Procedure, practice - method of verification, sample containers and pipes with oxygen, nitrogen, argon co 2, h 2, medical air and industrial air
In situ checks and tests with the working fluid at operating pressure address the need for disassembly and emptying, significantly reducing time and costs for pressure vessel and pipe inspections.
Patent Information
- Application Number
- PCT/RO2024/000022
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2024-07-09
- Filing Date
- 2024-12-16
- Publication Date
- 2026-01-15
AI Technical Summary
Existing methods require disassembly and emptying of pressure vessels and pipes for periodic checks and tests due to contamination, volume, weight, or inability to achieve required pressure, leading to prolonged downtime and high costs.
Perform checks and tests in situ with the working fluid at operating pressure, without disassembly or emptying, using a method that includes visual inspection, non-destructive testing, and leak testing, followed by pressure testing in a separate loop.
Reduces check and test times from 25-30 days to 3-4 days, saving costs and maintaining operational continuity by performing tests with the working fluid at operating conditions.
Smart Images

Figure RO2024000022_15012026_PF_FP_ABST
Abstract
Description
[0001] 12.2. Description o f the invention with the title
[0002] 1. Procedure, practice - method of verification, sample containers and pipes with oxygen, nitrogen, argon. CO2. Hz. medical air and industrial air
[0003] The invention is characterized by the fact that, in the parts below, 1 present all the new technical elements, marked with reference signs corresponding to those in the drawings and placed in brackets, which, in combination with the characteristics presented in the preamble, define the requested protection.
[0004] 2. Technical characteristics of the invention:
[0005] Procedure Checks, sample containers and pipes with p > 0.5 bar; V < 350 m3, Vma.i 550 m3, Pmax 1000 bar and other capacities and volumes, Parking 0.2 MPa + 3 MPa and other pressures, DNma.x< 2500 mm, Tminmax- - 196°C / +20°C + +65°C and other temperatures
[0006] Fluids in a physical state of aggregation, gases under pressure O2, N2, Argon, CO2, H2, Surgical and instrumental air, Industrial air, fluids in a physical state of aggregation, liquefied gases O2, N2, Ar, CO2
[0007] Fluids gr. 1 '2
[0008] J. Specification of the technical field to which the invention refers
[0009] The invention relates to the technical field
[0010] Industry: manufacturing lines, technological lines in the machine building industry, technological lines in the field of scientific research; wind tunnels, aviation, research and the field of nuclear physics and engineering
[0011] In Health - Medicine: Instrumental medicinal air and Surgical medicinal air
[0012] 4. Presentation of the state of the art
[0013] The current state of the art stipulates that during checks and tests at periodic control due CP (RI + IP), internal revision and pressure test, for the evaluation of the technical condition of pressure vessels and pressure pipes, the checks and tests should be carried out with these vessels and pipes removed from the installation, emptied, isolated from the rest of the installation, following which the tests will be made hydraulically and / or pneumatically with nitrogen or air if the manufacturer and / or the designer allows the tests to be performed with these fluids: water, nitrogen, air.
[0014] If it is not allowed to carry out these tests with these fluids, due to contamination considerations, (medicine and research in physics and nuclear engineering), (wind tunnel aviation research), or if it is not allowed to carry out hydraulic tests because of the volume size and weight; or if the performance of pneumatic tests with air or nitrogen is not allowed, or if the pressure test with air or nitrogen cannot be performed due to the fact that the required flow and pressure cannot be ensured at the value of the sealing pressure or, at the value of the test pressure resistance Plest(bar) the need to solve this technical problem arose.
[0015] 5. Presentation of the technical problem that the invention solves and presentation of the advantages in relation to the state of the art 12.2.- Description of the invention continuation
[0016] The invention solves the technical problems in the fields of applicability presented above under the conditions in which: it is not allowed to carry out samples and tests at IMSP - mechanical installations under pressure: fluid containers and pipes for contamination reasons it is not allowed to carry out the hydraulic test due to the large volume of the weight and the lack of the possibility of raising the pressure to the required value Piling (bar), P test (bar) the flow of air and / or nitrogen cannot be ensured at the required pressure
[0017] The problem is solved by the presented invention, by checks and tests in the installation / equipment of which these IMPS are a part (mechanical installations under pressure - containers and pipes), without removing them from the installation, without emptying the installation and these IMPS.
