Bidirectional Pre-tensioned Precast Concrete Slabs

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Existing pre-stressed precast concrete slab technologies are limited to pre-tensioning in only one direction, which restricts the length of slabs and increases the number of joints required in roadways, thereby slowing down the installation process and increasing maintenance costs.

Innovation Solution

A method for bi-directional pre-stressing and pre-tensioning concrete slabs by laying metal multi-strand wires both longitudinally and transversely before pouring, with optional post-tensioning after installation, using a specialized casting bed that allows for pre-tensioning in both directions, enabling longer slab lengths and reduced joints.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Length of moving object

If pre-tensioning is applied in only one direction, then the manufacturing process is simpler, but the slab length is limited and the number of joints increases

Engineering Contradiction:
Improveslab lengthVSAvoidpre-tensioning system complexity
Core Design Contradiction:
Length of moving objectVSDevice complexity

Solution Approach 1:

The patent transitions from unidirectional pre-tensioning to bidirectional pre-tensioning by adding transverse tensioning capability to the casting bed. This dimensional expansion allows slabs to be tensioned both longitudinally and transversely, enabling longer slab lengths without proportionally increasing system complexity through modular anchor and jack arrangements.

Inventive Principle:
Principle #17Another dimension (Dimensionality change)

Solution Approach 2:

The pre-tensioning system is segmented into multiple independent tensioning zones along the casting bed, with separate anchor points and hydraulic jacks for different sections. This segmentation allows bidirectional tensioning to be implemented through coordinated activation of discrete tensioning elements rather than requiring a completely integrated complex system.

Inventive Principle:
Principle #1Segmentation

2Productivity

If longer slab lengths are used, then the number of joints is reduced, but the pre-tensioning system becomes more complex

Engineering Contradiction:
Improveinstallation speedVSAvoidcasting bed complexity
Core Design Contradiction:
ProductivityVSDevice complexity

Solution Approach 1:

Bidirectional pre-tensioning is applied during the concrete casting process itself, before the slabs are transported and installed. This preliminary action embeds the tensioning system and anchor points within the concrete matrix during manufacturing, reducing on-site complexity while enabling longer slab lengths that improve installation productivity by reducing joint数量.

Inventive Principle:
Principle #10Preliminary action

3Length of stationary object

If bidirectional pre-tensioning is applied, then slab length can be increased, but the manufacturing process becomes more complex

Engineering Contradiction:
Improveslab lengthVSAvoidmanufacturing process simplicity
Core Design Contradiction:
Length of stationary objectVSEase of manufacture

Solution Approach 1:

The casting bed is designed with multi-functional anchor points and tensioning mechanisms that can apply tension in multiple directions. These universal components serve both longitudinal and transverse pre-tensioning functions, allowing increased slab length capability without proportionally increasing manufacturing process complexity through component multiplicity.

Inventive Principle:
Principle #6Universality (Multi-functionality)

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

This approach allows for longer slab lengths up to 60 feet, minimizing joints and reducing labor and material costs, while enabling faster installation and reduced maintenance, by transferring tension in both directions before the concrete is placed, and allowing for optional post-tensioning at the job site.

Implementation Method 1

When the tension is released, the tension is transferred to the hardened concrete and compression by static friction thus creating concrete in compression

Methodology Applied
Scientific EffectTension transfer through static friction: Static Friction

Implementation Method 2

Post tension cables are deployed through the tubes. Once the concrete hardens, the tendons are anchored at one end and tensioned at the other end using hydraulic jacks or rams

Methodology Applied
Scientific EffectHydraulic pressure: Hydraulic Press

Data Source

PatentUS8636441B2Dual direction pre-stressed pre-tensioned precast concrete slabs and process for same
Publication Date: 2014.01.28 CON-FAB CALIFORNIA CORP
  • US8636441B2 patent drawing
  • US8636441B2 patent drawing
  • US8636441B2 patent drawing

AI summary

A precast roadway slab is pre-tensioned longitudinally and transversely, and may also be post-tensioned. A casting bed has the capability of permitting pre-tensioning of a concrete cast to be carried out within the casting bed in both the longitudinal direction and in the transverse direction. Slots are provided at regular intervals within the side walls and jacking heads of the casting bed for tensioning wires to pass therethrough for pre-tensioning. The process utilizes a multilayer grid of pre-tensioning wires disposed within the casting bed, prior to pouring of the concrete. The cast concrete product can also be made with optional tubular ducts, laid parallel to the longitudinal wires, for post-tensioning subsequent to the cast of the concrete. The post-tensioning of the hardened cast, if called for, takes place at the job site.