Multi-level tunnel structure having upper tunnel and lower tunnel connected, and construction method therefor

The method of independently excavating upper and lower tunnels with a support frame facilitates efficient and flexible multi-level tunnel construction, reducing costs and time while ensuring stable slab formation.

US20260366424A1Pending Publication Date: 2026-11-19BT CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
US19/126062
Authority / Receiving Office
US · United States
Patent Type
Applications(United States)
Current Assignee / Owner
Priority Date
2022-11-02
Filing Date
2023-11-01
Publication Date
2026-11-19

AI Technical Summary

Technical Problem

Existing multi-level tunnel construction methods increase construction costs and periods due to unnecessary excavation areas and require precise, potentially damaging drilling for accurate slab formation, limiting design flexibility and efficiency.

Method used

A method involving the independent excavation of upper and lower tunnels with circular cross-sections using an excavator, followed by installing a support frame between them, forming side surface parts, and constructing slabs to distinguish layers, allowing for efficient drilling and flexible design.

Benefits of technology

Enables economical and efficient tunnel construction with reduced excavation time, allowing for various standards and easy slab positioning, enhancing construction stability and flexibility.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure US20260366424A1-D00000_ABST
    Figure US20260366424A1-D00000_ABST
Patent Text Reader

Abstract

A multi-level tunnel structure (MT) having an upper tunnel and a lower tunnel connected, and a construction method (M) therefor including an upper and lower tunnel formation step for, by using a tunnel boring machine, drilling, close to each other, an upper tunnel and a lower tunnel having circular cross-sections; a support frame installation step for installing a support frame so as to pass through between the upper tunnel and the lower tunnel such that the upper end of the support frame supports the upper tunnel in a state where the lower end of the support frame is seated in the lower tunnel; a side surface part formation step for forming side surface parts by excavating such that, excluding the upper half part of the upper tunnel and the lower half part of the lower tunnel.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present invention relates to a multi-level tunnel structure having an upper tunnel and a lower tunnel connected to each other, and a construction method therefor, and more specifically, to a multi-level tunnel structure and a construction method therefor, in which an upper tunnel and a lower tunnel, which have a circular cross-section, are drilled close to each other using an excavator to form linings on each of inner circumferential surfaces of the upper tunnel and lower tunnel, respectively, a support frame is installed to pass through between the upper tunnel and the lower tunnel so that side surface parts are formed by excavating a lower half part of the upper tunnel and an upper half part of the lower tunnel to communicate with each other in a state where the upper tunnel is supported, wall linings are formed to extend to the linings, and at least one slab is formed on the side surface part to distinguish between an upper layer and a lower layer.BACKGROUND ART

[0002] Large cities around the world are facing serious urban traffic congestion due to increasing population and vehicles. Environmental problems occurring due to conventional internal combustion engine vehicles are expected to be solved soon as electric vehicles are gradually replaced, but extreme traffic congestion is a continuous obstacle to human attempts to minimize temporal and spatial limitations.

[0003] In order to solve this problem, in recent years, a method has been proposed in which a wide-area railway network is installed to establish a metropolitan area railway network, or a new deep underground road is newly established in order to resolve congestion and utilize a narrow space in three dimensions, so that a ground part is used as a BRT or a central bus lane, and an underground part is used for the movement of vehicles.

[0004] In particular, overseas tunnel construction service companies are concentrating on technology development using underground tunnels with the aim of recovering transportation problems and urban landscape, and developing new transportation means that may move quickly, and as a result, a new concept excavator, Prufrock, has been proposed, and research and development continues even now.

[0005] In the near future, it is expected that a road network similar to the capillaries of the human body is formed by forming a tunnel network underground in large cities and by forming an overpass above some elevated sections to enable continuous vehicle operation. In particular, it is expected that a new concept of transportation means is developed that may enable passengers to reach the destination by autonomously searching for a route when the passengers enter and board an unmanned vehicle associated with an autonomous vehicle, and may maximize the number of moving passengers by effectively utilizing the surface area of the road by minimizing the vehicle spacing.

[0006] However, since the urban area has limited space utilization, it is required to increase the surface area of the road through multi-leveling from an excavation stage of the tunnel. However, as shown in FIG. 1a, in most of the multi-level tunnels proposed in the related art, as a circular perforation 1 is formed at a time with a diameter large enough to form a multi-layer and a lining 2 and a slab 3 are formed inside the circular perforation 1, the excavation area is unnecessarily increased, resulting in a limitation in that the construction cost and the construction period are inevitably increased.