[0018] Checks and tests being done with the working fluid at the working pressure in the distinct loop.
[0019] I specify that the national regulatory authority in the field of pressure equipment, ISCIR admits and accepts this Procedure of checks and tests, samples and the European and international certification body on the Brussels list, Tt / KAustria with REXNAR accreditation for pressure equipment 97 / 23 / EC accepts and has issued the certifications for this field of applicability with European recognition. I am attaching the PE of the ISCIR accepting the procedure for this field of applicability.
[0020] The invention solves the high technical problems that did not have a solution, it is a process - a method, an operational procedure that reduces the time of checks, tests at facilities and complex equipment in which containers and pipes under pressure are mounted and installed from 25 + 30 days to 3 + 4 days, the savings being considerable, not having to remove these containers, pipes, installations, equipment from operation, not having to empty them, mounting, installing, carrying out tests in the installation / equipment.
[0021] 6. Disclosure o f the Invention as claimed - invention with the title Procedure - practice - method of checks and samples containers and pipes with oxygen, nitrogen, argon, CO2, H2, medical air and industrial air and Presentation of Advantages in Relation to the State of the Art
[0022] Checks and tests at the due date of the mechanical installation under pressure, vessels and pipes CP - periodic control (R1 + IP) - internal revision + pressure test - are done in order to evaluate their technical condition for safe operation, checks and tests that are carried out based on the (procedure) of this procedure, - practice - verification method, which is the object of the invention patent application.
[0023] The procedure -practice - method of checking and testing containers and pipes with oxygen, nitrogen, argon, CO2, Hi, medical air and industrial air which is the subject of the invention patent application is characterized by the fact that:
[0024] It does not require the removal, dismantling and emptying of containers and pipes for fluids from the installation in which they are mounted, installed.
[0025] It does not require the redeployment and installation of containers and pipes from the installation from which they were dismantled for carrying out the tests
[0026] Checks and tests are done with the installation of which these containers and pipes are part in working condition without stopping and emptying the installation 12.2.- continuation
[0027] Checks and tests are done with the working fluid, at the working pressure, at the operating pressure of the installation in a separate loop
[0028] Since the hydraulic test is not possible due to contamination and / or due to the high volume and weight of the working fluid, checks and tests are done with working fluid, considerably reducing the time of checks and costs
[0029] Since the pneumatic tests cannot be performed due to the volume, high fluid flow rate and the lack of possibility to raise the pressure to the required values of pressure P tightness (bar), and Presistence (bar) the tests and checks are done with the working fluid, at the effective working pressure, reducing - considerable trial times, reducing related costs, greatly reducing test pressures and at the same time solving the technical problem of rising the pressure to high values in containers and pipes with very large volumes and very high pressures.
[0030] 7. Detailed presentation of a method of realization
[0031] The logical sequence of stages on operations and phases that characterize the process, with the presentation of the conditions for the development of the parameters and the technical means used'. STAGES
[0032] Visual - external inspection of the installations that include containers and pipes Verification of the agreement between the data on the stamp plates of the containers, pipes, installations with the technical data in the technical, construction books and with the technical data in the technical operating books of these IMPS - mechanical installations under pressure
[0033] Checking the condition of the outer surfaces of the base materials and welds as per the related SR EN reference
[0034] Verification of dimensional and shape deviations with references to SR EN 5817; SR EN 6520, for the quality class of welds B
[0035] Bumps, deformations, cracks, defects are not allowed
[0036] Checking the condition of fittings, safety valves, security accessories (devices for limiting pressure, temperature, fluid level - pressure switches, temperature switches, level regulators, pressure transducers, temperature regulators, programmable controllers, sensors monitoring, etc., AMCs - measuring and control devices, gas leak detection
[0037] - All these must be in good working order and with metrological verification with the ADMITTED result
[0038] After these checks, a report will be issued with the results with reference the applicable European norms with the recording Conclusions and Results ADMITTED - The checks are carried out by operators certified for VT according to the related European standards and authorized by ISCIR for visual control of VT, with up-to-date authorizations and visas.
