Method for developing and ventilating deep ramp
By placing ice blocks in the connecting tunnels and temporary ventilation shafts constructed in deep inclined tunnels, and using local fans for forced ventilation, the problem of poor ventilation in deep inclined tunnels was solved, fresh air flow was introduced and the temperature was reduced, thereby improving the quality and safety of the working environment.
Patent Information
- Application Number
- PCT/CN2026/075136
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2025-05-10
- Filing Date
- 2026-01-27
- Publication Date
- 2026-11-19
AI Technical Summary
In the development of deep slopes, the lack of a ventilation system leads to the circulation of polluted air by local fans, resulting in poor air quality and high ambient temperature at the working face, making it difficult to improve the ventilation environment.
Along the slope, the intake shaft connecting tunnel was constructed on the lower level, and local fans were used for forced ventilation. Ice blocks were placed in the temporary ventilation shaft to cool it down, gradually improving the ventilation environment.
By introducing fresh airflow and cooling measures, the ventilation environment of the deep ramp development work face was improved, which increased work efficiency and reduced occupational hazards.
Smart Images

Figure CN2026075136_19112026_PF_FP_ABST
Abstract
Description
A method for ventilation in deep sloping tunnel development Technical Field
[0001] This invention belongs to the field of mining technology and relates to a method for improving the ventilation environment of deep ramp development faces. This method is mainly applicable to the development of deep underground ramps. The deep ramps refer to ramps buried at depths exceeding 800m. Background Technology
[0002] As a current technology, in the development of deep inclined ramps, since a ventilation system has not yet been established, forced ventilation can only be achieved using local fans. Because this method cannot introduce fresh airflow, the ventilation by local fans is a recirculation of stale air, resulting in poor air quality and high ambient temperature at the working face, making it difficult to meet the requirements for improving the ventilation environment at the working face. Technical issues
[0003] The technical problem to be solved by the present invention is to provide a ventilation method for deep ramp development, which further improves the ventilation environment of the deep ramp development working face by introducing fresh air flow. Technical solutions
[0004] The technical solution of the present invention is as follows:
[0005] A method for ventilation during the development of deep inclined ramps involves the following steps: When the inclined ramp is developed to a certain depth, an intake shaft connecting tunnel is constructed on the lower side of the ramp. After the upper section of the intake shaft is connected to this connecting tunnel, a sealed brick wall is constructed in the connecting tunnel, and forced ventilation is achieved using local fans. When the inclined ramp is developed further down a certain distance, a temporary ventilation shaft is constructed in the connecting tunnel near the working face. A sealed brick wall is constructed, and ice is placed in the temporary ventilation shaft to cool the fresh air transmitted from the upper part. Forced ventilation is then achieved using local fans. When the inclined ramp is developed to a certain depth again, the intake shaft connecting tunnel and the upper section intake shaft are constructed repeatedly. After they are connected, all ventilation facilities and sealed brick walls are removed from the upper part. A sealed brick wall is then constructed in the connecting tunnel, and forced ventilation is achieved using local fans.
[0006] The aforementioned deep ramp development and ventilation method includes the following steps:
[0007] 1) Continue to extend the existing ramps in the upper part of the roadway to the deep part; the construction of the intake pipe cable shaft connecting roadway and the intake pipe cable shaft has been completed in the corresponding section roadway below the existing ramps; in the intake pipe cable shaft connecting roadway, the first drilling chamber is constructed vertically to the intake pipe cable shaft connecting roadway.
[0008] 2) Construct an intake shaft connecting tunnel on the lower part of the deep inclined ramp sidewall; construct a second drilling chamber perpendicular to the intake shaft connecting tunnel at a position 3m to 5m inward from the opening of the intake shaft connecting tunnel; construct a reverse intake shaft and intake shaft connecting tunnel in the first drilling chamber using a reverse drilling rig; construct a sealing brick wall at the position beyond the opening of the second drilling chamber, and install the local fan inside the sealing brick wall; connect the ventilation duct to the air outlet of the local fan outside the sealing brick wall.
