Construction Progress Tracking via Image-Model Superposition
Find Innovative SolutionsGenerate Solutions
Solution Overview
Problem
Current project management systems require significant labor to update construction project progress status accurately and in a timely manner, as they often rely on manual input of information.
Innovation Solution
A project management apparatus and method that acquires on-site images and engineering model data, generates a composite image by superimposing the data, and allows users to input progress information directly on a display screen, reducing the need for manual documentation and streamlining the update process.
Engineering Contradictions & Design Principles
Engineering Contradiction Analysis
1Productivity
If manual input methods are used to update progress information, then information can be entered into the system, but the labor required and time consumed increase significantly
Solution Approach 1:
The system automatically captures progress information by acquiring on-site images and matching them with engineering model data, eliminating the need for manual data entry. The progress status is updated self-service style through automated image recognition and data matching processes.
Solution Approach 2:
The patent replaces manual mechanical input operations with automated image-based recognition systems. Cameras capture on-site images, and image processing algorithms automatically extract progress information, substituting human manual entry with automated optical and computational systems.
2Measurement precision
If detailed progress information is tracked for each component, then project management accuracy improves, but the complexity of data collection and input increases
Solution Approach 1:
The system uses a universal image-based approach that can track multiple components and work units simultaneously through a single imaging process. The same camera and image processing pipeline serve multiple measurement and tracking functions across different components, reducing overall system complexity.
Solution Approach 2:
The patent introduces an image database as an intermediary layer between the physical construction site and the progress management system. Images serve as a universal mediator that captures information about multiple components, which then gets automatically matched with engineering model data to update progress status.
3Ease of operation
If progress updates are delayed to reduce input workload, then labor requirements decrease, but the accuracy and timeliness of project management deteriorate
Solution Approach 1:
The system enables continuous progress monitoring by automatically capturing on-site images and updating progress status in real-time or near-real-time. The automated image acquisition and processing pipeline maintains continuous operation without requiring periodic manual intervention, ensuring both timeliness and operational simplicity.
Solution Approach 2:
The system provides automated feedback by comparing on-site images with engineering model data and immediately updating progress status. This closed-loop feedback mechanism ensures that progress information is continuously validated and updated, maintaining reliability while eliminating manual input requirements.
Data Source
AI summary
Provided is a project management apparatus including: a first acquisition unit configured to acquire an on-site image obtained by photographing a construction site in which an installation object is to be constructed; a second acquisition unit configured to acquire engineering model data on each of a plurality of components forming the installation object; a display control unit configured to display, on a display apparatus, a composite image obtained by superimposing the engineering model data on the on-site image; and a reception unit configured to receive an operation of a user, wherein the display control unit is configured to display, based on the operation performed on the composite image by the user, a display screen for causing the user to input information relating to progress of a work unit containing a work of a component corresponding to the engineering model data selected by the user, on the display apparatus.