[0039] After carrying out these checks with good results - ADMITTED, we move on to carrying out non-destructive checks, according to the specialized method:
[0040] UTS- ultrasonic thickness control
[0041] UTS- ultrasonic control of welds
[0042] MT- magnetic control test - with magnetic powders as appropriate: with permanent magnets with electromagnets 12.2.-continuation
[0043] PT - control with penetrating liquids
[0044] Control with metallographic replicas as appropriate
[0045] Checking the macrostructure
[0046] Grain condition and size
[0047] Intergranular state
[0048] The non-destructive tests on the specialty method are carried out by ZS'CZZ?-authorized non-destructive control laboratories with ISCIR - authorized RTEND technical personnel, with non-destructive control operators certified on the specialty method according to the relevant European norm and authorized by ISCIR or by an ISCIR - authorized nondestructive control operator.
[0049] Non-destructive control bulletins will be issued using the specialized method with ADMITTED results as appropriate, and at UTg it will be checked whether the minimum measured thickness is not below the minimum admissible resistance thickness.
[0050] The tightness of the installation, containers and pipes for fluids is checked with gas leak detectors and classic testers
[0051] It is checked whether the safety valves have a valid check-adjustment report and declaration of conformity.
[0052] It is checked whether the security accessories: transducers, sensors have valid metrological verification
[0053] Check if the installation is grounded
[0054] It is checked that gas leak detectors on detection levels are functional and with metrological verification
[0055] Compliance with SSM and PCI requirements is checked with their display, with the display of work and operating instructions, the existence of warning plates, the existence of safety data sheets for working fluids,
[0056] After checking the automation installation with the related functions: control, protection, adjustment, signaling, monitoring with good results, this check will be recorded in a technical report checking the automation installation with continuous adjustment and monitoring.
[0057] After carrying out these checks, non-destructive checks, leak testing with good results, Admitted, it is possible to proceed to carrying out samples and tests in a separate loop: that is, in the complete installations in which the pressure vessels and pipelines for pressure fluids are mounted - installed.
[0058] The tests will be done at the effective working pressure, with working fluid at the pressures
[0059] P Two, -king (bar) - 15 minutes
[0060] P tightness (bar) - 60 de minutes, at the actual test pressures of the installations, at the actual working pressures with working fluid
[0061] It is checked and recorded in the test report, the actual working pressures and temperatures on the pipeline route at the outlet of the containers, on the return route and intermediate pressures and intermediate temperatures with recording in the test report, monitoring if possible and if the installation is with data monitoring and recording, with the setting of actual working parameters on AMCs - measuring and control devices, pressure transducers. 12.2. - continuation
[0062] It is verified that the parameters - pressures, temperatures are within the limits allowed by the project and the technical book for the construction of containers and pipes, and a Technical Report for the assessment of the technical condition of IMSPs - mechanical installations under pressure - pressure vessels and pipes for fluids under pressure will be issued, with chapter of conclusions approved by the technical expert RADTE - certified by ISCIR and authorized by ISCIR through Authorization issued by ISCIR - for examinations, checks, technical investigations in use for pressure vessels and pressure pipes for fluids.
[0063] In the conclusions chapter will be recorded the technical characteristics and technical parameters for which the IMSP can be authorized (pressure vessels and pipelines for pressurized fluids) upon due technical verification according to the technical characteristics guaranteed by the manufacturer, and in the case of containers and pipelines under pressure with technical expertise and with the technical characteristics admitted and accepted by ISCIR as a result of the technical expertise, the operation authorization with the characteristics admitted and accepted by the technical expertise and the conclusion chapter - with the technical characteristics recorded as a result of the verification and testing procedure.
[0064] Concrete examples of the realization of this invention are: Procedure of checks and tests at: a) The nitrogen containers that supply the accelerator tank of 127 m3, Tmax14 bar, Pworking 11.5 bar from the FIN Research and Development Institute, Horia Hulubei Institute of Nuclear Physics and Engineering - Bucharest.