[0009] 3) For every section of the deep ramp construction, a connecting tunnel is constructed perpendicular to the deep ramp. A temporary ventilation shaft connected to the ventilation duct is set up in one of the connecting tunnels, and a sealed brick wall is constructed at the entrance of the temporary ventilation shaft. A local fan is installed in the sealed brick wall, and the outlet of the local fan is connected to the ventilation duct. Ice blocks are placed on the bottom plate of the temporary ventilation shaft.
[0010] 4) Construct a connecting tunnel for the intake shaft on the lower part of the deep slope sidewall, and construct a third drilling chamber perpendicular to the intake shaft connecting tunnel at a position 3m to 5m inward from the opening of the intake shaft connecting tunnel; construct a reverse intake shaft in the second drilling chamber using a reverse drilling rig to connect it with the intake shaft connecting tunnel; construct a sealing brick wall at a position beyond the opening of the third drilling chamber inward from the opening of the intake shaft connecting tunnel, and install the local fan in the sealing brick wall; construct a sealing brick wall at the opening of the upper intake shaft connecting tunnel.
[0011] Preferably, in step 2), the inverted air intake shaft is a vertical shaft.
[0012] Preferably, in step 3), the air supply capacity of the local fan in the temporary ventilation shaft is less than that of the upper local fan.
[0013] Preferably, in step 3), an air vent is installed in the enclosed brick wall to allow personnel to enter and exit when adding ice.
[0014] Preferably, in step 4), when constructing the sealing brick wall at the opening of the upper intake shaft connecting tunnel, the sealing brick wall encloses the second drilling rig chamber inside.
[0015] Preferably, in step 4), before installing the local fan and the enclosed brick wall in the connecting tunnel of the intake shaft, the local fan, air duct and enclosed brick wall installed in the upper intake shaft connecting tunnel are removed, and the local fan, air duct, ice block and enclosed brick wall installed in the temporary ventilation tunnel are removed. Beneficial effects
[0016] The positive effects of this invention are as follows:
[0017] First, the fresh airflow from above is transmitted to the deep ramp working face through the inverted air intake shaft and local fans, improving the ventilation environment of the working face. This invention, by constructing an inverted air intake shaft and utilizing local fans, can transmit fresh airflow from above to the deep ramp working face, improving the air quality at the working face and making it easier to cool the working environment, thus achieving the goal of improving the ventilation environment of the working face.
[0018] Secondly, the use of temporary ventilation shaft cooling technology can further reduce the temperature of fresh airflow and improve the ventilation environment of the working face. This invention places ice blocks inside the temporary ventilation shaft, which can further reduce the temperature of the fresh airflow transmitted from the top to the temporary ventilation shaft. Then, local fans are used to transport the cooled fresh airflow to the deep slope development working face, further improving the ventilation environment of the working face.
[0019] Third, the improved ventilation environment leads to higher work efficiency and reduces occupational hazards for workers. Construction using the ventilation method of this invention improves the ventilation environment of the ramp excavation face, effectively increasing tunneling efficiency and reducing occupational hazards to workers. Attached Figure Description
[0020] Figure 1 is a plan view of the deep ramp before construction according to an embodiment of the present invention;
[0021] Figure 2 is a plan view of the construction process shown in Figure 1;
[0022] Figure 3 is a longitudinal projection of Figure 2;
[0023] Figure 4 is a cross-sectional view of Figure 2, section I-I;
[0024] Figure 5 is a cross-sectional view of section II-II in Figure 2;
[0025] In the diagram: 1—Constructed ramp; 2—Sectional tunnel; 3—Connecting tunnel to intake pipe cable shaft; 4—Intake pipe cable shaft; 5—Deep ramp; 6—Connecting tunnel to ramp; 7—Drilling rig chamber; 8—Reversed intake shaft; 9—Connecting tunnel to intake shaft; 10—Local fan; 11—Enclosed brick wall; 12—Ventilation duct; 13—Temporary ventilation shaft; 14—Ice block; 15—Air door. Embodiments of the present invention
[0026] The present invention will be further described below with reference to the accompanying drawings and specific embodiments.
[0027] Referring to Figures 1, 2, 3, 4, and 5, this invention relates to an embodiment of a ventilation method for developing deep ramps, which includes the following steps:
[0028] Step 1: Continuing from the existing upper ramp 1, further extend the deeper ramp 5 downwards.
