Black start method and power generation system

By controlling power transformer voltages to an initial level and gradually increasing to a second level after load connection, the self-starting process is stabilized, preventing excessive currents and ensuring successful system startup.

SA1120263568A1Pending Publication Date: 2026-10-05SUNGROW POWER SUPPLY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
SA1120263568
Authority / Receiving Office
SA · SA
Patent Type
Applications
Current Assignee / Owner
Filing Date
2026-04-16
Publication Date
2026-10-05

AI Technical Summary

Technical Problem

Existing self-starting processes in power conversion systems fail due to excessive inrush currents when connecting a load, exceeding the rated current and causing system failures.

Method used

Control the voltage of power transformers to an initial predetermined level lower than the rated voltage before connecting the load, and then gradually increase to the second predetermined voltage after load connection, ensuring the total apparent power does not exceed the system's capacity, thereby preventing large impulse currents.

Benefits of technology

Ensures successful self-starting by preventing excessive inrush currents, protecting power conversion systems and ensuring stable operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0F549335-4F5E-473A-BC91-B7D7FCACB2EE
    Figure 0F549335-4F5E-473A-BC91-B7D7FCACB2EE
  • Figure 54C9B8E5-3F76-4EA0-9D0E-FEE69C705E01
    Figure 54C9B8E5-3F76-4EA0-9D0E-FEE69C705E01
  • Figure 60F2D3C3-11A8-4067-B6A9-3297555675B4
    Figure 60F2D3C3-11A8-4067-B6A9-3297555675B4
Patent Text Reader

Abstract

The invention relates to a method of black start (BS) power unit operation (starting from scratch without reliance on external sources) and to a power generation system. The method includes: a black start controller or an energy management system (EMS) that sends booster instructions to the power conversion systems (PCSs) for black start operation to reach a predetermined initial voltage. The alternating current sides of the PCSs are connected in parallel to supply the load, and the first predetermined voltage is lower than the second predetermined voltage. When the black start controller or energy management system detects that the voltage of the PCSs has reached the first predetermined voltage, it issues an instruction to introduce the load. Once the load is introduced, booster instructions are sent to all PCSs, so that the voltage of all PCSs increases from the first predetermined voltage to the second predetermined voltage.This solution allows the load to be successfully inserted, so that the self-startup is successful. (Figure 1)
Need to check novelty before this filing date? Find Prior Art