[0065] Nitrogen container 36 m3and nitrogen container 50 m3with pressures 6 ^ 18 bar and nitrogen compressor group - CNC, RT - ISCIR accepted checks. b) Containers with CO;, from complex installations with CO; in physical state - liquid and gaseous from logistics warehouses with CO; installations - dozens of installations - checks and samples accepted CNCIR - ISCIR.
[0066] 12.4 Drawings
[0067] In the following, I present in Figure 1 a representative drawing of a complex nitrogen installation in the field of a scientific research nitrogen technological line, which includes 36 m3and 50 m3nitrogen containers that supply nitrogen to the 127 m3 accelerator tank, pipes for nitrogen fluids, a nitrogen compressor group with the related automation and monitoring installation.
[0068] The R1 containers of 50 m3at 18 bar and R2 of 36 m3at 16 bar supply:
[0069] - directly in the case of the 50 m3container at 18 bar up and R2 of 36 m3to a pressure of 14 bar, the accelerator tank container and below this pressure the supply is made via nitrogen compressors.
[0070] Via nitrogen compressors in the case of the 36 m3container with P = 6 bar
[0071] The checks and tests for periodic control at the CP (RI + IP) due date (internal inspection and pressure test) are performed with the nitrogen supply system of the accelerator tank at a working pressure of 11.2 + 11.5 bar with nitrogen working fluid, without the need to remove the three containers from the system, isolate and empty them to perform the tests with air + nitrogen fluid.
[0072] The containers will be visually inspected VT 100%, checking the base material and welds quality class B, according to SR EN 5817 and SR EN 6520 with issuing a VT examination report according to applicable EN. It is examined non-destructively by the method - specialty
[0073] UTgbase material on the corrugation 500 x 500 mm
[0074] UTS- ultrasonic the welding for g > 4 mm- cap la cap 100%;
[0075] MT - welds in proportion de 100%
[0076] PT - alternative for welding; tests and trials are carried out at Piucru
[0077] A technical report is issued for each container with an assessment of the technical condition and a conclusions chapter with the parameters and technical characteristics allowed for periodic inspection authorization.
[0078] The advantage of this procedure - procedure - method of checks and tests that constitute the object of the invention is that the installation of which the containers and pipes are part remain in working condition, it does not require their emptying, the checks and tests are done with the working fluid at the working pressure with authorization to operate at the technical characteristics guaranteed by the manufacturer.
Claims
12. 3 ClaimsRelated to the patent application with the title: Procedure - practice - method of checks, sample containers and pipes with oxygen, nitrogen, argon, CCh, H2, medical air and industrial airTechnical characteristics of the invention:P > 0,5 bar; V < 350 m3and other capacitiesV max 550 m35 Pmax > 1000 barPiucru 0,2 MPa + 3 MPa and other pressuresDNmax 2500 mmTmin / max- 196°C / +20 + 65°C and other temperaturesFluids in a physical state of aggregation gases under pressure O2, N2, Ar, CO2, H2, Medical air, Industrial air- Fluids in a physical state of aggregation, liquefied gases O2, N2, Ar, CO2 Fluids group 1 and fluids group 2(57) The invention with the title of this application is characterized by the fact that::- checks and tests on containers and pipes in the technological installation / Equipment at the periodic inspection due date (Internal inspection + IP pressure test) in order to extend the authorization, operation are performed with the working fluid at the working pressure, without dismantling, emptying, isolating these pressure equipment- at cryogenic liquid tanks the vacuum degree is checked according to the requirements of the project- non-destructive tests are performed based on specific documentation - instructions that are drawn up based on the procedure, practice, verification method, the technical condition of these pressure equipment is assessed and a technical report is issued for each pressure equipment, container and pipe with an assessment of the technical condition and a chapter of conclusions with the parameters at which they can operate safely and at which the operation authorization can be extended.1 . Exclusive right to exploit, use, during the validity period of this invention patent2. Right to prohibit third parties from using this procedure - practice - method from thedate of registration of the application for invention patent at OSIM.
3. The consent of the inventor as the owner shall be granted only in written form by concluding a contract with the third party for each separate use.
4. I request protection of the invention according to the legislation in force, for the duration of the validity of the invention - the patent.
5. The rights and exclusivity are requested from the date of registration with OSIM for the entire duration of the validity of the invention - the patent.