Construction planning support device

The construction plan formulation support device integrates and updates map data to estimate excavation locations accurately, addressing map inaccuracies and optimizing construction plans, thereby reducing time and costs by coordinating with other projects.

WO2026239508A1PCT designated stage Publication Date: 2026-11-19NT T INC
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
PCT/JP2025/017469
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Filing Date
2025-05-14
Publication Date
2026-11-19

AI Technical Summary

Technical Problem

Conventional construction methods for underground infrastructure require separate and consecutive work by different operators, leading to increased construction time and costs due to inaccuracies in map information, which can result in unnecessary excavation and delays.

Method used

A construction plan formulation support device that integrates map data from multiple operators, estimates positional accuracy using past construction history, and estimates excavation locations with margins to account for map inaccuracies, while updating maps based on actual excavation results.

Benefits of technology

This approach allows for shorter construction periods and reduced costs by improving map accuracy and optimizing construction plans, even when initial map information is not precise, by integrating and updating map data and coordinating with other construction projects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure JP2025017469_19112026_PF_FP_ABST
    Figure JP2025017469_19112026_PF_FP_ABST
Patent Text Reader

Abstract

A construction planning support device comprising: a map data integration unit that integrates map information on the basis of an underground map relating to a buried object provided by one or more business operators, and an aboveground map provided by a business operator related to an aboveground facility; a map accuracy estimation unit that estimates the positional accuracy of the underground map on the basis of the underground map and past construction history in an area including a location where the buried object is positioned; and an excavation spot estimation unit that estimates an excavation spot on the basis of the integrated map information and the estimated positional accuracy of the underground map. 
Need to check novelty before this filing date? Find Prior Art

Description

Construction plan formulation support device

[0001] The present invention relates to a construction plan formulation support device.

[0002] Conventionally, construction works for electricity, gas, water supply, communications and the like have been carried out individually by each operator. For this reason, for example, after the construction of the buried pipeline for water pipes is completed, it has been necessary to perform construction work again for the construction of the buried pipeline for the communication network at the same location. In such cases, different operators will consecutively perform construction work at the same location, which has resulted in the problem of increased construction time and costs.

[0003] To address such problems, a method has been proposed in which construction plans of different operators are coordinated for joint execution as a single construction work, so as to reduce the construction period and costs compared to the case of performing consecutive separate construction works (see, for example, Non-Patent Document 1).

[0004] "Initiatives for Sharing Businesses Toward Realizing a Sustainable Society", NTT Technical Journal January 2025 Issue

[0005] However, in the method described in Non-Patent Document 1, construction plans and construction locations of different operators are coordinated from a macroscopic perspective to implement joint construction, but from a microscopic perspective, it is premised that the facility information and map information held by different operators are accurate in order to identify the construction location at the construction site. When the accuracy of the map information is not high, the trouble of actually performing several excavation works or the like to confirm the correct position arises. As a result, the construction period could not be shortened in some cases.

[0006] In view of the above circumstances, the present invention aims to provide a technology capable of shortening the construction period even when the accuracy of map information is not high.

[0007] One aspect of the present invention is a construction plan formulation support device comprising: a map data integration unit that integrates map information based on an underground map of buried objects provided by one or more businesses and an above-ground map provided by businesses related to facilities installed above ground; a map accuracy estimation unit that estimates the positional accuracy of the underground map based on past construction history in an area including the location of the buried objects and the underground map; and an excavation location estimation unit that estimates excavation locations based on the integrated map information and the estimated positional accuracy of the underground map.

[0008] This invention makes it possible to shorten the construction period even when the accuracy of map information is not high.

[0009] This figure shows an example of the configuration of the support system in the embodiment. This flowchart shows the processing flow performed by the construction plan formulation support system in the embodiment. This flowchart shows the processing flow performed by the business operator D terminal in the embodiment. This flowchart shows the processing flow performed by the construction plan formulation support system in the embodiment. This flowchart shows the processing flow performed by the construction plan formulation support system in the embodiment. This flowchart shows the processing flow performed by the construction plan formulation support system in the embodiment. This figure illustrates the difference between the conventional method and the method of estimating excavation locations in the present invention.

[0010] One embodiment of the present invention will be described below with reference to the drawings.

[0011] Figure 1 shows an example of the configuration of the support system 10 in an embodiment. The support system 10 comprises a business operator A terminal 100, a business operator B terminal 200, a business operator C terminal 300, a city planner terminal 400, a business operator D terminal 500, and a construction plan formulation support system 600. The business operator A terminal 100, business operator B terminal 200, business operator C terminal 300, city planner terminal 400, business operator D terminal 500, and the construction plan formulation support system 600 are connected via a network 700. The network 700 is, for example, the internet.

[0012] In the following description, terminals A (100), B (200), C (300), urban planner (400), and D (500) provide information used to formulate construction plans in the construction plan formulation support system (600). Terminal D (500) also requests support for construction plans to be implemented from the construction plan formulation support system (600). This is just an example, and the number of terminals provided by the support system (10) is not particularly limited. Furthermore, the terminal requesting support for construction plans from the construction plan formulation support system (600) may be any terminal other than terminal D (500), such as terminal A (100), terminal B (200), or terminal C (300).