Description

To enable specialists in this field to better understand and implement technical solutions in accordance with the inventions presented herein, the application scenarios are described below along with accompanying drawings. With reference to Figure 1, it represents a schematic diagram of an electricity generation system according to one of the incarnations of the present invention. The electricity generation system, according to one embodiment of the present invention, comprises a power management system, a local control unit, a self-starting control unit, and multiple power conversion systems. In one embodiment of the present invention, the number of power conversion systems is not limited. The alternating-current sides of all power conversion systems are connected in parallel to each other to supply the load. The self-starting unit is designed to control the power conversion systems. In self-starting solutions in the relevant field, each power conversion system outputs a second predefined voltage level. When a load is connected to a power conversion system, a large inrush current is generated, causing the total power to exceed the rated current of the power conversion system and resulting in self-start failure. To address the aforementioned technical issues, the power generation system, according to one embodiment of the present invention, employs a self-starting method as follows. During the self-starting process, the voltage of each power transformer is first controlled to raise it to the initial predetermined voltage, and then the load is connected. After the load is connected, the voltage of the power transformer is further controlled to rise from the initial predetermined voltage to the second predetermined voltage. The initial predetermined voltage is lower than the second predetermined voltage. Therefore, when a large impulse current flows from the load, the total apparent power cannot exceed the total apparent power of all power transformers, thus preventing the generation of large impulse currents on the power transformers and ensuring the success of the self-starting process. The following is a detailed description of the embodiments of the present invention, accompanied by drawings to explain and interpret the aims, features, and advantages of the present invention. With reference to Figure 2, it represents a flowchart of the self-starting method according to one of the incarnations of the present invention. The self-starting method according to one of the incarnations of the present invention includes: steps S201 and S202. In step S201, the self-starting controller or power management system sends instructions to raise the voltage to a predefined first voltage to each of the power conversion systems undergoing self-starting. The AC sides of the power conversion systems undergoing self-starting are connected in parallel to supply the load. The first predefined voltage is lower than the second predefined voltage. The value of the second predefined voltage is not limited in the present invention and is normally set to the rated voltage of the power conversion system. To facilitate understanding, the following embodiments of the present invention provide an example of a self-starting mechanism sending multiple instructions to a power conversion system. The system and method, according to the embodiments of the present invention, may exclude self-starting and include only an energy management system, in which case the energy management system sends multiple instructions to the power conversion system. When the system includes both an energy management system and self-starting, it is the self-starting mechanism that sends the instructions to the power conversion system. It should be understood that the power generation system, according to the embodiment of the present invention, can be a new energy system, including photovoltaic energy, energy storage, wind power, or similar. Self-starting is performed in off-grid mode, i.e., it starts without electricity. The power management system of the power generation system sets the off-grid mode, enabling self-starting. Additionally, the power management system sets the inverter voltage and frequency values ​​for the power conversion systems and sends them to a local controller, which then simultaneously sends them to each power conversion system. The power management system can also set the minimum number of power conversion systems subject to self-starting. This means that some power conversion systems in the power generation system undergo self-starting while others do not, or that all power conversion systems undergo self-starting, which is unlimited in the embodiments of the present invention. During the self-start process, each power conversion system can be defined as a primary power conversion system or a secondary power conversion system, and the load is controlled to be connected only when the voltage of both the primary power conversion system and the secondary power conversion system rises to the first predetermined voltage. It must be understood that, for a power conversion system, devices that operate on a power conversion system are all loads. In step S202, the self-start controller detects that the voltage of each of the power conversion systems subject to the self-start process rises to the first predetermined voltage, and sends instructions to the power management system about connecting the load. After the load is connected, the self-start sends instructions about the voltage rise to each of the power conversion systems subject to the self-start process, causing the voltage of each of the power conversion systems subject to the self-start process to rise from the first predetermined voltage to the second predetermined voltage. With reference to Figure 3, it represents a schematic diagram of the low-voltage self-start of a power conversion system according to one of the incarnations of the present invention. In Figure 3, the horizontal axis represents time T, and the vertical axis represents the voltage U for each power conversion system. Line segment AB indicates the voltage rise of the power conversion system, i.e., from 0 to the first preset voltage V. Line segment BC indicates the voltage rise phase (plateau), i.e., the voltage remains constant at the first preset voltage V. The load is connected through segment BC. After the load is connected, the power conversion system voltage continues to rise, as shown by line segment CD, until it reaches the second preset voltage U0 at point D. During the self-start process in the relevant field, the load is connected after the voltage of the power conversion system rises to the second predetermined voltage U0. Consequently, the power is excessively high, exceeding the power capacity of the power conversion systems, which leads to the failure of the self-start process. In the self-starting method as described in the present invention, the voltage of