Communication method and apparatus
By configuring paging resources in the NTN system and allocating paging opportunities to downlink time domain resources in different time domain units, the problems of low paging capacity and conflicts are solved, thereby improving paging capacity and ensuring normal system operation.
Patent Information
- Application Number
- PCT/CN2026/096370
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2025-05-16
- Filing Date
- 2026-05-12
- Publication Date
- 2026-11-19
AI Technical Summary
In the existing non-terrestrial network (NTN) paging mechanism, the paging timing may occur during the guard interval or uplink transmission period in the TDD frame structure, resulting in reduced paging capacity and easy paging timing conflicts, making it impossible to perform paging normally.
By configuring paging resources, the first paging opportunity and the second paging opportunity occupy downlink time domain resources in different time domain units, ensuring that the paging opportunity corresponds to different paging opportunities in different time domain units, avoiding conflicts and improving paging capacity.
It effectively improves paging capacity, avoids paging timing conflicts, and ensures that the system can perform paging normally.
Smart Images

Figure CN2026096370_19112026_PF_FP_ABST
Abstract
Description
Communication methods and devices
[0001] This application claims priority to Chinese Patent Application No. 202510642070.5, filed on May 16, 2025, entitled "Communication Method and Apparatus", the entire contents of which are incorporated herein by reference. Technical Field
[0002] This application relates to the field of communications, and more particularly to a communication method and apparatus. Background Technology
[0003] Non-terrestrial networks (NTNs) provide network connectivity services to terminals on the ground via satellites or high-altitude platform systems at different orbital altitudes. Internet of Things (IoT) NTNs leverage this fusion of satellite communication networks and terrestrial cellular networks to connect multiple dimensions of space, air, land, and sea, unaffected by terrain limitations, providing communication support for IoT devices and serving as an important supplement to terrestrial cellular communication technology. To adapt to the long propagation delay characteristics of IoT-NTNs, a 90ms time division duplex (TDD) frame structure is introduced. However, this structure presents new challenges to traditional paging mechanisms: the original paging timing may fall within the guard period (GP) or uplink (UL) transmission period. Paging timings during GP or UL transmission periods cannot be used for paging. To improve paging capacity, it is considered to postpone the paging opportunity in the current TDD frame to the subsequent downlink (DL) transmission period. However, if multiple paging opportunities in the same TDD frame are postponed arbitrarily, multiple paging opportunities may occur on the same downlink transmission resource, resulting in paging opportunity conflicts and causing the system to be unable to perform paging normally.
[0004] Therefore, there is an urgent need for an effective paging scheme that can increase paging capacity while avoiding paging timing conflicts. Summary of the Invention
[0005] This application provides a communication method and apparatus that improves paging capacity while avoiding paging timing conflicts.
[0006] Firstly, a communication method is provided, which can be applied to a terminal device, or the terminal device can be replaced by components applicable to the terminal device (such as chips, chip systems, processors, etc.), or it can also be a logic module or software capable of realizing all or part of the functions of the terminal device, etc. This application does not limit this.
[0007] The method includes: a terminal device receiving a first message for configuring paging resources, the paging resources including a first paging timing and a second paging timing, the first paging timing occupying non-downlink time domain resources in a first time domain unit, the second paging timing occupying non-downlink time domain resources in the first time domain unit, or the second paging timing occupying downlink time domain resources in a second time domain unit, the second time domain unit being located after the first time domain unit in the time domain; the terminal device receiving control messages at the two paging timings of the downlink time domain resources in the second time domain unit, the control messages being used to schedule paging messages, the first paging timing and the second paging timing respectively corresponding to different paging timings in the downlink time domain resources of the second time domain unit.
[0008] In this context, a time-domain unit (such as the first time-domain unit and the second time-domain unit) can be a unit of measurement in the time domain, and is not necessarily the smallest time unit. For example, in a 90ms TDD frame structure, a time-domain unit can be a TDD frame. Downlink time-domain resources in a time-domain unit can be, for example, downlink subframes. Non-downlink time-domain resources in a time-domain unit can include uplink time-domain resources (such as downlink subframes) and / or guard intervals.
[0009] In other words, based on the configured paging resources, when the first paging opportunity occupies non-downlink time domain resources in the first time domain unit, the first paging opportunity cannot be used for paging, resulting in a reduction in paging capacity. Therefore, it is considered to map the first paging opportunity to a paging opportunity in the downlink time domain resources of the second time domain unit, and then achieve paging through the paging opportunity corresponding to the first paging opportunity in the downlink time domain resources of the second time domain unit, thereby improving paging capacity. Furthermore, based on the configured paging resources, the paging opportunity corresponding to the second paging opportunity in the downlink time domain resources of the second time domain unit should be different from the paging opportunity corresponding to the first paging opportunity in the downlink time domain resources of the second time domain unit.
[0010] In one implementation, the second paging timing can occupy non-downlink time domain resources in the first time domain unit. In this case, the second paging timing can be mapped to a paging timing in the downlink time domain resources of the second time domain unit to increase paging capacity. Meanwhile, the first paging timing and the second paging timing correspond to different paging timings in the second time domain unit. In another implementation, the second paging timing can occupy downlink time domain resources in the second time domain unit. In this case, the first paging timing can be mapped to a paging timing in the downlink time domain resources of the second time domain unit that is different from the second paging timing, or the first paging timing can be mapped to a paging timing in the downlink time domain resources of the second time domain unit, and the position of the second paging timing can be adjusted. After adjustment, the second paging timing and the first paging timing correspond to different paging timings in the downlink time domain resources of the second time domain unit.
[0011] Based on this, the paging timings located in non-downlink time domain resources in the first time domain unit (such as the first paging timing, or the first paging timing and the second paging timing) are mapped to downlink time domain resources in the second time domain unit, and the first paging timing and the second paging timing correspond to different paging timings on the downlink time domain resources of the second time domain unit, thereby avoiding paging timing conflicts and ensuring effective paging capacity.
[0012] Secondly, a communication method is provided, which can be applied to a network device, or the network device can be replaced by a component applicable to the network device (such as a chip, chip system, processor, etc.), or it can also be a logic module or software capable of realizing all or part of the functions of the network device, etc. This application does not limit this.
[0013] The method includes: a network device sending a first message for configuring paging resources, the paging resources including a first paging timing and a second paging timing, the first paging timing occupying non-downlink time domain resources in a first time domain unit, the second paging timing occupying non-downlink time domain resources in the first time domain unit, or the second paging timing occupying downlink time domain resources in a second time domain unit, the second time domain unit being located after the first time domain unit in the time domain; and sending control messages at the two paging timings in the downlink time domain resources of the second time domain unit, the control messages being used to schedule paging messages, the first paging timing and the second paging timing respectively corresponding to different paging timings in the downlink time domain resources of the second time domain unit.
[0014] The second aspect mentioned above corresponds to the technical solution in the first aspect, and the beneficial effects achieved are similar, so they will not be repeated here.
[0015] In conjunction with the first or second aspect described above, in one possible implementation, the paging timing corresponding to the first paging timing on the downlink time domain resources in the second time domain unit is associated with the position of the first paging timing in the first time domain unit.
[0016] In other words, the position of the first paging opportunity in the first time domain unit is used to determine the corresponding paging opportunity on the downlink time domain resource in the second time domain unit. For example, the position of the first paging opportunity in the first time domain unit is related to which paging opportunity of the downlink time domain resource the first paging opportunity is delayed to.
[0017] By utilizing the location information of the first paging opportunity in the first time domain unit to determine its corresponding paging opportunity on the downlink time domain resources in the second time domain unit, the allocation efficiency of paging opportunities can be improved and paging opportunity conflicts can be reduced.
[0018] In conjunction with the first or second aspect above, in one possible implementation, the paging time corresponding to the first paging time on the downlink time domain resources in the second time domain unit is associated with the position of the first paging time among M paging times in the first time domain unit, and the M paging times occupy the non-downlink time domain resources in the first time domain unit.
[0019] Among them, all M paging opportunities are located in the non-downlink time domain resources of the first time domain unit. The position of the first paging opportunity among the M paging opportunities is used to determine the paging opportunity corresponding to the first paging opportunity on the downlink time domain resources in the second time domain unit, thereby optimizing the configuration of paging opportunities, increasing paging capacity, and reducing paging opportunity conflicts.
[0020] In conjunction with the first or second aspect described above, in one possible implementation, the paging timing corresponding to the second paging timing on the downlink time domain resources in the second time domain unit is associated with the location of the second paging timing.
[0021] For example, the paging timing corresponding to the second paging timing on the downlink time domain resources in the second time domain unit can be associated with the second paging timing being in the first time domain unit or the second time domain unit. For example, when the second paging timing is in the second time domain unit, the second paging timing corresponds to a preset paging timing on the downlink time domain resources in the second time domain unit. Or, when the second paging timing is in the first time domain unit, the paging timing corresponding to the second paging timing on the downlink time domain resources in the second time domain unit is associated with the position of the second paging timing in the first time domain unit.
[0022] In other words, the location of the second paging opportunity is used to determine the corresponding paging opportunity on the downlink time domain resources in the second time domain unit. For example, the location of the second paging opportunity in the first time domain unit is related to which paging opportunity of the downlink time domain resources in the second time domain unit the second paging opportunity is delayed to. Similarly, when the second paging opportunity is in the second time domain unit, it is related to which paging opportunity of the downlink time domain resources in the second time domain unit the second paging opportunity is adjusted to.
[0023] By establishing a correlation between the location of the second paging opportunity and the corresponding paging opportunity on the downlink time domain resources within that second time domain unit, the allocation of paging resources can be made more rational. This correlation method helps to flexibly adjust the paging opportunity on the downlink time domain resources according to the actual location of the second paging opportunity, thereby improving paging efficiency and reducing paging conflicts.
[0024] In conjunction with the first or second aspect above, in one possible implementation, when the second paging opportunity occupies non-downlink time domain resources in the first time domain unit, the paging opportunity corresponding to the second paging opportunity on the downlink time domain resources in the second time domain unit is associated with the position of the second paging opportunity among M paging opportunities in the time domain unit, and the M paging opportunities occupy non-downlink time domain resources in the first time domain unit.
[0025] Among them, all M paging opportunities are located in the non-downlink time domain resources of the first time domain unit. The position of the second paging opportunity among the M paging opportunities is used to determine the paging opportunity corresponding to the first paging opportunity on the downlink time domain resources in the second time domain unit, thereby optimizing the configuration of paging opportunities, increasing paging capacity, and reducing paging opportunity conflicts.
[0026] In conjunction with the first or second aspect above, in one possible implementation, the first time domain unit includes at least two time domain sub-units, different time domain sub-units correspond to different paging opportunities on downlink time domain resources in the second time domain unit, and the first paging opportunity and the second paging opportunity belong to different time domain sub-units in the at least two time domain sub-units.
[0027] That is, by dividing the first time domain unit, the first paging opportunity and the second paging opportunity are assigned to different time domain sub-units. The paging opportunity in each time domain sub-unit corresponds to the same paging opportunity on the downlink time domain resources in the second time domain unit. It should be understood that this division method can be applied to each original, but within the same time domain unit, each time domain sub-unit includes at most one paging opportunity. Thus, through the correspondence between the time domain sub-unit and the paging opportunity on the downlink time domain resources in the second time domain unit, the paging opportunities in different time domain sub-units correspond to different paging opportunities on the downlink time domain resources in the second time domain unit, thereby avoiding paging opportunity conflicts.
[0028] In conjunction with the first or second aspect above, in one possible implementation, the first message carries a parameter indicating the density of paging opportunities, wherein at the density of paging opportunities indicated by the parameter, the amount of time domain resources occupied by the M paging opportunities in the first time domain unit is less than the amount of downlink time domain resources in the second time domain unit.
[0029] In other words, different paging opportunities in the first time domain unit can correspond to different paging opportunities on the downlink time domain resources in the second time domain unit. Since the number of time domain resources occupied by M paging opportunities is less than the number of downlink time domain resources in the second time domain unit, there is no paging opportunity conflict when the downlink time domain resources in the second time domain unit can also include the second paging opportunity.
[0030] In conjunction with the first or second aspect above, in one possible implementation, the first message carries a parameter indicating the density of paging opportunities, and the second time-domain unit includes at least two paging opportunities at the density of paging opportunities indicated by the parameter.