[0013] (Configuration) Operator A terminal 100 is a terminal operated by infrastructure operator A, which manages one or more infrastructure facilities. Here, infrastructure facilities include underground buried facilities such as electricity, gas, water, and communications. Operator A terminal 100 holds information on buried facilities map 101, equipment replacement information 102, and construction history 103. The buried facilities map 101 is a map of underground facilities such as buried pipelines owned by infrastructure operator A. In other words, the buried facilities map 101 is an underground map of buried facilities managed by infrastructure operator A. The buried facilities map 101 includes location information indicating the installation location of the buried facilities.

[0014] Equipment replacement information 102 is information indicating the planned replacement timing of infrastructure equipment, calculated based on the service life and degree of deterioration of the infrastructure equipment owned by infrastructure operator A. Construction history 103 represents the past construction history in the area including the location of buried objects managed by infrastructure operator A. For example, construction history 103 includes information indicating the error (deviation) between the location information of buried objects shown in map information used during past construction and the actual location information of buried objects identified during construction.

[0015] In response to a request from the construction plan formulation support system 600, the operator A terminal 100 notifies the construction plan formulation support system 600 of the buried object map 101, equipment replacement information 102, and construction history 103 via the network 700.

[0016] The Operator B terminal 200 is a terminal operated by infrastructure operator B, which manages one or more infrastructure facilities. The Operator B terminal 200 holds information on buried infrastructure maps 201, equipment replacement information 202, and construction history 203. The buried infrastructure map 201 is a map of underground facilities such as buried pipelines owned by infrastructure operator B. In other words, the buried infrastructure map 201 is an underground map of buried infrastructure managed by infrastructure operator B. The buried infrastructure map 201 includes location information indicating the installation locations of the buried infrastructure.

[0017] Equipment replacement information 202 is information indicating the planned replacement timing of infrastructure equipment, calculated based on the service life and degree of deterioration of the infrastructure equipment owned by infrastructure operator B. Construction history 203 represents the past construction history in the area including the location of buried objects managed by infrastructure operator B. For example, construction history 203 includes information indicating the error (deviation) between the location information of buried objects shown in map information used during past construction and the actual location information of buried objects identified during construction.

[0018] In response to a request from the construction plan formulation support system 600, the operator B terminal 200 notifies the construction plan formulation support system 600 of the buried infrastructure map 201, equipment replacement information 202, and construction history 203 via the network 700.

[0019] Operator C terminal 300 is a terminal operated by a map operator that possesses a ground map. Operator C terminal 300 holds information on the ground map 301. The ground map 301 is a map that shows the location information of equipment placed on the ground. Equipment placed on the ground includes roads and buildings on the ground, as well as ground equipment that can serve as landmarks for other underground structures (for example, manholes, handholes, ground and underground entrances and exits, etc.). Roads and buildings on the ground are equipment with highly accurate location information linked to latitude and longitude information, etc. In response to a request from the construction plan formulation support system 600, Operator C terminal 300 notifies the construction plan formulation support system 600 of the information on the ground map 301 via the network 700.

[0020] The urban planner terminal 400 is a terminal operated by an organization responsible for urban planning. Here, the organization responsible for urban planning is, for example, a local government or a major construction company. The organization responsible for urban planning is responsible for large-scale urban planning, disaster prevention planning, road and street paint repair planning, etc. The urban planner terminal 400 holds information on urban planning 401. Urban planning 401 is information that shows construction plans based on future urban planning and repair plans. In response to a request from the construction plan formulation support system 600, the urban planner terminal 400 notifies the construction plan formulation support system 600 of the information on urban planning 401 via the network 700.

[0021] The operator D terminal 500 is a terminal operated by infrastructure operator D, which manages one or more infrastructure facilities. The operator D terminal 500 holds information on buried infrastructure maps 501, equipment replacement information 502, construction history 503, and construction plans 504. The buried infrastructure map 501 is a map of underground facilities such as buried pipelines owned by infrastructure operator D. In other words, the buried infrastructure map 501 is an underground map of buried infrastructure managed by infrastructure operator D. The buried infrastructure map 501 includes location information indicating the installation locations of the buried infrastructure.

[0022] Equipment replacement information 502 is information indicating the planned replacement timing of infrastructure equipment, calculated based on the service life and degree of deterioration of the infrastructure equipment owned by infrastructure operator D. Construction history 503 represents the past construction history in the area including the location of buried objects managed by infrastructure operator D. For example, construction history 503 includes information indicating the error (deviation) between the location information of buried objects shown in map information used during past construction and the actual location information of buried objects identified during construction.

[0023] Construction plan 504 represents a construction plan for roads, building reconstructions, etc., that is planned to commence in the future. Infrastructure operator D operates operator D terminal 500 to notify the construction plan formulation support system 600 of the buried object map 501, equipment replacement information 502, construction history 503, and construction plan 504 via the network 700 in order to estimate the construction site and appropriate construction schedule. As a result, infrastructure operator D obtains information to support the formulation of the construction plan from the construction plan formulation support system 600. The information to support the formulation of the construction plan includes information such as excavation sites and revised construction plans.