each power converter is controlled to rise to a predetermined initial voltage, which is lower than the predetermined second voltage during the self-starting process. When a power converter remains at its initial predetermined voltage, the load is connected. After the load is connected, the voltage of the power converter is further controlled to rise from the initial predetermined voltage to the second predetermined voltage. The initial predetermined voltage is lower than the second predetermined voltage. Therefore, when the load is connected during the phase in which the power converter is operating at the initial predetermined voltage, even if there is a large inrush current from the load, the total apparent power of the power generation system is not excessively high and does not exceed the total apparent power of all power converters. In this case, large inrush currents on the power converters are prevented for the success of the self-starting process. To prevent a power conversion system from being subjected to large surge currents, self-starting controls the voltage rise of the power conversion system from the first preset voltage to the second preset voltage only when the total apparent power of the power generation system is below a preset apparent power threshold. When the total apparent power of all power conversion systems subjected to self-starting is greater than or equal to the preset apparent power, the system is suspended to reduce the total apparent power of all power conversion systems subjected to self-starting. This is because the surge current generated during load connection decreases over time, resulting in a corresponding decrease in total apparent power. In the self-starting method according to one embodiment of the present invention, a voltage-ramping instruction can be sent to each of the power conversion systems subjected to self-starting after the load is connected, as follows: Self-starting detects that the total apparent power of all power conversion systems is greater than a predefined power threshold. It is suspended to detect that the total apparent power of all power conversion systems is less than a predefined apparent power, and a voltage-ramping instruction is sent to each power conversion system. The predefined power threshold is greater than the predefined apparent power. To ensure successful self-startup and protect power conversion systems from excessive surge currents, the power conversion systems are not immediately controlled to raise their voltage to the second preset voltage after the load is connected. Instead, the total apparent power of the power generation system is detected. For example, when the load is initially connected, the total apparent power of all power conversion systems may be relatively high, for instance, exceeding 75% of the rated apparent power (Pn). In such cases, the system enters a hold period until the total apparent power of all power conversion systems falls below the preset apparent power, and a voltage rise instruction is sent to each power conversion system. The power conversion system voltage then rises from the first preset voltage to the second preset voltage. For example, the preset apparent power might be set at 25% of Pn. These values ​​are provided as examples for illustration purposes only and may vary according to actual requirements. Below, a specific implementation method is described with reference to the drawings. With reference to Figure 4, it represents a flowchart of the self-starting method according to another embodiment of the present invention. The self-starting method according to the embodiment of the present invention includes: Steps from S401 to S404. In step S401, the self-start controller sends instructions to raise the voltage up to the first predetermined voltage to each of the power conversion systems subject to the self-start process. In step S402, the self-start, upon receiving feedback signals corresponding to the first self-start instruction from all power conversion systems subject to self-start, sends a second self-start instruction to each of the power conversion systems subject to self-start, and is held to receive feedback signals corresponding to the second self-start instruction returned from all power conversion systems subject to self-start. The specific forms of self-starting instructions are not limited to the embodiment of the present invention. Each self-starting instruction aims to achieve synchronization between different power conversion systems; that is, it serves as a synchronized pulse signal. Power conversion systems subject to self-starting include a primary power conversion system and a secondary power conversion system. In one implementation, the self-starter receives a feedback signal corresponding to the initial self-start instruction from the primary power converter system, and another feedback signal corresponding to the initial self-start instruction from the secondary power converter system. All power converter systems include at least one primary power converter system and one secondary power converter system. The self-starting sends a second self-starting instruction to at least one dependent power conversion system, and, upon receiving a feedback signal corresponding to the second self-starting instruction from at least one dependent power conversion system, sends the second self-starting instruction to the main power conversion system, and is held to receive a feedback signal corresponding to the second self-starting instruction from the main power conversion system. The self-start is suspended to receive feedback signals corresponding to the second self-start instruction received from the power conversion systems undergoing self-starting before proceeding to the next step. In the self-starting method as embodied in the present invention, the self-start first sends the second self-start instruction to the dependent power conversion system and then sends the second self-start instruction to the primary power conversion system. In step S403, the self-start controller detects that the voltage of each of the power conversion systems subject to the self-start process rises to the first predetermined voltage, and sends instructions about connecting the load to the energy management system. When the voltage of each power conversion system rises to the initial preset voltage and remains at that initial voltage, the self-starter receives feedback signals corresponding to a fourth self-start instruction sent by all the power conversion systems. These feedback signals then send instructions to the power management system to connect the load. The self-starter waits for the power management system to connect the load. The power management system connects the load when it detects that the self-starter is waiting for the load to be connected. In step S404, after the load is connected, the autostart detects that the total apparent power of all power