Diffusion Bonded Fluid Delivery System for Semiconductor Processing

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

In semiconductor processing, existing fluid delivery systems face challenges in maintaining high leak integrity and corrosion resistance, particularly when handling toxic and corrosive gases like hydrogen and helium, due to the generation of particulates from rough surfaces and dead spaces in machined manifolds, which can lead to safety hazards and system downtime.

Innovation Solution

A diffusion bonding method is employed to fabricate fluid delivery systems using stainless steel sheets, involving pattern etching, electropolishing, grinding, and precise alignment, followed by uni-axial or HIP diffusion bonding at controlled temperatures and pressures to create a leak-tight, corrosion-resistant structure with reduced particulate generation and dead space.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Manufacturing precision

If traditional machining methods are used to manufacture fluid delivery manifolds, then manufacturing simplicity is maintained, but particulate generation increases and surface smoothness deteriorates

Engineering Contradiction:
Improvesurface smoothnessVSAvoidparticulate generation
Core Design Contradiction:
Manufacturing precisionVSObject-generated harmful factors

Solution Approach 1:

The patent replaces traditional mechanical machining operations with diffusion bonding technology. Instead of machining manifolds from solid blocks (which generates particulates), the invention uses diffusion bonding to assemble pre-formed, smooth-surfaced components, thereby eliminating particulate generation during manufacturing while achieving the desired structural integrity and fluid flow characteristics.

Inventive Principle:
Principle #28Mechanics substitution (Replace mechanical system)

Solution Approach 2:

The patent changes the manufacturing approach from subtractive machining to additive diffusion bonding. By controlling parameters such as bonding temperature, pressure, and time, the process achieves smooth surfaces and high precision without the particulate generation inherent in traditional machining methods.

Inventive Principle:
Principle #35Parameter changes

2Reliability

If diffusion bonding is used to manufacture fluid delivery systems, then leak integrity and corrosion resistance are improved, but manufacturing complexity increases

Engineering Contradiction:
Improveleak integrityVSAvoidmanufacturing complexity
Core Design Contradiction:
ReliabilityVSDevice complexity

Solution Approach 1:

The patent divides the fluid delivery system into multiple separable components that are manufactured independently and then joined through diffusion bonding. This segmentation allows each component to be optimized and manufactured separately using standard techniques, reducing overall manufacturing complexity while achieving high leak integrity through the diffusion-bonded joints.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The diffusion bonding process acts as an intermediary technique that joins components with molecular-level bonding. This intermediate process creates bonds that are as strong as or stronger than the base material, achieving high reliability without requiring complex welding or brazing operations.

Inventive Principle:
Principle #24Intermediary (Mediator)

3Reliability

If diffusion bonding is used to create leak-tight structures, then helium leak rate is reduced, but processing time and system downtime increase

Engineering Contradiction:
Improvehelium leak rateVSAvoidsystem downtime
Core Design Contradiction:
ReliabilityVSLoss of time

Solution Approach 1:

The patent performs preliminary preparation of bonding surfaces including cleaning, polishing, and positioning before the diffusion bonding process. This preliminary action ensures that the actual bonding operation is quick and efficient, reducing overall processing time while achieving the required helium leak rate of 1×10^-9 cc/sec or better.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The patent optimizes diffusion bonding parameters such as temperature, pressure, and time to achieve the desired leak integrity in the shortest possible time. By carefully controlling these parameters, the process achieves helium leak rates of 1×10^-9 cc/sec while minimizing system downtime through efficient processing cycles.

Inventive Principle:
Principle #35Parameter changes

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

The method produces a fluid delivery system with enhanced mechanical strength, corrosion resistance, and high leak integrity, meeting stringent semiconductor industry standards, including a helium leak rate of 1×10−9 cc/sec, while minimizing particulate generation and system downtime.

Implementation Method 1

A diffusion bonding method is employed to fabricate fluid delivery systems using stainless steel sheets, involving pattern etching, electropolishing, grinding, and precise alignment, followed by uni-axial or HIP diffusion bonding at controlled temperatures and pressures to create a leak-tight, corrosion-resistant structure

Methodology Applied
Scientific EffectDiffusion bonding: Diffusion Welding

Data Source

PatentUS7798388B2Method of diffusion bonding a fluid flow apparatus
Publication Date: 2010.09.21 APPLIED MATERIALS INC
  • US7798388B2 patent drawing
  • US7798388B2 patent drawing
  • US7798388B2 patent drawing

AI summary

The present invention relates to a method of diffusion bonding of steel and steel alloys, to fabricate a fluid delivery system of the kind which would be useful in semiconductor processing and in other applications which require high purity fluid handling.