[0031] In other words, the parameter indicating the density of paging opportunities carried in the first message should indicate that at least one time domain unit (such as the second time domain unit) includes at least two paging opportunities. In this case, it is necessary to consider the paging opportunity conflict that may exist between the first paging opportunity and the second paging opportunity on the downlink time domain resources in the second time domain unit. Therefore, the method provided in the embodiments of this application is adopted to correspond the first paging opportunity and the second paging opportunity to different paging opportunities in the downlink time domain resources in the second time domain unit.
[0032] In conjunction with the first or second aspect described above, in one possible implementation, the parameter nB carrying the first message indicating the density of paging timing is T / 2, T / 4, or T / 8.
[0033] In other words, when nB is T / 2, T / 4, or T / 8, paging capacity is increased by adjusting or delaying the first and second paging opportunities. It should be understood that if the paging opportunity density is too low (e.g., each time domain unit includes at most one paging opportunity), there is no paging opportunity conflict. However, if the paging opportunity density is too high (e.g., the number of paging opportunities in each time domain unit exceeds the number of pagers that the downlink time domain resources in the second time domain unit can support), paging opportunity conflicts become unavoidable. Therefore, configuring a suitable paging opportunity density in the first message ensures optimized paging opportunities. Alternatively, when the paging opportunity density configured in the first message meets the above constraints, adjusting or delaying the first and second paging opportunities ensures optimized paging opportunities.
[0034] Thirdly, a communication method is provided. The execution subject of this method is similar to that of the first aspect, and will not be described again for the sake of brevity.
[0035] The method includes: a terminal device receiving a first message for configuring paging resources, the paging resources including a first paging frame in a first time domain unit; the terminal device receiving a control message at a paging timing of the first downlink time domain resource, the control message for scheduling paging messages, the paging timing of the first downlink time domain resource being associated with the position of the first paging frame in the first time domain unit, the first downlink time domain resource belonging to either a first time domain unit or a second time domain unit, the second time domain unit being located after the first time domain unit in the time domain.
[0036] In other words, based on the configured paging resources, the position of the first paging frame in the first time domain unit is associated with the paging timing on the first downlink time domain resource. Or, the position of the first paging frame in the first time domain unit is used to determine the paging timing corresponding to the first paging frame on the first downlink time domain resource, thereby ensuring that the paging timing associated with the first paging frame is located in the downlink time domain resource, thereby improving paging capacity.
[0037] Fourthly, a communication method is provided. The execution subject of this method is similar to that of the second aspect, and will not be elaborated further for the sake of brevity.
[0038] The method includes: a network device sending a first message for configuring paging resources, the paging resources including a first paging frame in a first time domain unit; the network device sending a control message at a paging timing of the first downlink time domain resource, the control message for scheduling paging messages, the paging timing of the first downlink time domain resource being associated with the position of the first paging frame in the first time domain unit, the first downlink time domain resource belonging to the first time domain unit or a second time domain unit, the second time domain unit being located after the first time domain unit in the time domain.
[0039] The fourth aspect mentioned above corresponds to the technical solution in the third aspect, and the beneficial effects achieved are similar, so they will not be repeated here.
[0040] In conjunction with the third or fourth aspect above, in one possible implementation, the first message carries a parameter indicating the density of paging opportunities, the location of the paging opportunity on the first downlink time domain resource on the first downlink time domain resource being associated with the location of the first paging frame in the first time domain unit and the parameter.
[0041] In other words, the parameters of the position of the first paging frame in the first time domain unit and the density of knowledge paging opportunities are used to determine the position of the paging opportunity corresponding to the first paging frame on the first downlink time domain resource. This improves the allocation efficiency of paging opportunities and reduces paging opportunity conflicts.
[0042] In conjunction with the third and fourth aspects above, in one possible implementation, under the paging timing density indicated by the parameter, the first time domain unit includes N paging frames, each of which belongs to a different time domain sub-unit in the first time domain unit, and each of the different time domain sub-units corresponds to a different paging timing on the first downlink time domain resource.
[0043] That is, by dividing the first time domain unit, N paging frames are divided into different time domain sub-units, and the paging frames in each time domain sub-unit correspond to the same paging timing on the downlink time domain resources. It should be understood that this division method can be applied to each time domain unit, but within the same time domain unit, each time domain sub-unit includes at most one paging frame. Thus, through the correspondence between the time domain sub-unit and the paging timing on the first downlink time domain resources, the paging frames in different time domain sub-units correspond to different paging timings on the first downlink time domain resources, thereby avoiding paging timing conflicts.
[0044] In conjunction with the third and fourth aspects above, in one possible implementation, when the starting position of the downlink time domain resources in the first time domain unit is included in the first paging frame, the first downlink time domain resources are included in the first time domain unit; or, when the starting position of the downlink time domain resources in the first time domain unit is not included in the first paging frame, the first downlink time domain resources are included in the second time domain unit.
[0045] In other words, whether the starting position of the downlink time-domain resources in the first time-domain unit is included in the first paging frame is used to determine whether the paging timing corresponding to the first paging frame is located in the first time-domain unit or the second time-domain unit. It should be understood that if the starting position of the downlink time-domain resources in the first time-domain unit is included in the first paging frame, the paging timing corresponding to the first paging frame can be located in the downlink time-domain resources of the current first time-domain unit, such as within the first paging frame. If the starting position of the downlink time-domain resources in the first time-domain unit is not included in the first paging frame, the first paging frame is located after the downlink time-domain resources, and therefore the paging resources corresponding to the first paging frame cannot be located in the downlink time-domain resources of the current first time-domain unit. Thus, the paging timing corresponding to the first paging frame is located in the downlink time-domain resources of the second time-domain unit. This ensures that the paging resources corresponding to the first paging frame are located in the downlink time-domain resources, thereby improving paging capacity.
[0046] Fifthly, this application provides a communication device, including modules or units for implementing the methods of the first aspect, second aspect, third aspect, fourth aspect, or any possible implementation. Specifically, the modules, units, or means can be implemented in software, in hardware, or in a combination of software and hardware.
[0047] In a sixth aspect, this application provides a communication device including one or more processors for executing a computer program (also referred to as code or instructions) in a memory, such that the communication device implements the methods of the first aspect, the second aspect, the third aspect, the fourth aspect, or any possible implementation.
[0048] Optionally, the device further includes a memory for storing computer programs and data. The memory is coupled to the processor, which, when executing the computer program stored in the memory, can implement the methods described in the first, second, third, fourth aspects, or any of the possible embodiments.
[0049] Optionally, the device further includes a communication interface for communicating with other devices. For example, the communication interface may be a transceiver, circuit, bus, module, or other type of communication interface.
[0050] In a seventh aspect, this application provides a chip system including at least one processor for supporting the implementation of the functions involved in the first, second, third, fourth aspects or any possible implementation described above.
[0051] In one possible design, the chip system also includes a memory for storing computer programs and data, which may be located inside or outside the processor.
[0052] The chip system can consist of chips or include chips and other discrete components.
[0053] In one possible design, the chip system also includes a power supply circuit for supplying power to the chip system.
[0054] Eighthly, this application provides a computer-readable storage medium including a computer program that, when run on a computer, causes the computer to implement the methods of the first aspect, the second aspect, the third aspect, the fourth aspect, or any possible implementation.
[0055] Ninthly, this application provides a computer program product comprising: a computer program that, when run, causes a computer to perform the methods of the first aspect, the second aspect, the third aspect, the fourth aspect, or any possible implementation.
[0056] In a tenth aspect, embodiments of this application provide a system including the aforementioned terminal device and network device.
[0057] The fifth to tenth aspects of this application correspond to the technical solutions of the first to fourth aspects of this application. The beneficial effects achieved by each aspect and the corresponding feasible implementation are similar, and will not be described again. Attached Figure Description
[0058] Figure 1 is a schematic diagram of a satellite communication system provided in an embodiment of this application;
[0059] Figure 2 is a schematic diagram of a frame structure provided in an embodiment of this application;
[0060] Figure 3 is a schematic diagram of the interaction flow of a communication method provided in an embodiment of this application;
[0061] Figure 4 is a schematic diagram of a frame structure provided in an embodiment of this application;
[0062] Figure 5 is a schematic diagram of the interaction flow of a communication method provided in an embodiment of this application;
[0063] Figure 6 is a schematic block diagram of a possible apparatus provided in an embodiment of this application;
[0064] Figure 7 is another schematic block diagram of the device provided in the embodiments of this application. Detailed Implementation
[0065] To facilitate understanding of the embodiments of this application, the following points will be explained first:
[0066] In this embodiment, the terms "first," "second," etc., distinguish between identical or similar items with essentially the same function and purpose, without limiting their order or quantity. Furthermore, the terms "first" and "second" are not necessarily different. In this embodiment, "first," "second," etc., can also distinguish between different services, messages, resources, etc., as mentioned below.
[0067] In this application embodiment, "at least one" may include one or more, and "multiple" in this application embodiment includes two or more.
[0068] The communication method provided in this application can be applied to various communication systems, such as: Long Term Evolution (LTE) systems, Advanced Long Term Evolution (LTE-A) systems, New Radio (NR) systems, evolution systems of NR systems, LTE-based access to unlicensed spectrum (LTE-U) systems, NR-based access to unlicensed spectrum (NR-U) systems, NTN systems, Wireless Local Area Networks (WLAN), Wireless Fidelity (WiFi), 5th Generation Wireless System (5G) or other communication systems, or future communication systems, etc.
[0069] In key sectors such as space communication, aeronautical communication, and maritime communication, satellites play an irreplaceable role. Satellite communication boasts advantages such as long communication distances, large coverage areas, and flexible networking, providing services to both fixed and various mobile terminals. The 3rd Generation Partnership Project (3GPP) standards organization has released 5G technology standards and is researching space-ground integrated communication technologies, primarily combining existing 5G standards with satellite communication technologies to achieve full global coverage. Research has already commenced, and studies have been conducted on the architecture of satellite-5G integration.
[0070] Figure 1 is a schematic diagram of a satellite communication system provided in an embodiment of this application. As shown in Figure 1, the ground mobile terminal communicates with the satellite through a 5G New Radio access network. The 5G base station is deployed on the satellite and connected to the ground core network through a wireless link. Simultaneously, wireless links exist between the satellites to complete signaling interaction and user data transmission between base stations. In this scenario, the network equipment involved in the technical solution of this application is the base station, and the terminal equipment is the terminal shown in the figure. The network elements in Figure 1 and their interfaces are described below:
[0071] The terminal is a mobile device that supports 5G New Radio, typically such as a mobile phone or tablet. It can access the satellite network via the air interface and initiate services such as making calls and accessing the internet.
[0072] Base stations primarily provide wireless access services, allocate wireless resources to access terminals, and provide reliable wireless transmission protocols and data encryption protocols.
[0073] The core network includes services such as user access control, mobility management, session management, user security authentication, and accounting. It consists of multiple functional units, which can be divided into control plane and data plane functional entities. The Authentication Management Function (AMF) is responsible for user access management, security authentication, and mobility management. The User Plane Function (UPF) is responsible for managing user plane data transmission, traffic statistics, and other functions.
[0074] Ground station: Responsible for forwarding signaling and service data between satellite base stations and the core network.
[0075] The new air interface is the wireless link between the terminal and the base station.
[0076] The Xn interface is the interface between 5G base stations and is mainly used for signaling interactions such as handover.
[0077] The NG interface is the interface between the 5G base station and the 5G core network. It mainly interacts with the non-access stratum (NAS) signaling of the core network, as well as the user's service data.
[0078] The terminal equipment involved in the embodiments of this application may also be referred to as user equipment (UE), access terminal, user unit, user station, mobile station, mobile station, remote station, remote terminal, mobile device, user terminal, terminal, wireless communication equipment, user agent, or user device, etc.
[0079] Terminal devices can be stations (STs) in WLANs, cellular phones, cordless phones, Session Initiation Protocol (SIP) phones, Wireless Local Loop (WLL) stations, Personal Digital Assistant (PDA) devices, handheld devices with wireless communication capabilities, computing devices or other processing devices connected to a wireless modem, in-vehicle devices, wearable devices, terminal devices in future communication systems such as NR networks, or terminal devices in future evolved Public Land Mobile Network (PLMN) networks, etc.
[0080] In the embodiments of this application, the terminal device can be deployed on land, including indoor or outdoor, handheld, wearable or vehicle-mounted; it can also be deployed on water (such as ships); and it can also be deployed in the air (such as drones, airplanes, balloons and satellites).