conversion systems is greater than the predefined power threshold. It then suspends to detect that the total apparent power of all power conversion systems is less than the predefined apparent power. A voltage surge instruction is then sent to each power conversion system, causing the voltage of each power conversion system undergoing autostart to rise from the first predefined voltage to the second predefined voltage. The predefined power threshold is greater than the predefined apparent power. After sending a voltage surge instruction to each of the power conversion systems undergoing self-starting, the self-starter receives feedback signals corresponding to the third self-start instruction from all the power conversion systems undergoing self-starting, indicating the completion of the self-start process. The self-starter then assigns all the power conversion systems as dependent power conversion systems, and a local controller begins responding to power transmission instructions from the power management system. In the self-starting method as described in the embodiments of the present invention, when each power conversion system raises its voltage to the first predetermined voltage, the load is connected, potentially producing a large impulse current. The system is suspended until the impulse current decreases and stabilizes, at which point the impulse load start-up is complete. For example, in one embodiment, after the self-start detects the end of the maximum load current and finds that the total apparent power of all power conversion systems is less than the predetermined apparent power, the self-start sends a self-start voltage rise instruction to each power conversion system. Upon receiving the self-start voltage rise instruction, each power conversion system controls its voltage to rise to the second predetermined voltage. Based on the self-starting method according to the above embodiments, the electricity generation system is also provided according to one of the embodiments of the present invention, which is described in detail in the accompanying drawings. With reference to Figure 5, it represents a schematic diagram of an electricity generation system according to one of the incarnations of the present invention. The electricity generation system, according to one embodiment of the present invention, includes: a black-start controller100 and multiple power conversion systems200. All or part of the multiple power conversion systems are subject to a black-start operation, and the AC sides of the power conversion systems subject to the black-start operation are connected to each other in parallel to supply the load. The Self-Start 100 system is designed to send instructions to raise the voltage to the first preset voltage for each of the 200 power conversion systems undergoing self-starting. The AC sides of the power conversion systems undergoing self-starting are connected in parallel to supply the load. The first preset voltage is lower than the second preset voltage for each power conversion system. It should be understood that the electricity generation system, according to the embodiment of the present invention, can be a novel energy system, including photovoltaic energy, energy storage, wind power, or similar. Self-starting is performed in external grid mode, i.e., it starts without electricity. The power management system of the electricity generation system sets the external grid mode, enabling self-starting. Additionally, the power management system sets the inverter voltage and frequency values ​​for the power conversion systems and sends them to a local controller, which then simultaneously sends them to each power conversion system. The power management system can also set the minimum number of power conversion systems subject to self-starting. This means that some power conversion systems in the electricity generation system undergo self-starting while others do not, or that all power conversion systems undergo self-starting, which is unlimited in the embodiments of the present invention. Self-start 100 is designed to: detect that the voltage of each of the power conversion systems subject to self-starting rises to the first predetermined voltage, send instructions about connecting the load to the power management system, and send instructions about the voltage rise, after the load is applied, to each of the power conversion systems subject to self-starting, causing the voltage of each of the power conversion systems subject to self-starting to rise from the first predetermined voltage to the second predetermined voltage. The Power Management System 300 is designed to control the load being connected. The Self-Start 100 is connected to the Power Management System 300. In the self-starting method as described in the present invention, the power conversion voltage is controlled to rise to the first predetermined voltage, which is lower than the second predetermined voltage, during the self-starting process. When the power conversion system remains at its voltage level at the first predetermined voltage without further change, the load is connected. After the load is connected, the power conversion system voltage is further controlled to rise from the first predetermined voltage to the second predetermined voltage. The first predetermined voltage is lower than the second predetermined voltage. Thus, when the load is connected during the phase in which the power conversion system is operating at the first predetermined voltage, even if there is a large inrush current from the load, the total apparent power of the power generation system is not excessively high and does not exceed the total apparent power of all the power conversion systems. In this case, large inrush currents on the power conversion systems are prevented, ensuring the success of the self-starting process. Before the self-start controller detects that the voltage of each of the power conversion systems subject to self-starting rises to the first predetermined voltage, self-starting is also designed to: send, upon receiving feedback signals corresponding to the first self-starting instruction from all the power conversion systems subject to self-starting, the second self-starting instruction to each of the power conversion systems subject to self-starting, and is suspended to receive feedback signals corresponding to the second self-starting instruction from each of the power conversion systems subject to self-starting. Upon receiving feedback signals corresponding to the first self-start instruction from all power conversion systems subject to the self-start process, the second self-start instruction is sent to each of the power conversion systems subject to the self-start process, and is suspended to receive feedback signals corresponding to the second self-start instruction from all power conversion systems subject to the self-start process as follows: The self-start system receives