[0007] Meanwhile, in order to implement efficient multi-leveling of tunnels, a “multi-level tunnel construction method” of Korean Registered Patent No. 10-2136951 (Registered in Jul. 16, 2020, hereinafter referred to as “prior art document”) has been proposed. In the prior art document, as shown in FIG. 1b, in constructing a multi-level tunnel including upper and lower parts, an upper tunnel 1a is first excavated, an arch formation part 4 that is easily removed later is installed under the upper tunnel, and slab concrete is poured on the upper part to reinforce an upper part of a lower tunnel 1b to be excavated. Thereafter, the arch formation part 4 is removed and the lower tunnel 1b is excavated under the slab concrete 3.

[0008] The prior art document has an advantage in that the slab concrete 3 formed by the arch formation part 4 may be directly used as a slab for multi-level construction, but there is a difficulty in that a bottom surface of the slab concrete has to be precisely formed in an arch shape for drilling of the lower tunnel. In addition, in using an excavator such as a tunnel boring machine (TBM), accurate drilling is required along the bottom surface of the slab concrete, but there is an additional problem that the slab concrete is easily damaged due to construction errors.DISCLOSURETechnical Problem

[0009] The present invention is proposed to solve the above problems, and an object of the present invention is to provide a multi-level tunnel structure having an upper tunnel and a lower tunnel connected to each other and a construction method therefor, in which the upper tunnel and the lower tunnel may be independently excavated so that drilling may be easily and economically performed, the multi-level tunnel structure may be formed in various standards from a minimum of 12 ft to achieve an excellent workability, side surface parts may be simply constructed by effectively supporting the upper tunnel, and a slab may be freely positioned according to conditions of a site.Technical Solution

[0010] To solve the above technical problem, a construction method (M) for a multi-level tunnel structure having an upper tunnel and a lower tunnel connected to each other of the present invention includes: an upper and lower tunnel formation step (S10) of drilling an upper tunnel (10) and a lower tunnel (20), which have a circular cross-section, close to each other using an excavator; a support frame installation step (S20) of installing a support frame (100) to pass through between the upper tunnel (10) and the lower tunnel (20) so that an upper end of the support frame (100) supports the upper tunnel (10) in a state where a lower end of the support frame (100) is seated on the lower tunnel (20); a side surface part formation step (S30) of forming side surface parts (30) by excavating a lower half part (10b) of the upper tunnel (10) and an upper half part (20a) of the lower tunnel (20) to communicate with each other, except for an upper half part (10a) of the upper tunnel (10) and a lower half part (20b) of the lower tunnel (20); and a slab formation step (S40) of forming at least one slab (40) on the side surface parts (30) to distinguish between an upper layer and a lower layer.

[0011] In addition, the upper and lower tunnel formation step (S10) may include: an upper and lower tunnel drilling step (S11) of drilling the upper tunnel (10) and the lower tunnel (20); and a lining formation step (S12) of forming linings (11, 21) on inner circumferential surfaces of the upper tunnel (10) and the lower tunnel (20), respectively.

[0012] In addition, the side surface part formation step (S30) may include: a side surface part excavation step (S32) of excavating the lower half part (10b) of the upper tunnel (10) and the upper half part (20a) of the lower tunnel (20) to communicate with each other; a wall lining formation step (S34) of forming wall linings (31) on the side surface parts (30); and a support frame removal step (S35) of removing the support frame (100).

[0013] In addition, the side surface part formation step (S30) may further include a lining removal step (S31) of removing linings formed on the lower half part (10b) of the upper tunnel (10) and the upper half part (20a) of the lower tunnel (20).

[0014] In addition, the side surface part formation step (S30) may further include a side surface part reinforcement step (S33) of reinforcing the excavated side surface part (30) by inserting a support material (35) into the side surface part (30).

[0015] In addition, the slab formation step (S40) may include: a main slab formation step (S41) of forming a main slab (41) to connect opposite sides of the side surface parts (30) to each other; and a lower slab formation step (S42) of forming a lower slab (42) to connect lower half parts (20b) of the lower tunnel (20) to each other.