[0029] Within the lowermost section of the constructed ramp 1, the construction of the connecting tunnel 3 and the air intake cable shaft 4 has been completed (i.e., in the early stages of production, the construction of the lowermost section of the ramp 1 was completed using the constructed ramp 1, and the construction of the connecting tunnel 3 and the air intake cable shaft 4 has been completed within the connecting tunnel 2). In the connecting tunnel 3, the first drilling chamber 7 is constructed vertically.
[0030] Step one is completed, forming a channel for the downward transmission of fresh air. After the fresh air is introduced through the intake pipe cable well 4, it can be transmitted to the deeper parts in sequence through the intake pipe cable well connecting roadway 3 and the first drilling rig chamber 7, supplying air for the subsequent development of the deep inclined roadway working face.
[0031] Step 2: When the deep ramp 5 is excavated to a certain depth, construct the intake shaft connecting tunnel 9 on the lower side of the deep ramp 5 to transmit fresh air downwards. At a point 3m to 5m inwards from the opening of the intake shaft connecting tunnel 9, construct the second drilling chamber 7 perpendicular to the intake shaft connecting tunnel 9. Inside the first drilling chamber 7, use a raise boring machine to construct the reverse intake shaft 8, connecting it to the intake shaft connecting tunnel 9. At this point, the intake end of the reverse intake shaft 8 is connected to the intake cable shaft connecting tunnel 3 through the first drilling chamber 7, and the outlet end is connected to the intake shaft connecting tunnel 9.
[0032] Construct a sealed brick wall 11 3 meters inward from the opening of the intake shaft connecting tunnel 9, beyond the opening of the second drilling chamber 7 within this tunnel. Install the local ventilation fan 10 within the sealed brick wall 11 (Note: The air inlet of the local ventilation fan 10 is initially connected to the intake shaft connecting tunnel 9, and the innermost part of the intake shaft connecting tunnel 9 is the reverse intake shaft 8). Outside the sealed brick wall 11, connect the ventilation duct 12 to the air outlet of the local ventilation fan 10. Thus, the air inlet of the local ventilation fan 10 within the sealed brick wall 11 is connected to the intake shaft connecting tunnel 9, and the air outlet is connected to the ventilation duct 12. The local ventilation fan 10 provides forced ventilation through the ventilation duct 12, achieving the purpose of downward delivery of fresh airflow.
[0033] After the completion of step two, the following functions were achieved: Fresh air flow is introduced into the intake cable shaft 4. This fresh air flow flows sequentially through the intake cable shaft connecting tunnel 3, the first drilling rig chamber 7, the reverse intake shaft 8, the intake shaft connecting tunnel 9, and the local fan 10 before entering the ventilation duct 12. The fresh air flow is then transported downwards through the ventilation duct 12. Initially, the transported fresh air flow is supplied to the deep inclined ramp 5 working face, and later it is used to supply air to the subsequent temporary ventilation duct 13, which then continues to supply air to the working face below.
[0034] Step 3: During the downward development of the deep ramp 5, approximately every 150m of construction, a 10m long connecting tunnel 6 is constructed perpendicular to the deep ramp 5 (Note: After the deep ramp 5 is completed, the intermediate or segmented tunnels 2 are constructed from the connecting tunnel 6. Before the deep ramp 5 is completed, the intermediate or segmented tunnels 2 are generally not constructed, or only a few are constructed according to production needs). As the deep ramp 5 continues to descend a certain distance, to reduce the temperature of the fresh airflow in the ventilation duct 12 of the local fan 10, a temporary ventilation shaft 13 is installed in one of the connecting tunnels 6 already constructed near the working face of the deep ramp 5. The temporary ventilation shaft 13 is 6m long, and a closed brick wall 11 is constructed at the entrance of the temporary ventilation shaft 13. The space inside the temporary ventilation shaft 13 is connected to the ventilation duct 12 described in Step 2. A local ventilation fan 10 is installed in the enclosed brick wall 11. The air inlet of the local ventilation fan 10 is connected to a temporary ventilation shaft 13, and the air outlet is connected to a ventilation duct 12 for downward airflow. A certain number of ice blocks 14 are placed on the bottom plate of the temporary ventilation shaft 13. Using the temporary ventilation shaft 13, forced ventilation is provided downwards through the local ventilation fan 10 connected to the ventilation duct 12.