a feedback signal corresponding to the initial self-start instruction from a primary power conversion system, and a feedback signal corresponding to the initial self-start instruction from a secondary power conversion system, where all power conversion systems include at least one primary power conversion system and one secondary power conversion system; The self-starting sends the second self-starting instruction to at least one dependent power conversion system, and, upon receiving the feedback signal corresponding to the second self-starting instruction from at least one dependent power conversion system, sends the second self-starting instruction to the main power conversion system, and is suspended to receive the feedback signal corresponding to the second self-starting instruction from the main power conversion system. When the self-start controller detects that the voltage of each of the power conversion systems subject to the self-start process rises to the first predetermined voltage, it sends instructions to the power management system about connecting the load as follows: When the voltage of each of the power conversion systems subject to the self-start process rises to the first predetermined voltage and each of the power conversion systems subject to the self-start process remains at its voltage level at the first predetermined voltage, the self-start receives feedback signals corresponding to the fourth instruction regarding self-starting sent by all the power conversion systems subject to the self-start process, and sends instructions about connecting the load to the power management system. To prevent a power conversion system from being subjected to large inrush currents, self-starting controls the power conversion system voltage to rise from the first preset voltage to the second preset voltage only when the total apparent power of the power generation system is below a preset apparent power threshold. When the total apparent power of all power conversion systems subject to self-starting is greater than or equal to the preset apparent power, the system is suspended to reduce the total apparent power of all power conversion systems subject to self-starting. This is because the inrush current generated during load connection decreases over time, resulting in a corresponding decrease in the total apparent power. To ensure successful self-starting and protect the power conversion system from excessive surge currents, the power conversion system is not immediately controlled to raise its voltage to the second preset voltage after the load is connected. Instead, the total apparent power of the power generation system is detected. For example, when the load is initially connected, the total apparent power of all power conversion systems may be relatively high, for instance, exceeding 75% of the rated apparent power (Pn). In such cases, the system enters a hold period until the total apparent power of all power conversion systems falls below the preset apparent power, at which point a voltage rise instruction is sent to each power conversion system. Consequently, the power conversion system voltage rises from the first preset voltage to the second preset voltage. For example, the preset apparent power might be set at 25% of Pn. These values ​​are provided as examples for illustration purposes only and may vary according to actual requirements. The self-start control unit, upon detecting that the total apparent power of the power conversion systems subject to the self-start process is less than the predefined apparent power, sends instructions about connecting the load to the energy management system as follows: Self-start is suspended when it is discovered that the total apparent power of all power conversion systems is greater than the predefined power threshold, or when it is discovered that the total apparent power falls below the predefined apparent power, and instructions are sent about a voltage rise to each of the power conversion systems, where the predefined power threshold is greater than the predefined apparent power. To ensure successful self-starting and protect the power conversion system from excessive surge currents, the power conversion system is not immediately controlled to raise its voltage to the second preset voltage after the load is connected. Instead, the total apparent power of the power generation system is detected. For example, when the load is initially connected, the total apparent power of all power conversion systems may be relatively high, for instance, exceeding 75% of the rated apparent power (Pn). In such cases, the system enters a hold period until the total apparent power of all power conversion systems falls below the preset apparent power, and a voltage rise instruction is sent to each power conversion system. Consequently, the power conversion system voltage rises from the first preset voltage to the second preset voltage. For example, the preset apparent power might be set at 25% of the rated apparent power (Pn). These values ​​are provided as examples for illustration purposes only and may vary according to actual requirements. In an electricity generation system as embodied in the present invention, when each power conversion system raises its voltage to the first predetermined voltage and a load is connected to a power conversion system, this may produce a large impulse current. The system is suspended until the impulse current decreases and stabilizes, and the impulse-load start-up is completed. For example, in one embodiment, after the self-starter detects the end of the maximum load current and finds that the total apparent power of all power conversion systems is less than the predetermined apparent power, the self-starter sends a self-start voltage rise instruction to each power conversion system. Upon receiving the self-start voltage rise instruction, a power conversion system controls its voltage to raise the voltage to the second predetermined voltage. The embodiments of the present invention are described sequentially, with each embodiment highlighting its difference from the others. Therefore, one embodiment may refer to other embodiments of the same or similar parts. The system or apparatus described in the embodiments corresponds to the method described in the embodiments and is thus described in a relatively simple manner. According to the description of the incarnations declared, specialists in the field can implement or use the present invention. The various modifications made to the incarnations are obvious to those skilled in the field, and the general principles set forth in the present invention can be implemented in other incarnations without departing from the spirit or scope of the present invention. Therefore, the present invention is not limited to the incarnations described herein, but must be compatible with the broader scope consistent with the new principles and features declared herein.

