Industrial Status Viewer for Project Schedule Visualization

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Conventional project management tools, such as Gantt charts, fail to accurately represent the magnitude of behind-schedule conditions and lack detail in visualizing the status of equipment and structural elements, leading to miscommunication of resource utilization and project progress.

Innovation Solution

A computer-based industrial status viewer system that generates progress views by processing project schedule and CAD drawing files, depicting expected and actual completion percentages of tasks and operations, with interactive features to highlight deviations and allow user control over view content.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Loss of information

If conventional Gantt charts are used to represent project schedules, then the schedule can be visualized, but the magnitude of behind-schedule conditions is miscommunicated and detail in equipment status is lost

Engineering Contradiction:
Improveproject progress informationVSAvoidvisualization system complexity
Core Design Contradiction:
Loss of informationVSDevice complexity

Solution Approach 1:

The patent combines multiple data sources (project management software data, CAD drawings, bar coding systems) into a single integrated visualization system. The industrial status viewer merges schedule information with visual representations of equipment and structural elements, creating a unified view that preserves both macro schedule status and micro equipment details without requiring separate systems.

Inventive Principle:
Principle #5Merging (Combining)

Solution Approach 2:

The patent introduces bar code labels as intermediary elements that link physical equipment/structural elements to their digital representations in the visualization system. These bar codes serve as mediators between the physical project elements and the software-generated visual indicators, enabling accurate tracking and visualization without direct complex integration between all system components.

Inventive Principle:
Principle #24Intermediary (Mediator)

2Loss of information

If detailed equipment and structural element status is visualized, then communication of resource utilization improves, but the system complexity increases

Engineering Contradiction:
Improveresource utilization informationVSAvoidvisualization system complexity
Core Design Contradiction:
Loss of informationVSDevice complexity

Solution Approach 1:

The patent applies local quality by providing different levels of visual detail for different project elements based on their importance and status. Critical equipment and structural elements receive detailed visual indicators showing specific completion percentages and resource utilization, while less critical elements receive simplified representations. This selective detail approach communicates essential resource information without overwhelming the viewer with uniform complexity across all elements.

Inventive Principle:
Principle #3Local quality

3Loss of information

If the visualization system includes all project elements, then complete project status is achieved, but the clarity of individual element status is reduced

Engineering Contradiction:
Improveproject status informationVSAvoidstatus deviation visibility
Core Design Contradiction:
Loss of informationVSMeasurement precision

Solution Approach 1:

The patent segments the project visualization into distinct hierarchical levels: overall project schedule view, equipment-level status views, and structural element views. Each segment can be examined independently with appropriate visual indicators. The system allows users to drill down from high-level schedule information to detailed equipment status by interacting with specific elements, maintaining measurement precision for individual elements while providing complete project status through the segmented structure.

Inventive Principle:
Principle #1Segmentation

4Ease of operation

If traditional scheduling tools are used, then schedule management is simplified, but the ability to communicate magnitude of delays and resource utilization is insufficient

Engineering Contradiction:
Improveschedule management easeVSAvoidproject progress communication
Core Design Contradiction:
Ease of operationVSLoss of information

Solution Approach 1:

The patent creates a universal visualization system that works with multiple project management software platforms (Primavera P6, Microsoft Project, Oracle Applications) and integrates various data sources (CAD drawings, bar coding systems). The industrial status viewer serves multiple functions: it displays schedule progress, tracks equipment status, monitors resource utilization, and provides visual alerts for delays. This multi-functional approach maintains ease of operation by accepting standard project data formats while dramatically improving project progress communication through unified visual indicators.

Inventive Principle:
Principle #6Universality (Multi-functionality)

Data Source

PatentUS8275653B2Industrial status viewer system and method
Publication Date: 2012.09.25 VARDAMAN
  • US8275653B2 patent drawing
  • US8275653B2 patent drawing
  • US8275653B2 patent drawing

AI summary

A method of providing industrial status views reflecting a schedule for industrial project plan generated by a project schedule planning and management application includes uploading the industrial project plan schedule, uploading CAD drawing files comprising a physical layout of resources, structural elements and equipment units included in the project plan schedule, extracting project data from the uploaded project schedule and CAD drawing files and generating Plan progress views that reflect expected completion percentages of intended project tasks and operations over a fixed industrial project timeline, according to the plan schedule, as well as Comparison progress views depicting a difference between the expected and actual project progress.