[0016] In addition, a supporting part (110) for supporting the upper tunnel (10) may be formed at the upper end of the support frame (100), a base part (120) seated on the lower tunnel (20) may be formed at the lower end of the support frame (100), and the supporting part (110) and the base part (120) may be integrally assembled by a connection rod (130).

[0017] In addition, the supporting part (110) may have an arc-shaped loop (111) for supporting the upper tunnel (10) to transfer a load to the connection rod (130) by a support frame (112), and the base part (120) may transfer the load, which is received from the connection rod (130), to a base (122) that makes contact with the lower tunnel (20), via a dispersion frame (121).

[0018] Meanwhile, a multi-level tunnel structure (MT) having an upper tunnel (10) and a lower tunnel (20) connected to each other of the present invention, is formed by using the upper tunnel (10) and the lower tunnel (20) drilled to have a circular cross-section in close to each other, in which an upper half part (10a) of the upper tunnel (10) and a lower half part (20b) of the lower tunnel (20) are excavated to communicate with each other so as to vertically form side surface parts (30) having linear shapes, linings (11, 21) are formed on the upper half part (10a) of the upper tunnel (10) and the lower half part (20b) of the lower tunnel (20), wall linings (31) are formed on the side surface parts (30) to extend to the linings (11, 21), and at least one slab (40) is formed on the side surface parts (30) to distinguish between an upper layer and a lower layer.

[0019] In addition, the slab (40) may include a main slab (41) configured to connect opposite sides of the side surface parts (30) and a lower slab (42) configured to connect lower half parts (20b) of the lower tunnel (20), so that a pipe shaft (PS) may be provided below the lower slab (42).Advantageous Effects

[0020] According to the multi-level tunnel structure having an upper tunnel and a lower tunnel connected to each other of the present invention and the construction method therefor, it is sufficient to drill the upper tunnel and the lower tunnel, which have a circular cross-section, close to each other using an excavator, so that independent excavation of each of the upper and lower tunnels is possible, thereby enabling efficient drilling.

[0021] In particular, the upper and lower tunnels are drilled to have a circular cross-section so as to correspond to the shape of the excavator because a process of separately forming or arranging a bottom part is unnecessary, so that the drilling is easily performed and a construction period is shortened, thereby obtaining an economical effect.

[0022] In addition, since the multi-level tunnel structure may be formed in various standards from a minimum of 12 ft according to the standards of the excavator, the degree of freedom in design may be secured, and the slab may be freely positioned.

[0023] Furthermore, since the upper end of the support frame may be simply installed to support the upper half part of the upper tunnel in a state where the lower end of the support frame is seated on the lower half part of the lower tunnel, the side surface parts may be simply constructed by excavating the lower half part of the upper tunnel and the upper half part of the lower tunnel to communicate with each other.

[0024] In addition, since the support frame may be assembled with the supporting part of the support frame around the support hole between the upper tunnel and the lower tunnel, the support frame may be easily installed.

[0025] In addition, since the excavated side surface part may be reinforced with a support material in a state where the support frame supports the upper half part of the upper tunnel, construction stability of the side surface part be achieved.DESCRIPTION OF DRAWINGS

[0026] FIG. 1a is a sectional view showing a multi-level tunnel constructed using a tunnel boring machine (TBM) according to the related art.

[0027] FIG. 1b is a sectional view sequentially showing a construction method for a multi-level tunnel according to the prior art document.

[0028] FIG. 2 is a block diagram showing a construction method for a multi-level tunnel structure of the present invention in time series.

[0029] FIG. 3 is a conceptual sectional view showing the overall process of the construction method for a multi-level tunnel structure according to one embodiment of the present invention.

[0030] FIG. 4 is a conceptual sectional view sequentially showing the detailed process of a support frame installation step according to one embodiment of the present invention.

[0031] FIG. 5a is a perspective view showing an installation state of a support frame according to one embodiment of the present invention.

[0032] FIG. 5b is a perspective view showing an installation state of a support frame according to another embodiment of the present invention.

[0033] FIGS. 6a and 6b are conceptual sectional views sequentially showing the detailed process of a side surface part formation step according to one embodiment of the present invention.

[0034] FIG. 7 is a sectional view showing a multi-level tunnel structure according to another embodiment of the present invention.BEST MODEL

[0035] Hereinafter, a multi-level tunnel structure MT having an upper tunnel and a lower tunnel connected to each other of the present invention and a construction method M therefor will be described in more detail with reference to the accompanying drawings and a preferred embodiment.

