the control device can determine that water exists in the water body if the difference between the first re-measured temperature and the second re-measured temperature is less than a preset value.

[0026] In addition, the sensor unit includes an outlet temperature sensor for measuring the temperature of the outlet, and the first temperature and the second temperature can be measured by the outlet temperature sensor.

[0027] Additionally, the control device can execute the heating control when the first temperature is lower than a predetermined value.

[0028] In addition, the water detection control is a water supply control that controls the valve module to allow water to flow into the water body through the inlet for a preset water supply time; And a drain control that controls the valve module to allow water that has flowed into the inside of the water body to flow out of the water body through the outlet, wherein the control device executes the water supply control, and obtains the first temperature, which is the temperature of the water body measured by the sensor unit before executing the water supply control, and obtains the second temperature, which is the temperature of the water body measured by the sensor unit after executing the water supply control, and determines that water exists in the water body if the difference between the first temperature and the second temperature is greater than a preset water supply control temperature difference value, and if the difference between the first temperature and the second temperature is less than a preset value, the drain control is additionally executed, and determines that water exists in the water body if the difference between the temperature of the water body measured by the sensor unit before executing the drain control and the temperature of the water body measured by the sensor unit after executing the drain control is greater than a preset drain control temperature difference value.

[0029] In addition, the water detection control further includes a heater capable of heating water inside the water body and at least one of the water bodies, and the water supply control controls the valve module to allow water to flow into the water body through the inlet for a preset water supply time; And a heating control that operates the heater for a predetermined time, wherein the control device executes the water supply control, and obtains the first temperature, which is the temperature of the water body measured by the sensor unit before executing the water supply control, and obtains the second temperature, which is the temperature of the water body measured by the sensor unit after executing the water supply control, and if the difference between the first temperature and the second temperature is greater than a preset value, it is determined that water exists in the water body, and if the difference between the first temperature and the second temperature is less than a preset value, the heating control is executed, and if the difference between the temperature of the water body measured by the sensor unit before executing the heating control and the temperature of the water body measured by the sensor unit after executing the heating control is less than a preset heating control temperature difference value, it is determined that water exists in the water body.

[0030] Additionally, when it is determined that water exists in the water body, the control device can control the valve module to allow more water to enter the water body for a predetermined period of time.

[0031] In addition, the control device can determine whether the difference between the third temperature, which is the temperature at which water is determined to exist in the water body, and the first temperature, for the predetermined period of time, is outside a pre-input reference temperature range, and can control the valve module to be closed before the predetermined period of time elapses if the difference between the third temperature and the first temperature is outside the reference temperature range.

[0032] In addition, the water detection control includes a water supply control that controls the valve module to allow water to flow into the water body through the inlet for a preset water supply time, and the control device can perform a freeze determination control that obtains the first temperature, which is the temperature of the water body measured by the sensor unit, before executing the water supply control, and determines whether at least one of the water body and the valve module is frozen based on the first temperature.

[0033] In addition, the control device, in the freezing judgment control, if the first temperature is lower than the pre-input freezing judgment temperature, opens the valve module for a pre-input freezing judgment time, and if the first temperature is lower than the pre-input freezing judgment temperature after the freezing judgment time, determines that at least one of the water body and the valve module is frozen, and in the freezing judgment control, if the first temperature is higher than the pre-input freezing judgment temperature, determines that it is not frozen.

[0034] According to one embodiment of the present invention, there is an effect of being able to detect the water level contained in a bidet without a water level detection sensor.

[0035] In addition, according to one embodiment of the present invention, there is an effect of reducing the cost required for a water level detection sensor by not having a water level detection sensor.

[0036] In addition, the bidet according to one embodiment of the present invention has the effect of being able to determine whether it is frozen without a water level detection sensor.

[0037] FIG. 1 is a block diagram schematically showing a bidet according to one embodiment of the present invention.

[0038] Figure 2 is a flowchart of freezing judgment control according to one embodiment of the present invention.

[0039] Figure 3 is a flowchart showing the water supply base control of a bidet according to one embodiment of the present invention.

[0040] Figure 4 is a flowchart showing normal closing control of a bidet according to one embodiment of the present invention.

[0041] Figure 5 is a flowchart showing the heating base control of a bidet according to one embodiment of the present invention.

[0042] Figure 6 is a flowchart showing the drain base control of a bidet according to one embodiment of the present invention.

[0043] Figure 7 is a flowchart showing how the water supply base control, heating base control, and drain base control of a bidet are linked and performed according to one embodiment of the present invention.

[0044] Hereinafter, specific embodiments for implementing the technical idea of ​​the present invention will be described in detail with reference to the drawings.

[0045] In addition, when explaining the present invention, if it is determined that a detailed description of a related known configuration or function may obscure the gist of the present invention, the detailed description is omitted.

[0046] Additionally, when it is said that a component is 'inflowing into' or 'supplied into' another component, it should be understood that it may be directly inflowing into or supplied to that other component, but there may also be other components in between.

[0047] The terminology used herein is intended solely to describe specific embodiments and is not intended to limit the invention. Singular expressions include plural expressions unless the context clearly dictates otherwise.

[0048] Additionally, terms that include ordinal numbers, such as "first," "second," etc., may be used to describe various components, but these components are not limited by such terms. These terms are used solely to distinguish one component from another.

