Composite Bridge Girder Grid Assembly via Cement Grouting

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Current bridge construction methods face challenges in simplifying the production of girder grids and roadway slab elements, leading to complex and costly processes, especially in welding and transporting large, bulky components, which increases production costs and disrupts traffic routes.

Innovation Solution

A construction method where a girder grid is formed on-site by assembling longitudinal and transverse beams with cement-based grouting, followed by the addition of in-situ concrete to connect the components, allowing for prefabrication of smaller, easily transportable parts and eliminating the need for extensive formwork and weather-sensitive welding.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Productivity

If large and bulky girder grids are transported to the construction site, then the bridge can be assembled quickly, but the production costs increase and traffic routes are disrupted

Engineering Contradiction:
Improveassembly speedVSAvoidproduction cost
Core Design Contradiction:
ProductivityVSQuantity of substance

Solution Approach 1:

The girder grid is divided into individual longitudinal girders and transverse girders that can be manufactured separately and transported independently to the construction site, where they are assembled on-site. This segmentation reduces transport complexity and costs while maintaining assembly efficiency.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The construction process moves from transporting complete three-dimensional girder grids to transporting one-dimensional beam elements that are assembled into the grid structure on-site, reducing spatial requirements and transport costs.

Inventive Principle:
Principle #17Another dimension (Dimensionality change)

2Strength

If welding is used to connect girders, then strong connections are achieved, but the process becomes weather-sensitive and time-consuming

Engineering Contradiction:
Improveconnection strengthVSAvoidconstruction time
Core Design Contradiction:
StrengthVSProductivity

Solution Approach 1:

The welding process is replaced with a casting process using cement-based grout to connect the girders. This substitution eliminates weather sensitivity and reduces construction time while maintaining connection strength through the rigid cement matrix.

Inventive Principle:
Principle #28Mechanics substitution (Replace mechanical system)

Solution Approach 2:

The connection method changes from thermal welding to chemical cementation, altering the fundamental parameters of the joining process to eliminate temperature dependence and weather sensitivity.

Inventive Principle:
Principle #35Parameter changes

3Stability of the object's composition

If extensive formwork is used for concrete construction, then structural integrity is ensured, but the complexity and cost of production increase

Engineering Contradiction:
Improvestructural integrityVSAvoidformwork complexity
Core Design Contradiction:
Stability of the object's compositionVSDevice complexity

Solution Approach 1:

The cement-based grout serves its own formwork function by being contained within the girder assembly gaps themselves, eliminating the need for separate external formwork structures. The grout fills and defines the connection zones without requiring additional shaping equipment.

Inventive Principle:
Principle #25Self-service

4Productivity

If prefabricated parts with large dimensions are used, then fewer components need to be assembled, but transport becomes more difficult and costly

Engineering Contradiction:
Improveassembly efficiencyVSAvoidtransportability
Core Design Contradiction:
ProductivityVSEase of manufacture

Solution Approach 1:

The bridge superstructure is segmented into standardized, smaller-dimensional girder elements that are easier to manufacture and transport, while the modular nature allows for efficient on-site assembly into the complete bridge structure.

Inventive Principle:
Principle #1Segmentation

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

This approach reduces production costs, minimizes traffic disruptions, and enables the construction of bridges with medium spans up to 50 meters, as it simplifies the assembly process, reduces material usage, and allows for high-quality connections under various weather conditions.

Implementation Method 1

at least the side members and the cross members are connected to one another by a cement-based casting

Methodology Applied
Scientific EffectAdhesion: Adhesive

Implementation Method 2

assembling longitudinal and transverse beams with cement-based grouting

Methodology Applied
Scientific EffectCohesion: Cohesion

Implementation Method 3

allowing for prefabrication of smaller, easily transportable parts and eliminating the need for extensive formwork

Methodology Applied
Scientific EffectAdhesion: Adhesive

Data Source

PatentEP2088244B1Reinforced concrete or composite bridge and method for their production
Publication Date: 2013.03.20 SSF INGE
  • EP2088244B1 patent drawingFigure 1
  • EP2088244B1 patent drawingFigure 2a~2b
  • EP2088244B1 patent drawingFigure 3

AI summary

The method involves connecting longitudinal carriers (1) and cross beams (2) to a support grid by grouting, and hardening the grouting. Prefabricated plate elements (4) are positioned on flanks, and are fixed on the support grid by filling of in-situ concrete (5). The support grid is prepared outside of its installation position, and is subsequently placed in the installation position. The cross beams are assembled on upper sides of the longitudinal carriers. The in-situ concrete is applied up to height of upper sides of the cross beams. An independent claim is also included for a system for preparing a steel-concrete composite structure.