[0081] In the embodiments of this application, the terminal device may be a mobile phone, a tablet computer, a computer with wireless transceiver capabilities, a virtual reality (VR) terminal device, an augmented reality (AR) terminal device, a wireless terminal device in industrial control, a wireless terminal device in self-driving, a wireless terminal device in remote medical care, a wireless terminal device in a smart grid, a drone, a wireless terminal device in transportation safety, a wireless terminal device in a smart city, or a wireless terminal device in a smart home, etc.
[0082] By way of example and not limitation, in this embodiment, the terminal device can also be a wearable device. Wearable devices, also known as wearable smart devices, are a general term for devices that utilize wearable technology to intelligently design and develop everyday wearables, such as glasses, gloves, watches, clothing, and shoes. Wearable devices are portable devices that are worn directly on the body or integrated into the user's clothing or accessories. Wearable devices are not merely hardware devices, but also achieve powerful functions through software support, data interaction, and cloud interaction. Broadly speaking, wearable smart devices include those that are feature-rich, large in size, and can achieve complete or partial functions without relying on a smartphone, such as smartwatches or smart glasses, as well as those that focus on a specific type of application function and require the use of other devices such as smartphones, such as various smart bracelets and smart jewelry for vital sign monitoring.
[0083] Before describing the communication method provided in the embodiments of this application in detail, in order to better understand the method provided in the embodiments of this application, the relevant technologies involved in this application will be briefly explained first.
[0084] 1. Full-duplex mode:
[0085] Currently, communication systems often use frequency division duplex (FDD) or time-division duplex (TDD) for bidirectional information transmission. In TDD mode, uplink and downlink communication are divided into time segments. Within a TDD frame or a TDD period (hereinafter referred to as a TDD frame), part of the time is used for downlink communication and the other part is used for uplink communication.
[0086] When TDD mode is applied to IoT NTN, it can be called TDD NTN mode. The operating frequency band of this TDD NTN mode can be, for example, 1616MHz-1626.5MHz. In the TDD operating frequency band, N radio frames constitute one TDD frame. One TDD frame can include D consecutive DL subframes, U consecutive UL subframes, and GP. Referring to Figure 2, as a possible design, the duration of one TDD frame can be 90ms, meaning one TDD frame can include 9 radio frames, and one TDD frame includes 8 consecutive DL subframes (e.g., occupying 8ms), 8 consecutive UL subframes (e.g., occupying 8ms), and 2 GPs (e.g., GP occupies 50ms between DL and UL subframes and GP occupies 24ms after the UL subframe). However, it should be understood that this application does not limit the duration of the TDD frame or the number of uplink / downlink subframes.
[0087] With N=9 and D=U=8, it is feasible to detect and receive at least one of the narrowband primary synchronization signal (NPSS), narrowband secondary synchronization signal (NSSS), or master information block (MIB) in narrowband IoT (NB-IoT).
[0088] In the TDD frame structure, DL subframes and UL subframes are in different radio frames but have the same index, such as DL1&UL1, DL2&UL2, DL3&UL3, DL4&UL4.
[0089] 2. Time-domain unit:
[0090] For example, it can be one or more frames, one or more subframes, one or more slots, one or more symbols, or other defined temporal units. It's important to note that a temporal unit is a unit of measurement in the time domain, and not necessarily the smallest unit of time.
[0091] The method provided in this application embodiment will be described below using a TDD frame as an example of a time-domain unit. The UL subframe in a TDD frame can be a time-domain resource used for uplink transmission, or referred to as uplink time-domain resource; the DL subframe in a TDD frame can be a time-domain resource used for downlink transmission, or referred to as downlink time-domain resource. It should be noted that resources in a TDD frame other than the downlink time-domain resources included in the DL subframe can be referred to as non-downlink time-domain resources.
[0092] 3. Anchor carrier:
[0093] In NB-IoT systems, the specific carrier that carries critical control information and some service data is called the anchor carrier. For example, the anchor carrier can carry the aforementioned NPSS, NSSS, or MIB. Carriers other than the anchor carrier are called non-anchor carriers.
[0094] 4. Paging Configuration:
[0095] The terminal periodically wakes up in idle (RRC_IDLE) or inactive (RRC_INACTIVE) state to detect paging messages, and sleeps the rest of the time to save power. The network agrees on the paging transmission time through a discontinuous reception (DRX) period (T) (or paging period). The terminal device calculates the specific paging frame (PF) and paging occasion (PO) based on the system frame number (SFN) and subframe number.
[0096] Regular broadcasts over the network ensure that terminal devices within the coverage area can access the service. This can be specifically carried through paging control channel (PCCH) configuration fields (such as PCCH-Config). For example, PCCH-Config-NB-r13, defined in 3GPP TS36.331 V17.5.0, is the core parameter set for NB-IoT paging configuration, which includes two key parameters:
[0097] 1) defaultPagingCycle-r13:
[0098] This represents the paging period T. Its value is an enumeration type {rf128, rf256, rf512, rf1024}, which corresponds to different paging periods (e.g., rf128 means the paging period is 128 radio frames).
[0099] 2) nB-r13:
[0100] This represents the density of POPs. Its values are enumerated, including 4T, 2T, T, T / 2, T / 3, T / 8, T / 16, T / 32, T / 64, T / 128, T / 256, T512, T / 1024,... These values represent the ratio of the number of POPs to the number of radio frames within a paging cycle. For example, 2T means there are 2 POPs per radio frame, T means there is 1 POP per radio frame, T / 2 means there is one POP every two radio frames, and so on.
[0101] 5. Paging Resources:
[0102] Paging frame PF: SFN mod T = (T div N) * (UE_ID mod N)
[0103] Here, SFN is the system frame number, also known as the sequence number of the radio frame, used to identify the paging frame; the paging period T can be indicated by the paging configuration, such as the defaultPagingCycle-r13 mentioned above; N represents the number of PFs within one paging period T, where N is min(T, nB), and nB is indicated by the paging configuration, such as the configuration from PCCCH-Config-NB-r13. This formula is used to determine the radio frame position where the terminal detects the paging message. Through the modulo operation relationship between the system frame number, the paging period, and the terminal identifier (UE_ID), synchronization between the terminal and the network on the paging frame is achieved.
[0104] Paging timing PO: i s =floor(UE_ID / N mod N) s )
[0105] Among them, i s For paging timing index; N s N represents the number of POs within a PF. s The value is max(1, nB / T). This formula is used to determine the subframe index during paging. This is achieved by performing a hierarchical modulo operation on the terminal identifier, combining N and N... s The value of determines the subframe position of the PO that detects the paging message.
[0106] i s The relationship between the subframe number and the PO can be seen in Table 1 below. The narrowband physical downlink control channel (NPDCCH) is transmitted on the valid DL subframe, and paging messages are scheduled through the NPDCCH.
[0107] Table 1
[0108] Based on the above paging configuration, the configured PF and PO may be located in non-downlink time domain resources within a 90ms TDD frame structure, such as UL subframes or GP periods. Since the network cannot perform paging on non-downlink time domain resources (e.g., it cannot transmit downlink control information and therefore cannot schedule paging messages), the system cannot perform paging normally at all times, resulting in low system paging capacity. To address this low paging capacity issue, the paging timing for non-downlink time domain resources in the paging configuration is postponed to subsequent downlink time domain resources (e.g., 8 consecutive downlink subframes in the next TDD frame). However, if multiple paging timings in the same TDD frame are postponed to the same position, or if the paging timing in the current TDD frame is postponed to the same position as the paging timing in subsequent downlink time domain resources, a paging timing conflict will occur, causing the system to fail to perform paging normally.
[0109] This application proposes a paging scheme that configures paging resources based on a first message. These paging resources include a first paging opportunity and a second paging opportunity. The first and second paging opportunities correspond to two paging opportunities in the downlink time domain resources of the second time domain unit, respectively. By receiving control messages through two different paging opportunities in the downlink time domain resources, paging messages are scheduled. This ensures that there are no PO conflicts between the delayed paging opportunity and other delayed paging opportunities or other paging opportunities in the subsequent downlink time domain resources, thereby enabling the system to perform paging normally and effectively improving paging capacity.
[0110] It should be noted that this application does not limit the application scenario. For example, it is not limited to NB-IoT NTN communication systems. In any scenario where paging capacity is limited, the paging scheme provided in the embodiments of this application can be adopted.
[0111] The methods provided in the embodiments of this application will be described in detail below with reference to the accompanying drawings. The following specific embodiments can be combined with each other, and the same or similar concepts or processes may not be described again in some embodiments.
[0112] It should be understood that this application does not limit the implementing entity. Figure 3 illustrates the interaction between a terminal device and a network device as an example. The terminal device can be replaced by components applicable to terminal devices, such as chips, chip systems, processors, etc., or it can also be a logic module or software capable of implementing some or all of its functions; the network device can be replaced by components applicable to network devices, such as chips, chip systems, processors, etc., or it can also be a logic module or software capable of implementing some or all of its functions. This application does not limit this.
[0113] Figure 3 is a schematic diagram of the interaction flow of a communication method provided in an embodiment of this application. The method 200 shown in Figure 3 may include steps S210 and S220, and the various steps in method 200 are described in detail below.
[0114] S210, the network device sends the first message to the terminal device, and correspondingly, the terminal device receives the first message from the network device.
[0115] The first message is used to configure paging resources, such as configuring PF and PO. For example, the paging resources configured in the first message may include a first paging timing and a second paging timing. The first message may be called a paging configuration message, and this application does not limit its naming. Paging configuration and paging resources can be referred to in the examples above. For instance, the paging timing is associated with the parameter nB indicating the density of paging timings and the paging period T carried in the paging configuration message. When this configuration method is applied to a TDD frame structure, one or more paging timings in the configured paging resources may be located in the non-downlink time domain resources of the TDD frame structure, and another one or more paging timings may be located in the downlink time domain resources of the TDD frame structure. Furthermore, based on the different densities of the paging timings configured in the first message, a TDD frame structure may include one or more paging timings. Of course, when the density of paging timings is low, a TDD frame structure may not have any paging timings.
[0116] Taking the configuration of paging resources under a 90ms TDD frame structure as an example, each TDD frame can be summarized as a time-domain unit. This application does not limit the position of the eight consecutive downlink subframes in the TDD frame; the eight consecutive downlink subframes can occupy any eight consecutive subframes in the TDD frame. These eight consecutive subframes can be in the same radio frame or two adjacent radio frames. As an example, referring to Figure 4, the eight consecutive downlink subframes can be in the first and second radio frames of the TDD frame. For example, the eight consecutive downlink subframes include: subframes with indices #3 to #9 in the first radio frame of the TDD frame, and the subframe with index #0 in the second radio frame. Taking the example of 8 consecutive downlink subframes occupying the first and second radio frames, when the PF is located in the first radio frame, the PO in the PF is more likely to be in a downlink subframe. Based on this, it can be considered that the PF (or the PO in the PF) is located in the downlink time domain resource of the time domain unit. Alternatively, when the PO is located in any subframe #3 to #9 in the PF, it can be considered that the PO in the PF is located in the downlink time domain resource of the time domain unit. When the PF is located in the second radio frame, the PO in the PF is more likely to be in a non-downlink subframe. Based on this, it can be considered that the PF (or the PO in the PF) is located in the non-downlink time domain resource of the time domain unit. Alternatively, when the PO is located in any subframe #1 to #9 in the PF, it can be considered that the PO in the PF is located in the non-downlink time domain resource of the time domain unit. For ease of understanding, the following explanation will be based on the example that when the PF is located in the first radio frame of the TDD frame, the PO in the PF is in the downlink time domain resource, and when the PF is located in the second radio frame of the TDD frame, the PO in the PF is in the non-downlink time domain resource. Referring to Figure 4, each time domain unit may include multiple radio frames. For example, a 90ms TDD frame may include 9 radio frames. In addition to the radio frames that include the downlink subframes mentioned above and the PF, other frames may also be included. Other frames may include uplink subframes and / or guard intervals.