[0049] The term "comprising" as used in the specification means specifying a particular characteristic, region, integer, step, operation, element and / or component, but does not exclude the presence or addition of other particular characteristics, regions, integers, steps, operations, elements, components and / or groups.

[0050] Hereinafter, a specific configuration of a bidet (1) according to one embodiment of the present invention will be described with reference to the drawings.

[0051] Referring to Fig. 1, a bidet (1) can be used to spray cleansing water toward a user to cleanse the user's body. The bidet (1) may include a water body (100), a sensor unit (200), a valve module (300), a heater (400), a spray nozzle assembly (500), and a control device (600).

[0052] The water body (100) can temporarily accommodate water. The water body (100) may have an inlet (110) for allowing water to flow into the water body (100) and an outlet (120) for allowing water flowing into the water body (100) to flow out of the water body (100). The inlet (110) may be formed at the lower portion of the water body (100), and the outlet (120) may be formed at the upper portion of the water body (100). In the present specification, the water flowing into and flowing out of the water body (100) may include cleaning water. This cleaning water is a liquid having a cleaning function, and may be, for example, simple tap water or electrolyzed water having a cleaning effect. However, the present invention is not limited thereto, and any liquid having a cleaning function may be used without limitation.

[0053] The sensor unit (200) can measure the temperature of one or more of the inlet (110) and the outlet (120). The sensor unit (200) can include a first temperature sensor (210) and a second temperature sensor (220).

[0054] The first temperature sensor (210) can be placed at the inlet (110) to measure the temperature of the inlet (110). For example, the first temperature sensor (210) can measure the temperature of air passing through the inlet (110) when the water body (100) is empty. Additionally, the first temperature sensor (210) can measure the temperature of water passing through the inlet (110) when the water body (100) is filled with water. The first temperature sensor (210) can also be placed at a position adjacent to the inlet (110) to measure the temperature of an area adjacent to the inlet (110).

[0055] The second temperature sensor (220) can be placed at the outlet (120) to measure the temperature of the outlet (120). For example, the second temperature sensor (220) can measure the temperature of air passing through the outlet (120) when the water body (100) is empty. In addition, the second temperature sensor (220) can measure the temperature of water passing through the outlet (120) when the water body (100) is filled with water. This second temperature sensor (220) can also be placed at a position adjacent to the outlet (120) to measure the temperature of an area adjacent to the outlet (120).

[0056] The temperature measured by the first temperature sensor (210) and the second temperature sensor (220) can be transmitted to the control device (600).

[0057] The valve module (300) can be opened and closed to block or allow water to flow in through the inlet (110). This valve module (300) can be placed at one or more of the inlet (110) and the outlet (120). In addition, the operation of the valve module (300) can be controlled by the control device (600).

[0058] The heater (400) can heat water inside the water body (100) and one or more of the water bodies (100). The heater (400) can be placed inside the water body (100). The heater (400) can be controlled by a control device (600).

[0059] The spray nozzle assembly (500) may be formed with a spray hole for spraying water onto the user's body. The spray nozzle assembly (500) may receive water to be sprayed from a water body (100). The spray nozzle assembly (500) may further include a washing water hole for spraying water onto the device, and a drain hole for spraying water supplied after the water body (100) is full. However, at least one of the water sprayed onto the device and the water to be drained may be configured to be discharged through the spray hole.

[0060] The control device (600) can control the opening and closing of the valve module (300) based on the temperature of one or more of the inlet (110) and outlet (120) measured by the sensor unit (200). This control device (600) can be implemented by a computing device and memory including a microprocessor, and the method of implementation thereof is obvious to those skilled in the art, so further detailed description is omitted.

[0061] Below, the logic for controlling the opening and closing of the valve module (300) based on the temperature of one or more of the inlet (110) and outlet (120) measured by the sensor unit (200) by the control device (600) to detect the water level is described in detail.

[0062] The control device (600) can perform freezing judgment control to determine whether water can flow in the water body (100). By performing freezing judgment control, the control device (600) can determine whether the bidet (1) is exposed to a low temperature environment and the water body (100), valve module (300), and flow path are frozen, and can prevent the heater (400) from operating in a situation where water is not supplied to the water body (100).

[0063] Hereinafter, with reference to FIG. 2, the freeze determination control will be described. The freeze determination control can be performed before the valve module (300) is opened. In the freeze determination control, the control device (600) can obtain at least one of the inlet initial temperature and the outlet initial temperature through at least one of the first temperature sensor (210) and the second temperature sensor (220). In the freeze determination control, the control device (600) determines whether at least one of the inlet initial temperature and the outlet initial temperature is higher than the freeze determination temperature.

[0064] If at least one of the inlet initial temperature and the outlet initial temperature is lower than the freezing judgment temperature in the freezing judgment control, the control device (600) performs water inflow control to open the valve module (300) to allow water to flow within the water body (100), and determines whether a pre-input freezing judgment time has elapsed from the time the freezing judgment control is started. If the freezing judgment time has not elapsed, the control device (600) restarts the freezing judgment control, re-acquires at least one of the inlet initial temperature and the outlet initial temperature through at least one of the first temperature sensor (210) and the second temperature sensor (220), and determines whether at least one of the re-acquired inlet initial temperature and the outlet initial temperature is higher than the freezing judgment temperature. If the freezing judgment control is repeatedly performed and the freezing judgment time elapses, the abnormal closure control described below is performed and the freezing judgment control is terminated.