Claims

1. The black-start method involves: sending instructions, via a black-start controller (BS) or energy management system (EMS), to raise the voltage to the first predetermined voltage for each power conversion system (PCS) undergoing the black-start process; the alternating-current sides of the PCS are connected in parallel to connect the load; and the black-start or energy management system detects that the voltage of each PCS has risen to the first predetermined voltage, sends instructions to connect the load, and sends instructions for the voltage to rise, after the load is connected, to each PCS.This causes the voltage of each power conversion system undergoing the black-start process to rise from the initial preset voltage to a second preset voltage, where the initial preset voltage is lower than the second preset voltage.

2. The black-start method, according to protection element 1, is implemented before the voltage of each power conversion system undergoing the black-start process is detected to have risen to the initial preset voltage. The method also includes the following: Upon receiving feedback signals corresponding to the first black-start instruction from all power conversion systems undergoing the black-start process, the second black-start instruction is sent to each power conversion system undergoing the black-start process and is then suspended to receive feedback signals corresponding to the instruction.The second instruction concerns the black-start of all power conversion systems undergoing the black-start process.

3. The black-start method, according to protection element 2, involves sending the second black-start instruction to each power conversion system upon receiving feedback signals corresponding to the first black-start instruction from all power conversion systems undergoing the black-start process. The waiting period for receiving feedback signals corresponding to the second black-start instruction from all power conversion systems undergoing the black-start process includes: receiving the feedback signal corresponding to the first black-start instruction from the system.The primary power conversion system receives a feedback signal corresponding to the first black-start instruction from a secondary power conversion system. All power conversion systems consist of at least one primary and one secondary power conversion system. The second black-start instruction is sent to at least one secondary power conversion system, and the black-start system receives a feedback signal corresponding to the second black-start instruction from at least one secondary power conversion system. The second black-start instruction is then sent to the primary power conversion system and is held to receive a feedback signal corresponding to the second black-start instruction from the primary power conversion system.