[0024] In the following explanation, if buried object maps 101, 201, and 501 are not specifically distinguished, they may simply be referred to as "buried object maps." Similarly, if equipment replacement information 102, 202, and 502 are not specifically distinguished, they may simply be referred to as "equipment replacement information." Similarly, if construction history 103, 203, and 503 are not specifically distinguished, they may simply be referred to as "construction history." In the example above, there are multiple infrastructure operators, but it is sufficient to have one or more infrastructure operators. That is, the construction plan formulation support system 600 only needs to be equipped with one or more of the operator A terminal 100, operator B terminal 200, and operator D terminal 500.

[0025] The construction plan formulation support system 600 is a system that supports users in formulating construction plans. In this explanation, the user is, for example, business operator D, which operates business operator D terminal 500. Based on information obtained from business operator A terminal 100, business operator B terminal 200, business operator C terminal 300, urban planner terminal 400, and business operator D terminal 500, the construction plan formulation support system 600 estimates excavation locations and formulates an appropriate construction plan based on the construction plan 504 of business operator D terminal 500.

[0026] The construction plan formulation support system 600 includes a map data integration unit 601, a map accuracy estimation unit 602, an excavation location estimation unit 603, a buried object map update unit 604, a construction cost calculation unit 605, a construction period calculation unit 606, a construction method selection unit 607, and a construction plan optimization unit 608. Note that the construction plan formulation support system 600 may implement each of the above functions using a single information processing device. In this case, the construction plan formulation support system 600 may be configured as a construction plan formulation support device.

[0027] Furthermore, the construction plan formulation support system 600 may implement each of the above-mentioned functional units using multiple information processing devices. In this case, the multiple information processing devices work together to support the user in formulating a construction plan. For example, when each of the above-mentioned functional units is implemented using multiple information processing devices, one information processing device may be implemented as an excavation location estimation device equipped with a map data integration unit 601, a map accuracy estimation unit 602, and an excavation location estimation unit 603, while another information processing device may be implemented as a construction plan formulation support device equipped with a buried object map update unit 604, a construction cost calculation unit 605, a construction period calculation unit 606, a construction method selection unit 607, and a construction plan optimization unit 608.

[0028] The map data integration unit 601 integrates map information based on the buried object maps (buried object maps 101, 201, and 501) provided by operator A terminal 100, operator B terminal 200, and operator D terminal 500, respectively, and the ground map 301 provided by operator C terminal 300. Specifically, the map data integration unit 601 aligns the coordinates and scales of each buried object map and the ground map 301 and integrates them into a single map. As a result, the map data integration unit 601 generates an integrated map.

[0029] The map accuracy estimation unit 602 estimates the positional accuracy of each buried object map for each business operator or region based on each buried object map and each construction history (construction histories 103, 203, and 503). For example, the map accuracy estimation unit 602 estimates the positional accuracy of the buried object map 101 provided by business operator terminal 100 based on each construction history. If construction has been carried out in a certain region in the past, it is conceivable that there may be errors in the positional accuracy of the buried object maps held by each business operator. Therefore, the map accuracy estimation unit 602 estimates the positional accuracy of each buried object map based on each construction history.

[0030] The excavation location estimation unit 603 estimates the excavation location based on the integrated map and the positional accuracy of each buried object map estimated by the map accuracy estimation unit 602. When replacing an existing buried pipeline, the excavation location estimation unit 603 estimates the excavation location to include the location of the buried object shown on the buried object map and to include the range in which the buried object may exist based on the positional accuracy. In other words, the excavation location estimation unit 603 estimates the excavation location not only around the location of the buried object shown on the buried object map, but also within a range that includes a margin in the buried object's positional information. On the other hand, when laying a new pipeline, the excavation location estimation unit 603 estimates the excavation location to include a range that includes a margin in the buried object's positional information, and to include areas where no buried pipeline exists.

[0031] The buried object map update unit 604 updates each buried object map based on the location information of the buried objects obtained from actual excavation work. Specifically, the buried object map update unit 604 updates the location information and accuracy of each buried object map. Here, actual excavation work refers to the user actually excavating at the excavation site estimated by the excavation site estimation unit 603. This makes it possible to identify the actual location information of the buried objects.

[0032] The buried object map update unit 604 acquires actual location information of buried objects obtained through actual excavation work by the user. Based on the error between the acquired actual location information of buried objects and the location information of buried objects shown in each buried object map, the buried object map update unit 604 updates each buried object map to match the location information of buried objects shown in each map to the actual location information of buried objects. By updating the location information of buried objects shown in each buried object map, the buried object map update unit 604 also updates the accuracy. Furthermore, it updates the location information of buried objects in the integrated map using the updated buried object maps.

[0033] The construction cost calculation unit 605 calculates the costs required for the construction based on the construction plan 504 provided by the user. For example, the construction cost calculation unit 605 calculates the costs required for the construction based on the decrease in the accuracy of estimating the excavation site due to map accuracy.

[0034] The construction period calculation unit 606 calculates the period required for construction based on the construction plan 504 provided by the user. For example, the construction period calculation unit 606 calculates the period required for construction based on the decrease in the accuracy of estimating excavation locations due to map accuracy.

[0035] The construction method selection unit 607 selects an appropriate construction method based on the surrounding environment of the construction site, including the ground and land values, and past construction history.

