Problem

Traditional dock construction methods face limitations such as lengthy erection times, difficulties with varying seabed conditions, and imprecise pile lane positioning due to limited reach of foundation equipment designed for solid ground, leading to inefficient and non-optimal deck structures.

Innovation Solution

A dock building apparatus featuring a cantilever arm with a lifting device and foundation building tool, allowing for precise X-Y positioning of piles and deck installation, enabling the construction of docks from the shore with improved reach and efficiency, potentially eliminating the need for marine works.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Length of moving object

If traditional foundation building apparatus is used, then equipment can be installed on solid ground, but reach is limited and cannot access construction area effectively

Engineering Contradiction:
Improvereach of foundation equipmentVSAvoidadaptability to different ground conditions
Core Design Contradiction:
Length of moving objectVSAdaptability or versatility

Solution Approach 1:

The apparatus transitions from ground-based operation to water-based operation by positioning the cantilever arm over the construction area. The support structure extends into the water, allowing the foundation building tool to reach and install piles directly in the construction area, effectively adding a spatial dimension to the equipment's reach capability.

Inventive Principle:
Principle #17Another dimension (Dimensionality change)

Solution Approach 2:

The water is used as an intermediary medium to support the cantilever arm structure. By positioning the support structure in the water rather than on land, the apparatus can bridge the gap between the shore and the construction area, enabling foundation building operations in areas that were previously inaccessible.

Inventive Principle:
Principle #24Intermediary (Mediator)

2Productivity

If traditional methods are used, then construction can proceed, but erection time is lengthy and efficiency is low

Engineering Contradiction:
Improveconstruction efficiencyVSAvoiderection time
Core Design Contradiction:
ProductivityVSLoss of time

Solution Approach 1:

The apparatus is pre-positioned on the shore with the cantilever arm extended over the construction area before pile installation begins. This preliminary positioning eliminates the need for time-consuming on-site assembly and allows immediate commencement of foundation building operations, significantly reducing erection time.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The apparatus enables continuous operation by allowing the foundation building tool to work continuously from the shore-based position over the construction area. There are no interruptions for repositioning equipment or setting up temporary structures, maintaining continuous productive action throughout the construction process.

Inventive Principle:
Principle #20Continuity of useful action

3Manufacturing precision

If foundation equipment is designed for solid ground, then operation is simplified, but positioning precision is insufficient for optimal deck structure

Engineering Contradiction:
Improvepositioning precision of pilesVSAvoidcomplexity of positioning system
Core Design Contradiction:
Manufacturing precisionVSDevice complexity

Solution Approach 1:

The apparatus incorporates positioning systems that provide feedback on the location of the foundation building tool relative to the construction area. This feedback mechanism enables precise positioning of piles by adjusting the tool's position along the cantilever arm, ensuring accurate placement for optimal deck structure while managing system complexity through controlled feedback loops.

Inventive Principle:
Principle #23Feedback

Data Source

PatentUS10179984B2Dock building apparatus and method of construction using the same
Publication Date: 2019.01.15 SOLETANCHE FREYSSINET SAS
  • US10179984B2 patent drawing
  • US10179984B2 patent drawing
  • US10179984B2 patent drawing

AI summary

A dock building apparatus comprises a cantilever arm (11) having a first portion configured to be supported on a ground area and a second portion for overhanging a construction area. The cantilever arm (11) is displaceable perpendicularly to the length of the cantilever arm. The apparatus further includes a lifting device (19) movable along the cantilever arm for bringing construction materials including foundation members from the ground area to the second portion of the cantilever arm, and a foundation building tool (15) movable along the cantilever arm for installing the foundation members in the construction area.