[0035] Explanation: Fresh air from the intake shaft connecting tunnel 9 enters the ventilation duct 12 through the local fan 10, and is then delivered downwards through the ventilation duct 12 to the working face of the deep ramp 5. When the working face of the deep ramp 5 is close to the local fan 10, the temperature of the fresh air is relatively low, which can meet the ventilation needs of the working face. As the deep ramp 5 extends, the working face of the deep ramp 5 is farther from the local fan 10. Due to the influence of the surrounding high temperature environment, the temperature of the fresh air reaching the working face is relatively high, making it difficult to meet the ventilation needs of the working face. To solve this problem, ventilation is modified in a ramp connecting tunnel 6 that has been developed in the deep ramp 5, which is transformed into a temporary ventilation chamber 13. Ice blocks 14 are placed inside to cool the fresh air transmitted from above in the temporary ventilation chamber 13, and then the local fan 10 is used to compress the air from this modified temporary ventilation chamber 13.
[0036] After the completion of step three, the following functions were achieved: fresh air flow is forced into the ventilation duct 12 by the local fan 10 installed in the closed brick wall 11 of the connecting roadway 9 of the intake shaft, and then transported downward to the temporary ventilation chamber 13 through the ventilation duct 12. After being cooled by ice blocks 14, it is then forced into the ventilation duct 12 by the local fan 10 installed in the closed brick wall 11 at the entrance of the temporary ventilation chamber 13, and continues to transport fresh air flow downward to the tunneling face through the ventilation duct 12.
[0037] Considering air leakage in the ventilation duct 12, the air supply capacity of the local fan 10 in the temporary ventilation duct 13 is less than that of the upper local fan 10.
[0038] In addition, an air vent 15 is installed in the enclosed brick wall 11 for personnel to enter and exit, so that ice blocks 14 can be added as needed to meet the airflow cooling requirements.
[0039] Step 4: When the deep ramp 5 is further excavated to a certain depth, an intake shaft connecting tunnel 9 is constructed on the lower side of the deep ramp 5. 3m to 5m inward from the opening of this intake shaft connecting tunnel 9, a third drilling chamber 7 is constructed perpendicular to it. In the second drilling chamber 7 of the upper intake shaft connecting tunnel 9, a reverse-segment intake shaft 8 is constructed using a raise boring machine to connect it to the intake shaft connecting tunnel 9.
[0040] After the tunnel is completed, the local fan 10, ventilation duct 12, and sealing brick wall 11 installed in the upper intake shaft connecting tunnel 9 are removed. The local fan 10, ventilation duct 12, ice block 14, and sealing brick wall 11 installed in the temporary ventilation tunnel 13 are also removed. The sealing brick wall 11 is reconstructed near the opening of the upper intake shaft connecting tunnel 9 to ensure that the sealing brick wall 11 encloses the upper second drilling chamber 7. The sealing brick wall 11 is constructed 3m inward from the opening of the intake shaft connecting tunnel 9, beyond the opening of the third drilling chamber 7 in this tunnel, and the local fan 10 is installed in the sealing brick wall. The local fan 10 is connected to the ventilation duct 12 for forced downward ventilation.
[0041] After the completion of step four, the following functions were achieved: Fresh air flow is introduced through the intake pipe cable shaft 4. This fresh air flow flows sequentially through the intake pipe cable shaft connecting tunnel 3, the first drilling rig chamber 7, the upper reverse section intake shaft 8, the upper intake shaft connecting tunnel 9, the second drilling rig chamber 7, the reverse section intake shaft 8 in the current intake shaft connecting tunnel 9, the current intake shaft connecting tunnel 9, and the local fan 10 installed in the closed brick wall 11 of the current intake shaft connecting tunnel 9. After being forced in, it enters the ventilation duct 12 and is transported downward to the tunneling face through the ventilation duct 12.
[0042] As the deep ramp 5 continues to be developed downwards, the temporary ventilation shaft 13 is modified, the intake shaft connecting tunnel 9, the drilling rig chamber 7 and the reverse intake shaft 8 are constructed in a cyclical manner according to steps three and four above, and the sealing brick wall 11 is constructed. Local fans are installed for forced ventilation until the deep ramp 5 is developed.