[0065] Meanwhile, when the control device (600) determines whether at least one of the inlet initial temperature and the outlet initial temperature is higher than the freezing judgment temperature, if at least one of the inlet initial temperature and the outlet initial temperature is determined to be higher than the freezing judgment temperature, the control device (600) terminates the freezing judgment control and initiates the water supply base control described later.

[0066] The control device (600) can perform water detection control to determine the presence or absence of water. The control device (600) can determine whether water exists above a predetermined level through water detection control. For example, the control device (600) can determine whether the inside of the water body (100) is fully filled with water through water detection control. Before performing the determination logic of the water detection control, the control device (600) stores the temperature of the water body (100) measured by the sensor unit (200) as a first temperature in the memory, and when performing the determination logic of the water detection control, the presence or absence of water in the water body (100) can be determined based on the relationship between the second temperature, which is the temperature of the water body (100) measured by the sensor unit (200), and the previously stored first temperature. For example, before the water body (100) water detection control is performed based on the difference between the second temperature and the first temperature, the control device (600) can control the valve module (300) to allow water to flow within the water body (100). Therefore, in the water detection control, the first temperature may be the temperature of the water body measured by the sensor unit (200) before controlling the valve module (300) to allow water to flow within the water body (100). This water detection control may include water supply base control, drain base control, and heating base control.

[0067] Hereinafter, the water supply base control will be described with reference to FIG. 3. In the water supply base control, a water supply control may be performed in which a control device (600) controls a valve module (300) to allow water to flow into the water body (100) through the inlet (110) for a preset water supply time. The control device (600) may open the valve module (300) in the water supply control. Before the valve module (300) is opened, the control device (600) may obtain at least one of the first inlet temperature and the first outlet temperature through at least one of the first temperature sensor (210) and the second temperature sensor (220). In addition, when the preset water supply time has elapsed after executing the water detection control, the control device (600) may obtain the second inlet temperature through the first temperature sensor (210) and may obtain the second outlet temperature through the second temperature sensor (220). This feeding time can be a value selected from the range of 4 to 6 seconds.

[0068] In the water supply base control, the first temperature may be a temperature obtained before the water supply control is performed, and the second temperature may be a temperature of the water in the water body (100) measured after the water supply control is performed. The first temperature and the second temperature described above may be a first inlet temperature and a second inlet temperature, or a first outlet temperature and a second outlet temperature. The control device (600) may calculate a water supply control temperature difference, which is a difference between the first inlet temperature and the second inlet temperature, and control the opening and closing of the valve module (300) based on the water supply control temperature difference. For example, the control device (600) may perform normal closing control on the valve module (300) when the water supply control temperature difference deviates from a preset first reference temperature range. Here, the first reference temperature range may be -3°C to 3°C. If the water supply control temperature difference exceeds the preset first reference temperature range, the control device (600) determines that water has been received through the inlet (110) and performs normal closing control.

[0069] Hereinafter, the normal closing control will be described with reference to FIG. 4. In the normal closing control, the control device (600) may control the valve module (300) to immediately close, but may also control the valve module (300) to allow more water to enter the water body (100) during a preset closing delay time. In this case, when controlling to allow more water to enter, the control device (600) may acquire a third temperature, which is the temperature of the water body (100), and store it in an internal memory before controlling the valve module (300) to allow water to flow within the water body (100), and may acquire a fourth temperature, which is the temperature of the water body (100), when the water supply time has elapsed from the time the valve module (300) is opened. The third temperature may be the first outlet temperature acquired in the water supply base control. In addition, the fourth temperature may be referred to as the third outlet temperature as it is the temperature obtained through the second temperature sensor when the normal closing control is performed. In addition, although the terms third temperature and fourth temperature are used in the description of the above normal closing control to distinguish them from the first temperature and the second temperature in the description of the water detection control, this does not mean that the third temperature and the fourth temperature are different from the first temperature and the second temperature, respectively. In other words, the third temperature may be the same temperature value as the first temperature, and the fourth temperature (the third outlet temperature) may be the same temperature value as the second temperature (the second outlet temperature).

[0070] In the normal closing control, the control device (600) calculates the difference between the first outlet temperature and the third outlet temperature, and can control the opening and closing of the valve module (300) based on the difference between the first outlet temperature and the third outlet temperature. For example, if the difference between the first outlet temperature and the third outlet temperature is outside the preset second reference temperature range, the valve module (300) is closed when the preset first closing delay time has elapsed from the time at which the water supply time has elapsed. In this case, the control device (600) determines that water is passing through the outlet (120), and additional water flows into the water body (100), and the valve module (300) is closed. Here, the second reference temperature range may be -3°C to 3°C, and the first closing delay time may be a value selected from the range of 4 seconds to 6 seconds. Meanwhile, when the normal closing control is initiated, if the water body (100) is filled with water above a predetermined level or is full, and water is supplied in excess of the capacity of the water body (100), the water that enters the water body (100) during the first closing delay time of the normal closing control can be discharged to the outside of the bidet (1) through the spray nozzle assembly (600).