[0036] First, the construction method M for a multi-level tunnel structure having an upper tunnel and a lower tunnel connected to each other of the present invention will be described. As shown in the block diagram of FIG. 2, the construction method M for a multi-level tunnel structure of the present invention includes an upper and lower tunnel formation step S10, a support frame installation step S20, a side surface part formation step S30, and a slab formation step S40.

[0037] As shown in FIG. 3, the upper and lower tunnel formation step S10 is a step of drilling an upper tunnel 10 and a lower tunnel 20, which have a circular cross-section, close to each other using an excavator. The excavator may be selectively adopted to have a diameter corresponding to a width of a tunnel to be constructed, and may be drilled in various standards from 12 ft, which is a minimum standard corresponding to the width of the road. In this case, the upper tunnel 10 and the lower tunnel 20 are preferably formed to have the same diameter.

[0038] Any one of the upper tunnel 10 and the lower tunnel 20 may be excavated by a predetermined length, and then the other thereof may be excavated in parallel, but preferably, the lower tunnel 20 may be excavated first, and then the upper tunnel 10 may be excavated at the corresponding position so as to be spaced apart from the lower tunnel 20 by a predetermined interval with different heights. Meanwhile, according to an embodiment, when the ground is a hard rock layer, it may be also constructed such that a pair of excavators individually excavate the upper tunnel 10 and the lower tunnel 20, respectively, in order to further shorten a construction period.

[0039] Further, the upper tunnel 10 and the lower tunnel 20 may be drilled to have a circular cross-section corresponding to the shape of the excavator so that construction efficiency may be improved, and the upper tunnel 10 and the lower tunnel 20 are individually excavated while being spaced apart from each other by a predetermined interval so as not to affect each other, and thus drilling is easily performed, thereby shortening the construction period.

[0040] Meanwhile, the upper and lower tunnel formation step S10 may include an upper and lower tunnel drilling step S11 of drilling the upper tunnel 10 and the lower tunnel 20, and a lining formation step S12 of forming linings 11 and 21 on inner circumferential surfaces of the upper tunnel 10 and the lower tunnel 20, respectively. The linings 11 and 21 formed on the upper tunnel 10 and the lower tunnel 20 may be assembled and constructed in such a manner that previously manufactured segment blocks 11a and 21a are arranged offset so as to correspond to curvatures of the upper tunnel 10 and the lower tunnel 20, and may be manufactured by forming a concrete layer having a predetermined thickness surfaces thereof.

[0041] Thereafter, as shown in FIG. 3, the support frame installation step S20 is a step of installing a support frame 100 to pass through between the upper tunnel 10 and the lower tunnel 20 so that an upper end of the support frame 100 supports the upper tunnel 10 in a state where a lower end of the support frame 100 is seated on the lower tunnel 20.

[0042] A supporting part 110 for supporting the upper tunnel 10 may be formed at the upper end of the support frame 100, a base part 120, which is seated on the lower tunnel 20 to receive an upper load, may be formed at the lower end of the support frame 100, and the supporting part 110 and the base part 120 may be integrally assembled by a connection rod 130 passing through the upper and lower tunnels 10 and 20 in a state where the supporting part 110 and the base part 120 are separated from each other.

[0043] Therefore, in the support frame installation step S20, a support hole 15 may be formed in the center of the upper end of the lower tunnel 20 through the upper tunnel 10. That is, the support hole 15 is vertically formed by a length corresponding to a distance between the upper tunnel 10 and the lower tunnel 20, and the support hole 15 is provided such that the connection rod 130 is inserted thereinto, so that the supporting part 110 and the base part 120 may be integrally assembled. Thus, the support frame 100 may be easily installed or disassembled.

[0044] Meanwhile, the supporting part 110 may be formed in a semicircular structure so as to enable effective support while making contact with an upper half part 10a of the upper tunnel 10, and the connection rod 130 may be integrally formed and assembled with any one of the supporting part 110 and the base part 120, and the supporting part 110, the base part 120, and the connection rod 130 may also be assembled with each other while being separated from each other. In addition, according to the embodiment, frames constituting the supporting part 110 and the base part 120 may also be formed to be selectively disassembled and assembled to secure constructability.

