GLDA Salt Viscosity Control in Hydraulic Fracturing Fluids

Solution Overview

Problem

Current hydraulic fracturing gels in low-permeability subterranean formations face challenges in transporting large-sized or large quantities of proppant due to insufficient viscosity at ambient temperatures, and existing rheology modifiers do not provide sufficient flexibility in viscosity control for optimal well treatment.

Innovation Solution

A well servicing fluid comprising a GLDA salt, a viscosifying agent, and a crosslinker is used, where the GLDA salt contains a metal cation chelated with a GLDA anion, allowing for controlled viscosity increase and subsequent decrease through chelation, enabling efficient proppant transport and fracture management.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Quantity of substance

If cross-linkers are used to increase fluid viscosity, then proppant transport capability is improved, but gel removal difficulty increases

Engineering Contradiction:
Core Design Contradiction:
Quantity of substanceVSEase of repair

Solution Approach 1:

The patent employs a breakdown agent that chemically modifies the cross-linked gel structure by breaking cross-links between polymer chains. This parameter change transforms the gel from a highly viscous cross-linked state to a lower viscosity non-cross-linked state, enabling easy removal after proppant transport is complete

Inventive Principle:
Principle #35Parameter changes

Solution Approach 2:

The fluid system dynamically transitions between two viscosity states: initially maintaining high viscosity through cross-linking for proppant transport, then switching to low viscosity through breakdown agent action for easy removal. This dynamic property allows the same fluid to serve dual functions at different stages

Inventive Principle:
Principle #15Dynamics

2Volume of moving object

If gel viscosity is increased for proppant transport, then fracture width increases, but gel removal becomes more difficult

Engineering Contradiction:
Core Design Contradiction:
Volume of moving objectVSEase of repair

Solution Approach 1:

The breakdown agent chemically alters the gel structure by cleaving cross-links, changing the viscosity parameter from high to low. This allows the gel to have been high-viscosity during injection to create wide fractures, then becomes low-viscosity for easy cleanup

Inventive Principle:
Principle #35Parameter changes

Solution Approach 2:

The breakdown agent selectively removes the cross-linking component from the gel structure without affecting the polymer backbone or proppant. This extraction of the cross-linking function reduces viscosity while preserving the gel's ability to have created wide fractures

Inventive Principle:
Principle #2Taking out (Extraction)

3Loss of time

If cross-linking delay additives are used, then viscosity development timing is controlled, but fluid composition complexity increases

Engineering Contradiction:
Core Design Contradiction:
Loss of timeVSDevice complexity

Solution Approach 1:

The breakdown agent is pre-incorporated into the fracturing fluid composition in an inactive or dormant state. Upon injection into the formation, it becomes activated and begins breaking cross-links. This preliminary inclusion allows timing control without requiring separate delayed-action mechanisms

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The breakdown agent is designed to automatically activate and function based on down-hole conditions (temperature, pressure, chemical environment) without requiring additional control mechanisms or complex timing devices. The fluid system self-regulates the breakdown timing through the inherent properties of the breakdown agent

Inventive Principle:
Principle #25Self-service

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

The solution achieves a significant reduction in viscosity, facilitating the transport of larger proppant sizes and quantities while maintaining desirable gel properties during fracturing, thereby enhancing hydrocarbon production and simplifying gel removal.

Implementation Method 1

viscosity of the well servicing fluid in the well is decreased to a second viscosity less than the first viscosity by chelating the crosslinker with the GLDA anion, which counteracts the crosslinking

Methodology Applied
Scientific EffectChelation:

Data Source

PatentUS10233385B2Well treatment methods and fluids with GLDA salt
Publication Date: 2019.03.19
  • US10233385B2 patent drawing
  • US10233385B2 patent drawing

AI summary

A well servicing fluid includes ingredients including a GLDA salt, a crosslinker, and a viscosifying agent that is not crosslinked by the crosslinker. A well treatment method includes forming a well servicing fluid with ingredients including a GLDA salt, a viscosifying agent, and a crosslinker, the GLDA salt containing a metal cation chelated with a GLDA anion. The well servicing fluid is inserted into a well in a formation. The method includes crosslinking the viscosifying agent and attaining a first viscosity of the well servicing fluid using the crosslinker. After the attaining of the first viscosity, viscosity of the well servicing fluid in the well is decreased to a second viscosity less than the first viscosity by using the GLDA anion. The GLDA salt may be a GLDA calcium salt and the crosslinker may be a zirconium crosslinker.