[0071] In addition, if the difference between the first outlet temperature and the third outlet temperature in the normal closing control falls within the second reference temperature range, the control device (600) acquires the third outlet temperature defined as the temperature acquired by the second temperature sensor (220) while the second closing delay time has elapsed from the time when the water supply time has elapsed. The second closing delay time may be set to be longer than the first closing delay time, and may be a value selected from the range of 25 to 35 seconds, for example. In this case, the control device (600) calculates the difference between the first outlet temperature and the third outlet temperature, and controls the valve module (300) based on the calculated difference between the first outlet temperature and the third outlet temperature.

[0072] If the difference between the first outlet temperature and the third outlet temperature calculated in the normal closing control is outside the second reference temperature range, the valve module (300) is closed when the first closing delay time has elapsed from the time at which the water supply time has elapsed.

[0073] Conversely, if the difference between the first outlet temperature and the third outlet temperature calculated in the normal closing control falls within the second reference temperature range, the valve module (300) remains open while the second closing delay time elapses from the time when the water supply time has elapsed. In addition, the control device (600) repeatedly acquires the outlet temperature as the third outlet temperature through the second temperature sensor (220) and compares the acquired third outlet temperature with the first outlet temperature. In this way, the control device (600) continues to supply water into the water body (100) until the difference between the third outlet temperature and the first outlet temperature exceeds the second reference temperature range, and closes the valve module (300) when the second closing delay time elapses. In other words, even if the difference between the first outlet temperature and the third outlet temperature falls within the second reference temperature range at the time when the normal closing control is started (i.e., the time when it is determined that water exists in the water body (100), the control device (600) repeatedly obtains the difference between the first outlet temperature and the third outlet temperature from the time when the water supply time has elapsed to the second closing delay time, and if it is determined that the difference between the first outlet temperature and the third outlet temperature is outside the second reference temperature range, the valve module (300) can be closed even before the second closing delay time has elapsed.

[0074] Meanwhile, if the water supply control temperature difference falls within the first reference temperature range in the water supply base control, it may be determined that water does not flow normally into the water body (100) and the temperature change in the sensor unit (200) is minimal, so abnormal closure control may be performed. However, on the contrary, the water supply control temperature difference falling within the first reference temperature range in the water supply base control may be because the temperature around the water body (100) is similar to the temperature of the water flowing into the water body (100), so the temperature change in the sensor unit (200) is minimal. Therefore, when the water supply control temperature difference falls within the first reference temperature range in the water supply base control, the control device (600) may not immediately perform abnormal closure control, but may perform one or more of the heating base control and the drain base control described below. The control device (600) can perform heating base control or drain base control after a predetermined waiting time has elapsed when the temperature difference between the water supply control and the water supply base control falls within the first reference temperature range. This waiting time can be, for example, 3 seconds.

[0075] Hereinafter, the heating base control will be described with reference to FIG. 5. As previously described, the heating base control is performed in relation to the water supply base control when the water supply control temperature difference falls within a preset first reference temperature range. However, this is not necessarily limited to this, and the heating base control may be performed independently without precedence by the water supply base control.

[0076] In the heating base control, a heating control can be performed in which the control device (600) controls the heater (400) to heat the water inside the water body (100). Here, the heating of the water inside the water body (100) includes both the concept of the heater (400) being contained in the water and directly heating the water, and the concept of the heater (400) heating the water body (100) itself to indirectly heat the water. In this heating control, the heating state of the heater (400) can be controlled to be maintained for a preset heating time from a predetermined heating reference time. In other words, in the heating base control, the water inside the water body (100) can be heated by the heater (400) for a preset heating time. This heating time can be, for example, 2 seconds.

[0077] Meanwhile, when the heating base control is performed subsequent to the water supply base control, the heating control can be performed when the water supply control temperature difference falls within a preset first reference temperature range, and the heating reference point in time can be the point in time when the water supply time in the water supply base control has elapsed.

[0078] On the other hand, the control device (600) can determine whether the temperature of the water body (100) is lower than a preset threshold temperature before performing heating control, and if the temperature of the water body (100) is lower than the preset threshold temperature, the heater (400) can perform heating control so that the water body (100) is heated. Here, the temperature of the water body (100) may be the outlet temperature (second outlet temperature) obtained through the second temperature sensor (220), and the threshold temperature may be a value selected from a range of 38°C to 42°C, and as a more detailed example, may be 40°C.

[0079] In the heating base control, the control device (600) can obtain the pre-heating temperature, which is the temperature before operating the heater (400), and the post-heating temperature, which is the temperature of the water in the water body (100) measured after the heating control is performed. These pre-heating temperature and post-heating temperature can be obtained through the second temperature sensor (220). In addition, in the heating base control, the pre-heating temperature and post-heating temperature may be concepts corresponding to the first temperature and the second temperature in the description of the water detection control, respectively.

[0080] In this way, when the first temperature and the second temperature are acquired through the second temperature sensor (220) and the water supply base control and the heating base control described above are performed continuously, the pre-heating temperature in the heating base control may be a concept corresponding to the second water outlet temperature in the water supply base control. In addition, when the water in the water body (100) is heated by the heater (400), the temperature after heating acquired from the second temperature sensor (220) may be referred to as the fourth water outlet temperature. The control device (600) controls the opening and closing of the valve module (300) based on the heating control temperature difference calculated based on the difference between the second water outlet temperature and the fourth water outlet temperature in the heating base control.

