Component Mounting Line Design Device Optimizing Board Production Sequence

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Existing printed circuit board production techniques do not adequately account for the time and effort required to change configurations when producing multiple types of boards, leading to increased overall cycle time.

Innovation Solution

A component mounting line design device calculates and optimizes the change plan to minimize the amount of change work needed when switching between board types, ensuring boards are produced in an order that reduces configuration changes, thereby shortening cycle time.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Productivity

If the component mounting line configuration is optimized for each board type to minimize cycle time, then the cycle time for individual board types is reduced, but the amount of change work when switching between board types increases

Engineering Contradiction:
Improvecycle timeVSAvoidchange work time
Core Design Contradiction:
ProductivityVSLoss of time

Solution Approach 1:

The system pre-calculates and stores the optimal component mounting line configuration for each board type before production begins. By preparing these configurations in advance and calculating the change work required between different configurations, the system can plan the production sequence to minimize total change work time, rather than reacting to configuration changes as they occur during production.

Inventive Principle:
Principle #10Preliminary action

2Adaptability or versatility

If the component mounting line configuration is frequently changed to accommodate different board types, then production flexibility is improved, but the overall production efficiency decreases due to increased change work

Engineering Contradiction:
Improveproduction flexibilityVSAvoidoverall production efficiency
Core Design Contradiction:
Adaptability or versatilityVSProductivity

Solution Approach 1:

The system calculates the change work required between different component mounting line configurations and uses this feedback information to determine the optimal production sequence. By incorporating change work calculations into the production planning process, the system can balance production flexibility with overall efficiency, sequencing board types in an order that minimizes total change work while still accommodating different board type requirements.

Inventive Principle:
Principle #23Feedback

Data Source

PatentEP2268120B1Component mounting line design device, program, and component mounting system
Publication Date: 2017.06.14 YAMAHA MOTOR CO LTD
  • EP2268120B1 patent drawingFigure 1
  • EP2268120B1 patent drawingFigure 2
  • EP2268120B1 patent drawingFigure 3~5

AI summary

To calculate such a change plan of a component mounting line that reduces the amount of change work of the component mounting line in producing a plurality of boards (190) as small as possible. A production sequence calculation section (121) of a component mounting line design device (110) calculates, for each pair of the board types, an amount of work in changing a component mounting line identified by component mounting line information corresponding to one board type contained in the pair to a component mounting line identified by component mounting line information corresponding to other board type contained in the pair and identifies an order of putting into a component mounting line of a board type so as to produce in an order from a board type wherein the amount of work is smaller.