[0036] The construction plan optimization unit 608 formulates an appropriate construction plan for executing the construction plan 504 provided by the user, based on the cost calculated by the construction cost calculation unit 605, the period calculated by the construction period calculation unit 606, the construction method selected by the construction method selection unit 607, the urban plan 401 provided from the urban planner terminal 400, and the construction plans of other businesses. For example, the construction plan optimization unit 608 formulates an optimal construction plan, including the unification of construction, based on the urban plan 401, the construction schedules of other businesses, the service life of each infrastructure facility, etc. Here, unification of construction means reviewing the construction plan 504 provided by the user and implementing joint construction with other businesses. By unifying construction, it is possible to reduce the amount of work at the same location to one time, thereby shortening the period.

[0037] (Example of operation 1) Figure 2 is a flowchart showing the processing flow performed by the construction plan formulation support system 600 in the embodiment. Figure 2 describes the processing flow from the start of use by the user (infrastructure operator D) to the estimation of excavation locations by the construction plan formulation support system 600.

[0038] The construction plan formulation support system 600 receives a service application from a user (step S101). The user operates the operator D terminal 500 to provide the construction plan formulation support system 600 with information on the buried infrastructure map 501, equipment replacement information 502, construction history 503, and construction plan 504 via the network 700. The construction plan formulation support system 600 receives the information on the buried infrastructure map 501, equipment replacement information 502, construction history 503, and construction plan 504 provided by the operator D terminal 500 (step S102).

[0039] The construction plan formulation support system 600 requests infrastructure operators A and B to provide information such as underground utility maps. Furthermore, the construction plan formulation support system 600 requests operator C to provide surface map information. In response to the request from the construction plan formulation support system 600, infrastructure operator A operates operator A terminal 100 to provide the underground utility map 101, equipment replacement information 102, and construction history 103 to the construction plan formulation support system 600 via the network 700. Similarly, in response to the request from the construction plan formulation support system 600, infrastructure operator B operates operator B terminal 200 to provide the underground utility map 201, equipment replacement information 202, and construction history 203 to the construction plan formulation support system 600 via the network 700. Similarly, in response to the request from the construction plan formulation support system 600, operator C operates operator C terminal 300 to provide surface map 301 information to the construction plan formulation support system 600 via the network 700.

[0040] The map data integration unit 601 generates an integrated map using each buried object map (buried object maps 101, 201, 501) provided by the user and other businesses, and the surface map 301 (step S103). The map data integration unit 601 outputs the generated integrated map to the excavation location estimation unit 603. The map accuracy estimation unit 602 estimates the positional accuracy of the buried object maps based on each past construction history (construction history 103, 203, and 503) provided by the user and other businesses, and each buried object map (buried object maps 101, 201, 501) (step S104). The map accuracy estimation unit 602 outputs information indicating the estimated positional accuracy of the buried object maps to the excavation location estimation unit 603.

[0041] The excavation location estimation unit 603 updates the location information of the buried objects in the integrated map by setting a margin in accordance with the information indicating the positional accuracy of the estimated buried object map output from the map accuracy estimation unit 602 (step S105). For example, the excavation location estimation unit 603 updates the location information of the buried objects in the integrated map by setting a margin that takes into account the error in the location information of the buried objects according to the information indicating the positional accuracy of the buried object map.

[0042] Subsequently, the excavation location estimation unit 603 estimates the excavation locations based on the updated integrated map (step S106). For example, in the case of work to replace existing buried objects, the excavation location estimation unit 603 estimates locations where the target buried objects are likely to exist as excavation locations. Here, the excavation locations are candidates that are close to the location of the buried objects on the integrated map. On the other hand, when laying new pipelines, the excavation location estimation unit 603 estimates locations where the existing buried objects are unlikely to exist as excavation locations. The excavation locations may be, for example, within a set margin range and at a predetermined distance from the location of the buried objects on the integrated map. This is because the further away from the location of the buried objects on the integrated map, the lower the probability of the buried objects being present. In this way, the excavation location estimation unit 603 estimates the excavation locations. The excavation location estimation unit 603 notifies the operator D terminal 500 of the updated integrated map and information indicating the estimated excavation locations (step S107).

[0043] As shown in Figure 2, the construction plan formulation support system 600 unifies and integrates the position coordinates of the map information (each buried object map and ground map 301) possessed by each operator, thereby generating an integrated map that enables centralized management of above-ground and underground facility information. The construction plan formulation support system 600 estimates the position accuracy of the map information by region or by operator based on the position information of each buried object map possessed by each operator and past construction information. The construction plan formulation support system 600 estimates an excavation location based on the estimated position accuracy and the integrated map.

[0044] Note that in Figure 2, the construction plan formulation support system 600 requests the information possessed by each operator each time it receives a service use application from a user. In contrast, information possessed by operators other than the user may be shared in advance, and the construction plan formulation support system 600 may use the pre-shared information. In this case, the construction plan formulation support system 600 does not need to request information from operators other than the user in Figure 2.

[0045] Here, for maps for which past construction history or accuracy information does not exist, the accuracy defined for each map scale may be used. For example, in the case of a map with a scale of 1 / 500 (a map with a map level of 500), the allowable error for positional displacement is 25 cm. Therefore, the construction plan formulation support system 600 uses the map accuracy obtained from the scale as an initial value, and thereafter corrects (updates) the positional displacement of the map for each location in accordance with the actual positional displacement during excavation work. When the map information is updated by correcting the positional displacement of the map, the farther away from the excavation location, the greater the deviation from the actually measured value.