[0045] Thereafter, as shown in FIG. 3, the side surface part formation step S30 is a step of vertically forming side surface parts 30 having linear shapes by excavating a lower half part 10b of the upper tunnel 10 and an upper half part 20a of the lower tunnel 20 to communicate with each other, except for an upper half part 10a of the upper tunnel 10 and a lower half part 20b of the lower tunnel 20.

[0046] In this case, since the upper half part 10a of the upper tunnel 10 is supported by the supporting part 110 of the supporting frame 100, even if the lower half part 10b of the upper tunnel 10 and the upper half part 20a of the lower tunnel 20 are excavated, the upper half part 10a of the upper tunnel 10 may be stably supported without collapsing, so that construction easiness may be achieved in forming the side surface parts 30 to be described later.

[0047] The side surface part formation step S30 may include a lining removal step S31 of removing linings formed on the lower half part 10b of the upper tunnel 10 and the upper half part 20a of the lower tunnel 20. In this case, in the linings 11 and 21 of the upper and lower tunnels 10 and 20, the segment blocks 11a and 21a located at a boundary part between the upper and lower half parts may be manufactured in a structure capable of being easily broken or separated, or half block-shaped segment blocks may be disposed.

[0048] In addition, when a lining of a concrete layer is formed, it is preferable to construct the linings 11 and 12, which are located on the lower half part 10b of the upper tunnel 10 and the upper half part 20a of the lower tunnel 20, to be easily removed by forming fragile parts with a construction joint.

[0049] In addition, the side surface part formation step S30 may include a wall lining formation step S34 of forming wall linings 31 on the side surface parts 30. As a result, the linings 11 and 21 remaining on the upper half part 10a of the upper tunnel 10 and the lower half part 20b of the lower tunnel 20 are constructed to be continuous with the wall linings 31, thereby completing a tunnel structure in which the linings 11 and 21 remaining on the upper half part 10a of the upper tunnel 10 and the lower half part 20b of the lower part 20 are formed on upper and lower parts of the side surface part 30, and the wall linings 31 are formed at opposite sides of the side surface part 30. In this case, the wall linings 31 may be also formed by assembling and disposing the segment blocks 31a, and the side surface parts 30 may be formed by forming linings of the concrete layer.

[0050] Thereafter, as shown in FIG. 3, the slab formation step S40 is a step of forming at least one slab 40 on the side surface parts 30 to distinguish between an upper layer and a lower layer. The slab 40 may be assembled and constructed such that a PC block 40a is connected to the side surface part 30, and to this end, a binding steel bar may be exposed at the side surface part 30. In addition, the slab 40 may be manufactured by assembling a mold, placing rebars, and curing on-site cast concrete.

[0051] In this case, the slab formation step S40 may include a main slab formation step S41 of forming a main slab 41 to connect opposite sides of the side surface parts 30 to each other, and a lower slab formation step S42 of forming a lower slab 42 to connect lower half parts 20b of the lower tunnel 20 to each other.

[0052] At least one main slab 41 may be formed as a component for distinguishing between an upper layer and a lower layer and performing its original function such as moving movement means. That is, when diameters of the upper tunnel 10 and the lower tunnel 20 are relatively large, a tunnel structure having a multi-level structure may be constructed by forming a plurality of main slabs 41.

[0053] In addition, a lower slab 42 may be formed at the lowermost end to connect the lower half parts 20b of the lower tunnel 20 to each other, and a pipe shaft PS may be provided below the lower slab 42 such that a drain pipe or a telecommunications wiring may move. In this case, the construction may be performed from a lower part to an upper part, and the lower slab formation step S42 may be first performed, and the main slab formation step S41 may be performed.

[0054] As described above, according to the construction method M for a multi-level tunnel structure having an upper tunnel and a lower tunnel connected to each other of the present invention, the upper tunnel and lower tunnel having a circular cross-section may be independently excavated using an excavator, so that construction efficiency may be improved, the multi-level tunnel structure MT may be formed in various standards from a minimum of 12 ft according to the standards of the excavator, so that the degree of freedom in design may be secured, the slab 40 may be freely positioned, and the support frame 100 may be easily installed and disassembled.Mode for Invention

[0055] Hereinafter, the support frame installation step S20 and the side surface part formation step S30 will be described in more detail.