[0081] Here, the heating control temperature difference may be simply calculated as the temperature difference between the fourth outlet temperature obtained when the heating control is terminated and the second outlet temperature, but it may also be calculated in another way. For example, the control device (600) may not only obtain the fourth outlet temperature when the heating control is terminated, but may also obtain the fourth outlet temperature at a predetermined number of temperature measurements at predetermined intervals from the time when the heating control is terminated, calculate the temperature difference between the second outlet temperatures for each of the plurality of fourth outlet temperatures obtained, and add up the calculated temperature differences to calculate the heating control temperature difference. In other words, the fourth outlet temperature is obtained at each interval time interval and the difference between the second outlet temperatures is calculated, and the difference between the fourth outlet temperature and the second outlet temperature is calculated as the number of temperature measurements. The differences between the fourth outlet temperature and the second outlet temperature are added up as the number of temperature measurements to calculate the heating control temperature difference. Here, the interval time and the number of temperature measurements may be, for example, 1 second and 4 times, respectively. According to this example, the control device (600) may obtain the 4th outlet temperature every 1 second, calculate the difference between the 4th outlet temperature and the 2nd outlet temperature 4 times, and calculate the heating control temperature difference by adding up the 4 calculated differences between the 4th outlet temperatures and the 2nd outlet temperatures.

[0082] When this heating control is terminated, if the calculated heating control temperature difference is lower than the preset heating judgment reference value, it is determined that there is water in the water body (100), and normal closing control is performed on the valve module (300). In this way, it can be understood that the fact that the calculated heating control temperature difference is lower than the preset heating judgment reference value means that since water is contained in the water body (100), even if the heater (400) heats during the heating time due to the heat capacity of the water, the temperature increase is minimal (the calculated heating control temperature difference is lower than the preset heating judgment reference value). Here, the heating judgment reference value may be a value selected from the range of 5°C to 8°C.

[0083] In addition, the control device (600) can set the heating judgment reference value differently based on the second temperature. For example, the control device (600) can set the heating judgment reference value to be larger as the second temperature is larger. As a more detailed example, the control device (600) can set the heating judgment reference value to 5°C when the second temperature is in a first temperature range of 0°C to 15°C, set the heating judgment reference value to 6°C when the second temperature is in a second temperature range of 16°C to 20°C, set the heating judgment reference value to 7°C when the second temperature is in a third temperature range of 21°C to 30°C, and set the heating judgment reference value to 8°C when the second temperature is in a fourth temperature range of 31°C to 40°C.

[0084] In addition, when the heating control is terminated, if the calculated heating control temperature difference is higher than the set heating judgment reference value, it is determined that there is no water or there is significantly little water in the water body (100), and the heating control is performed again. In this way, it can be understood that the fact that the calculated heating control temperature difference is higher than the preset heating judgment reference value means that there is no water or the amount of water contained in the water body (100) is small, so the heat capacity inside the water body (100) is low, and the temperature rises when the heater (400) heats it.

[0085] When the heating control is terminated, if the calculated heating control temperature difference is higher than the set heating judgment reference value, the control device (600) can immediately perform abnormal closing control.

[0086] Meanwhile, as another example, when the heating control is terminated, if the calculated heating control temperature difference is higher than the set heating judgment reference value, the control device (600) does not immediately perform abnormal closing control, but performs the heating control again in the same or similar manner as the above-described heating control, and recalculates the heating control temperature difference in the same or similar manner as the above-described method and compares it with the heating judgment reference value, thereby determining the opening and closing of the valve module (300). When the heating control is terminated, if the calculated heating control temperature difference is higher than the set heating judgment reference value, the heating control and the calculation of the heating control temperature difference and the comparison with the heating judgment reference value may be repeated for a preset number of heating control repetitions.

[0087] Below, as a more detailed example, it is explained that since the recalculated heating control temperature difference is higher than the heating judgment reference value, the recalculation of the temperature difference of the heating control temperature difference and the comparison of the heating judgment reference value and the heating control temperature difference are performed twice more.

[0088] In the heating base control, if the heating control temperature difference is higher than the preset heating judgment reference value, the second heating control is performed, and before the heater (400) is operated again, the temperature of the water body (100) can be obtained through the sensor unit (200). In addition, the control device (600) determines whether the temperature of the water body (100) is lower than the preset threshold temperature before reheating, and if the temperature of the water body (100) is lower than the preset threshold temperature, the heating control can be performed again so that the water body (100) is reheated. The time for which the re-performed heating control is maintained may be set to be the same as the heating time in the initially performed heating control, but may also be set differently.

[0089] In addition, the temperature of the water body (100) after the secondary heating control can be acquired through the second temperature sensor (220). The control device (600) can recalculate the heating control temperature difference based on the difference between the temperature before reheating acquired from the second temperature sensor (220) before the water in the water body (100) is reheated by the heater (400) and the reheating temperature acquired from the second temperature sensor (220) when the water body (100) is reheated by the heater (400), and control the opening and closing of the valve module (300) based on the recalculated heating control temperature difference. In this way, when the temperature of the water body (100) is acquired from the second temperature sensor (220), the temperature before reheating can be named the fifth outlet temperature or the first remeasured temperature, and the temperature after reheating can be named the sixth outlet temperature or the second remeasured temperature. The heating control temperature difference during reheating can be calculated in the same manner as the initially calculated heating control temperature difference.