[0046] Here, for example, as one form of position accuracy correction, the construction plan formulation support system 600 may normally use a method that, based on the premise that buried objects are arranged in a straight line, corrects the position information of the buried objects to correct the deviation at multiple locations when there are a plurality of excavation points, and extrapolates the outer side thereof by linear interpolation. At this time, if the extrapolation results in a position exceeding the error of the original map level, the construction plan formulation support system 600 performs correction so that the maximum error value becomes the value of the original map accuracy. Even when there is only one excavation point, since a certain section along the buried object is excavated, the position of the buried object outside the excavation point may be obtained by extrapolation based on the actually measured value of the corresponding section.

[0047] In addition, as a method for correcting the position of the map, non-rigid alignment such as affine transformation used in processing such as general image processing deformation can also be combined. Regarding the accuracy after correcting the positions including the surroundings by extrapolation or deformation processing, the accuracy is set to 0 cm at the excavation points where the positional deviation is eliminated by the correction, and the accuracy is reset so that the allowable error reaches the original map level as the distance from the excavation point increases. For example, in a case where the error exceeds the original map level error due to extrapolation, since the distance from the excavation point is sufficiently large, the accuracy is set to be approximately the same as the original map level error.

[0048] (Operation Example 2) Figure 3 is a flowchart showing the flow of processing performed by the operator D terminal 500 in the embodiment. Note that FIG. 3 describes the flow of processing for excavation work by the operator D who is a user.

[0049] The operator D terminal 500 receives the updated integrated map and information indicating the estimated excavation location transmitted from the construction plan formulation support system 600 (step S201). Based on the received updated integrated map and information indicating the estimated excavation location, operator D investigates the area around the estimated excavation location using detectors, etc., at the site and performs excavation (step S202). This allows operator D to identify the actual location information of the buried object. For example, operator D identifies the actual location information of the buried object by estimating the location information at the location where the buried object is located. Operator D operates the operator D terminal 500 to notify the construction plan formulation support system 600 of the actual location information of the buried object at the excavation location obtained as a result of the excavation work (step S203).

[0050] As shown in Figure 3, users of the construction plan formulation support system 600 receive estimated results of appropriate excavation locations for the construction site by notifying the system 600 of their own construction plan 504. During excavation, the user compares the integrated map with the actual location information of the buried objects, and if there is a discrepancy in the location information, the user notifies the system 600 accordingly.

[0051] (Operation Example 3) Figure 4 is a flowchart showing the processing flow performed by the construction plan formulation support system 600 in the embodiment. Figure 4 describes the processing flow for updating map information based on the results of excavation work performed by the user, business operator D.

[0052] The construction plan formulation support system 600 receives actual location information of buried objects at the excavation site transmitted from the business operator D terminal 500 (step S301). The buried object map update unit 604 determines whether there is a discrepancy in the location of the buried objects based on the received actual location information of the buried objects at the excavation site and the location information of the buried objects shown on each buried object map (step S302). Here, the buried object map update unit 604 determines that there is a discrepancy in the location of the buried objects if there is an error between the actual location information of the buried objects at the excavation site and the location information of the buried objects shown on each buried object map. The range of error for determining whether there is a discrepancy in the location of the buried objects is set in advance. The buried object map update unit 604 determines that there is no discrepancy in the location of the buried objects if there is no error between the actual location information of the buried objects at the excavation site and the location information of the buried objects shown on each buried object map.

[0053] If the buried object map update unit 604 determines that there is a discrepancy in the location of the buried object (step S302-YES), the buried object map update unit 604 updates each buried object map provided by infrastructure operators A, B, and D, respectively (step S303). Specifically, the buried object map update unit 604 updates each buried object map so that the location information of the buried object in each map becomes the actual location information of the buried object at the excavation site.

[0054] Furthermore, the buried object map update unit 604 updates the position accuracy information of each buried object map provided by infrastructure operators A, B, and D (step S304). Furthermore, the buried object map update unit 604 updates the integrated map (step S305). Specifically, the buried object map update unit 604 updates the integrated map so that the position information of the buried objects in the integrated map becomes the actual position information of the buried objects at the excavation site.

[0055] Subsequently, the buried infrastructure map update unit 604 creates a construction history for each infrastructure operator based on the respective buried infrastructure maps provided by infrastructure operators A, B, and D, and the actual location information of the buried infrastructure (step S306). The buried infrastructure map update unit 604 creates a construction history that includes information indicating the error between the buried infrastructure map 101 provided by infrastructure operator A and the actual location information of the buried infrastructure. The buried infrastructure map update unit 604 creates a construction history that includes information indicating the error between the buried infrastructure map 201 provided by infrastructure operator B and the actual location information of the buried infrastructure. The buried infrastructure map update unit 604 creates a construction history that includes information indicating the error between the buried infrastructure map 501 provided by infrastructure operator D and the actual location information of the buried infrastructure.