[0056] As shown in FIG. 4, in the support frame installation step S20, it is preferable that a base part installation step S21 of installing the base part 120 of the support frame 100 in the lower tunnel 20 is performed. In the base part installation step S21, a connection rod 130 is integrally or separately formed at an upper end of the base part 120 to allow the connection rod 130 to pass through the support hole 15.

[0057] During the installation of the base part 120, a supporting part installation step S22 of installing the supporting part 110 of the support frame 100 in the upper tunnel 10 is performed. A lower end of the supporting part 110 is bound to the connection rod 130, so that the upper half part 10a of the upper tunnel 10 may be stably supported by the support frame 100.

[0058] Meanwhile, as shown in FIG. 5a, it is preferable that the supporting part 110 for supporting the upper tunnel 10 of the support frame 100 installed in the support frame installation step S20 has an arc-shaped loop 111 connected to a support frame 112 to transfer a load to the connection rod 130 such that the upper half part10a of the upper tunnel 10 is supported.

[0059] Meanwhile, as shown in FIG. 5b, the lining 11 installed on the upper tunnel 10 may have a plurality of nut holes 11b, and the arc-shaped loop 111 of the supporting part 110 may be manufactured in a frame shape. In this case, the frame-shaped loop 111 may have through-holes formed at positions corresponding to the nut holes 11b so that bolts may bind the loop 111 and the lining 11 to each other.

[0060] In addition, the arc-shaped loop frame 111 and the support frame 112 are formed to be fastened to and separated from each other, and the loop frame 111 may be manufactured in a truss structure even when the support frame 100 is removed, and thus the loop frame 11 may remain such that the upper half part 10a of the upper tunnel 10 is permanently supported.

[0061] Meanwhile, as shown in FIG. 5b, reinforcement pieces 11c, which are reinforced with a metal material having a predetermined thickness in a longitudinal direction, may be formed at both lower end parts of the lining 11 or segment 11a constructed in the upper half part 10a of the upper tunnel 10 such that the frame-type loop 111 is stably supported and sufficient rigidity is secured. In this case, it is preferable that the nut holes 11b described above are also formed in the reinforcement pieces 11c. The reinforcement piece 11c also performs a reinforcing function so that the segment 11a is stably supported on the lower side surface part 30.

[0062] In this case, a reinforcement fastening part 111a having a shape corresponding to the reinforcement piece 11c may be formed at both lower end parts of the frame-type loop 111, and a through-hole 111b may be formed at a corresponding position on the reinforcement fastening part 111a such that a fastening bolt may pass therethrough and may be fastened to the nut hole 11b. Accordingly, even when the support frame 100 is disassembled later, the frame-type loop 111 may remain to effectively support the upper half part 10a of the upper tunnel 10.

[0063] Further, the frame-type loop 111 may be spaced apart from the adjacent loop 111 to reduce the amount of material used and secure ease of installation, and a plurality of connection frames 113 may be installed between the adjacent loop frames 111 to reinforce the loop frames in the longitudinal direction.

[0064] In addition, the base part 120, which is seated on the lower tunnel 10 of the support frame 100 to transfer the load to the lower part, may disperse and transfer the load, which is received from the connection rod 130, to the base part 122 that at least partially makes contact with the lower tunnel 20, via a dispersion frame 121.

[0065] Meanwhile, as shown in FIGS. 6a and 6b, the side surface part formation step S30 may be subdivided into a lining removal step S31, a side surface part excavation step S32, a side surface part reinforcement step S33, a wall lining formation step S34, and a support frame removal step S35.

[0066] As described above, the lining removal step S31 is a step of removing the linings formed on the lower half part 10b of the upper tunnel 10 and the upper half part 20a of the lower tunnel 20, and it is preferable that the lining 11 of the upper tunnel 10 and the lining 21 of the lower tunnel 20 are manufactured in a structure capable of being broken or separated to facilitate removal, and according to the embodiment, fragile parts may be formed on the lining 11 or 21 with a construction joint. That is, in the initial lining formation step S12, the permanent linings 11 and 21 may be formed only on the upper half part 10a of the upper tunnel 10 and the lower half part 20b of the lower tunnel 20, and linings may be formed on the remaining lower half part 10b of the upper tunnel 10 and the remaining upper half part 20a of the lower tunnel 20 to be temporarily used or recycled.