[0117] When nB is T / 8, one of every eight radio frames is a PF, and this PF includes a PO, as shown in Figure 4(a). PF 11 is located in the second radio frame in time domain unit 1, PF 12 is located in the first radio frame in time domain unit 2, PF 13 is located in the ninth radio frame in time domain unit 2, PF 14 is located in the eighth radio frame in time domain unit 3, and so on. When each time domain unit includes nine radio frames, and nB is T / 8, then one of every eight time domain units includes two paging frames, and one of these two paging frames is located in the downlink time domain resource. The other paging frames configured in these eight time domain units are all located in non-downlink time domain units, such as PF 11, PF 13, and PF 14 located in non-downlink time domain resources, and PF 12 located in the downlink time domain resource.
[0118] When nB is T / 4, one of every four radio frames is a PF, and the PF includes a PO. As shown in Figure 4(b), PF 21 is the second radio frame in time domain unit 1, PF 22 is the sixth radio frame in time domain unit 1, PF 23 is the first radio frame in time domain unit 2, PF 24 is the fifth radio frame in time domain unit 2, PF 25 is the ninth radio frame in time domain unit 2, PF 26 is the fourth radio frame in time domain unit 3, PF 27 is the eighth radio frame in time domain unit 3, and so on. With each time domain unit comprising 9 radio frames and nB being T / 4, then one of every 4 time domain units comprises three paging frames, one of which is located in the downlink time domain resource. The other paging frames configured in these 4 time domain units are located in non-downlink time domain units. For example, PF 21, PF 22, PF 24, PF 25, PF 26 and PF 27 are located in non-downlink time domain resources, while PF22 is located in the downlink time domain resource.
[0119] When nB is T / 2, one of every two radio frames is a PF, and this PF includes a PO. As shown in Figure 4(c), PF 31 is located in the second radio frame in time domain unit 1, PF 32 is located in the fourth radio frame in time domain unit 1, PF 33 is located in the sixth radio frame in time domain unit 1, PF 34 is located in the eighth radio frame in time domain unit 1, PF 35 is located in the first radio frame in time domain unit 2, PF 36 is located in the third radio frame in time domain unit 2, PF 37 is located in the fifth radio frame in time domain unit 2, PF 38 is located in the seventh radio frame in time domain unit 2, PF 39 is located in the ninth radio frame in time domain unit 2, and so on. With each time domain unit comprising 9 radio frames and nB being T / 2, then one of every two time domain units comprises five paging frames, one of which is located in the downlink time domain resource, while the other paging frames configured in these two time domain units are located in non-downlink time domain units. For example, PF 31 to PF 34 and PF 36 to PF 39 are located in non-downlink time domain resources, while PF 35 is located in the downlink time domain resource.
[0120] In addition, nB can be any other value besides the one shown in Figure 4, and this application does not limit this value.
[0121] For ease of understanding, the paging scheme of this application will be described below using the first paging timing and the second paging timing in the paging resources configured in the first message. The second paging timing is located after the first paging timing in the time domain, that is, the first paging timing is located before the second paging timing in the time domain; it can also be referred to as the first paging timing being earlier than the second paging time, or the second paging time being later than the first paging timing; other paging timings in the paging resources can be referred to the processing methods of the first paging timing and the second paging timing (such as delay processing).
[0122] In a first possible implementation, the first paging timing and the second paging timing can be two different timings within the same time domain unit (such as the first time domain unit). In this case, the first paging timing and the second paging timing are located in non-downlink time domain resources of that time domain unit, meaning that neither the first paging timing nor the second paging timing can be used for paging. To improve paging capacity, these two paging timings can be adjusted, such as by delaying them to subsequent downlink time domain resources, such as downlink time domain resources in the second time domain unit. Furthermore, there is no conflict between the delayed paging timings; that is, the first paging timing and the second paging timing correspond to different paging timings in the downlink time domain resources. The second time domain unit is later than the first time domain unit. For example, if the first time domain unit is the TDD frame in which the first paging timing and the second paging timing are located, the second time domain unit can be the next TDD frame. It should be noted that this application does not limit the second time domain unit to being adjacent to the first time domain unit; for example, the second time domain unit can also be separated from the first time domain unit by one or more time domain units. Unless otherwise specified and without logical conflict, the downlink time domain resources that are adjusted or postponed in the following text refer to the downlink time domain resources in the second time domain unit.
[0123] For example, the first paging timing and the second paging timing can be paging timings in PF 21 and PF 22 shown in Figure 4(b), or paging timings in PF 24 and PF 25, or paging timings in PF 26 and PF 27, respectively. Taking the first paging timing located in PF 24 in time domain unit 2 and the second paging timing located in PF 25 in time domain unit 2 as an example, the PO in PF 24 can be delayed to the fourth downlink subframe in time domain unit 3, and the PO in PF 25 can be delayed to the sixth downlink subframe in time domain unit 3.
[0124] For example, the first paging timing and the second paging timing can be any two of PF 31 to PF 34 shown in Figure 4(c), or any two of PF 36 to PF 39. Taking the first paging timing located at PF 36 in time domain unit 2 and the second paging timing located at PF 37 in time domain unit 2 as an example, the PO in PF 36 can be delayed to the second downlink subframe in time domain unit 3, and the PO in PF 37 can be delayed to the third downlink subframe in time domain unit 3.
[0125] In the second possible implementation, the first paging timing and the second paging timing are in different time domain units. For example, the first paging timing is in the first time domain unit, and the second paging timing is in the second time domain unit, which is later than the first time domain unit. In this case, the first paging timing is in the non-downlink time domain resource of the first time domain unit, and the second paging timing is in the downlink time domain resource of the second time domain unit. That is, the first paging timing cannot be used for paging. In order to improve paging capacity, the first paging timing can be adjusted, such as by delaying the first paging timing to a subsequent downlink time domain resource, and the delayed first paging timing does not conflict with other paging timings.
[0126] In the first example, the first paging timing is adjusted while the temporal position of the second paging timing remains unchanged. For example, the first paging timing can be postponed to any downlink subframe in the downlink temporal resources other than the downlink subframe occupied by the second paging timing. There is no conflict between the postponed first paging timing and the second paging timing in the downlink temporal resources. In the second example, the first paging timing is postponed to the downlink temporal resources in the second temporal unit, while the position of the second paging timing in the downlink temporal resources is adjusted so that the downlink subframe occupied by the postponed first paging timing in the downlink temporal resources is different from the downlink subframe occupied by the adjusted second paging timing in the downlink temporal resources.
[0127] For example, the first paging timing can be the PO in PF 11 shown in Figure 4(a), and the second paging timing can be the PO in PF 12 shown in Figure 4(a). In the first example above, the PO in PF 12 can be located in the 6th downlink subframe in time domain unit 2, and the PO in PF 11 can be delayed to the 4th downlink subframe in time domain unit 2 (not shown in the figure); in the second example above, the PO in PF 11 can be delayed to the 6th downlink subframe in time domain unit 2, and PF 12 can be adjusted to the 4th downlink subframe in time domain unit 2.
[0128] In the second possible implementation described above, the first paging timing can also be located at PF 21 or PF 22 as shown in Figure 4(b), and the second paging timing can be located at PF 23 as shown in Figure 4(b). For example, in the first example described above, the PO in PF 23 can be located in the 6th downlink subframe in time domain unit 2, the PO in PF 21 can be delayed to the 4th downlink subframe in time domain unit 2, and the PO in PF 22 can be delayed to the 5th downlink subframe in time domain unit 2 (this delay method is not shown in the figure). As another example, in the second example described above, the PO in PF 21 is delayed to the 4th downlink subframe in time domain unit 2, the PO in PF 22 can be delayed to the 6th downlink subframe in time domain unit 2, and the PO in PF 23 is adjusted from the 6th downlink subframe in time domain unit 2 to the 5th downlink subframe in time domain unit 2. Alternatively, the first paging timing can be located at any one of PF 31 to PF 34 shown in Figure 4(c), and the second paging timing can be located at PF 35 shown in Figure 4(c). For example, in the first example above, the PO in PF 35 can be located in the 6th downlink subframe in time domain unit 2, the PO in PF 31 can be delayed to the 2nd downlink subframe in time domain unit 2, the PO in PF 32 can be delayed to the 3rd downlink subframe in time domain unit 2, the PO in PF 33 can be delayed to the 4th downlink subframe in time domain unit 2, and the PO in PF 34 can be delayed to the 5th downlink subframe in time domain unit 2. This delay method is not shown in the figure. As another example, in the second example above, the PO in PF 31 is delayed to the 2nd downlink subframe in time domain unit 2, the PO in PF 32 can be delayed to the 3rd downlink subframe in time domain unit 2, and the PO in PF 33 can be delayed to the 4th downlink subframe in time domain unit 2. The PO in PF 34 can be delayed to the 5th downlink subframe in time domain unit 2, and the PO in PF 35 can be adjusted from the 6th downlink subframe in time domain unit 2 to the 1st downlink subframe. In the example shown in Figure 4(b) or (c), the first paging timing and the second paging timing have similar implementations to PF 11 and PF 12 in Figure 4(a).
[0129] It should be noted that in the embodiments of this application, the paging timing is adjusted or postponed to the downlink time domain resources in the second time domain unit. In other words, the paging timing adjusted or postponed to the downlink time domain resources in the second time domain unit corresponds to the paging timing.
[0130] In one possible implementation, in the example shown in Figure 4(b), to avoid conflicts between paging opportunities corresponding to multiple paging opportunities in the downlink time domain resources, different paging opportunities correspond to different opportunities in the downlink time domain resources. For example, PF 21, PF 22, and PF 23 correspond to different downlink subframes in the downlink time domain resources of time domain unit 2. Similarly, in the example shown in Figure 4(c), to avoid conflicts between paging opportunities corresponding to multiple paging opportunities in the downlink time domain resources, different paging opportunities correspond to different opportunities in the downlink time domain resources. For example, PF 31 to PF 35 correspond to different downlink subframes in the downlink time domain resources of time domain unit 2, and PF 36 to PF 39 correspond to different downlink subframes in the downlink time domain resources of time domain unit 2. However, this application does not limit whether paging opportunities other than the first paging opportunity and the second paging opportunity are postponed, or whether there are resource conflicts between the postponed paging opportunities. In other words, in the embodiments of this application, when there are multiple paging opportunities in non-downlink time domain resources, some or all of them can be postponed.
[0131] This application provides some possible examples of how to postpone or adjust the paging timing (such as the first paging timing and the second paging timing) configured in the first message to downlink time domain resources.
[0132] Example 1: The paging opportunity corresponding to the first paging opportunity in the downlink time domain resource is associated with the position of the first paging opportunity in the first time domain unit; the paging opportunity corresponding to the second paging opportunity in the downlink time domain resource is associated with the position of the second paging opportunity in the first time domain unit. For example, the paging opportunity at position 1 in the first time domain unit corresponds to subframe 1 in the downlink time domain resource, the paging opportunity at position 2 in the first time domain unit corresponds to subframe 2 in the downlink time domain resource, and so on.
[0133] In some implementations, due to limitations in downlink time domain resources, the first time domain unit can be divided into at least two time domain sub-units, with different sub-units corresponding to different paging opportunities on the downlink time domain resources. To avoid paging opportunity conflicts in the downlink time domain resources, each divided time domain sub-unit should include only one paging opportunity.
[0134] Unless otherwise specified below, the term "time domain unit" can be understood as any time domain unit configured with paging resources.
[0135] Taking nB as T / 8 as an example, to ensure that there is no conflict between the corresponding POs in the downlink time domain resources of the second time domain unit when the paging timing of the first paging timing and the second paging timing are adjusted or delayed, the POs of the 2nd to 9th radio frames in the first time domain unit can be delayed to the subframe with index 'a' in the downlink time domain resources, and the PO of the 1st radio frame in the second time domain unit can be adjusted to the subframe with index 'b' in the downlink time domain resources, or the position of the PO of the 1st radio frame in the downlink time domain resources can remain unchanged (e.g., occupying the subframe with index 'c'). As shown in Figure 4(a), the PO in PF 11 is delayed to the subframe with index 'a' in the downlink time domain resources of time domain unit 2 (e.g., the 6th downlink subframe), and the PO in PF 12 is adjusted to the subframe with index 'b' in the downlink time domain resources of time domain unit 2 (e.g., the 4th downlink subframe). In each time domain unit, the 2nd to 9th radio frames form one time domain subunit, and the 1st radio frame forms another time domain subunit.