[0056] Subsequently, the buried infrastructure map update unit 604 notifies each infrastructure operator of the updated buried infrastructure map and the created construction history information (step S307). The buried infrastructure map update unit 604 notifies infrastructure operator A of the updated buried infrastructure map 101 and the created construction history information for infrastructure operator A. The buried infrastructure map update unit 604 notifies infrastructure operator B of the updated buried infrastructure map 201 and the created construction history information for infrastructure operator B. The buried infrastructure map update unit 604 notifies infrastructure operator D of the updated buried infrastructure map 501 and the created construction history information for infrastructure operator D.

[0057] As shown in Figure 4, the construction plan formulation support system 600 updates the integrated map and each contractor's buried object map based on the discrepancies notified by the user. Furthermore, the construction plan formulation support system 600 updates the positional accuracy of the map information for the relevant locations on the updated integrated map. At this time, since it is also necessary to update the map information for the surrounding areas of the excavation sites, the positional accuracy is also updated for the surrounding areas. The construction plan formulation support system 600 can also improve the accuracy of each contractor's buried object map by providing feedback on the updated buried object maps to the contractors who provided the maps, as needed.

[0058] (Example of operation 4) Figure 5 is a flowchart showing the processing flow performed by the construction plan formulation support system 600 in the embodiment. Figure 5 will explain the processing flow for construction plan creation support.

[0059] The construction plan optimization unit 608 receives a construction plan 504 from the user (step S401). Based on the received construction plan 504, the construction plan optimization unit 608 investigates whether there are any construction plans from other businesses at the construction site (step S402). Here, the construction plans of other businesses are assumed to include the urban plan 401 provided by business C. Based on the results of the investigation, the construction plan optimization unit 608 determines whether or not there are any construction plans from other businesses (step S403).

[0060] If the construction plan optimization unit 608 determines that there is a construction plan by another business operator (step S403-YES), the construction plan optimization unit 608 determines whether the user's construction plan can be postponed until the time when the other business operator's construction plan is to be executed (step S404). In determining whether it can be postponed until the time when the other business operator's construction plan is to be executed, the construction plan optimization unit 608 may also inquire with infrastructure operator D. In this case, the construction plan optimization unit 608 determines whether it can be postponed based on the response from infrastructure operator D.

[0061] Alternatively, the construction plan 504 provided by the user may include information regarding the period during which the construction can be extended. In this case, the construction plan optimization unit 608 determines whether or not the construction can be postponed by taking into account the information regarding the period during which the construction plans of other businesses will be executed, as well as the period during which the construction plans of other businesses will be executed. If the construction plan optimization unit 608 determines that the user's construction plan can be postponed until the period during which the construction plans of other businesses will be executed (step S404-YES), the construction plan optimization unit 608 reviews each construction plan and optimizes the construction plan to make it a joint construction project with other businesses (step S405). In this case, the construction plan optimization unit 608 will review at least the user's construction plan.

[0062] The construction plan optimization unit 608 receives cost information from the construction cost calculation unit 605, construction period calculation unit 606, and construction method information from the construction method selection unit 607 when formulating a construction plan. The construction cost calculation unit 605 calculates the costs required for the construction based on the construction plan 504 provided by the user, for example. The construction period calculation unit 606 calculates the period required for the construction based on the construction plan 504 provided by the user, for example. The construction method selection unit 607 selects an appropriate construction method based on the surrounding environment of the construction site, including the ground and land values, and past construction history, for example.

[0063] The construction plan optimization unit 608 then formulates an optimal construction plan based on the costs calculated by the construction cost calculation unit 605, the construction period calculated by the construction period calculation unit 606, the construction method selected by the construction method selection unit 607, and the construction plans of other businesses (including the urban plan 401). In this process, the construction plan optimization unit 608 formulates an optimal construction plan according to the priorities requested by the user, such as cost optimization and period optimization. The construction plan optimization unit 608 then provides information indicating the created optimal construction plan to the infrastructure business operator D.

[0064] On the other hand, if the construction plan optimization unit 608 determines that the user's construction plan cannot be postponed until the construction plans of other businesses are to be executed (step S404-NO), the construction plan optimization unit 608 determines whether or not it is possible to revise the construction plans of other businesses (step S406). In determining whether or not it is possible to revise the construction plans of other businesses, the construction plan optimization unit 608 may inquire with other businesses. In this case, the construction plan optimization unit 608 determines whether or not it is possible to revise the construction plans of other businesses based on the response from the other businesses.

[0065] If the construction plan optimization unit 608 determines that it is possible to revise the construction plans of other businesses (step S406-YES), the construction plan optimization unit 608 reviews each construction plan and optimizes it to be a joint construction project with other businesses (step S405). In this case, the construction plan optimization unit 608 will revise the construction plans of other businesses. For example, the construction plan optimization unit 608 may bring forward the construction plans of other businesses and optimize them to be a joint construction project with infrastructure business operator D.

[0066] On the other hand, if the construction plan optimization unit 608 determines that it is not possible to revise the construction plans of other businesses (step S406-NO), the construction plan optimization unit 608 plans to carry out the construction as originally planned (step S407). Here, "as originally planned" means creating a construction plan that carries out the construction exactly as described in the construction plan 504 provided by the user. Also, in the process of step S403, if the construction plan formulation support system 600 determines that there are no construction plans from other businesses (step S403-NO), the construction plan optimization unit 608 plans to carry out the construction as originally planned (step S407).

