Dynamic Project Activity Prioritization and Object Resizing

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Existing project management software lacks the ability to dynamically modify templates and prioritize activities effectively, leading to inefficiencies in project execution and resource allocation in the construction industry.

Innovation Solution

A computer-implemented method that prioritizes daily project activities based on attributes like early start, total float, and breakability, and allows for resizing of project objects, using a database-driven application platform to optimize activity scheduling and resource allocation.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Adaptability or versatility

If existing project management software uses manual data input for template modification, then the software can maintain a library of templates, but it lacks the ability to dynamically modify templates

Engineering Contradiction:
Improvetemplate modification capabilityVSAvoidsoftware system complexity
Core Design Contradiction:
Adaptability or versatilityVSDevice complexity

Solution Approach 1:

The patent implements dynamic template modification by allowing project managers to change template parameters (such as activity attributes, scheduling constraints, and resource allocation rules) in real-time based on project needs, transforming static templates into adaptable frameworks that evolve with project requirements

Inventive Principle:
Principle #15Dynamics

Solution Approach 2:

The system enables modification of template parameters including activity duration, start dates, resource requirements, and scheduling constraints, allowing templates to be customized for different project scenarios without requiring complete template recreation

Inventive Principle:
Principle #35Parameter changes

2Loss of information

If project management software processes multiple daily activities with multiple attributes, then comprehensive project information is available, but prioritizing activities becomes complex and time-consuming

Engineering Contradiction:
Improveproject information completenessVSAvoidactivity prioritization time
Core Design Contradiction:
Loss of informationVSLoss of time

Solution Approach 1:

The system pre-calculates and stores key attributes for each activity (total float, early start, late start, critical path status) before prioritization is needed, so that when daily activity prioritization is required, the system can quickly retrieve and process this pre-prepared information without time-consuming calculations

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The patent applies a systematic prioritization methodology that transforms multiple activity attributes into a unified priority ranking system, converting complex multi-dimensional activity data into actionable priority levels that guide daily project execution

Inventive Principle:
Principle #35Parameter changes

3Manufacturing precision

If project management software provides detailed activity attributes and scheduling information, then scheduling accuracy is improved, but resource allocation efficiency decreases

Engineering Contradiction:
Improvescheduling accuracyVSAvoidresource allocation efficiency
Core Design Contradiction:
Manufacturing precisionVSProductivity

Solution Approach 1:

The system dynamically adjusts resource allocation based on activity priority rankings derived from detailed scheduling attributes, automatically reassigning resources to high-priority activities while maintaining accurate scheduling information, thus balancing scheduling precision with resource utilization efficiency

Inventive Principle:
Principle #35Parameter changes

Data Source

PatentUS20240185183A1System and process for a real-time project management platform
Publication Date: 2024.06.06 ABRAHAM CYRIAC
  • US20240185183A1 patent drawing
  • US20240185183A1 patent drawing
  • US20240185183A1 patent drawing

AI summary

A computer implemented project management application is disclosed. The application can include a method for prioritizing for a current day each respective activity of a plurality of daily activities identified for a project. The application can include a method for resizing a size, shape, or configuration of an object used in a construction project. The application can include a method for selecting activities and resources for a project comprising a plurality of activities and a plurality of resources.