[0136] Taking nB as T / 4 as an example, in order to ensure that there is no conflict between the corresponding POs in the downlink time domain resources of the second time domain unit when the paging timing of the first paging timing and the second paging timing are adjusted or delayed, the POs of the 2nd to 5th radio frames in the first time domain unit can be delayed to the subframe with index d in the downlink time domain resources of the second time domain unit, the POs of the 6th to 9th radio frames in the first time domain unit can be delayed to the subframe with index e in the downlink time domain resources of the second time domain unit, and the PO of the 1st radio frame in the second time domain unit can be adjusted to the subframe with index f in the downlink time domain resources, or the position of the PO of the 1st radio frame in the second time domain unit in the downlink time domain resources can remain unchanged (e.g., occupying the subframe with index g). For example, as shown in Figure 4(b), the PO in PF 21 is delayed to the subframe with index d in the downlink time domain resources of time domain unit 2 (such as the 4th downlink subframe), the PO in PF 22 is delayed to the subframe with index e in the downlink time domain resources of time domain unit 2 (such as the 6th downlink subframe), and PF 23 is adjusted to the subframe with index f in the downlink time domain resources of time domain unit 2 (such as the 5th downlink subframe); as shown in Figure 4(b), the PO in PF 24 is delayed to the subframe with index d in the downlink time domain resources of time domain unit 3 (such as the 4th downlink subframe), and the PO in PF 25 is delayed to the subframe with index e in the downlink time domain resources of time domain unit 3 (such as the 6th downlink subframe). In each time domain unit, radio frames 2 to 5 form one time domain subunit, radio frames 6 to 9 form another time domain subunit, and radio frame 1 forms yet another time domain subunit.
[0137] Taking nB as T / 2 as an example, in order to ensure that there is no conflict between the corresponding POs in the downlink time domain resources of the second time domain unit when the paging timing of the first paging timing and the second paging timing are adjusted or delayed, the POs of the 2nd and 3rd radio frames in the first time domain unit can be delayed to the subframe with index h in the downlink time domain resources of the second time domain unit, the POs of the 4th and 5th radio frames in the first time domain unit can be delayed to the subframe with index i in the downlink time domain resources of the second time domain unit, the POs of the 6th and 7th radio frames in the first time domain unit can be delayed to the subframe with index j in the downlink time domain resources of the second time domain unit, the POs of the 8th and 9th radio frames in the first time domain unit can be delayed to the subframe with index k in the downlink time domain resources of the second time domain unit, and the PO of the 1st radio frame in the first time domain unit can be delayed to the subframe with index l in the downlink time domain resources of the second time domain unit, or the position of the PO of the 1st radio frame in the downlink time domain resources can remain unchanged. For example, as shown in Figure 4(c), the PO in PF 31 is delayed to the subframe with index h in the downlink time domain resource of time domain unit 2 (such as the second downlink subframe); the PO in PF 32 is delayed to the subframe with index i in the downlink time domain resource of time domain unit 2 (such as the third downlink subframe); the PO in PF 33 is delayed to the subframe with index j in the downlink time domain resource of time domain unit 2 (such as the fourth downlink subframe); the PO in PF 34 is delayed to the subframe with index k in the downlink time domain resource of time domain unit 2 (such as the fifth downlink subframe); and the PO in PF 35 is adjusted to the subframe with index l in the downlink time domain resource of time domain unit 2 (such as the first downlink subframe). Also, as shown in Figure 4(c), the PO in PF 36 is delayed to the subframe with index h in the downlink time domain resource of time domain unit 3 (such as the second downlink subframe). In PF 37, the PO is delayed to the subframe with index i in the downlink time domain resource of time domain unit 3 (such as the 3rd downlink subframe); in PF 38, the PO is delayed to the subframe with index j in the downlink time domain resource of time domain unit 3 (such as the 4th downlink subframe); and in PF 39, the PO is delayed to the subframe with index k in the downlink time domain resource of time domain unit 3 (such as the 5th downlink subframe). In each time domain unit, the 2nd and 3rd radio frames, the 4th and 5th radio frames, the 6th and 7th radio frames, the 8th and 9th radio frames, and the 1st radio frame constitute different time domain subunits.
[0138] In this context, the letters a through l represent different subframe index values, and there is no specific order among the indices represented by the letters.
[0139] The first time domain unit and the second time domain unit are relative terms. For example, in Figure 4(a), (b), or (c), the first time domain unit can be time domain unit 1 and the second time domain unit can be time domain unit 2, or the first time domain unit can be time domain unit 2 and the second time domain unit can be time domain unit 3. If the PO in time domain unit 1 is delayed to the downlink time domain resource in time domain unit 3, the first time domain unit can be time domain unit 1 and the second time domain unit can be time domain unit 3.
[0140] Example 2: The paging opportunity corresponding to the first paging opportunity on downlink time domain resources is associated with the position of the first paging opportunity among the M paging opportunities in the first time domain unit. The M paging opportunities occupy non-downlink time domain resources in the first time domain unit. The M paging opportunities can be all or part of the configured paging resources located on non-downlink time domain resources in the first time domain unit, and the M paging opportunities include the first paging opportunity. When the second paging opportunity is located in the first time domain unit, the M paging opportunities also include the second paging opportunity. The paging opportunity corresponding to the second paging opportunity on downlink time domain resources is associated with the position of the second paging opportunity among the M paging opportunities. When the second paging opportunity is located on downlink time domain resources in the second time domain unit, the M paging opportunities precede the second paging opportunity, and the paging opportunity corresponding to the second paging opportunity on downlink time domain resources is associated with the position of the second paging opportunity.
[0141] For example, each of the M paging opportunities can sequentially correspond to a subframe of the downlink time domain resource. For instance, the first paging opportunity corresponds to the first subframe of the downlink time domain resource, the second paging opportunity corresponds to the second subframe, the third paging opportunity corresponds to the third subframe, and so on. Similarly, the first paging opportunity corresponds to the first subframe, the second paging opportunity corresponds to the third subframe, the third paging opportunity corresponds to the fifth subframe, and so on. This application does not limit the correspondence order; for example, it can be sequential correspondence, interval correspondence as exemplified above, or reverse correspondence (e.g., correspondence from the 8th subframe to the 1st subframe). When the second paging opportunity is located in the second time domain resource, and the second paging opportunity is after the M paging opportunities, the M paging opportunities and the subsequent second paging opportunity can sequentially correspond to a subframe of the downlink time domain resource.
[0142] Taking nB as T / 8 as an example, PF 11 and PF 12 shown in Figure 4(a) can be sequentially assigned to the first and second subframes in the downlink time domain resources of time domain unit 2 (for example only, not shown in the figure). Taking nB as T / 4 as an example, PF 21, PF 22 and PF 23 shown in Figure 4(b) can be sequentially assigned to the first, second and third subframes in the downlink time domain resources of time domain unit 2 (for example only, not shown in the figure). Taking nB as T / 2 as an example, PF 31 to PF 35 shown in Figure 4(c) can be sequentially assigned to the first to fifth subframes in the downlink time domain resources of time domain unit 2 (for example only, not shown in the figure).
[0143] In some embodiments, the downlink time domain resources in the second time domain unit are also used to carry some important signaling and / or data. In this case, when the first paging timing and the second paging timing are adjusted or postponed to the downlink time domain resources, they need to be adjusted or postponed to the subframes in the downlink time domain resources that do not carry important signaling and / or data. In other words, the subframes occupied by the paging timings corresponding to the first paging timing and the second paging timing in the downlink time domain resources do not carry important signaling and / or data, thereby avoiding failure of important signaling and / or data transmission. For example, eight consecutive downlink subframes include: subframes with indices 3 to 9 in the first radio frame of the TDD frame, and subframe with index 0 in the second radio frame. Among them, the subframe with index 4 carries system information block type 1 (SIB1) 1, the subframe with index 5 carries NPSS, the subframe with index 9 carries NSSS, and the subframe with index 0 carries MIB. Then, the first paging timing and the second paging timing can be adjusted or postponed to the subframes with indices 3, 6, 7, and 8 in the downlink time domain resources.
[0144] Based on Example 1 above, the paging timing at different locations in the first time domain unit (such as paging timing within different time domain sub-units) can correspond to subframes in the downlink time domain resources that do not carry important signaling and / or data. For example, when nB is T / 8, as shown in Figure 4(a), the PO corresponding to PF 11 in the downlink time domain resources of time domain unit 2 can be located in subframe #3 of the first radio frame, and the PO corresponding to PF 12 in the downlink time domain resources of time domain unit 2 can be located in subframe #6 of the first radio frame; as another example, when nB is T / 4, as shown in Figure 4(b), the PO corresponding to PF 21 in the downlink time domain resources of time domain unit 2 is located in subframe #3 of the first radio frame, the PO corresponding to PF 22 in the downlink time domain resources of time domain unit 2 is located in subframe #6 of the first radio frame, and the PO corresponding to PF 23 in the downlink time domain resources of time domain unit 2 is located in subframe #7 of the first radio frame. The correspondence between the paging timings before and after the aforementioned adjustments or postponements is not shown in Figure 4; this correspondence is merely an example and not a limiting illustration.
[0145] Based on Example 2 above, the M paging opportunities in the first time domain unit can be sequentially mapped one-to-one to subframes in the downlink time domain resources that do not carry important signaling and / or data. For example, when nB is T / 8, PF 11 and PF 12 shown in Figure 4(a) can be sequentially mapped to subframes #3 and #6 of the first radio frame of time domain unit 2; similarly, when nB is T / 4, PF 21, PF 22, and PF 23 shown in Figure 4(b) can be sequentially mapped to subframes #3, #6, and #7 of the first radio frame of time domain unit 2. The correspondence between the paging opportunities before and after the above adjustment or delay is not shown in Figure 4; this correspondence is merely an example and not a limiting illustration.
[0146] For PO densities with nB of T / 2 or higher, since some downlink time domain resources need to carry 5 non-conflicting POs after adjustment or delay, when nB is T / 2, the scheme of adjusting and / or delaying POs can be applied to non-anchor carriers, thereby avoiding the impact on the transmission of important signaling and / or data when applied to anchor carriers.
[0147] Due to the limitation of downlink time domain resource capacity in the time domain unit, the number of time domain resources occupied by the M paging opportunities located in non-downlink time domain resources in the first time domain unit should be less than the number of downlink time domain resources in the second time domain unit to avoid conflicts between paging opportunities after adjustment or delay. The number M of paging opportunities located in non-downlink time domain resources in the first time domain unit is related to the density of paging opportunities. Taking a 90ms TDD frame as an example, when nB is T, each radio frame is a PF, meaning there are 8 paging opportunities located in non-downlink time domain resources. Therefore, when the second paging opportunity is located in the downlink time domain resources of the second time domain unit, the 8 paging opportunities in the first time domain unit after delay, as well as the second paging opportunity itself, all need to be carried in the downlink time domain resources of the second time domain unit. The 8 consecutive downlink subframes of the second time domain unit cannot carry 9 different paging opportunities. Therefore, when nB is less than T, using the paging scheme provided in this application can maximize the increase in paging capacity.
[0148] It is understood that when at least one time-domain unit in the paging resources configured in the first message includes at least two paging opportunities, the paging scheme provided in this application can resolve the potential PO conflict issue after adjusting or delaying the paging opportunity. For example, if the first time-domain unit includes a first paging opportunity, and the second time-domain unit includes a second paging opportunity and another paging opportunity, then the paging scheme provided in this application can avoid conflict with the second paging opportunity after delaying the first paging opportunity. If each time-domain unit in the paging resources configured in the first message includes at most one paging opportunity, and the paging opportunity is located in a non-downlink time-domain resource of the time-domain unit, such as the first paging opportunity in the first time-domain unit, delaying the first paging opportunity to the corresponding paging opportunity in the downlink time-domain resource of the second time-domain unit does not require consideration of the PO conflict issue. Taking a 90ms TDD frame as an example, when nB is T / 16, one radio frame out of every 16 radio frames is a PF, meaning that there is at most one PF in the time domain unit. Therefore, when nB is less than T / 16, the paging scheme provided in this application can be used to avoid PO conflict. When nB is greater than or equal to T / 16, the paging timing on non-downlink time domain resources can be directly delayed without considering the PO conflict issue.
