Problem

Existing voltage verification processes for electrical equipment are complex, time-consuming, and expose workers to electrical hazards due to the use of hand-held testers, necessitating a safer and more efficient method for verifying the absence of voltage.

Innovation Solution

A permanently installed absence of voltage tester system that uses radio frequency signals to verify connectivity of cable leads to power lines, employing RF signal generators and detectors to ensure proper connection and automate the verification process.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Device complexity

If hand-held portable test instruments are used for voltage verification tests, then the testing process can be performed with simple equipment, but the process becomes complex and time-consuming with multiple stages

Engineering Contradiction:
Improvetesting equipment simplicityVSAvoidvoltage verification time
Core Design Contradiction:
Device complexityVSLoss of time

Solution Approach 1:

The absence of voltage tester system performs self-diagnosis by automatically injecting test signals through its own leads and detecting the responses, eliminating the need for manual operation and multiple testing stages. The system verifies connectivity and detects errors autonomously, reducing both complexity and time requirements.

Inventive Principle:
Principle #25Self-service

Solution Approach 2:

The system performs preliminary connectivity verification by testing the continuity and integrity of leads before actual voltage measurement. This preliminary action prevents unnecessary exposure to electrical hazards and identifies potential issues before the main testing process begins.

Inventive Principle:
Principle #10Preliminary action

2Ease of operation

If hand-held testers are used for voltage verification, then portability is maintained, but workers are exposed to electrical hazards if equipment is not properly de-energized

Engineering Contradiction:
Improvetester portabilityVSAvoidelectrical hazard exposure
Core Design Contradiction:
Ease of operationVSObject-affected harmful factors

Solution Approach 1:

The system uses an intermediary RF signal injection method to verify lead connectivity before contacting potentially energized equipment. The RF signal acts as a safe mediator that can detect connectivity issues without exposing workers to electrical hazards, as it operates at low power and frequency.

Inventive Principle:
Principle #24Intermediary (Mediator)

Solution Approach 2:

The system performs preliminary lead integrity verification using RF signals before the worker approaches or contacts the equipment being tested. This preliminary action ensures that leads are properly connected and functional, eliminating the need for repeated testing and reducing exposure to electrical hazards.

Inventive Principle:
Principle #10Preliminary action

3Reliability

If multiple testing stages are implemented for voltage verification, then safety is improved, but the process becomes more complex and time-consuming

Engineering Contradiction:
Improvesafety verificationVSAvoidtesting process complexity
Core Design Contradiction:
ReliabilityVSDevice complexity

Solution Approach 1:

The system combines multiple testing stages into a single integrated process. The RF signal injection and detection functionality merges connectivity verification, lead integrity testing, and voltage verification into one automated sequence, maintaining safety while reducing complexity.

Inventive Principle:
Principle #5Merging (Combining)

Solution Approach 2:

The system implements feedback mechanisms where the detected RF signal responses are automatically analyzed to determine lead connectivity status. This feedback loop enables the system to self-diagnose and communicate results without requiring manual interpretation of multiple separate test results.

Inventive Principle:
Principle #23Feedback

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

The system significantly reduces the time required for voltage verification and enhances safety by ensuring accurate connectivity without direct exposure to electrical hazards, applicable to single- and multi-phase AC power systems, as well as DC power systems, and is robust against capacitive and inductive loads.

Implementation Method 1

generating a radio frequency (RF) signal at a predetermined frequency using an RF signal generator and transmitting the RF signal across a circuit including a pair of wire leads

Methodology Applied
Scientific EffectRadio frequency signal generation and transmission: Electromagnetic Induction

Implementation Method 2

receiving the RF signal at an RF detector; sensing an output of the RF detector

Methodology Applied
Scientific EffectRadio frequency signal detection: Electromagnetic Induction

Data Source

PatentUS12467958B2Connectivity verification for an absence of voltage tester system
Publication Date: 2025.11.11 PANDUIT CORP
  • US12467958B2 patent drawing
  • US12467958B2 patent drawing
  • US12467958B2 patent drawing

AI summary

A permanently installed absence of voltage tester (AVT) may include a connectivity verification system for verifying the connectivity of system cable leads to the main power lines in electrical equipment. An installed AVT may indicate whether the electrical equipment is in an electrically safe state without first requiring direct access to the equipment. One step in the AVT test procedure may include connectivity verification by the connectivity verification system, which may include a sub-procedure to confirm that the installed AVT is directly coupled as intended with direct connection to the equipment being monitored. The connectivity verification system may validate that the AVT is measuring the actual voltage on the power lines of the electrical equipment and has not registered a no-voltage condition due to an unknown disconnection error or installation failure.