[0090] When this secondary heating control is terminated, if the calculated heating control temperature difference is lower than the preset heating judgment reference value, it is determined that there is water in the water body (100), and normal closing control is performed on the valve module (300). It can be understood that the fact that the calculated heating control temperature difference is lower than the preset heating judgment reference value means that since water is contained in the water body (100), even if the heater (400) heats during the heating time due to the heat capacity of the water, the temperature increase is minimal (i.e., the calculated heating control temperature difference is lower than the preset heating judgment reference value).

[0091] In addition, when the secondary heating control is terminated, if the calculated heating control temperature difference is higher than the heating judgment reference value, it is determined that there is no water or a significantly small amount of water inside the water body (100), and the heating control is performed again. In this way, it can be understood that the fact that the calculated heating control temperature difference is higher than the preset heating judgment reference value means that there is no water or the amount of water contained in the water body (100) is small, so the heat capacity inside the water body (100) is low, and the temperature rises when the heater (400) heats it.

[0092] In the heating base control, if the heating control temperature difference calculated when the second heating control is completed is higher than the heating judgment reference value, the third heating control can be performed. If the heating control temperature difference recalculated in the third heating control is smaller than the heating judgment reference value, normal closing control is performed, but if the heating control temperature difference recalculated in the third heating control is also higher than the heating judgment reference value, abnormal closing control is performed. Here, in the abnormal closing control, an error message can be transmitted to the user through an alarm unit (not shown). When this abnormal closing control is performed, the valve module (300) is closed.

[0093] Meanwhile, since the calculated heating control temperature difference is higher than the set heating judgment reference value, while the heating control and the calculation of the heating control temperature difference and the comparison with the heating judgment reference value are performed the number of times the heating control is repeated, the water body (100) may be heated to a critical temperature or higher due to the heating control. If the water body (100) is overheated more than necessary by exceeding the critical temperature, the heating control may not be performed and the drain foundation control may be performed. For example, if the outlet temperature before the heating control is performed is higher than the critical temperature, or if the outlet temperature before the second heating control is performed after the heating control is determined to be higher than the heating judgment reference value and the heating control temperature difference is higher than the critical temperature, the control device (600) may perform the drain foundation control without subsequently performing the heating control.

[0094] Hereinafter, drain foundation control will be described with reference to FIG. 6. As previously described, drain foundation control is performed subsequent to water supply foundation control and heating foundation control, but it is not necessarily limited thereto, and drain foundation control may be performed independently without prior water supply foundation control and heating foundation control.

[0095] In the drain base control, drain control may be performed to control the valve module (300) to allow water that has flowed into the water body (100) to flow out of the water body (100) through the outlet (120). The control device (600) may open the valve module (300) in the drain control. By the drain control, water in the water body (100) is allowed to flow out of the water body (100) for a preset drain allowance time from a predetermined drain reference time point, and when the drain allowance time elapses, water in the water body (100) may be restricted from flowing out of the water body (100). When the drain base control is performed subsequent to the heating base control, the drain reference time point may be a time point at which the temperature of the water body (100) is determined to be higher than a critical temperature in the heating base control. Here, the drain allowance time can be a value selected from the range of 4 to 6 seconds.

[0096] In addition, when the drain base control is performed without following the heating base control, the control device (600) can determine whether the temperature of the water body (100) is lower than a preset threshold temperature before performing the drain base control, and can perform the drain control when the temperature of the water body (100) is higher than the preset threshold temperature. Here, the temperature of the water body (100) may be the outlet temperature (second outlet temperature) obtained through the second temperature sensor (220), and the threshold temperature may be a value selected from the range of 34°C to 36°C.

[0097] In the drain base control, the temperature of the water body (100) before performing the drain control and the temperature of the water body (100) after performing the drain control during the drain allowance time can be obtained. The drain allowance time can be, for example, 7 seconds or 8 seconds. The temperature of the water body (100) before performing the drain control and the temperature of the water body (100) after performing the drain control can be concepts corresponding to the first temperature and the second temperature in the description of the water detection control, respectively.

[0098] These first and second temperatures can be acquired from the second temperature sensor (220). In other words, the first temperature can be acquired from the second temperature sensor (220) before performing drain control, and the second temperature can be acquired from the second temperature sensor (220) after performing drain control. In this way, when the first and second temperatures are acquired from the second temperature sensor (220), the temperature acquired before performing drain control can be named as the seventh outlet temperature, and the temperature acquired after performing drain control can be named as the eighth outlet temperature.

[0099] In the drain base control, the control device (600) can calculate the drain control temperature difference, which is the difference between the seventh outlet temperature and the eighth outlet temperature, and control the opening and closing of the valve module (300) based on the drain control temperature difference. For example, if the drain control temperature difference is outside a preset third reference temperature range, normal closing control may be performed, and if the drain control temperature difference is within the third reference temperature range, abnormal closing control may be performed. Here, the third reference temperature range may be -3°C to 3°C.