[0149] In some embodiments, the first message may carry a parameter indicating the density of paging opportunities, such as nB as described above. In one possible implementation, to avoid a PO conflict caused by the number of time domain resources occupied by the M paging opportunities in the first time domain unit being greater than or equal to the number of downlink time domain resources in the second time domain unit, the paging opportunity density configured by the network device for the terminal device is less than T; that is, the parameter nB indicating the density of paging opportunities carried in the first message is less than T. In another possible implementation, the terminal device and the network device may adopt different paging opportunity delay schemes based on different paging opportunity densities. For example, when nB is less than or equal to T / 16, the first paging opportunity in the first time domain unit is delayed to the downlink time domain resources in the second time domain unit; when nB is greater than T / 16 and less than T, the first and second paging opportunities are adjusted or delayed to the downlink time domain resources in the second time domain unit, and the first and second paging opportunities correspond to different paging opportunities in the downlink time domain resources.
[0150] S220, the network device sends a control message at two paging opportunities in the downlink time domain resources of the second time domain unit. This control message is used to schedule paging messages.
[0151] Accordingly, the terminal device receives control messages at two paging opportunities in the downlink time domain resources of the second time domain unit. The two paging opportunities in the downlink time domain resources of the second time domain unit are the paging opportunities corresponding to the first paging opportunity and the second paging opportunity, respectively.
[0152] Based on the aforementioned first message and the preset or configured paging timing adjustment or delay rules, both the network device and the terminal device can determine the paging timing on the downlink time domain resources in the second time domain unit, and then transmit control messages on the two paging timings of the downlink time domain resources in the second time domain unit, thereby scheduling paging messages to achieve paging.
[0153] In one example of a paging timing adjustment or postponement rule, the rule indicates how to postpone M paging opportunities located in non-downlink time domain resources within a first time domain unit to downlink time domain resources in a second time domain unit. If the first and second paging opportunities are located in non-downlink time domain resources within the first time domain unit, the network device and terminal device, based on the paging timing adjustment or postponement rule, can postpone the first and second paging opportunities configured in the first message to their corresponding positions (such as the corresponding downlink subframes or paging opportunities) in the downlink time domain resources of the second time domain unit. For example, the first paging opportunity is postponed to a third paging opportunity, and the second paging opportunity is postponed to a fourth paging opportunity. The third and fourth paging opportunities occupy different resources in the downlink time domain resources of the second time domain unit; that is, the third and fourth paging opportunities are different.
[0154] In another example of the paging timing adjustment or postponement rule, the rule is used to instruct M paging opportunities in the first time domain unit that are not located in the downlink time domain resources to be postponed to the downlink time domain resources of the second time domain unit, and to adjust the paging opportunities in the second time domain unit. If the second paging opportunity is located in the downlink time domain resources of the second time domain unit, the network device and the terminal device, based on the paging timing adjustment or postponement rule, can postpone the first paging opportunity configured in the first message to the third paging opportunity, and adjust the second paging opportunity configured in the first message to the fourth paging opportunity. The third and fourth paging opportunities occupy different resources in the downlink time domain resources of the second time domain unit; the second and fourth paging opportunities can be the same or different.
[0155] The rules for adjusting or delaying paging timings indicate the corresponding paging timings on downlink time domain resources in the second time domain for the M paging timings in the first time domain unit and / or the paging timings on downlink time domain resources in the second time domain unit, or in other words, they indicate this correspondence. For example, it indicates the paging timing corresponding to the first paging timing on downlink time domain resources in the second time domain unit, and the paging timing corresponding to the second paging timing on downlink time domain resources in the second time domain unit. The paging timings corresponding to the first and second paging timings on downlink time domain resources in the second time domain unit have been explained in the previous examples, see Examples 1 and 2 above, and will not be repeated for brevity.
[0156] The rules for adjusting or delaying the paging timing mentioned above can be preset, such as by agreement or by configuration of network devices.
[0157] It should be noted that the downlink time domain resources in the second time domain unit may include multiple paging opportunities, which may be determined based on the adjustment or delay rules of the paging opportunities in the example above. These multiple paging opportunities include at least the paging opportunity corresponding to the first paging opportunity on the downlink time domain resources of the second time domain unit, and the paging opportunity corresponding to the second paging opportunity on the downlink time domain resources of the second time domain unit. In addition, they may also include the paging opportunities corresponding to other paging opportunities in the first time domain unit that are not located on downlink time domain resources on the downlink time domain resources of the second time domain unit.
[0158] Therefore, in this embodiment, the network device configures paging resources to the terminal device, and the first paging opportunity in the paging resources occupies the non-downlink time domain resources in the first time domain unit, and the second paging opportunity in the paging resources occupies the non-downlink time domain resources in the first time domain unit or the downlink time domain resources in the second time domain unit. Based on the paging resources configured by the network device, the terminal device receives control messages on the downlink time domain resources in the second time domain unit, thereby scheduling paging messages to realize paging. The downlink time domain resources in the second time domain unit include the paging opportunities corresponding to the first paging opportunity and the second paging opportunity. For example, the first paging opportunity may be postponed to the downlink time domain resources of the second time domain unit, the second paging opportunity may be adjusted or postponed to the downlink time domain resources of the second time domain unit, or the position of the second paging opportunity in the downlink time domain resources may remain unchanged. Therefore, the paging timing (such as the first paging timing, or the first paging timing and the second paging timing) located in the non-downlink time domain resources in the first time domain unit is delayed, and the first paging timing and the second paging timing correspond to different paging timings on the downlink time domain resources of the second time domain unit, thereby avoiding PO conflicts and ensuring effective paging capacity.
[0159] Figure 5 is a schematic diagram of the interaction flow of a communication method provided in an embodiment of this application. The method 300 shown in Figure 5 may include steps S310 and S320, and the various steps in method 300 are described in detail below.
[0160] S310, the network device sends a first message to the terminal device, the first message being used to configure paging resources, the paging resources including a first paging frame in a first time domain unit.
[0161] The first message, also known as the paging configuration message, is not subject to naming restrictions in this application. Paging configurations and resources can be found in the examples above, and will not be repeated here for the sake of brevity.
[0162] In this embodiment, the paging resources configured in the first message may include one or more paging frames in the first time domain unit, and these one or more paging frames include the first paging frame. The position of the one or more paging frames configured in the first message in the first time domain unit is associated with one or more paging opportunities. In other words, the terminal device can determine the paging opportunity corresponding to each paging frame based on the one or more paging frames configured in the first message. Based on this, the first message can be used to configure paging frames and paging opportunities, or it can only configure paging frames. When the first message also configures paging opportunities, the configured paging opportunities may not actually be used for paging.
[0163] The following explanation uses the first paging frame in the paging resources as an example. Other paging frames in the paging resources configured in the first message can determine the associated paging timing in a similar way to the first paging frame.
[0164] The paging timing associated with the first paging frame can be located in the first downlink time domain resource. In one example, the first downlink time domain resource can belong to the first time domain unit, that is, the first paging frame and the paging timing corresponding to the first paging frame are located in the same time domain unit. In another example, the first downlink time domain resource can belong to the second time domain unit after the first time domain unit.
[0165] In one possible implementation, in order to ensure that the paging timing corresponding to the first paging frame is located in the downlink time domain unit, the first paging frame can always be assigned to the downlink time domain resource of the second time domain unit, that is, the first paging frame is assigned to the first downlink time domain resource in the second time domain unit.
[0166] In another possible implementation, the paging timing corresponding to the first paging frame can be determined to be in the first time domain unit or the second time domain unit based on the position of the first paging frame in the first time domain unit. For example, if the starting position of the downlink time domain resources in the first time domain unit is included in the first paging frame, taking a 90ms TDD frame structure as an example, subframes #3 to #9 in the first paging frame are downlink subframes. In this case, the first paging frame is considered to be located in the downlink time domain resources, and the paging timing corresponding to the first paging frame can be located in the downlink time domain resources of the first time domain unit. If it is located in the first paging frame, that is, the first downlink time domain resources are included in the first time domain unit. On the other hand, if the starting position of the downlink time domain resources in the first time domain unit is not included in the first paging frame, taking a 90ms TDD frame structure as an example, subframe #0 in the first paging frame is a downlink subframe, or the first paging frame does not include downlink subframes, in this case, the first paging frame is considered to be located in non-downlink time domain resources, and the paging timing corresponding to the first paging frame will be located in the downlink time domain resources of the second time domain unit, that is, the first downlink time domain resources are included in the second time domain unit.
[0167] For example, the paging timing position in the first downlink time domain resource can be associated with the position of the first paging frame in the first time domain unit. For instance, if the first paging frame at position 1 in the first time domain unit corresponds to subframe 1 in the first downlink time domain resource, then the paging timing corresponding to the first paging frame is located at subframe 1 in the first downlink time domain resource. Different paging frames in the first time domain unit can correspond to paging timings at different positions in the first downlink time domain resource.
[0168] Based on the above example, the paging timing corresponding to the first paging frame can be determined based on parameters n and delay. Here, n is the starting position of the time domain unit where the first downlink time domain resource is located. If the starting position of the downlink time domain resource in the first time domain unit is included in the first paging frame, then n is the starting position of that first time domain unit. Conversely, if the starting position of the downlink time domain resource in the first time domain unit is not included in the first paging frame, then n is the starting position of the second time domain unit. delay is the position of the paging timing corresponding to the first paging frame within the first downlink time domain resource, or it can be understood as the offset of the paging timing corresponding to the first paging frame relative to the starting position of its respective time domain unit.
[0169] In some implementations, the position of the paging timing corresponding to the first paging frame in the first downlink time domain resource is also related to the density of paging timings.
[0170] In some implementations, due to limitations in the first downlink time domain resources, the first time domain unit can be divided into at least two time domain sub-units. Paging frames in different time domain sub-units correspond to different paging opportunities on the downlink time domain resources. To avoid paging opportunity conflicts in the downlink time domain resources, each divided time domain sub-unit should include only one paging opportunity. That is, the N paging frames in the first time domain unit can belong to different time domain sub-units within the first time domain unit, and different time domain sub-units correspond to different paging opportunities on the first downlink time domain resources. The N paging frames can be all or part of the paging frames located in the first time domain unit from the configured paging resources, and the N paging frames include the first paging frame.
[0171] Taking nB as T / 8 as an example, as shown in Figure 4(a), PF 12 is in the first radio frame of time domain unit 2. The paging timing corresponding to PF 12 is located in the downlink time domain resource of time domain unit 2, and the paging timing corresponding to PF 12 is subframe #5 in the first radio frame of time domain unit 2. PF 13 is in the ninth radio frame of time domain unit 2. The paging timing corresponding to PF 13 is located in the downlink time domain resource of time domain unit 3, and the paging timing corresponding to PF 13 is subframe #3 in the first radio frame of time domain unit 3. Among them, the time domain subunit composed of the first radio frame corresponds to subframe #5, and the other time domain subunit composed of the second to ninth radio frames of the time domain unit corresponds to subframe #3. Subframe #5 is subframe #5 in the first radio frame of the first time domain unit, and subframe #3 is subframe #3 in the first radio frame of the second time domain unit. The above correspondence between PF and paging timing is not shown in Figure 4. This correspondence is only an example and not a limiting description.
[0172] Taking nB as T / 4 as an example, as shown in Figure 4(b), PF 23 is the first radio frame in time domain unit 2, the paging timing corresponding to PF 23 is located in the downlink time domain resource in time domain unit 2, and the paging timing corresponding to PF 23 is subframe #5 in the first radio frame in time domain unit 2; PF 24 is the fifth radio frame in time domain unit 2, the paging timing corresponding to PF 24 is located in the downlink time domain resource in time domain unit 3, and the paging timing corresponding to PF 24 is subframe #3 in the first radio frame in time domain unit 3; PF 25 is the ninth radio frame in time domain unit 2, the paging timing corresponding to PF 25 is located in the downlink time domain resource in time domain unit 3, and the paging timing corresponding to PF 25 is subframe #0 in the second radio frame in time domain unit 3. In this diagram, the first time-domain sub-unit consisting of the first radio frame corresponds to subframe #5; another time-domain sub-unit consisting of the second to fifth radio frames corresponds to subframe #3; and another time-domain sub-unit consisting of the sixth to ninth radio frames corresponds to subframe #0. Subframe #5 is subframe #5 in the first radio frame of the first time-domain unit, subframe #3 is subframe #3 in the first radio frame of the second time-domain unit, and subframe #0 is subframe #0 in the second radio frame of the second time-domain unit. The correspondence between the PF and the paging timing described above is not shown in Figure 4; this correspondence is merely an example and not a limiting illustration.