[0067] Thereafter, the side surface part excavation step S32 is a step of excavating the lower half part 10b of the upper tunnel 10 and the upper half part 20a of the lower tunnel 20 to communicate with each other. In this case, since the upper half part 10a of the upper tunnel 10 maintains a state of being stably supported by the support frame 100, the side surface parts 30 may be effectively formed.

[0068] Meanwhile, FIG. 7 shows a multi-level tunnel structure MT according to another embodiment of the present invention, in which the side surface parts 30 may be formed to have a width wider than that of the upper tunnel 10 and the lower tunnel 20, and the slab 40 may also be formed to have a length that corresponds thereto. Therefore, the width may be varied if necessary to secure a width of the lane wider or to form an emergency passage depending on the section.

[0069] Next, the side surface part reinforcement step S33 is a step of reinforcing the excavated side surface part 30 by inserting a support material 35 into the side surface part 30. The side surface part reinforcement step S33 may be performed by various known methods, but it is preferable to insert a steel pipe by drilling the side surface part such that the steel pipe is inserted thereinto and to reinforce the side surface part by injecting a grout material.

[0070] Thereafter, the wall lining formation step S34 is a step of forming wall linings 31 on the side surface part 30, in which the linings 11 and 21 remaining on the upper half part 10a of the upper tunnel 10 and the lower half part 20b of the lower tunnel 20 are connected to each other to form an integrated lining structure.

[0071] Next, the support frame removal step S35 is a step of removing the support frame 100 because the lining 11 formed on the upper half part 10a of the upper tunnel 10 is stably supported by the wall lining 31 of the side surface part 30.

[0072] In this case, the arc-shaped loop 111 and the support frame 112 are formed to be fastened to and separated from each other, and the loop 111 may be manufactured in a truss structure even when the support frame 100 is removed so as to remain such that the upper half part 10a of the upper tunnel 10 is permanently supported.

[0073] Meanwhile, the multi-level tunnel structure MT having an upper tunnel and a lower tunnel connected to each other is a structure completed by the time-series characteristics of the above-described construction method M, and a detailed description thereof will be omitted. In addition, the multi-level tunnel structure MT of the present invention may secure the same structural characteristics and construction advantages by the above-described construction method.

[0074] According to one embodiment, the upper tunnel 10 and the lower tunnel 20, which have a circular cross-section, are drilled close to each other using an excavator to form linings 11 and 21 on inner circumferential surfaces of the upper tunnel 10 and the lower tunnel 20, respectively.

[0075] In addition, the support frame 100 is installed to pass through between the upper tunnel 10 and the lower tunnel 20, and the lower half part 10b of the upper tunnel 10 and the upper half part 20a of the lower tunnel 20 are excavated to communicate with each other in a state where the upper tunnel 10 is supported, so that after the linear-shaped side surface part 30 are vertically formed, the support frame 100 is removed, and thus the wall linings 31 are formed on the side surface parts 30 and extend to the linings 11 and 21.

[0076] In addition, at least one slab 40 is formed on the side surface part 30 to distinguish between the upper layer and the lower layer, thereby completing the multi-level tunnel structure MT of the present invention.

[0077] In this case, the slab 40 may include a main slab 41 configured to connect opposite sides of the side surface parts 30 and a lower slab 42 configured to connect lower half parts 20b of the lower tunnel 20, so that a pipe shaft PS may be provided below the lower slab 42.

[0078] It will be understood by those of ordinary skill in the art that the multi-level tunnel structure MT having an upper tunnel and a lower tunnel connected to each other and the construction method M thereof, which are described above, may be implemented in other specific forms without changing the technical spirit or essential features of the present invention.

[0079] Therefore, it should be understood that the embodiments described above are exemplary in all aspects and are not restrictive, and the scope of the present invention is indicated by the claims to be described later rather than the above-described detailed description of the invention, and it should be interpreted that all changes or modifications derived from the meaning and scope of the claims and the equivalent concept are included in the scope of the present invention.INDUSTRIAL APPLICABILITY

[0080] Transportation means using the underground, including subways, hardly hinders traffic or walking on the ground and enables fast movement. The highway is a useful transportation facility, but in a case where the highway is installed in the basement of the city center, when an interchange is constructed as a three-dimensional intersection, it is difficult to install a large number of interchanges in a narrow city center because the interchange occupies a wide area. However, when a middle-level tunnel of the present invention is used, all left turns need to be rotated by 90° like a right turn instead of 270°, and thus connection lamps of the three-dimensional intersection have a large turning radius and the size of the intersection is reduced by 10 times or more, so that all three-dimensional intersections may be installed where necessary. Furthermore, a transportation means that enables high frequency traveling of Nonstop, such as a highway, may have a capacity that is two times or more and three times faster than a subway by using the feature of the intersection having a small size and a large turning radius.