[0100] Meanwhile, as another example, if the drain control temperature difference falls within the third reference temperature range in the drain foundation control, the abnormal closing control is not immediately performed, but the drain control is performed again in the same or similar manner as the above-described drain control, and the drain control temperature difference is recalculated in the same or similar manner as the above-described method and compared with the third reference temperature range to determine the opening and closing of the valve module (300). If the drain control temperature difference falls within the third reference temperature range in the drain foundation control, the drain control, the recalculation of the drain control temperature difference, and the comparison between the drain control temperature difference and the reference temperature may be repeated as many times as the preset drain control repetition number. The number of drain control repetitions may be, for example, two times.

[0101] In this way, when the drain control and the calculation of the drain control temperature difference are performed a second time, the temperature obtained before the second drain control is performed may be named the third re-measured temperature or the ninth outlet temperature, and the temperature obtained after the second drain control is performed may be named the fourth re-measured temperature or the tenth outlet temperature. When the second drain control is terminated and the calculated re-drain temperature control is out of the third reference temperature range, normal closing control may be performed, and when the calculated re-drain temperature control falls within the third reference temperature range, abnormal closing control may be performed.

[0102] Meanwhile, the water supply base control, drain base control, and heating base control described above can be performed in conjunction with each other.

[0103] Hereinafter, with reference to FIG. 7, an example in which water supply base control, drain base control, and heating base control are performed in conjunction with each other will be described. First, water supply base control can be performed. In the water supply base control, if the water supply control temperature difference is outside the preset first reference temperature range, normal closing control is performed on the valve module (300), and if the water supply control temperature difference is within the preset first reference temperature range, the control device (600) can obtain the temperature of the water body (100) through the sensor unit (200) and determine whether to perform heating base control or drain base control based on the temperature of the water body (100).

[0104] When the temperature difference of the water supply control is determined to be within the preset first reference temperature range and the temperature of the water body (100) is lower than the critical temperature, the control device (600) may perform heating base control and perform normal closing control or abnormal closing control depending on the result of the heating base control. However, when the temperature of the water body (100) is heated to or higher than the critical temperature by repeating the heating control in the heating base control, the heating base control may be stopped and drain base control may be performed. The drain base control may be performed when the temperature of the water body (100) is higher than the critical temperature, and normal closing control or abnormal closing control may be performed depending on the result of the heating base control.

[0105] In this way, the bidet (1) according to one embodiment of the present invention can detect the water level contained within the bidet without a water level detection sensor via a control device (600). In this case, the water level detection sensor is omitted, thereby reducing the cost required for the water level detection sensor.

[0106] In addition, the bidet (1) according to one embodiment of the present invention has the effect that the control device (600) can determine whether the bidet (1) is frozen without a water level detection sensor.

[0107] Although the embodiments of the present invention have been described as specific embodiments, these are merely examples, and the present invention is not limited thereto, but should be construed to have the broadest scope in accordance with the technical concepts disclosed in this specification. Those skilled in the art may implement patterns of shapes not specified by combining / substituting the disclosed embodiments, but this also does not depart from the scope of the present invention. In addition, those skilled in the art may easily modify or alter the disclosed embodiments based on this specification, and it is clear that such modifications or alterations also fall within the scope of the present invention.

Claims

1. In a bidet that can detect the presence of water inside by measuring the temperature of the water, A spray nozzle assembly having a spray hole formed to spray water onto the user's body; A water body having an inlet through which water flows in from an external water source and an outlet through which the water flows out toward the injection hole; A sensor unit for measuring the temperature of the above water body; A valve module that opens and closes to allow water to flow into or out of the water body; and It includes a control device that controls one or more of the above-mentioned injection nozzle assembly, the above-mentioned water body, and the above-mentioned valve module, The above control device, Execute water detection control to determine the presence or absence of water in the above water body, Before controlling the valve module to allow water to flow within the water body, the presence or absence of water within the water body is determined based on the relationship between the first temperature, which is the temperature of the water body measured by the sensor unit, and the second temperature, which is the temperature of the water body measured by the sensor unit after executing the water detection control. Controlling the valve module according to the presence or absence of water in the water body; Bidet.

2. In paragraph 1, The above water detection control is, Includes a water supply control that controls the valve module to allow water to flow into the water body through the inlet for a preset water supply time, The above control device, Before executing the water supply control, the first temperature, which is the temperature of the water body measured by the sensor unit, is acquired, and after executing the water supply control, the second temperature, which is the temperature of the water body measured by the sensor unit, is acquired, and the presence or absence of water in the water body is determined based on the relationship between the first temperature and the second temperature. Bidet.

3. In paragraph 2, The above control device, If the difference between the first temperature and the second temperature is greater than a preset value, it is determined that water exists in the water body. Bidet.

4. In paragraph 2, The above sensor unit includes an inlet temperature sensor for measuring the temperature of the inlet, The first temperature and the second temperature are measured by the inlet temperature sensor. Bidet.

5. In paragraph 1, The above water detection control is, Includes a drain control that controls the valve module to allow water flowing into the interior of the water body to flow out of the water body through the outlet, The above control device, Before executing the drain control, the first temperature, which is the temperature of the water body measured by the sensor unit, is acquired, and after executing the drain control, the second temperature, which is the temperature of the water body measured by the sensor unit, is acquired, and the presence or absence of water in the water body is determined based on the relationship between the first temperature and the second temperature. Bidet.

6. In paragraph 5, The above control device, If the difference between the first temperature and the second temperature is greater than a preset value, it is determined that water exists in the water body. Bidet.