[0173] Taking nB as T / 2 as an example, as shown in Figure 4(c), PF 35 is in the first radio frame of time domain unit 2. The paging timing corresponding to PF 35 is located in the downlink time domain resource of time domain unit 2, and the paging timing corresponding to PF 35 is subframe #5 in the first radio frame of time domain unit 2; PF 36 is in the third radio frame of time domain unit 2. The paging timing corresponding to PF 36 is located in the downlink time domain resource of time domain unit 3, and the paging timing corresponding to PF 36 is subframe #3 in the first radio frame of time domain unit 3; PF 37 is in the fifth radio frame of time domain unit 2. The paging timing corresponding to PF 37 is located in the downlink time domain resource of time domain unit 3, and the paging timing corresponding to PF 37 is subframe #4 in the first radio frame of time domain unit 3; PF 38 is in the seventh radio frame of time domain unit 2. The paging timing corresponding to PF 38 is located in the downlink time domain resource of time domain unit 3, and PF The paging timing corresponding to PF 38 is subframe #0 in the second radio frame in time domain unit 3; PF 39 is in the ninth radio frame in time domain unit 2, the paging timing corresponding to PF 39 is located in the downlink time domain resource in time domain unit 3, and the paging timing corresponding to PF 39 is subframe #6 in the first radio frame in time domain unit 3. In this diagram, the time-domain sub-unit consisting of the first radio frame corresponds to subframe #5; the other time-domain sub-unit consisting of the second and third radio frames corresponds to subframe #3; the other time-domain sub-unit consisting of the fourth and fifth radio frames corresponds to subframe #4; the other time-domain sub-unit consisting of the sixth and seventh radio frames corresponds to subframe #0; and the other time-domain sub-unit consisting of the eighth and ninth radio frames corresponds to subframe #6. Subframe #5 is subframe #5 in the first radio frame of the first time-domain unit; subframe #3 is subframe #3 in the first radio frame of the second time-domain unit; subframe #4 is subframe #4 in the first radio frame of the second time-domain unit; subframe #0 is subframe #0 in the second radio frame of the second time-domain unit; and subframe #6 is subframe #6 in the first radio frame of the second time-domain unit. The above correspondence between PF and paging timing is not shown in Figure 4; this correspondence is merely an example and not a limiting illustration.
[0174] This application does not limit the specific location of the paging timing corresponding to each time domain sub-unit within the first downlink time domain unit. The location of the paging timing corresponding to the first paging frame within the first downlink time domain unit can be preset, such as by protocol agreement, or can be configured by network equipment.
[0175] For ease of understanding, the position of the paging timing corresponding to the first paging frame in the first downlink time domain resource is determined using Table 2 below.
[0176] Table 2
[0177] In Table 2, i_tdd represents the index of the position of the first paging frame in the first time domain unit. For example, when the first paging frame is radio frame #0 in the first time domain unit and nB = T / 8, the paging timing corresponding to the first paging frame is on the subframe with index 5 in the first downlink time domain resource. Similarly, when the first paging frame is radio frame #1 in the first time domain unit and nB = T / 4, the paging timing corresponding to the first paging frame is on the subframe with index 3 in the first downlink time domain resource, and so on.
[0178] The correspondence between the first paging frame and the paging timing in the first downlink time domain resource is only an example and not a limiting description. For example, the values in Table 1 above can be replaced with other values.
[0179] Optionally, in addition to the correspondence between paging frames and paging timings in the above example, the N paging frames in the first time domain unit can sequentially correspond to paging timings at different positions (e.g., different subframes) in the first downlink time domain resource. For example, the first paging frame in the N paging frames corresponds to the first subframe in the first downlink time domain resource, the second paging timing corresponds to the second subframe in the first downlink time domain resource, and so on. This application does not limit the correspondence order; for example, it can be the sequential correspondence in the aforementioned example, or it can be a reverse correspondence (e.g., a correspondence from the 8th subframe to the 1st subframe), an interval correspondence, etc. Similar to the implementation in Example 2 above, it will not be elaborated further for the sake of brevity.
[0180] S320, the network device sends a control message during the paging time of the first downlink time domain resource, and the control message is used to schedule the paging message.
[0181] Accordingly, the terminal device receives the control message during the paging time of the first downlink time domain resource.
[0182] Based on the aforementioned first message and the preset or configured correspondence rules between paging frames and paging timing, both network devices and terminal devices can determine the paging timing corresponding to the first paging frame, and then transmit control messages on the first downlink time domain resources, thereby scheduling paging messages to achieve paging.
[0183] For example, the correspondence rule between paging frames and paging timings is used to indicate how to correspond the paging frame configured in the first message to the paging timing of the first downlink time domain resource. This correspondence rule also indicates the correspondence between paging frames and paging timings. Taking the first paging frame as an example, in this correspondence rule, the paging timing on the first downlink time domain resource is associated with the position of the first paging frame in the first time domain unit, or the paging timing on the first downlink time domain resource is associated with the position of the first paging frame in the first time domain unit and the parameter indicating the paging density in the first message. The paging timing corresponding to the first paging frame in the first downlink time domain resource has been explained in the previous example and will not be repeated for brevity.
[0184] The correspondence between the paging time frame and the paging timing mentioned above can be preset, such as by protocol agreement, or can be configured by network device.
[0185] It should be noted that in the above S320, the paging timing on the first downlink time domain resource can be determined based on the correspondence rule between the paging frame and the paging timing in the example above.
[0186] Therefore, in this embodiment, the network device configures paging resources to the terminal device. Based on the paging resources configured by the network device, the terminal device receives control messages on the first downlink time domain resource, thereby scheduling paging messages to achieve paging. The paging timing in the first downlink time domain resource is determined based on the position of the first paging frame in the first time domain unit. Thus, on the one hand, it ensures that the paging timing corresponding to the first paging frame is located in the downlink time domain resource, improving paging capacity. On the other hand, when the first time domain unit includes multiple paging frames, determining the paging timing at different positions in the downlink time domain resource based on the position of each paging frame in the first time domain unit can avoid PO conflicts and further ensure paging capacity.
[0187] The method embodiment shown in Figure 5 and the method embodiment shown in Figure 3 above can implement paging independently or in combination; this application does not limit this. For example, considering processing overhead and latency, a paging scheme that matches the density of paging opportunities is selected.
[0188] In the various embodiments of this application, unless otherwise specified or in case of logical conflict, the terminology and / or descriptions between the various embodiments are consistent and can be referenced by each other. Technical features in different embodiments can be combined to form new embodiments according to their inherent logical relationships.
[0189] The methods provided in the embodiments of this application have been described in detail above with reference to several accompanying drawings. The apparatus provided in the embodiments of this application will now be described with reference to the accompanying drawings.
[0190] Figure 6 is a schematic block diagram of a possible apparatus provided in an embodiment of this application. As shown in Figure 6, one apparatus provided in this application, apparatus 400, includes a transceiver module 410 and a processing module 420.
[0191] One possible design is that the device 400 is used to implement the functions of the terminal device or network device in the method embodiment shown in FIG3 above.
[0192] For example, when the device 400 is used to implement the function of the terminal device in the method embodiment shown in FIG3 above, the transceiver module 410 can be used to receive a first message, which is used to configure paging resources. The paging resources include a first paging timing and a second paging timing. The first paging timing occupies non-downlink time domain resources in the first time domain unit, and the second paging timing occupies non-downlink time domain resources in the first time domain unit, or the second paging timing occupies downlink time domain resources in the second time domain unit. The second time domain unit is located after the first time domain unit in the time domain. The processing module 420 can be used to receive control messages through the transceiver module 410 for the two paging timings of the downlink time domain resources in the second time domain unit. The control messages are used to schedule paging messages. The first paging timing and the second paging timing correspond to different paging timings in the downlink time domain resources of the second time domain unit, respectively.
[0193] For example, when the device 400 is used to implement the function of the network device in the method embodiment shown in FIG3 above, the transceiver module 410 can be used to send a first message, which is used to configure paging resources. The paging resources include a first paging timing and a second paging timing. The first paging timing occupies the non-downlink time domain resources in the first time domain unit, and the second paging timing occupies the non-downlink time domain resources in the first time domain unit, or the second paging timing occupies the downlink time domain resources in the second time domain unit. The second time domain unit is located after the first time domain unit in the time domain. The processing module 420 can be used to send control messages through the transceiver module 410 for the two paging timings of the downlink time domain resources in the second time domain unit. The control messages are used to schedule paging messages. The first paging timing and the second paging timing correspond to different paging timings in the downlink time domain resources of the second time domain unit, respectively.
[0194] Another possible design is that the device 400 is used to implement the functions of the terminal device or network device in the method embodiment shown in FIG5 above.
[0195] For example, when the device 400 is used to implement the function of the terminal device in the method embodiment shown in FIG5 above, the transceiver module 410 can be used to receive a first message, which is used to configure paging resources, the paging resources including a first paging frame in a first time domain unit; the processing module 420 can be used to receive a control message through the transceiver module 410 when the paging opportunity of the first downlink time domain resource is available, the control message is used to schedule the paging message, the paging opportunity on the first downlink time domain resource is associated with the position of the first paging frame in the first time domain unit, the first downlink time domain resource belongs to the first time domain unit or the second time domain unit, the second time domain unit is located after the first time domain unit in the time domain.
[0196] For example, when the device 400 is used to implement the function of the network device in the method embodiment shown in FIG5 above, the transceiver module 410 can be used to send a first message, which is used to configure paging resources, the paging resources including a first paging frame in a first time domain unit; the processing module 420 can be used to send a control message through the transceiver module 410 when the paging opportunity of the first downlink time domain resource is available, the control message is used to schedule the paging message, the paging opportunity on the first downlink time domain resource is associated with the position of the first paging frame in the first time domain unit, the first downlink time domain resource belongs to the first time domain unit or a second time domain unit, the second time domain unit is located after the first time domain unit.
[0197] The device 400 can be used to implement any of the aforementioned method embodiments, and will not be described in detail for the sake of brevity.
[0198] It is understood that the division of units in the above-described device is merely a logical functional division. Each function can correspond to a functional unit, or two or more functions can be integrated into one functional unit. In actual implementation, all or some units can be integrated into a single physical entity, or they can be distributed across different physical entities. Furthermore, the aforementioned functional units can be implemented in hardware, software, or a combination of both. Whether a function is executed in hardware or software depends on the specific application and design constraints of the technical solution. Those skilled in the art can use different methods to implement the described functions for each specific application, but such implementation should not be considered beyond the scope of this application.
[0199] Figure 7 is another schematic block diagram of the device provided in an embodiment of this application. As shown in Figure 7, the device 500 includes one or more processors 510. The processor 510 may be a general-purpose processor or a special-purpose processor, etc. For example, it may be a baseband processor or a central processing unit. The baseband processor may be used to process communication protocols and communication data, and the central processing unit may be used to control the device (e.g., a vehicle or a chip), execute software programs, and process data from the software programs.
[0200] Optionally, in one design, processor 510 may include a computer program (also referred to as code or instructions) that can be executed on processor 510, causing device 500 to perform the methods performed by the terminal device or network device in the above method embodiments. In yet another possible design, device 500 includes circuitry (not shown in FIG. 7) for implementing the functions of the terminal device or network device in the above method embodiments.
[0201] For example, processor 510 may be used to execute a computer program in memory to implement the steps performed by a terminal device or network device in the method embodiment.
[0202] Optionally, the device 500 may include one or more memories 520 storing computer programs (sometimes referred to as code or instructions) that can be run on the processor 510, causing the device 500 to perform the methods performed by the terminal device or network device in the above embodiments.
[0203] Optionally, the processor 510 and / or memory 520 may also store data. The processor and memory may be configured separately or integrated together.
[0204] Optionally, the device 500 may also include a communication interface 530. The processor 510, sometimes referred to as a processing unit, controls the device (e.g., a terminal device or a network device). The communication interface 530, sometimes referred to as a transceiver unit, transceiver, transceiver circuit, or transceiver, is used to implement the transceiver function of the device; for example, the communication interface 530 can be used to receive first configuration information.
[0205] Optionally, the device 500 also includes a communication interface 530. The processor 510 and the communication interface 530 are coupled to each other. It is understood that the communication interface 530 can be a transceiver or an input / output interface.
