Problem

In HVDC power transmission systems, faults on DC power transmission lines can lead to prolonged damping of transient currents, particularly in VSC-based systems with half-bridge cells, necessitating a longer time for pole isolation and disrupting active and reactive power transmission.

Innovation Solution

An interface arrangement with at least two poles, including a converter, a circuit breaker, and a neutral bus line with a switching element, allows for quick damping of transient currents by entering a blocking mode and disconnecting from the ground electrode, facilitating rapid fault clearance and pole isolation.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Power

If VSC-based converters with half-bridge cells are used in HVDC systems, then power transmission capability is improved, but fault clearance time increases due to inability to rapidly damp transient currents

Engineering Contradiction:
Improvepower transmission capabilityVSAvoidfault clearance time
Core Design Contradiction:
PowerVSLoss of time

Solution Approach 1:

A neutral bus switching element is introduced as an intermediary component between the converter and ground electrode. This switching element enables rapid disconnection of the neutral bus during faults, allowing transient currents to be quickly damped to zero without requiring the converter itself to have current breaking capability, thus resolving the contradiction between maintaining power transmission capability and reducing fault clearance time

Inventive Principle:
Principle #24Intermediary (Mediator)

Solution Approach 2:

The fault isolation function is segmented into two independent parts: (1) the converter valve which maintains power transmission capability, and (2) the neutral bus switching element which handles fault clearance. This segmentation allows each component to be optimized for its specific function without compromising the other

Inventive Principle:
Principle #1Segmentation

2Device complexity

If conventional protection systems are used without neutral bus switching elements, then device complexity is reduced, but transient current damping time increases

Engineering Contradiction:
Improveprotection system complexityVSAvoidtransient current damping duration
Core Design Contradiction:
Device complexityVSDuration of action of moving object

Solution Approach 1:

The neutral bus switching element acts as a simple intermediary that provides rapid fault isolation by disconnecting the neutral bus from ground. This adds minimal complexity to the protection system while dramatically reducing transient current damping time from seconds to milliseconds

Inventive Principle:
Principle #24Intermediary (Mediator)

Solution Approach 2:

The neutral bus switching element is pre-configured and ready to operate immediately upon fault detection. By having the switching element in place beforehand, the system can rapidly respond to faults without requiring complex real-time control algorithms, thus reducing damping time with minimal added complexity

Inventive Principle:
Principle #10Preliminary action

Data Source

PatentUS10374412B2Method and arrangement for facilitating clearing of a pole fault and isolation of a faulted pole in a power transmission system
Publication Date: 2019.08.06 HITACHI ENERGY LTD
  • US10374412B2 patent drawing
  • US10374412B2 patent drawing
  • US10374412B2 patent drawing

AI summary

A control unit rod interface arrangement couples between AC and DC power systems. The interface includes at least two poles for coupling between the DC and AC power systems. Each of the poles includes a converter for conversion between AC and DC power. If a fault has occurred in one of the poles, a transient current, or fault current, may flow through a neutral bus line connected to the pole, the pole's converter and the location of the fault in the pole. Such a transient or fault current should preferably be damped out as quickly as possible, after which the pole may be electrically isolated from the other components of the interface arrangement. Such a transient or fault current may be damped out relatively quickly by opening of a neutral bus switching element of the neutral bus line connected to the pole after the converter has entered a blocking mode and a circuit breaker at the AC side of the converter has been opened so as to effect discontinuation of flow of current between the AC side of the converter and the AC power system.