4. The black-start method, according to protection element 1, involves detecting that the voltage of each power conversion system undergoing the black-start process rises to the initial predetermined voltage and includes sending instructions to the energy management system about connecting the load. This involves: detecting that the voltage of each power conversion system rises to the initial predetermined voltage and remains at that initial predetermined voltage; receiving feedback signals corresponding to the fourth black-start instruction sent by all power conversion systems; and sending instructions to the energy management system about connecting the load.

5. The black-start method, according to protection element 1, involves sending, after the load is connected, instructions about the voltage rise to each power conversion system undergoing the black-start process.On: Detecting that the total apparent power of all power conversion systems is greater than a predefined power threshold, and suspending, via the black-start process, the detection that the total apparent power is less than the predefined apparent power, and sending voltage surge instructions to each power conversion system where the predefined power threshold is greater than the predefined apparent power.

6. A power generation system, including: an array of power conversion systems; and a black-start controller or energy management system, where all or part of the array of power conversion systems is subject to the black-start process, and the alternating-current aspects of the power conversion systems subject to the black-start process are connected to each other in parallel to supply the load. The black-start system is designedThe energy management system is designed to send instructions to raise the voltage to the first preset voltage for each power conversion system undergoing the black-start process. The black-start system, or energy management system, detects that the voltage of each power conversion system undergoing the black-start process has risen to the first preset voltage and sends instructions to connect the load to the energy management system. It then sends instructions for the voltage to rise, after the load is applied, to each power conversion system undergoing the black-start process. This causes the voltage of each power conversion system undergoing the black-start process to rise from the first preset voltage to the second preset voltage, where the first preset voltage is lower than the second preset voltage.

7. Power Generation SystemAccording to protection element 6, the black-start system is also designed to: Before the black-start system or energy management system detects that the voltage of each power conversion system undergoing the black-start process has risen to the first predetermined voltage, it sends, upon receiving feedback signals corresponding to the first black-start instruction from all power conversion systems undergoing the black-start process, the second black-start instruction to each of those systems, and suspends operation to receive feedback signals corresponding to the second black-start instruction from all power conversion systems undergoing the black-start process.

8. Power generation system according toFor protection element 7, the black-start or energy management system sends, upon receiving feedback signals corresponding to the first black-start instruction from all power conversion systems undergoing the black-start process, the second black-start instruction to each of the power conversion systems undergoing the black-start process. It is then suspended to receive feedback signals corresponding to the second black-start instruction from all power conversion systems undergoing the black-start process, as follows: The black-start receives the feedback signal corresponding to the first black-start instruction from a primary power conversion system, and receives the feedback signal corresponding to the first instruction.Regarding black-start from the power conversion system, all power conversion systems include at least one main power conversion system and at least one subordinate power conversion system. The black-start or energy management system sends the second black-start instruction to at least one subordinate power conversion system. The black-start receives a feedback signal corresponding to the second black-start instruction from at least one subordinate power conversion system, then sends the second black-start instruction to the main power conversion system. It is then held to receive a feedback signal corresponding to the second black-start instruction from the main power conversion system.

9. Power Generation SystemAccording to any of the protection elements from 6 to 8, the black-start or energy management system detects that the voltage of each power conversion system undergoing the black-start process rises to the first predetermined voltage and sends instructions to the energy management system about connecting the load as follows: The black-start or energy management system detects that the voltage of each power conversion system rises to the first predetermined voltage and remains at that first predetermined voltage. It receives feedback signals corresponding to the fourth black-start instruction sent by all power conversion systems undergoing the black-start process and sends instructions about connecting the load to the energy management system.

10. Power generation system according to any of the protection elementsProtection elements 6 to 8, where the black-start or energy management system sends instructions about voltage surges, after the load is applied, to each of the power conversion systems subject to the black-start process as follows: The black-start or energy management system detects that the total apparent power of all power conversion systems is greater than the predefined power threshold, and the black-start is suspended if it detects that the total apparent power is less than the predefined apparent power and sends instructions about voltage surges to each of the power conversion systems, where the predefined power threshold is greater than the predefined apparent power.