Double-Deck Bridge Jig Frame Demounting Method

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Current methods for constructing multi-span double-deck steel structure bridges require a large number of jig frames, leading to high construction costs and prolonged construction periods, as all jig frames are laid before construction and disassembled after completion.

Innovation Solution

A double-deck multi-span bridge construction method that involves mounting and demounting jig frames in a span-separated mode, allowing for the reuse of upper and lower chord jig frames, thereby reducing construction costs and shortening the construction period by enabling simultaneous construction operations on disassembled spans.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Reliability

If all jig frames are laid before construction and disassembled after completion, then the bridge structure can be supported during construction, but the construction cost is high and the construction period is long

Engineering Contradiction:
Improvebridge structure supportVSAvoidconstruction period
Core Design Contradiction:
ReliabilityVSLoss of time

Solution Approach 1:

The patent divides the bridge into multiple spans and applies different construction methods to different spans. The first span uses traditional complete support method, while subsequent spans use a segmented approach where jig frames are disassembled after supporting only the current span construction, allowing parallel construction activities across different spans.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The patent introduces a dynamic construction approach where the support method changes during construction. Jig frames are temporarily installed to support the current span, then disassembled and relocated to support the next span, transforming from a static complete-support system to a dynamic progressive-support system.

Inventive Principle:
Principle #15Dynamics

2Reliability

If all jig frames are laid before construction and disassembled after completion, then the bridge structure can be supported during construction, but the construction cost is high

Engineering Contradiction:
Improvebridge structure supportVSAvoidjig frame quantity
Core Design Contradiction:
ReliabilityVSQuantity of substance

Solution Approach 1:

The patent implements a recovery system where jig frames are not discarded after use but are disassembled, relocated, and reused for supporting the next span construction. This recovering approach reduces the total quantity of jig frames needed from requiring complete replacement to requiring only single-use installation per span.

Inventive Principle:
Principle #34Discarding and recovering

Solution Approach 2:

The patent makes the jig frames universal by designing them to serve multiple functions: first supporting the first span construction, then being relocated to support the second span construction, and potentially reused again. This multi-functionality reduces the total number of jig frames required compared to traditional single-use approach.

Inventive Principle:
Principle #6Universality (Multi-functionality)

3Ease of manufacture

If all jig frames are disassembled at one time, then the construction process is simplified, but the bridge structure cannot digest its internal deformation which may result in warping of the free end of mounting

Engineering Contradiction:
Improveconstruction process simplicityVSAvoidbridge structure deformation control
Core Design Contradiction:
Ease of manufactureVSManufacturing precision

Solution Approach 1:

The patent segments the jig frame disassembly process by span, where each span's jig frames are disassembled and relocated individually rather than all at once. This segmentation allows the bridge structure to progressively adapt to its final position span by span, preventing sudden deformation accumulation that could cause warping.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The patent applies preliminary action by gradually disassembling and relocating jig frames before the bridge construction is complete. This progressive preliminary disassembly allows the structure to gradually digest its internal deformations as each span is completed, preventing the accumulation of deformation that would occur if all jig frames were disassembled simultaneously at the end.

Inventive Principle:
Principle #10Preliminary action

Data Source

PatentUS20240093443A1Double-deck multi-span bridge construction method
Publication Date: 2024.03.21 CHINA CONSTR SCI & IND CORP LTD
  • US20240093443A1 patent drawing
  • US20240093443A1 patent drawing
  • US20240093443A1 patent drawing

AI summary

Disclosed in the present disclosure is a double-deck multi-span bridge construction method. According to the double-deck bridge construction method of the present disclosure, construction is carried out by using a method of disassembling a support jig frame in a graded and span-separated mode, an upper chord jig frame and a lower chord jig frame can be used in a recycle manner, and construction costs are reduced. In addition, a construction period of building the support jig frame is shortened, and other construction operations can be synchronously carried out on a span in which the jig frame is disassembled, for example, fire retardant coating construction can be carried out on a mounted bridge deck after the jig frame is disassembled, and the construction period of a double-deck multi-span bridge is effectively shortened. Additionally, according to the double-deck multi-span bridge construction method in embodiments of the present disclosure, the upper chord jig frame and the lower chord jig frame are disassembled in a graded manner, thereby ensuring that a bridge structure can be smoothly and safely transitioned to a designed stress state.