Continuous Metal Foam Composite Panel Production

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The production of metal foam composite bodies is inefficient and expensive due to the lack of a systematic approach for multi-shift utilization, resulting in high costs and limited productivity in manufacturing precisely shaped panels.

Innovation Solution

A continuous production method using a production line with a quasi-continuous infrared oven and a calibration press, where prefabricated aluminum foam body elements are inserted between cover layers, heated to the reaction temperature, and then cooled, allowing for precise control of foaming conditions and homogeneous metallurgical connections between layers.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Productivity

If individual manufacturing without systematic approach is used, then manufacturing flexibility is maintained, but productivity and efficiency deteriorate

Engineering Contradiction:
Improveproduction efficiencyVSAvoidsystem complexity
Core Design Contradiction:
ProductivityVSDevice complexity

Solution Approach 1:

The production process is divided into distinct segments: powder mixing station, axial pressing station, foaming station, and cooling station. Each station performs a specific function in the continuous production line, enabling multi-shift utilization and high productivity while maintaining process control.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The patent implements a continuous production line where aluminum foam body elements are continuously produced through sequential operations (mixing, pressing, foaming, cooling) without interruption. The system allows multi-shift utilization with continuous operation, eliminating downtime between production cycles.

Inventive Principle:
Principle #20Continuity of useful action

2Manufacturing precision

If axial compression molding is used to produce aluminum foam body elements, then material density is improved, but production speed deteriorates

Engineering Contradiction:
Improvedimensional accuracyVSAvoidproduction speed
Core Design Contradiction:
Manufacturing precisionVSProductivity

Solution Approach 1:

Aluminum foam body elements are pre-formed with precise dimensions through axial compression molding before being placed in the foaming mold. This preliminary shaping ensures dimensional accuracy is achieved during the compression stage, allowing the subsequent foaming process to proceed rapidly without compromising precision.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The patent replaces traditional slow mechanical foaming processes with a rapid chemical foaming mechanism. Aluminum powder mixed with blowing agent (e.g., TiH2) undergoes exothermic reaction upon heating, generating gas that rapidly expands the foam structure, significantly reducing production time while maintaining dimensional control.

Inventive Principle:
Principle #28Mechanics substitution (Replace mechanical system)

3Reliability

If conventional foaming process is used, then foaming completeness is achieved, but production time increases

Engineering Contradiction:
Improvefoaming completenessVSAvoidproduction cycle time
Core Design Contradiction:
ReliabilityVSLoss of time

Solution Approach 1:

The patent optimizes foaming parameters including temperature (heating to reaction temperature of blowing agent), pressure (maintaining pressure during foaming), and time (predetermined foaming duration). These parameter changes enable complete foaming to occur rapidly in a controlled manner, reducing production cycle time while ensuring thorough foam formation.

Inventive Principle:
Principle #35Parameter changes

Solution Approach 2:

The conventional slow mechanical or thermal diffusion foaming is replaced with rapid chemical reaction-based foaming. The exothermic reaction of aluminum powder with blowing agent generates immediate gas expansion, achieving complete foaming in minutes rather than hours, thus maintaining reliability while dramatically reducing production time.

Inventive Principle:
Principle #28Mechanics substitution (Replace mechanical system)

4Strength

If metallurgically integral bonding is used for cover layers, then structural strength is improved, but manufacturing complexity increases

Engineering Contradiction:
Improvestructural strengthVSAvoidmanufacturing process complexity
Core Design Contradiction:
StrengthVSDevice complexity

Solution Approach 1:

The patent combines the foaming process with metallurgical bonding in a single integrated operation. Cover layers are placed on the foaming mold, and during the heating and foaming process, the molten aluminum from the expanding foam metallurgically bonds to the cover layers, achieving structural strength without requiring separate bonding operations or complex assembly equipment.

Inventive Principle:
Principle #5Merging (Combining)

Solution Approach 2:

The metallurgical bonding occurs continuously during the foaming process itself, rather than as a separate discrete step. The heat required for foaming simultaneously enables the metallurgical reaction between aluminum foam and cover layers, maintaining continuous production flow while achieving strong structural bonds.

Inventive Principle:
Principle #20Continuity of useful action

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

This method enables the high-productivity, continuous production of dimensionally precise metal foam composite panels with improved aesthetic appeal and structural strength, reducing costs by optimizing the foaming process and eliminating the need for additives like adhesives or screws.

Implementation Method 1

introduced between the cover layers and then continuously inserted into an infrared oven for foaming

Methodology Applied
Scientific EffectInfrared radiation: Infrared Radiation

Implementation Method 2

heated to the reaction temperature of the aluminum foam body element(s)... the sandwich panels being subjected to geometry-dependent targeted heat input up to the reaction temperature

Methodology Applied
Scientific EffectPhase change: Phase Change

Implementation Method 3

an aluminum metal powder is mixed with a blowing agent, e.g. TiH2, and then compressed... after heating the foam mold or the component with the foam material, the component is foamed

Methodology Applied
Scientific EffectChemical reaction: Chemical Bonding

Implementation Method 4

the sandwich panels are then transferred by a handling device to a downstream inline calibration press, then guided through a cooling tunnel

Methodology Applied
Scientific EffectCompression: Compression

Data Source

PatentEP3100803B1Method and apparatus for manufacturing metal foam composite bodies
Publication Date: 2020.07.15 HAVEL METAL FOAM GMBH
  • EP3100803B1 patent drawingFigure 1
  • EP3100803B1 patent drawingFigure 2
  • EP3100803B1 patent drawingFigure 3

AI summary

The invention relates to a method for the continuous production of metal foam composite panels in a production line, in particular metal foam composite panels as sandwich panels, with aluminum face sheets and an aluminum foam core between the face sheets, wherein prefabricated sandwich panels are continuously passed through an infrared oven, a plurality of, preferably extruded, aluminum foam core elements are inserted between the face sheets, and the sandwich panels are passed through a plurality of controllable temperature zones in the infrared oven, wherein the sandwich panels are heated with geometry-dependent targeted heat input up to the reaction temperature of the aluminum foam core elements and held at a stabilization temperature for a predetermined period to form a homogeneous metallic bond between the face sheets and a core formed from the aluminum foam core elements.The closed-cell aluminium foam body between these and the sandwich panels is transferred by a handling device into a downstream in-line calibration press, then guided through a cooling tunnel and discharged from the production line.