Bridge Tubular Pile Positioning Platform for Precise Joint Alignment

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Traditional hoisting methods for tubular piles in bridge construction face challenges such as excessive local stress, high equipment usage, prolonged hoisting times, and difficulty in accurately controlling the spatial position and connection of joints, especially in complex environments where large cranes are not feasible.

Innovation Solution

A fabricated rapid construction platform for bridges, comprising a fixing frame, upper-layer and lower-layer tubular pile position control structures, and a console, utilizing telescopic hydraulic rods and gear mechanisms to clamp and adjust the position of tubular piles, enabling precise alignment and rotation for accurate joint connections.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Force

If large cranes are used to hoist tubular piles, then the lifting capacity is sufficient, but the cost increases exponentially and the construction site cannot meet the placement requirements

Engineering Contradiction:
Improvelifting capacityVSAvoidcrane size and cost
Core Design Contradiction:
ForceVSDevice complexity

Solution Approach 1:

The patent divides the tubular pile into multiple sections that can be hoisted separately using smaller, more manageable lifting forces. Each section is then connected on-site through splicing operations, eliminating the need for single large-crane lifts and reducing both crane size requirements and associated costs.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The tubular pile sections are pre-fabricated and prepared at the factory before transportation to the construction site. This preliminary preparation includes creating connection interfaces and ensuring proper alignment features, allowing on-site assembly to proceed efficiently without requiring excessive lifting capacity during the actual installation phase.

Inventive Principle:
Principle #10Preliminary action

2Device complexity

If traditional hoisting methods are used, then simple equipment is required, but excessive local stress is generated on the tubular pile

Engineering Contradiction:
Improvehoisting equipment simplicityVSAvoidlocal stress on tubular pile
Core Design Contradiction:
Device complexityVSStress or pressure

Solution Approach 1:

By dividing the tubular pile into multiple lighter sections, the local stress concentration points are distributed across multiple connection zones rather than concentrating the entire load at single hoisting points. This segmentation allows for more uniform stress distribution during both hoisting and connection operations.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The patent introduces specialized connection structures and splicing mechanisms that act as intermediaries between the hoisting equipment and the tubular pile sections. These intermediary components distribute the lifting forces more evenly across the pile sections and provide controlled stress transfer during connection, preventing excessive local stress while maintaining equipment simplicity.

Inventive Principle:
Principle #24Intermediary (Mediator)

3Device complexity

If traditional hoisting methods are used, then fewer control apparatuses are needed, but accurate adjustment of tubular pile spatial position cannot be achieved

Engineering Contradiction:
Improvenumber of control apparatusesVSAvoidspatial position accuracy of tubular pile
Core Design Contradiction:
Device complexityVSManufacturing precision

Solution Approach 1:

The patent incorporates positioning sensors, measurement devices, and control systems that provide real-time feedback on the spatial position of tubular pile sections during hoisting and assembly. This feedback mechanism enables continuous monitoring and adjustment of position, ensuring precise alignment and placement accuracy while coordinating multiple control apparatuses through automated control loops.

Inventive Principle:
Principle #23Feedback

Solution Approach 2:

The patent employs dynamically adjustable positioning mechanisms that can adapt their control parameters during the assembly process. The control apparatuses can modify their operation in real-time based on the current state of the structure being assembled, allowing for precise spatial positioning even as the configuration changes during construction. This dynamic control enables accurate positioning without requiring an excessive number of static control devices.

Inventive Principle:
Principle #15Dynamics

4Device complexity

If conventional assembly methods are used, then simple procedures are followed, but significant time is consumed in the hoisting process

Engineering Contradiction:
Improveassembly procedure simplicityVSAvoidhoisting process duration
Core Design Contradiction:
Device complexityVSLoss of time

Solution Approach 1:

By pre-fabricating tubular pile sections with connection interfaces and preparation features at the factory, the on-site assembly process is significantly accelerated. The preliminary preparation eliminates time-consuming field fabrication steps and allows for rapid connection of sections using standardized procedures, reducing overall hoisting and assembly time while maintaining procedural simplicity.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

Dividing the tubular pile into pre-fabricated sections enables parallel preparation and transportation of multiple segments before assembly. This segmentation allows different sections to be ready simultaneously, and the modular nature of the sections facilitates quicker connection operations compared to assembling a single large piece, thereby reducing total hoisting process duration while keeping assembly procedures straightforward.

Inventive Principle:
Principle #1Segmentation

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

The platform ensures safe, efficient, and cost-effective installation of tubular piles with precise positional control, allowing for rapid assembly and connection, suitable for various diameters, and reducing the need for large cranes.

Implementation Method 1

Each said control arm comprises a hydraulic cylinder and a control arm, wherein one end of the control arm is connected to the hydraulic cylinder, and the other end of the control arm is provided with a clamping plate

Methodology Applied
Scientific EffectHydraulic pressure: Hydraulic Press

Data Source

PatentUS12618207B2Fabricated rapid construction platform for bridge and control method therefor
Publication Date: 2026.05.05 GUANGXI TRANSPORTATION SCI & TECH GRP CO LTD
  • US12618207B2 patent drawing
  • US12618207B2 patent drawing
  • US12618207B2 patent drawing

AI summary

Provided is a fabricated rapid construction platform for a bridge, including a fixing frame, an upper-layer tubular pile position control structure, a lower-layer tubular pile position control structure, and a console, the fixing frame includes a bottom rail platform, supporting posts, a top operation platform, and several supporting legs; the upper-layer tubular pile position control structure and the lower-layer tubular pile position control structure are provided between the bottom rail platform and the top operation platform; the upper-layer tubular pile position control structure includes two sub-structures arranged symmetrically about the central axis of a second through hole, and each sub-structure includes a braking device, a vertical control arm, and a horizontal control arm. The lower-layer tubular pile position control structure includes an annular frame, a revolution driving device, and four lower control arms.