7. In paragraph 5, The above control device, If the difference between the first temperature and the second temperature is less than a preset value, the drain control is additionally performed, The presence or absence of water in the water body is determined based on the relationship between the first re-measured temperature obtained from the sensor unit before the additional drain control is performed and the second re-measured temperature obtained from the sensor unit after the additional drain control is performed. Bidet.

8. In paragraph 7, The above control device, If the difference between the first re-measured temperature and the second re-measured temperature is greater than a preset value, it is determined that water exists in the water body. Bidet.

9. In paragraph 5, The above sensor unit includes an outlet temperature sensor for measuring the temperature of the outlet, The first temperature and the second temperature are measured by the outlet temperature sensor. Bidet.

10. In paragraph 5, The above control device, When the above first temperature is greater than a predetermined value, the drain control is executed. Bidet.

11. In paragraph 1, Further comprising a heater capable of heating the water inside the water body, The above water detection control is, Includes a heating control that operates the above heater for a predetermined period of time, The above control device, Before executing the heating control, the first temperature, which is the temperature of the water body measured by the sensor unit, is acquired, and after executing the heating control, the second temperature, which is the temperature of the water body measured by the sensor unit, is acquired. Bidet.

12. In paragraph 11, The above control device, If the difference between the first temperature and the second temperature is less than a preset value, it is determined that water exists in the water body. Bidet.

13. In paragraph 11, The above control device, If the difference between the first temperature and the second temperature is greater than a preset value, the heating control is additionally performed, The presence or absence of water in the water body is determined based on the relationship between the first re-measured temperature obtained from the sensor unit before the additional heating control is performed and the second re-measured temperature obtained from the sensor unit after the additional heating control is performed. Bidet.

14. In paragraph 13, The above control device, If the difference between the first re-measured temperature and the second re-measured temperature is less than a preset value, it is determined that water exists in the water body. Bidet.

15. In paragraph 11, The above sensor unit includes an outlet temperature sensor for measuring the temperature of the outlet, The first temperature and the second temperature are measured by the outlet temperature sensor. Bidet.

16. In paragraph 11, The above control device, When the first temperature is lower than a predetermined value, the heating control is executed. Bidet.

17. In paragraph 1, The above water detection control is, A water supply control that controls the valve module to allow water to flow into the water body through the inlet for a preset water supply time; and Includes a drain control that controls the valve module to allow water flowing into the interior of the water body to flow out of the water body through the outlet, The above control device, When executing the water supply control, the first temperature, which is the temperature of the water body measured by the sensor unit before executing the water supply control, is acquired, and the second temperature, which is the temperature of the water body measured by the sensor unit after executing the water supply control, is acquired, and if the difference between the first temperature and the second temperature is greater than a preset water supply control temperature difference value, it is determined that water exists in the water body. If the difference between the first temperature and the second temperature is less than a preset value, the drain control is additionally executed, but if the difference between the temperature of the water body measured by the sensor unit before executing the drain control and the temperature of the water body measured by the sensor unit after executing the drain control is greater than a preset drain control temperature difference value, it is determined that water exists in the water body. Bidet.

18. In paragraph 1, Further comprising a heater capable of heating water inside the water body and at least one of the water bodies, The above water detection control is, A water supply control that controls the valve module to allow water to flow into the water body through the inlet for a preset water supply time; and Includes a heating control that operates the above heater for a predetermined period of time, The above control device, The above water supply control is executed, but before executing the water supply control, the first temperature, which is the temperature of the water body measured by the sensor unit, is acquired, and after executing the water supply control, the second temperature, which is the temperature of the water body measured by the sensor unit, is acquired, and if the difference between the first temperature and the second temperature is greater than a preset value, it is determined that water exists in the water body. If the difference between the first temperature and the second temperature is less than a preset value, the heating control is executed, but if the difference between the temperature of the water body measured by the sensor unit before executing the heating control and the temperature of the water body measured by the sensor unit after executing the heating control is less than a preset heating control temperature difference value, it is determined that water exists in the water body. Bidet.

19. In paragraph 1, The above control device, If it is determined that water exists in the water body, the valve module is controlled to allow more water to enter the water body for a predetermined period of time. Bidet.

20. In paragraph 19, The above control device, When it is determined that water exists within the water body, it is determined whether the difference between the third temperature, which is the temperature at which water is determined to exist within the water body, and the first temperature during the predetermined period of time is outside a pre-input reference temperature range, If the difference between the third temperature and the first temperature exceeds the reference temperature range, the valve module is controlled to close before the predetermined time elapses. Bidet.

21. In paragraph 1, The above water detection control is, Includes a water supply control that controls the valve module to allow water to flow into the water body through the inlet for a preset water supply time, The above control device, Before executing the water supply control, the first temperature, which is the temperature of the water body measured by the sensor unit, is acquired, and a freezing judgment control is performed to determine whether at least one of the water body and the valve module is frozen based on the first temperature. Bidet.

22. In paragraph 21, The above control device, In the above freezing judgment control, if the first temperature is lower than the pre-input freezing judgment temperature, the valve module is opened for the pre-input freezing judgment time, and if the first temperature is lower than the pre-input freezing judgment temperature after the freezing judgment time, it is determined that at least one of the water body and the valve module is frozen. In the above freezing judgment control, if the first temperature is higher than the pre-input freezing judgment temperature, it is judged not to be frozen. Bidet.