Cable Anchorage Reinforcement for Eccentric Bridge Girder Connections

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Existing solutions for strengthening cable-to-girder connections in bridges are inadequate when there is significant eccentricity between the cable and girder axes, requiring temporary supports, extensive welding, and de-tensioning/re-tensioning of cables, leading to high costs and complexity.

Innovation Solution

A system using post-tensioned bars and additional steel elements, such as an extended guide pipe and stiffening plates, redistributes forces without de-tensioning cables, minimizing welds and temporary supports, and ensuring load capacity even with substantial eccentricity.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Strength

If traditional strengthening methods (welding additional steel ribs and diaphragms) are used, then the load capacity of cable-to-girder connection is improved, but the device complexity and construction difficulty increase significantly

Engineering Contradiction:
Improveload capacity of cable-to-girder connectionVSAvoidcomplexity of strengthening system
Core Design Contradiction:
StrengthVSDevice complexity

Solution Approach 1:

The strengthening system is divided into modular components: anchor pipes positioned at specific locations, post-tensioned bars as separate tensile elements, and prestressing bars as distinct compressive elements. This segmentation allows each component to perform its specific function independently, simplifying the overall system compared to integrated welded ribs and diaphragms

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The invention extracts the strengthening function from the traditional welded rib-and-diaphragm system and implements it through separate, dedicated elements: anchor pipes for cable anchorage, post-tensioned bars for tensile reinforcement, and prestressing bars for compressive reinforcement. This extraction simplifies construction by allowing independent installation of each element

Inventive Principle:
Principle #2Taking out (Extraction)

2Strength

If extensive full-penetration welds are created inside confined space of deck girder, then the strength of connection is improved, but the ease of manufacture and construction difficulty worsen

Engineering Contradiction:
Improveconnection strengthVSAvoidease of welding in confined space
Core Design Contradiction:
StrengthVSEase of manufacture

Solution Approach 1:

The welding operations are extracted from the confined interior space of the deck girder and relocated to the exterior. Anchor pipes are welded to the outer surface of the deck girder, and post-tensioned bars are installed from outside, eliminating the need for difficult interior welding operations

Inventive Principle:
Principle #2Taking out (Extraction)

Solution Approach 2:

Anchor pipes serve as intermediary elements that connect the cable anchorage system to the deck girder from the exterior. These pipes provide a convenient interface for welding and bar installation, mediating between the cable forces and the girder structure without requiring interior access

Inventive Principle:
Principle #24Intermediary (Mediator)

3Reliability

If temporary piers and cable de-tensioning are used, then the safety during repair is improved, but the loss of time and construction cost increase

Engineering Contradiction:
Improvesafety during repairVSAvoidduration of repair work
Core Design Contradiction:
ReliabilityVSLoss of time

Solution Approach 1:

The strengthening elements (anchor pipes, post-tensioned bars, prestressing bars) are designed and positioned to provide immediate structural support upon installation. The system is configured so that the existing cable tensions can be maintained throughout the repair process, eliminating the need for preliminary de-tensioning actions

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The strengthening system is designed to work with the existing cable tensions rather than requiring them to be reduced. The post-tensioned bars and prestressing bars automatically adjust to the existing load conditions, allowing the structure to support itself during construction without temporary piers

Inventive Principle:
Principle #25Self-service

4Strength

If traditional strengthening methods are used, then the load capacity is improved, but the total cost increases due to labor-intensive welding and temporary supports

Engineering Contradiction:
Improveload capacityVSAvoidconstruction cost
Core Design Contradiction:
StrengthVSEase of manufacture

Solution Approach 1:

The system segments the strengthening function into standardized components (anchor pipes, post-tensioned bars, prestressing bars) that can be manufactured independently and installed systematically. This reduces on-site labor requirements compared to custom-fitted welded ribs and diaphragms

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The invention replaces the labor-intensive welding-based mechanical system with a prestressing-based system. Post-tensioned bars and prestressing bars create forces through tension and compression rather than relying solely on welded connections, reducing the amount of welding required and associated labor costs

Inventive Principle:
Principle #28Mechanics substitution (Replace mechanical system)

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

The system effectively strengthens cable-to-girder connections by redistributing internal forces, increasing load-bearing capacity, and simplifying repairs by eliminating the need for temporary supports and extensive welding, while maintaining structural integrity.

Implementation Method 1

two post-tensioned bars (1, 2) are attached to the flanges of the down - lower strip - deck girder - lower flange (G) of girder and upper strip- deck girder = upper flange (E) of girder and to the already installed side plate - sheet metal (D)

Methodology Applied
Scientific EffectPost-tensioning: Tension

Implementation Method 2

The anchorage pipe, the pipe into which the multi-strand stay-cable is anchored by means of a stressing head, is connected - fixed permanently, e.g. by welding, to a side plate arranged parallel to the webs of the deck girders

Methodology Applied
Scientific EffectWelding: Welding

Implementation Method 3

The system effectively strengthens cable-to-girder connections by redistributing internal forces, increasing load-bearing capacity

Methodology Applied
Scientific EffectForce redistribution: Force

Data Source

PatentEP4671445A1System for strengthening cable anchorage of bridge
Publication Date: 2025.12.31 POLITECHNIKA GDANSKA
  • EP4671445A1 patent drawingFigure 1~2
  • EP4671445A1 patent drawingFigure 3~5
  • EP4671445A1 patent drawingFigure 6~7

AI summary

The invention concerns a system for strengthening cable-to-girder connection in cable-stayed bridges. The system is particularly suitable for retrofitting cable-to-girder connections that exhibited design deficiencies and/or have already undergone significant service induced deterioration.