Generator Set Circuit Breaker Synchronization Testing Before Grid Connection

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The synchronization grid-connection of newly-built generator set outlet switch apparatus is often marred by issues such as poor device manufacturing, poor mounting quality, and inappropriate parameter setting, leading to potential burn-out of the generator and outlet switch apparatus due to non-synchronization closing.

Innovation Solution

A method and apparatus for synchronization test of a generator set outlet switch apparatus that includes determining the correctness of the wiring phase sequence, checking for synchronous three-phase closings, measuring and recording two-side voltage waveform data, and evaluating the synchronization closing performance using a simulated quality coefficient.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Productivity

If synchronization grid-connection is performed without prior verification, then the startup process is faster, but the generator and outlet switch apparatus may burn out due to non-synchronization closing

Engineering Contradiction:
Improvestartup speedVSAvoidsynchronization closing reliability
Core Design Contradiction:
ProductivityVSReliability

Solution Approach 1:

The patent implements preliminary verification actions before synchronization grid-connection, including checking wiring phase sequence correctness, verifying synchronous three-phase closings, and measuring voltage waveform data. These preliminary checks ensure synchronization closing reliability is confirmed before actual grid-connection occurs, preventing burnout while maintaining efficient startup through automated testing procedures.

Inventive Principle:
Principle #10Preliminary action

2Reliability

If comprehensive synchronization testing is performed, then the synchronization closing performance is verified, but the testing time and complexity increase

Engineering Contradiction:
Improvesynchronization closing performance verificationVSAvoidtesting time
Core Design Contradiction:
ReliabilityVSLoss of time

Solution Approach 1:

The patent replaces complex manual testing procedures with automated electronic testing systems. The synchronization testing apparatus automatically checks wiring phase sequences, measures voltage waveform data, and evaluates synchronization closing performance through computerized analysis, significantly reducing testing time while maintaining comprehensive verification of synchronization closing performance.

Inventive Principle:
Principle #28Mechanics substitution (Replace mechanical system)

3Manufacturing precision

If detailed parameter checking is performed, then the manufacturing and mounting quality is verified, but the testing complexity increases

Engineering Contradiction:
Improvedevice quality verificationVSAvoidtesting apparatus complexity
Core Design Contradiction:
Manufacturing precisionVSDevice complexity

Solution Approach 1:

The patent designs a universal testing apparatus that can perform multiple verification functions through integrated modules. The system checks wiring phase sequences, measures voltage waveforms, analyzes synchronization closing timing, and evaluates overall performance using a single multi-functional device, reducing testing complexity while maintaining comprehensive quality verification capabilities.

Inventive Principle:
Principle #6Universality (Multi-functionality)

Data Source

PatentUS12422483B2Generator set circuit breaker apparatus synchronization test method and apparatus, device, and medium
Publication Date: 2025.09.23 CSG POWER GENERATION CO LTD MAINT & TEST CO
  • US12422483B2 patent drawing
  • US12422483B2 patent drawing
  • US12422483B2 patent drawing

AI summary

A method of synchronization test of a generator set outlet switch apparatus includes that: prior to a synchronization grid-connected closing of an outlet switch apparatus of a target generator set, a wiring phase sequence of a synchronization apparatus is determined to be correct; then three-phase closings of the outlet switch apparatus are determined to be synchronous; two-side voltage waveform data at a closing moment of the outlet switch apparatus is measured and recorded; and a simulated synchronization closing quality coefficient of the outlet switch apparatus of the target generator set is determined according to the two-side voltage waveform data, and a synchronization closing performance of the outlet switch apparatus of the target generator set is evaluated according to the simulated synchronization closing quality coefficient.