Problem

Existing anchor elements that protrude from drilled holes in materials pose safety risks and obstacles when their required length is slightly longer than standard lengths, and custom-tailored lengths are costly.

Innovation Solution

Cutting the protruding portion of standard-length anchor elements to the required length and covering it with a protective cap, using an adhesive material to ensure safety and durability, while allowing for reliable anchoring and reduced production costs.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Ease of manufacture

If a standard-length anchor element is used, then production cost is reduced, but the projecting portion becomes too long and represents a safety risk and/or obstacle

Engineering Contradiction:
Improveproduction costVSAvoidsafety risk
Core Design Contradiction:
Ease of manufactureVSObject-affected harmful factors

Solution Approach 1:

The anchor element is divided into two parts: a standardized anchor portion that remains in the material and a separate protective cap that covers the projecting portion. This segmentation allows the anchor element to be manufactured in standard lengths while eliminating the safety risk of the projecting portion through the protective cap.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

A protective cap is introduced as an intermediary component between the anchor element and the environment. This protective cap covers the projecting portion, eliminating the safety risk and obstacle problems while allowing the use of cost-effective standard-length anchor elements.

Inventive Principle:
Principle #24Intermediary (Mediator)

2Manufacturing precision

If a custom-tailored length anchor element is manufactured, then the projecting portion length is precisely matched to requirements, but production costs are high

Engineering Contradiction:
Improvelength precisionVSAvoidproduction cost
Core Design Contradiction:
Manufacturing precisionVSEase of manufacture

Solution Approach 1:

The solution segments the anchor element into a standardized mass-produced anchor portion and a separate protective cap. This allows the anchor element to be manufactured in standard lengths at low cost, while the protective cap provides the necessary length customization and protection without increasing anchor element production costs.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

Instead of changing the manufacturing parameters of the anchor element itself, the solution changes the state of the projecting portion by covering it with a protective cap. This parameter change approach maintains cost-effectiveness while achieving the desired length precision and safety.

Inventive Principle:
Principle #35Parameter changes

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

Ensures safe, reliable, and cost-effective anchoring without safety risks or obstacles, with enhanced protection against environmental factors and improved anchoring strength.

Implementation Method 1

The protective cap is attached to the projecting section by means of an adhesive material (24)

Methodology Applied
Scientific EffectAdhesive bonding: Adhesive

Data Source

PatentEP3971426B1Method for setting an anchor element and arrangement comprising such an anchor element in a material
Publication Date: 2025.07.30 TOGE DUBEL
  • EP3971426B1 patent drawingFigure 1
  • EP3971426B1 patent drawingFigure 2
  • EP3971426B1 patent drawingFigure 3

AI summary

An arrangement is designed with an anchor element (4) anchored in a borehole (3) in a material (2), which protrudes from the borehole (3) with a cut-off overhang section (Au') to which a protective cap (22) is attached.