[0067] Since excavation work requires the presence of related businesses and restrictions on road use, it is desirable to consolidate the work of multiple businesses if possible. Therefore, as shown in Figure 5, the construction plan formulation support system 600 can revise the construction plan to optimize the work period and timing of the excavation work, based on the user's construction plan as well as the business's construction plan (for example, including the urban plan 401). In this case, for things that cannot be postponed, such as the timing of facility opening, or things that cannot be changed, such as urban plans and disaster prevention plans, the construction plan is formulated so as not to postpone or change the timing from the originally planned period.

[0068] (Operation Example 5) Figure 6 is a flowchart showing the processing flow performed by the construction plan formulation support system 600 in the embodiment. Figure 6 describes the processing flow when the map accuracy is low. Here, low map accuracy refers to cases where it is difficult to narrow down the estimated range of the excavation site.

[0069] The construction plan optimization unit 608 receives the construction plan 504 from the user (step S501). The construction plan formulation support system 600 requests infrastructure operators A, B, and D to provide information on the buried infrastructure map. Furthermore, the construction plan formulation support system 600 requests operator C to provide information on the ground map. As a result, the construction plan formulation support system 600 obtains each of the buried infrastructure maps and the ground map 301. The map data integration unit 601 generates an integrated map using each of the buried infrastructure maps (buried infrastructure maps 101, 201, 501) and the ground map 301 provided by the user and other operators (step S502).

[0070] The construction plan optimization unit 608 determines whether the accuracy of the generated integrated map is low or not (step S503). Here, the criteria for determining whether the accuracy of the integrated map is low or not are set in advance. If the construction plan optimization unit 608 determines that the accuracy of the integrated map is not low (step S503-NO), the construction plan optimization unit 608 formulates a construction plan to carry out the construction as originally planned (step S504). On the other hand, if the construction plan optimization unit 608 determines that the accuracy of the integrated map is low (step S503-YES), the construction plan optimization unit 608 investigates whether there are any construction plans in the surrounding area (step S505). Here, surrounding construction plans refer to construction plans in the area around the location indicated in construction plan 504.

[0071] The construction plan optimization unit 608 determines whether or not there are construction plans in the surrounding area (step S506). If the construction plan optimization unit 608 determines that there are construction plans in the surrounding area (step S506-YES), the construction plan optimization unit 608 determines whether or not the order of the construction can be changed (step S507). If the construction plan optimization unit 608 determines that the order of the construction can be changed (step S507-YES), the construction plan optimization unit 608 modifies the construction plan so that the surrounding construction is carried out first (step S508). After that, the construction plan optimization unit 608 formulates a construction plan so that the construction is carried out according to the original plan (step S504).

[0072] If the construction plan optimization unit 608 determines that there are no other construction plans in the vicinity (step S506-NO), or if the construction plan optimization unit 608 determines that the order of the construction work cannot be changed (step S507-NO), the construction plan optimization unit 608 formulates a construction plan to carry out the work as originally planned (step S504).

[0073] In cases where map accuracy is low and it is difficult to narrow down the estimated range of excavation sites, as shown in Figure 6, the construction plan formulation support system 600 prioritizes construction at locations with high map accuracy in the surrounding area and improves map accuracy by updating map information and map accuracy through the relevant construction, thereby creating a construction plan that is appropriate to the location accuracy. Users can improve the efficiency of work costs and work periods by coordinating the construction plan with related businesses based on the revised construction plan provided by the construction plan formulation support system 600.

[0074] Figure 7 is a diagram illustrating the difference between the conventional method and the present invention in estimating the excavation location when replacing existing buried pipelines. Figure 7(A) shows the conventional method for estimating the excavation location, and Figure 7(B) shows the method for estimating the excavation location according to the present invention. In Figure 7, the solid line 20 indicates the location of buried objects on the buried object map, and the dotted line 21 indicates the actual location of buried objects.

[0075] As shown in Figure 7(A), in conventional buried object detection, the ranges R1 and R2 only investigate the area around the buried object (solid line 20) on the map, so the actual buried object (dotted line 21) cannot be found. The range of buried object detection changes depending on the accuracy of the map. Therefore, by limiting the range where the map's positional accuracy is high and expanding the search range where the map's positional accuracy is low, the present invention estimates ranges R3 and R4, which take errors into account, as the excavation site, as shown in Figure 7(B). This makes it possible to find the actual buried object (dotted line 21).

[0076] According to the support system 10 configured as described above, the construction plan formulation support system 600 includes a map data integration unit 601 that integrates map information based on each buried object map provided by one or more infrastructure operators that manage infrastructure facilities and a surface map 301 provided by a map operator; a map accuracy estimation unit 602 that estimates the positional accuracy of each buried object map based on past construction history 103, 203, 503 in the area including the location of the buried object and each buried object map; and an excavation location estimation unit 603 that estimates excavation locations based on the integrated map and the estimated positional accuracy of each buried object map.

[0077] In this way, the construction plan formulation support system 600 estimates excavation locations by adding a margin to the location information of buried objects according to the accuracy of the buried object maps obtained from one or more contractors. This makes it possible to estimate the location of the construction site with greater accuracy and narrow down the excavation locations. Therefore, it becomes possible to shorten the construction period even when the accuracy of the map information is not high.