[0206] When the device 500 is used to implement the above method embodiments, the processor 510 can be used to execute the functions of the processing unit 520, and the communication interface 530 can be used to execute the functions of the transceiver unit 510. Whether the communication interface 530 is used for sending or receiving depends on whether the device 500 is used to perform a sending or receiving action in the scheme it is executing.
[0207] When the aforementioned device 500 is a chip applied to a terminal, the chip implements the functions of the terminal in the above method embodiments. The terminal's chip receives signals from other modules (such as radio frequency modules or antennas) in the terminal, and these signals may be sent to the terminal by network devices; or, the terminal's chip sends signals to other modules (such as radio frequency modules or antennas) in the terminal, and these signals may be sent to network devices by the terminal.
[0208] When the aforementioned device 500 is a chip applied to a network device, the chip implements the functions of the network device in the above method embodiments. The chip of the network device receives signals from other modules in the network device, which may be signals sent by a terminal to the network device; or, the chip of the network device sends signals to other modules in the network device, which may be signals sent by the network device to a terminal.
[0209] It is understood that when the device 500 is a terminal device or a network device, the communication interface 530 can be a transceiver, specifically including a transmitter and a receiver, with the transmitter used to send signals and the receiver used to receive signals. When the device 500 is a chip applied to a terminal device or a network device, the communication interface 530 can be an input / output circuit, wherein the input circuit can be used for receiving and the output interface can be used for sending.
[0210] Optionally, the device 500 also includes a power supply circuit for supplying power to the device 500.
[0211] The above-described method embodiments can be applied to a processor, or implemented by a processor. A processor may be an integrated circuit chip with signal processing capabilities. During implementation, each step of the above method embodiments can be completed through integrated logic circuits in the processor's hardware or through software instructions.
[0212] The aforementioned processor can be a general-purpose processor, a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field-programmable gate array (FPGA), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, or any combination thereof. A general-purpose processor can be a microprocessor or any conventional processor.
[0213] The steps of the method disclosed in the embodiments of this application can be directly manifested as being executed by a hardware decoding processor, or executed by a combination of hardware and software modules in the decoding processor. The software modules can reside in mature storage media in the art, such as random access memory, flash memory, read-only memory, programmable read-only memory, electrically erasable programmable memory, or registers. This storage medium is located in memory, and the processor reads information from the memory and, in conjunction with its hardware, completes the steps of the above method.
[0214] The memory in the embodiments of this application can be volatile memory or non-volatile memory, or may include both volatile and non-volatile memory. The non-volatile memory can be read-only memory (ROM), programmable read-only memory (PROM), erasable programmable read-only memory (EPROM), electrically erasable programmable read-only memory (EEPROM), or flash memory. The volatile memory can be random access memory (RAM), which is used as an external cache. By way of example, but not limitation, many forms of RAM are available, such as static random access memory (SRAM), dynamic random access memory (DRAM), synchronous dynamic random access memory (SDRAM), double data rate synchronous dynamic random access memory (DDR SDRAM), enhanced synchronous dynamic random access memory (ESDRAM), synchronous linked dynamic random access memory (SLDRAM), and direct rambus RAM (DR RAM). It should be noted that the memory used in the systems and methods described herein is intended to include, but is not limited to, these and any other suitable types of memory.
[0215] This application also provides a chip system including at least one processor for supporting the implementation of the functions of the terminal device or network device involved in any of the above method embodiments, such as sending, receiving, or processing the information involved in the above methods.
[0216] In one possible design, the chip system also includes a memory for storing computer program instructions and data, which may be located inside or outside the processor.
[0217] The chip system can consist of chips or include chips and other discrete components.
[0218] This application also provides a computer program product, which includes a computer program (also referred to as code or instructions), wherein when the computer program is run, the method executed by the terminal device or the method executed by the network device in the above method embodiments is executed.
[0219] This application also provides a computer-readable storage medium storing a computer program (also referred to as code or instructions). When the computer program is run, the method executed by the terminal device or the method executed by the network device in the above method embodiments is executed.
[0220] This application also provides a communication system, which includes the aforementioned terminal equipment and network equipment.
[0221] The methods provided in the above embodiments can be implemented, in whole or in part, by software, hardware, firmware, or any combination thereof. When implemented in software, they can be implemented, in whole or in part, in the form of a computer program product. This computer program product may include one or more computer instructions. When these computer program instructions are loaded and executed on a computer, all or part of the processes or functions described in the embodiments of this application are generated. The computer may be a general-purpose computer, a special-purpose computer, a computer network, or other programmable device. The computer instructions may be stored in a computer-readable storage medium or transmitted from one computer-readable storage medium to another. For example, the computer instructions may be transmitted from one website, computer, server, or data center to another website, computer, server, or data center via wired (e.g., coaxial cable, fiber optic, digital subscriber line (DSL)) or wireless (e.g., infrared, wireless, microwave, etc.) means. The computer-readable storage medium may be any available medium accessible to a computer or a data storage device such as a server or data center that integrates one or more available media. The available medium may be a magnetic medium (e.g., floppy disk, hard disk, magnetic disk), an optical medium (e.g., DVD), or a semiconductor medium (e.g., solid-state disk (SSD)).
[0222] Those skilled in the art will recognize that the units and algorithm steps of the various examples described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are implemented in hardware or software depends on the specific application and design constraints of the technical solution. Those skilled in the art can use different methods to implement the described functions for each specific application, but such implementation should not be considered beyond the scope of this application.
[0223] Those skilled in the art will understand that, for the sake of convenience and brevity, the specific working processes of the systems, devices, and units described above can be referred to the corresponding processes in the foregoing method embodiments, and will not be repeated here.
[0224] In the several embodiments provided in this application, it should be understood that the disclosed systems, apparatuses, and methods can be implemented in other ways. For example, the apparatus embodiments described above are merely illustrative; for instance, the division of units is only a logical functional division, and in actual implementation, there may be other division methods. For example, multiple units or components may be combined or integrated into another system, or some features may be ignored or not executed. Furthermore, the coupling or direct coupling or communication connection shown or discussed may be through some interfaces; the indirect coupling or communication connection between apparatuses or units may be electrical, mechanical, or other forms.
[0225] The unit described as a separate component may or may not be physically separate. The component shown as a unit may or may not be a physical unit; that is, it may be located in one place or distributed across multiple network units. Some or all of the units can be selected to achieve the purpose of this embodiment according to actual needs.
[0226] In addition, the functional units in the various embodiments of this application can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit.
[0227] If this function is implemented as a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of this application, or part of it, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute all or part of the steps of the methods described in the various embodiments of this application. The aforementioned storage medium includes various media capable of storing program code, such as USB flash drives, portable hard drives, read-only memory, random access memory, magnetic disks, or optical disks.
[0228] In the various embodiments of this application, unless otherwise specified or in case of logical conflict, the terminology and / or descriptions of different embodiments are consistent and can be referenced by each other. The technical features of different embodiments can be combined to form new embodiments according to their inherent logical relationship.
Claims
1. A communication method characterized by comprising: include: Receive a first message, the first message being used to configure paging resources, the paging resources including a first paging timing and a second paging timing, the first paging timing occupying non-downlink time domain resources in a first time domain unit, the second paging timing occupying either non-downlink time domain resources in the first time domain unit or downlink time domain resources in a second time domain unit, the second time domain unit being located after the first time domain unit in the time domain; Control messages are received at two paging times in the downlink time domain resources of the second time domain unit. The control messages are used to schedule paging messages. The first paging time and the second paging time correspond to different paging times in the two paging times on the downlink time domain resources of the second time domain unit.
2. A communication method characterized by comprising: include: Send a first message, which is used to configure paging resources. The paging resources include a first paging opportunity and a second paging opportunity. The first paging opportunity occupies non-downlink time domain resources in a first time domain unit. The second paging opportunity occupies either non-downlink time domain resources in the first time domain unit or downlink time domain resources in the second time domain unit. The second time domain unit is located after the first time domain unit in the time domain. Control messages are sent at two paging times in the downlink time domain resources of the second time domain unit. The control messages are used to schedule paging messages. The first paging time and the second paging time correspond to different paging times in the two paging times on the downlink time domain resources of the second time domain unit.
3. The method according to claim 1 or 2, characterized in that, The paging opportunity corresponding to the first paging opportunity on the downlink time domain resources in the second time domain unit is associated with the position of the first paging opportunity in the first time domain unit.
4. The method according to claim 1 or 2, characterized in that, The paging opportunity corresponding to the first paging opportunity on the downlink time domain resources in the second time domain unit is associated with the position of the first paging opportunity among the M paging opportunities in the first time domain unit, and the M paging opportunities occupy the non-downlink time domain resources in the first time domain unit.
5. The method according to any one of claims 1 to 4, characterized in that, The paging opportunity corresponding to the downlink time domain resource in the second time domain unit is associated with the location of the second paging opportunity.
6. The method according to any one of claims 1 to 5, characterized in that, When the second paging opportunity occupies the non-downlink time domain resources in the first time domain unit, the paging opportunity corresponding to the second paging opportunity on the downlink time domain resources in the second time domain unit is associated with the position of the second paging opportunity among the M paging opportunities in the time domain unit, and the M paging opportunities occupy the non-downlink time domain resources in the first time domain unit.
7. The method of claim 5, wherein, The first time domain unit includes at least two time domain sub-units. Different time domain sub-units correspond to different paging opportunities on downlink time domain resources in the second time domain unit. The first paging opportunity and the second paging opportunity belong to different time domain sub-units in the at least two time domain sub-units.
8. The method according to any one of claims 1 to 7, characterized in that, The first message carries a parameter indicating the density of paging opportunities. Under the paging opportunity density indicated by the parameter, the number of time domain resources occupied by the M paging opportunities in the first time domain unit is less than the number of downlink time domain resources in the second time domain unit.
9. The method according to any one of claims 1 to 8, characterized in that, The first message carries a parameter indicating the density of paging opportunities, and the second time-domain unit includes at least two paging opportunities at the density of paging opportunities indicated by the parameter.
10. The method according to any one of claims 1 to 9, characterized in that, The parameter nB carrying the first message indicating the density of paging timing is T / 2, T / 4, or T / 8.
11. A communication method characterized by comprising: include: Receive a first message, the first message being used to configure paging resources, the paging resources including a first paging frame in a first time domain unit; A control message is received at the paging timing of the first downlink time domain resource. The control message is used to schedule the paging message. The paging timing on the first downlink time domain resource is associated with the position of the first paging frame in the first time domain unit. The first downlink time domain resource belongs to the first time domain unit or the second time domain unit. The second time domain unit is located after the first time domain unit in the time domain.
12. A communication method characterized by comprising: include: Send a first message, the first message being used to configure paging resources, the paging resources including a first paging frame in a first time domain unit; A control message is sent at the paging timing of the first downlink time domain resource. The control message is used to schedule the paging message. The paging timing of the first downlink time domain resource is associated with the position of the first paging frame in the first time domain unit. The first downlink time domain resource belongs to the first time domain unit or the second time domain unit. The second time domain unit is located after the first time domain unit in the time domain.
13. The method according to claim 11 or 12, characterized in that, The first message carries a parameter indicating the density of paging opportunities, and the location of the paging opportunity on the first downlink time domain resource on the first downlink time domain resource is associated with the location of the first paging frame in the first time domain unit and the parameter.
14. The method of claim 13, wherein, Under the paging timing density indicated by the parameter, the first time domain unit includes N paging frames, each of which belongs to a different time domain sub-unit in the first time domain unit, and each of the different time domain sub-units corresponds to a different paging timing on the first downlink time domain resource.
15. The method according to any one of claims 11 to 14, characterized in that, The starting position of the downlink time-domain resources in the first time-domain unit is included in the first paging frame, and the first downlink time-domain resources are included in the first time-domain unit; or, When the starting position of the downlink time domain resources in the first time domain unit is not included in the first paging frame, the first downlink time domain resources are included in the second time domain unit.
16. A communications device, characterized by include: A module for performing the method as described in any one of claims 1 to 15.
17. A communications device, characterized by Includes: a processor for retrieving and executing computer program instructions from memory, causing the communication device to perform the method as described in any one of claims 1 to 15.
18. The communication apparatus according to claim 17, wherein The communication device also includes the memory.
19. A computer-readable storage medium, characterized in that, Used to store computer program instructions, the computer program causing the computer to perform the method as described in any one of claims 1 to 15.
20. A computer program product, characterised in that, It includes computer program instructions that cause a computer to perform the method as described in any one of claims 1 to 15.