[0081] When vehicles in opposite directions travel on an upper layer and a lower layer of a middle-level tunnel, the vehicles may branch off to any one of the left and right sides or merge, and thus the vehicles joining at several places in the downtown may travel with high frequency and may branch off to several places. In the middle-level tunnel essential for installing a small intersection in the basement of a narrow existing downtown, the above method of excavating using a circular excavator and then connecting the upper tunnel and the lower tunnel to each other to form a slab is faster and more efficient than the existing tunnel excavation method. In addition, it is easy to design the completed tunnel sectional view to minimize a space unnecessary for the vehicles to travel on a second level road.

Claims

1. A construction method for a multi-level tunnel structure having an upper tunnel and a lower tunnel connected to each other, the construction method comprising:an upper and lower tunnel formation step of drilling an upper tunnel and a lower tunnel, which have a circular cross-section, close to each other using an excavator;a support frame installation step of installing a support frame to pass through between the upper tunnel and the lower tunnel so that an upper end of the support frame supports the upper tunnel in a state where a lower end of the support frame is seated on the lower tunnel;a side surface part formation step of forming side surface parts by excavating a lower half part of the upper tunnel and an upper half part of the lower tunnel to communicate with each other, except for an upper half part of the upper tunnel and a lower half part of the lower tunnel; anda slab formation step of forming at least one slab on the side surface parts to distinguish between an upper layer and a lower layer.

2. The construction method of claim 1, wherein the upper and lower tunnel formation step includes:an upper and lower tunnel drilling step of drilling the upper tunnel and the lower tunnel; anda lining formation step of forming linings on inner circumferential surfaces of the upper tunnel and the lower tunnel, respectively.

3. The construction method of claim 1, wherein the side surface part formation step includes:a side surface part excavation step of excavating the lower half part of the upper tunnel and the upper half part of the lower tunnel to communicate with each other;a wall lining formation step of forming wall linings on the side surface parts; anda support frame removal step of removing the support frame.

4. The construction method of claim 3, wherein the side surface part formation step further includes a lining removal step of removing linings formed on the lower half part of the upper tunnel and the upper half part of the lower tunnel.

5. The construction method of claim 3, wherein the side surface part formation step further includes a side surface part reinforcement step of reinforcing the excavated side surface part by inserting a support material into the side surface part.

6. The construction method of claim 1, wherein the slab formation step includes:a main slab formation step of forming a main slab to connect opposite sides of the side surface parts to each other; anda lower slab formation step (S42) of forming a lower slab to connect lower half parts of the lower tunnel to each other.

7. The construction method of claim 1, wherein a supporting part for supporting the upper tunnel is formed at the upper end of the support frame, a base part seated on the lower tunnel is formed at the lower end of the support frame, and the supporting part and the base part are integrally assembled by a connection rod8. The construction method of claim 7, wherein the supporting part has an arc-shaped loop for supporting the upper tunnel to transfer a load to the connection rod by a support frame, and the base part transfers the load, which is received from the connection rod to a base that makes contact with the lower tunnel, via a dispersion frame.

9. A multi-level tunnel structure having an upper tunnel and a lower tunnel connected to each other, which is formed by using the upper tunnel and the lower tunnel drilled to have a circular cross-section in close to each other,wherein an upper half part of the upper tunnel and a lower half part of the lower tunnel are excavated to communicate with each other so as to vertically form side surface parts having linear shapes, linings are formed on the upper half part of the upper tunnel and the lower half part (20b) of the lower tunnel, wall linings are formed on the side surface parts to extend to the linings, and at least one slab is formed on the side surface parts to distinguish between an upper layer and a lower layer.

10. The multi-level tunnel structure of claim 9, wherein the slab includes a main slab configured to connect opposite sides of the side surface parts and a lower slab configured to connect lower half parts of the lower tunnel, so that a pipe shaft (PS) is provided below the lower slab.