[0078] Furthermore, the construction plan formulation support system 600 includes a buried object map updating unit 604 that updates each buried object map based on the location information of buried objects obtained by actually excavating the excavation locations estimated by the excavation location estimation unit 603, and feeds back the updated buried object maps to multiple infrastructure operators. In this way, the accuracy of the maps can be improved by feeding back errors in each buried object map. As a result, the time and cost caused by errors in excavation locations can be reduced.

[0079] Furthermore, the construction plan formulation support system 600, based on the construction plan 504 obtained from the user, formulates an optimal construction plan based on the construction plan 504 obtained from the user if there are no other construction plans from other businesses at the location indicated in the construction plan 504. If there are other businesses with construction plans, the system formulates a construction plan for joint construction with other businesses, or formulates an optimal construction plan based on the construction plan 504 obtained from the user, depending on the conditions of the other businesses' construction plans and the construction plan 504 obtained from the user. In this process, the construction plan formulation support system 600 also takes into account priorities such as cost optimization and time optimization when formulating the construction plan. As a result, the construction plan formulation support system 600 can formulate an optimal construction plan in accordance with priorities such as cost optimization and time optimization, based on the construction plans of one or more businesses, planned facility disclosures, urban plans 401, etc.

[0080] Furthermore, the construction plan formulation support system 600, when conditions are met where the location accuracy of the buried object map is poor, formulates a construction plan that prioritizes construction in the surrounding area with high map accuracy. This allows the system to prioritize construction in the surrounding area with high location accuracy when it is difficult to narrow down the estimated range of excavation sites due to the low location accuracy of the buried object map, thereby updating the map information and map accuracy with the relevant construction work. In this way, the construction plan formulation support system 600 improves map accuracy from the surrounding area and also creates a construction plan that is appropriate for the location accuracy. As a result, users can improve the efficiency of work costs and work periods by coordinating the construction plan with related businesses based on the revised construction plan.

[0081] (Variations) The above-mentioned buried object maps (for example, buried object maps 101, 201, 501) and surface map 301 may be provided by a person other than the above-mentioned business operator (for example, a specific person or another business operator).

[0082] In the above-described embodiment, some or all of the functional units of the construction plan formulation support system 600 are implemented as software by one or more processors, such as a CPU, executing a program stored in a storage device and memory having a non-volatile recording medium (non-temporary recording medium). The program may be recorded on a computer-readable non-temporary recording medium. A computer-readable non-temporary recording medium is, for example, a portable medium such as a flexible disk, magneto-optical disk, ROM (Read Only Memory), CD-ROM (Compact Disc-ROM), or a storage device such as a hard disk built into a computer system.

[0083] Some or all of the functional units of the construction plan formulation support system 600 may be implemented using hardware including electronic circuits (or circuits) such as LSI (Large Scale Integrated Circuit), ASIC (Application Specific Integrated Circuit), PLD (Programmable Logic Device), or FPGA (Field Programmable Gate Array).

[0084] While embodiments of this invention have been described in detail above with reference to the drawings, the specific configuration is not limited to these embodiments and includes designs and the like that do not depart from the spirit of this invention.

[0085] This invention can be applied to technologies that support the formulation of construction plans.

[0086] 10...Support system, 100...Operator A terminal, 101, 201, 301, 501...Underground infrastructure map, 102, 202, 302, 502...Equipment replacement information, 103, 203, 303, 503...Construction history, 200...Operator B terminal, 300...Operator C terminal, 400...City planner terminal, 500...Operator D terminal, 504...Construction plan, 600...Construction plan formulation support system, 601...Map data integration unit, 602...Map accuracy estimation unit, 603...Excavation location estimation unit, 604...Underground infrastructure map update unit, 605...Construction cost calculation unit, 606...Construction period calculation unit, 607...Construction method selection unit, 608...Construction plan optimization unit, 700...Network

Claims

1. A construction plan formulation support device comprising: a map data integration unit that integrates map information based on underground maps of buried objects provided by one or more businesses and above-ground maps provided by businesses related to above-ground facilities; a map accuracy estimation unit that estimates the positional accuracy of the underground map based on past construction history in the area including the location of the buried objects and the underground map; and an excavation location estimation unit that estimates excavation locations based on the integrated map information and the estimated positional accuracy of the underground map.

2. The construction plan formulation support device according to claim 1, further comprising: a map updating unit that updates the underground map based on location information of buried objects obtained by actually excavating the excavation locations estimated by the excavation location estimation unit, and feeds back the updated underground map to one or more businesses.

3. A construction plan optimization unit that formulates an optimal construction plan in response to a user's request, wherein the construction plan optimization unit identifies whether there are any construction plans of other businesses at the location indicated in the construction plan based on the construction plan obtained from the user, and if there are no construction plans of other businesses, it formulates an optimal construction plan based on the construction plan obtained from the user, and if there are construction plans of other businesses, it formulates a construction plan for joint construction with the other business, or formulates an optimal construction plan based on the construction plan obtained from the user, according to the conditions of the other business's construction plan and the construction plan obtained from the user, the construction plan formulation support device according to claim 1 or 2.

4. The construction plan optimization unit formulates a construction plan that prioritizes construction at locations with high map accuracy in the surrounding area when the condition of poor positional accuracy of the underground map is met, as described in claim 3.