[0043] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the scope of the present invention. Various modifications and improvements made by those skilled in the art to the technical solutions of the present invention without departing from the spirit of the present invention should fall within the protection scope defined by the claims of the present invention.
Claims
1. A method of developing an airway on a deep slope, characterized by: When the ramp is excavated to a certain depth, an intake shaft connecting tunnel is constructed on the lower side of the ramp. After the upper section intake shaft is connected to this connecting tunnel, a sealed brick wall is constructed in the connecting tunnel, and forced ventilation is carried out using local fans. When the ramp is excavated to a further depth, a temporary ventilation shaft is constructed in the ramp connecting tunnel near the working face. A sealed brick wall is constructed and ice is placed in the temporary ventilation shaft to cool the fresh air flow transmitted from the upper part, and forced ventilation is carried out using local fans. When the ramp is excavated to a certain depth again, the intake shaft connecting tunnel and the upper section intake shaft are constructed again. After they are connected, all ventilation facilities and sealed brick walls are removed from the upper part, and a sealed brick wall is constructed in the connecting tunnel, and forced ventilation is carried out using local fans.
2. The deep slope development ventilation method of claim 1, wherein Includes the following steps: 1) Continue to extend the existing ramps in the upper part of the roadway to the deep part; the construction of the intake pipe cable shaft connecting roadway and the intake pipe cable shaft has been completed in the corresponding section roadway below the existing ramps; in the intake pipe cable shaft connecting roadway, the first drilling chamber is constructed vertically to the intake pipe cable shaft connecting roadway. 2) Construct an intake shaft connecting tunnel on the lower part of the deep inclined ramp sidewall; construct a second drilling chamber perpendicular to the intake shaft connecting tunnel at a position 3m to 5m inward from the opening of the intake shaft connecting tunnel; construct a reverse intake shaft and intake shaft connecting tunnel in the first drilling chamber using a reverse drilling rig; construct a sealing brick wall at the position beyond the opening of the second drilling chamber, and install the local fan inside the sealing brick wall; connect the ventilation duct to the air outlet of the local fan outside the sealing brick wall. 3) For every section of the deep ramp construction, a connecting tunnel is constructed perpendicular to the deep ramp. A temporary ventilation shaft connected to the ventilation duct is set up in one of the connecting tunnels, and a sealed brick wall is constructed at the entrance of the temporary ventilation shaft. A local fan is installed in the sealed brick wall, and the outlet of the local fan is connected to the ventilation duct. Ice blocks are placed on the bottom plate of the temporary ventilation shaft. 4) Construct a connecting tunnel for the intake shaft on the lower part of the deep slope sidewall, and construct a third drilling chamber perpendicular to the intake shaft connecting tunnel at a position 3m to 5m inward from the opening of the intake shaft connecting tunnel; construct a reverse intake shaft in the second drilling chamber using a reverse drilling rig to connect it with the intake shaft connecting tunnel; construct a sealing brick wall at a position beyond the opening of the third drilling chamber inward from the opening of the intake shaft connecting tunnel, and install the local fan in the sealing brick wall; construct a sealing brick wall at the opening of the upper intake shaft connecting tunnel.
3. The deep slope development ventilation method of claim 2, wherein: In step 2), the inverted air intake shaft is a vertical shaft.
4. The deep slope development ventilation method of claim 2, wherein: In step 3), the air supply capacity of the local fans in the temporary ventilation shaft is less than that of the local fans at the top.
5. The deep slope development ventilation method of claim 2, wherein: In step 3), an air vent is installed in the enclosed brick wall to allow personnel to enter and exit when adding ice.
6. The deep slope development ventilation method of claim 2, wherein: In step 4), when constructing the sealing brick wall at the opening of the upper intake shaft connecting tunnel, the sealing brick wall will enclose the second drilling rig chamber inside.
7. The deep slope development ventilation method of claim 2, wherein: In step 4), before installing the local fan and enclosed brick wall in the connecting tunnel of this intake shaft, the local fan, air duct and enclosed brick wall installed in the upper intake shaft connecting tunnel are removed, and the local fan, air duct, ice block and enclosed brick wall installed in the temporary ventilation tunnel are removed.